gore road project file 0802 - london, ontario · there is an existing hydro one transmission line...
TRANSCRIPT
�������������� ����������������������������������������������������
������� ������������������� ��!�"#$%���$"&'(")� � �������
EXECUTIVE SUMMARY
Introduction
Constructed in 1940, the existing Gore Road Bridge is a single-span cast-in-place concrete T-beam bridge crossing Pottersburg Creek in southeast London. Gore Road is at the south limit of Kiwanis Park. The bridge carries two lanes of undivided traffic with a sidewalk on the north side of the bridge. The original bridge did not include a sidewalk, but a wood-framed sidewalk was added years ago and replaced in 2008. The bridge has a 50 degree skew to accommodate the natural alignment of the creek.
Gore Road is currently designated as an arterial road in Schedule ‘C’ of the City’s Official Plan with an average annual daily traffic (AADT) volume of 13,000 vehicles per day and is anticipated to remain as a two lane cross section for the foreseeable future. The City’s Bicycle Master Plan designates Gore Road as a secondary commuter route. Gore Road is a designated transit route used by London Transit Commission (LTC).
The area in the immediate vicinity of the bridge has a number of constraints that were considered in the design. There is an existing Hydro One transmission line that crosses from the south side of Gore Road to the north side, approximately 150 m west of the bridge and a London Hydro distribution line along the south side of Gore Road. There are no storm sewers east of the bridge on Gore Road and the storm sewers to the west are currently undersized. In addition, there is an existing sanitary sewer that crosses the creek via a syphon, immediately south of the bridge.
The City of London retained Dillon Consulting Limited to complete the Class Environmental Assessment (EA) and preliminary design for the replacement of the Gore Road Bridge as a Schedule “B” project following the Municipal Class EA. As required by the Class EA process, a range of alternatives were reviewed for the bridge:
� Do Nothing. As required by the Class EA, the “Do Nothing” option was considered which includes completing minimal maintenance on the structure. Due to the current condition, it is anticipated this option would result in permanent closure of the bridge within five to ten years
� Rehabilitate Bridge. Based on the evaluation completed, this alternative was not recommended as the bridge is 73 years old and is near the end of its useful life. There is
�������������� ����������������������������������������������������
������� ������������������� ��!�"#$%���$"&'(")� � ��������
significant deterioration to the structure and an extensive rehabilitation would potentially extend the life of the bridge by 15 to 20 years
� Replace Bridge. This alternative is preferred as it provides the best value to the City and minimizes ongoing maintenance costs compared to the rehabilitation alternative.
The Class EA also considered a number of super structure types for the new bridge:
� A concrete rigid frame, which requires little maintenance characteristics and has a relatively shallow structure depth, however the span exceeds the normal limits for this type of bridge and the construction would require extensive temporary in-water work
� A large buried structure (similar to the structure that was recently constructed at the Sarnia Road/CPR crossing). Conflict with the siphon, cost considerations and abutment type limitations eliminated this option from consideration
� A slab-on-girder bridge with steel girders is recommended as it avoids temporary work in the water for construction of the superstructure, accommodates longer spans and is a cost-effective bridge type.
The existing bridge will be replaced with a single span, concrete deck on steel girder structure supported by semi-integral abutments on spread footings. The roadway portion of the new bridge will accommodate a 13 m wide roadway to allow for two through lanes, a sidewalk on both sides and potential for future on road cycling lanes. Initially, the bridge will be painted as a “share the road” lane for bicycles as Gore Road does not currently have separate cycling lanes. The bridge will support additional features including a raised profile to improve sightlines and a new watermain hung from the structure. The bridge has also been designed to accommodate the extension of the Kiwanis Park Pathway under the bridge.
The main branch of Pottersburg Creek passes under Gore Road Bridge and is designated a “Significant Corridor” in the Official Plan. Lands within the study area are primarily residential, with a commercial/light industrial area to the east. An active Barn Swallow nest, a species at risk, was observed on the bridge. An Environmental Impact Study (EIS) was completed as part of the Class EA and was presented to the Environment and Ecological Planning Advisory Committee for comments.
This study and bridge design has been completed in coordination with the ongoing Pottersburg Creek Subwatershed Study Update.
�������������� ����������������������������������������������������
������� ������������������� ��!�"#$%���$"&'(")� � ���������
Proposed Improvements
The major features of the preferred design include:
� New bridge at Pottersburg Creek: o Sidewalks on both sides o Widened roadway for on-street cycling (share the road) o Extend the Kiwanis Park asphalt pathway under the bridge
� Temporary pedestrian bridge during construction, north of the existing bridge, to maintain pedestrian access during construction
� Profile change due to hydraulic and road geometric requirements � Abandon an existing watermain under Gore Road and Pottersburg Creek. A new
watermain will be hung from the bridge � Utility (London Hydro Pole Line, etc.) relocations along the south right-of-way (ROW) � Storm sewers:
o Construct a new storm sewer system east of the bridge, which will outlet to Pottersburg Creek. The new outfall will be designed to control the quantity of water flowing to the creek
o Increase the size of the existing storm sewer west of the bridge and replace the headwall to meet City standards.
Construction will be completed over one construction season, with an anticipated start date of spring 2014.
Based on 2013 dollars, construction is anticipated to cost approximately $4.2 Million.
Traffic
Gore Road is planned to remain as a two lane arterial roadway for the foreseeable future. During construction, the bridge will be closed to traffic and a detour will be in place along Clarke Road and Hamilton Road. Temporary traffic calming measures are suggested along Braesyde Avenue to mitigate cut-through traffic along Braesyde Avenue. The temporary traffic calming measures (speed humps) have recently been used by the City on other construction projects where cut-through traffic and speeds were an issue.
�������������� ����������������������������������������������������
������� ������������������� ��!�"#$%���$"&'(")� � ��������
Public and Agency Consultation
Public and agency consultation was completed throughout the study and included one Public Information Centre (PIC) on March 6, 2013. The PIC was attended by over 30 area residents.
Comments were received throughout the duration of the study and overall were in favour of replacing the bridge. The majority of concerns raised involved traffic management during construction and increased traffic on Braesyde Avenue. Concerns were also received about sight lines when turning onto Gore Road from Montebello Drive. This project is focused on replacing the bridge and construction will not extend to Montebello Drive to address the existing sightline issues. The City should consider a future project to address the sightline issues at this intersection.
Impact Assessment and Mitigation Measures
Replacing the Gore Road Bridge will result in temporary impacts due to construction and permanent impacts such as loss of vegetation to widen the structure and construct the temporary pedestrian bridge. Potential impacts were reviewed as part of the design and have been minimized to the extent possible. The following provides a brief summary of potential impacts and mitigation measures. The City is committed to minimizing potential effects through a combination of design and construction techniques:
� Engineering and Traffic: Primary impact identified is a result of closing Gore Road at the bridge and providing a signed detour route on Hamilton Road and Clarke Road. Several residents identified concerns related to cut-through traffic on Braesyde Avenue during construction. To address the concerns, Braesyde Avenue will be signed for “Local Traffic Only” during construction and the City is considering providing temporary traffic calming measures on Braesyde Avenue
� Natural Environment: In-water works are required to remove the existing abutments and construct the new stormsewer outfalls. Vegetation removals, primarily associated with the new pathway under the bridge and the temporary pedestrian bridge are anticipated and include one Norway Maple, which is currently in poor condition, four trees recently planted by the City and approximately 600 square metres of low lying shrubs and grasses. The EIS provides a detailed assessment of mitigation measures included in the detailed design and construction stages. Construction activities will comply with the required fisheries timing windows and migratory bird nesting season.
�������������� ����������������������������������������������������
������� ������������������� ��!�"#$%���$"&'(")� � �������
One Barn Swallow nest, a Species at Risk, was observed on the bridge and there is potential for Queen Snake, also a Species at Risk to be in the study area. Discussions with the Ministry of Natural Resources (MNR) are required during detailed design to minimize potential impacts
� Cultural Resources: The bridge is not considered to have heritage significance. Based on input from the Ministry of Tourism, Culture and Sport, the need for an archaeological assessment will be assessed during detailed design.
Summary
The Class EA for the Gore Road Bridge Replacement was completed in accordance with the Municipal Class EA (2011) and recommends the existing bridge over Pottersburg Creek be replaced with a single span slab-on-steel girder bridge. To improve connections along the City’s pathway system, the project includes extending the Kiwanis Park asphalt pathway under the bridge. During construction, the bridge will be closed and a detour route along Hamilton Road and Clarke Road will be in place. A temporary pedestrian bridge will be constructed to provide access for pedestrians during construction.
The Class EA Project File documents the study process completed, including the public and agency consultation, evaluation process, preferred design and impacts and mitigation measures. The preferred design addresses the objectives of the Class EA study and potential impacts have been mitigated to the extent possible. The detailed design and construction will be completed as outlined in the Project File.
�������������� ���������������������������������������������������
������� ������������������� ��!�"#$%���$"&'(")� ��������
TABLE OF CONTENTS
i Executive Summary
1 Introduction
2 Phase 1, Problem Statement
3 Contact List
4 Notice of Study Commencement
5 Existing Conditions Roadway and Municipal Preliminary Design Kiwanis Park Pathway Preliminary Design Hydraulics Analysis Preliminary Structural Design Report Heritage Impact Assessment Environmental Impact Study Official Plan Schedules
6 Phase 2, Alternative Solutions
7 Public Information Centre
8 Preferred Design
9 Impacts and Mitigation Measures
10 Consultation with First Nations
11 Approvals and Schedule
�������������� ����������������������������������������������������
������� ������������������� ��!�"#$%���$"&'(")� � �����$�
1. INTRODUCTION
1.1 Background and Purpose of Report
The Gore Road Bridge crosses Pottersburg Creek and is located in southeast London (see Figure 1.1). The existing bridge was constructed in 1940 and is a single-span cast-in-place concrete T-girder bridge carrying two lanes of traffic. A wood-framed sidewalk was added to the bridge in 1970 and was replaced in 2008.
Due to the age and condition of the bridge, it is necessary for the City of London to replace the structure.
Dillon Consulting Limited was retained by the City of London to complete a Class Environmental Assessment (EA) and preliminary design for the replacement. This Project File documents the decision-making process leading to the selection of the recommended alternative for replacing the bridge. Following the final design and receipt of required approvals, construction is anticipated to commence in the spring of 2014.
The study area is generally bounded by Montebello Drive to the west, Hamilton Road to the south, Firestone Boulevard to the east and Eldorado Avenue to the north.
1.2 Class EA Process
Municipal infrastructure projects must meet the requirements of the Ontario ����������������������������. The Municipal Class EA (October 2000, as amended in 2007 and 2011) applies to a group or “class” of municipal water, wastewater and roads projects which occur frequently and have relatively minor and predictable impacts. These projects are approved under the ������, as long as they are planned, designed and constructed according to the requirements of the Class EA document.
The specific requirements of the Class EA for a particular project depend on the type of project, its complexity and the significance of environmental impacts. Four categories of projects are identified in the document, including Schedule “A+”, “A”, “B” and “C” projects. The replacement of the Gore Road Bridge is identified as a Schedule B project in the Class EA. �
�������������� ����������������������������������������������������
������� ������������������� ��!�"#$%���$"&'(")� � �����"�
As shown on Figure 1.2, a Schedule “B” project follows Phases 1 and 2 of the Class EA process and is “screened”:
� Phase 1 of the Class EA process consists of “Problem/Opportunity Identification” � Phase 2 consists of the development and evaluation of “Alternative Solutions” � Based on the objective of avoiding or minimizing adverse environmental impacts, the
Schedule “B” screening process involves: o The preparation of an inventory of the environment potentially affected by the
projecto Public and agency consultation o An impact assessment of the preferred alternative, including measures to
avoid/mitigate any adverse impacts o Documentation of the Class EA process in a Project File.
� � � ����
����
�����
������
������
�����*
������
� ��
���������
� ��������
����
��*��� ��������
��� �
�!�"���
�����
������
��
"#$%
���$"&'(
")
���
Figu
ree 1
.1: S
tudy
Aree
a�
����
�%�
� � � ����
����
�����
������
������
�����*
������
� ��
���������
� ��������
����
��*��� ��������
��� �
�!�"���
�����
������
��
"#$%
���$"&'(
")
Figu
re
��� 1.2:
Cla
ss E
nvvir
onm
enta
l Ass
essm
ent P
rocee
ss
����
�)�
�������������� �����������������������������������������������*���
������� ������������������� ��!�"#$%���$"&'(")� � �����$�
2. PHASE 1, PROBLEM STATEMENT
Phase 1 of the Class EA requires a Problem/Opportunity Statement be developed that outlines the need and objective for the study. The following problem statement was identified, based on the project background and need outlined in Section 1:
������������ ��������������+���,����������*��-�������������������� �����,�������.����/����0��1-�� �����������!��-���������*!� �-��,��*�����������������*�������������-���2��������*���������+���������� ��-�.���������������,������� �-���2�������.����0��1-�����3���� ����� �����*!� �-��, ��*����� �!,�� �*�. ����+� �*���,�� ����� �-��. ����� ��� �-�� ,��*����������������0���
�
Salu
tatio
nSu
rnam
eFi
rst N
ame
Org
aniz
atio
nD
epar
tmen
tT
itle
Add
ress
City
/Pro
vPo
stal
Cod
eT
el.
Fax
E-M
ail
Mr.
Polh
illB
udC
ity o
f Lon
don
War
d 1
Cou
ncill
orP.
O. B
ox 5
035
Lond
on, O
NN
6A 4
L951
9661
2550
x 4
882
bpol
hill@
lond
on.c
a
Ms.
Prow
seSh
ari
Min
istry
of T
ouris
m, C
ultu
re a
nd S
port
Off
ice
Her
itage
Pla
nner
/Arc
haeo
logi
st90
0 H
ighb
ury
Ave
nue
Lond
on, O
NN
6A 1
L351
9-67
5-77
4241
6-67
5-77
77sh
ari.p
row
se@
onta
rio.c
a
Mr.
Coo
per
Cra
igM
inis
try o
f Mun
icip
al A
ffai
rs a
nd H
ousi
ngC
omm
unity
Pla
nnin
g an
d D
evel
opm
ent
Plan
ner
659
Exet
er R
oad,
2nd
Flo
orLo
ndon
, ON
N6E
1L3
519-
873-
4769
519-
873-
4018
crai
g.co
oper
@on
tario
.ca
Mr.
Gra
ham
Bra
dM
inis
try o
f Nat
ural
Res
ourc
esA
lym
er D
istri
ctPl
anni
ng &
Info
rmat
ion
Man
agem
ent S
uper
viso
r61
5 Jo
hn S
treet
Nor
thA
ylm
er, O
NN
5H 2
S851
9-77
3-47
8051
9-77
3-90
14br
ad.j.
grah
am@
onta
rio.c
a
Ms.
McC
losk
eyA
man
daM
inis
try o
f Nat
ural
Res
ourc
esA
ylm
er D
istri
ctD
istri
ct P
lann
er61
5 Jo
hn S
treet
Nor
thA
ylm
er, O
NN
5H 2
S8am
anda
.mcc
losk
ey@
onta
rio.c
a
Mr.
Wal
ker
Kor
eyM
inis
try o
f Nat
ural
Res
ourc
es61
6 Jo
hn S
treet
Nor
thA
ylm
er, O
NN
5H 2
S951
9-77
3-47
37ko
rey.
wal
ker@
onta
rio.c
a
Min
istry
of t
he E
nviro
nmen
tEn
viro
nmen
tal A
ppro
vals
Bra
nch
2 St
. Cla
ir A
venu
e W
est,
Floo
r 12
ATo
ront
o O
NM
4V 1
L541
6-31
4-80
0141
6-31
4-84
52
Ms.
Duf
resn
eTi
naM
inis
try o
f the
Env
ironm
ent
Sout
hwes
t Reg
ion
Off
ice
Dis
trict
Man
ager
(Act
ing)
733
Exet
er R
oad
Lond
on, O
NN
6E 1
L351
9-87
3-50
3151
9-87
3-50
20tin
a.du
fres
ne@
onta
rio.c
a
Mr.
Arm
stro
ngB
illM
inis
try o
f the
Env
ironm
ent
Sout
hwes
t Reg
ion
Off
ice
Envi
ronm
enta
l Pla
nner
733
Exet
er R
oad
Lond
on, O
NN
6E 1
L351
9-87
3-50
1351
9-87
3-50
20bi
ll.ar
mst
rong
@on
tario
.ca
Mr.
Cop
elan
dTo
mC
ity o
f Lon
don
EES
- Was
tew
ater
and
Tre
atm
ent/
Was
tew
ater
& D
rain
age
Engi
neer
ing
Div
isio
n M
anag
erP.
O. B
ox 5
035
Lond
on, O
NN
6A 4
L951
9-66
1-25
00 x
466
2TC
opel
an@
lond
on.c
a
Mr.
Yan
chul
aJa
mes
City
of L
ondo
nPl
anni
ng D
ivis
ion
Man
ager
Com
mun
ity P
lann
ing
& U
rban
Des
ign
P.O
. Box
503
5Lo
ndon
, ON
N6A
4L9
519-
661-
2500
x 7
544
jyan
chul
@lo
ndon
.ca
Mr.
Mac
pher
son
And
rew
City
of L
ondo
nPl
anni
ng a
nd D
evel
opm
ent
Man
ager
, Par
ks P
lann
ing
nad
Des
ign
P.O
. Box
503
5Lo
ndon
, ON
N6A
4L9
519-
661-
2500
x 2
356
AM
acph
er@
lond
on.c
a
Mr.
Wel
ker
Rol
and
City
of L
ondo
nEE
S - W
ater
and
Eng
inee
ring
Rev
iew
/ Wat
er E
ngin
eerin
gD
ivis
ion
Man
ager
P.O
. Box
503
5Lo
ndon
, ON
N6A
4L9
519-
661-
2500
x 5
593
rwel
ker@
lond
on.c
a
Mr.
Hen
ryB
ruce
City
of L
ondo
nPl
anni
ng a
nd D
evel
opm
ent
Man
ager
P.O
. Box
503
5Lo
ndon
, ON
N6A
4L9
519-
661-
2500
x 5
349
bhen
ry@
lond
on.c
aM
s.K
richk
erB
erta
City
of L
ondo
nEE
S - S
torm
wat
er M
anag
emen
t Uni
t M
anag
er o
f Sto
rmw
ater
P.O
. Box
503
5Lo
ndon
, ON
N6A
4L9
519-
661-
2500
x 4
724
BK
richk
e@lo
ndon
.ca
Ms.
Bur
nsK
atie
Lond
on T
rans
it C
omm
issi
onD
irect
or o
f Tra
nspo
rtatio
n &
Pla
nnin
g45
0 H
ighb
ury
Ave
nue
Nor
thLo
ndon
, ON
N5W
5L2
kbur
ns@
lond
trans
it.ca
Mr.
Men
ard
Don
C
ity o
f Lon
don
Plan
ning
and
Dev
elop
men
tH
erita
ge P
lann
er
P.O
. Box
503
5Lo
ndon
, ON
N6A
4L9
519-
661-
2500
x 0
267
dmen
ard@
lond
on.c
a
Mr.
Kal
siIq
bal
Mid
dles
ex-L
ondo
n H
ealth
Uni
tM
anag
er, E
nviro
nmen
tal H
ealth
50 K
ing
Stre
et
Lond
on, O
NN
6A 5
L751
9-66
3-53
17 x
265
0Iq
bal.K
alsi
@m
lhu.
on.c
a
Sgt.
Scriv
ens
Rya
nLo
ndon
Pol
ice
Dep
artm
ent
Traf
fic a
nd C
omm
unity
Ser
vice
s60
1 D
unda
s Stre
etLo
ndon
, ON
N6B
1X
151
9-66
1-56
7051
9-66
1-64
95ts
criv
ens@
polic
e.lo
ndon
.ca
Mr.
Old
ridge
Dan
Lond
on F
ire D
epar
tmen
tD
eput
y C
hief
400
Hor
ton
Stre
et E
ast
Lond
on, O
NN
6B 1
L751
9-66
1-52
7951
9-66
1-84
19M
r.R
ober
tsN
iel
Mid
dles
ex-L
ondn
EM
SD
irect
or o
f Em
erge
ncy
Serv
ices
340
Wat
erlo
o St
reet
Lond
on, O
NN
6B 2
N6
519-
679-
5466
Ext
107
519-
679-
9509
Chi
efM
isko
kom
onJo
e C
hipp
ewas
of t
he T
ham
es F
irst N
atio
nR
R 1
Mun
cey,
ON
N0L
1Y
051
9-28
9-55
55 (m
ain)
, Cal
l Fal
en a
t C
onsu
ltatio
n O
ffic
e @
519
-289
-26
62 x
213
Chi
efC
loud
Liz
Chi
ppew
as o
f Ket
tle &
Sto
ny P
oint
Firs
t Nat
ion
53 In
dian
Lan
e, R
R2
Fore
st, O
NN
0N 1
J01-
519-
786-
2125
(Tra
nsfe
rred
to
Sue
Bra
zette
(?sp
))
Bra
zette
(con
firm
sp
ellin
g)Su
eC
hipp
ewas
of K
ettle
& S
tony
Poi
nt F
irst N
atio
nC
omm
unic
atio
ns &
Rel
atio
ns O
ffic
er
Chi
efPl
ain
Chr
isC
hipp
ewas
of A
amjiw
naan
g97
8 Ta
shm
oo A
venu
eSa
rnia
, ON
N7T
7H
551
9-33
6-84
10M
r.Pl
ain
Wils
onC
hipp
ewas
of A
amjiw
naan
gw
plai
n@aa
mjiw
naan
g.ca
Ms.
John
ston
Shar
ilyn
Chi
efPe
ters
Gre
gory
Mor
avia
n of
the
Tham
esR
R3
Tham
esvi
lle, O
NN
0P 2
K0
519
692-
3936
Chi
efW
addi
love
Patri
ckM
unse
e-D
elaw
are
Nat
ion
RR
1M
unce
y, O
NN
0L 1
Y0
(519
)289
-539
6C
hief
Hill
ier
Loui
seC
aldw
ell F
irst N
atio
n P.
O. B
ox 3
88
Leam
ingt
on, O
NN
8H 3
W3
519-
322-
1766
Chi
efA
bram
Joel
O
neid
a N
atio
n of
the
Tham
es22
12 E
lm A
venu
e, R
R 2
Sout
hwol
d, O
NN
0L 2
G0
1-(5
19)6
52-3
244
Mr.
Phill
ips
Stac
eyO
neid
a N
atio
n of
the
Tham
esC
onsu
ltatio
n C
oord
inat
or22
12 E
lm A
venu
e, R
R 2
Sout
hwol
d, O
NN
0L 2
G0
1-(5
19)6
52-3
244
Chi
efK
eway
osh
Bur
ton
Wal
pole
Isla
nd F
irst N
atio
nR
R3
Wal
lace
burg
, ON
N8A
4K
91-
519-
627-
1481
Mr.
Snow
sell
Mar
kU
pper
Tha
mes
Riv
er C
onse
rvat
ion
Aut
horit
yLa
nd U
se R
egul
atio
n O
ffic
er14
24 C
lark
e R
oad
Lond
on, O
NN
5V 5
B9
519-
451-
2800
519-
451-
1188
snow
sellm
@th
ames
river
.on.
caM
r.H
elst
enM
ark
Upp
er T
ham
es R
iver
Con
serv
atio
n A
utho
rity
Seni
or W
ater
Res
ourc
es E
ngin
eer
1424
Cla
rke
Roa
dLo
ndon
, ON
N5V
5B
951
9-45
1-28
0051
9-45
1-11
88he
lste
nm@
tham
esriv
er.o
n.ca
Mr.
Levi
nSa
ndy
McI
lwra
ith F
ield
Nat
ural
ists
of L
ondo
nB
ox 2
4008
Lond
on, O
NN
6H 5
C4
519-
457-
4593
s.le
vin@
sym
patic
o.ca
Mr.
Thom
pson
Gre
gU
rban
Lea
gue
of L
ondo
nC
hair
Gro
sven
or L
odge
, 101
7 W
este
rn R
oad
Lond
on, O
NN
6G 1
G5
519-
857-
8800
mw
gang
@gm
ail.c
om
Mr.
Stru
cket
tG
ary
Fairm
ont C
omm
unity
Ass
ocia
tion
68 M
eado
wlil
y R
oad
Nor
th
Lond
on, O
NN
5W 1
B6
Ms.
Wes
taw
ayLi
nda
Twee
dsm
uir P
ublic
Sch
ool
Prin
cipa
l34
9 Tw
eeds
mui
r Ave
nue
Lond
on, O
NN
5W 1
L551
9-45
2-86
20
Mr.
Bul
thui
sD
way
neLo
ndon
Dis
trict
Chr
istia
n Se
cond
ary
Scho
ol
Prin
cipa
l24
Bra
esyd
e A
venu
eLo
ndon
, ON
N5W
1V
351
9-45
5-43
60 x
222
dbul
thui
s@ld
css.
ca
Mr.
Pare
ntJo
hnSt
. Ber
nade
tte C
atho
lic E
lem
enta
ry S
choo
l Pr
inci
pal
155
Twee
dsm
uir A
venu
eLo
ndon
, ON
N5W
1K
951
9 67
5-44
18
Mr.
Bro
wn
Way
neM
ont B
lanc
Val
ley
Vie
w In
c.Su
perin
tend
ent
1176
Ham
ilton
Roa
d U
nit 1
01Lo
ndon
, ON
N5W
1A
951
9-45
7-42
40
Sout
hwes
tern
Ont
ario
Stu
dent
Tra
nspo
rtatio
n Se
rvic
es55
7 So
uthd
ale
Roa
d Ea
st, S
uite
201
Lond
on, O
NN
6E 1
A2
519-
649-
1160
519-
649-
1180
Mr.
Ols
thoo
rn
Hen
ryD
utch
Can
adia
n So
ciet
y17
38 G
ore
Roa
dLo
ndon
, ON
N5W
5L5
519-
455-
7170
Mr.
Cly
nick
Dav
eB
ell C
anad
aA
cces
s Im
plem
enta
tion
Man
ager
100
Dun
das S
treet
, Flo
or 4
YLo
ndon
, ON
N6H
4L6
519-
663-
6140
Mr.
Mac
Pher
son
Jam
ieLo
ndon
Hyd
roP.
O. B
ox 2
700
Lond
on, O
NN
6A 4
H6
Mr.
Feen
eyTe
dR
oger
s Cab
lesy
stem
800
Yor
k St
reet
Lond
on, O
NN
5W 2
S951
9-66
0-75
60te
d.fe
eney
@rc
i.rog
ers.c
om
Mr.
Orio
tisJi
mH
ydro
One
Net
wor
ks In
c.
Sout
hwes
t Ont
ario
, Ham
ilton
and
Nia
gara
Reg
ion
Seni
or R
eal E
stat
e C
oord
inat
or
185
Cle
gg R
oad
Mar
kham
, ON
L6
G 1
B7
905-
946-
6261
905-
946-
6242
jim.o
riotis
@hy
droo
ne.c
om
Prov
inci
al M
inis
trie
s
Loc
al R
epre
sent
ativ
es
Gor
e R
oad
Bri
dge
Rep
lace
men
t Cla
ss E
AC
onta
ct L
ist
City
of L
ondo
n
Em
erge
ncy
Serv
ices
Firs
t Nat
ions
Loc
al A
genc
ies &
Inte
rest
Gro
ups
Util
ities
Pro
. No.
12-
6524
SalutationSurnam
eFirst N
ame
Organization
Departm
entT
itleA
ddressC
ity/ProvPostal C
odeT
el.Fax
E-M
ail
Gore R
oad Bridge R
eplacement C
lass EA
Contact L
ist
Ms.
JonesB
ridgetteU
nion Gas Lim
itedC
oordinator Permits A
dministration
P.O. B
ox 2001, 50 Keil D
rive North
Chatham
, ON
N7M
5M1
519-436-4600 x.2737519-436-5353
Mr. &
Mrs.
FalconerM
iles & D
arlene1212 H
amilton R
oadLondon, O
NN
5W 1A
9the.falconers@
yahoo.ca
Mr &
Mrs.
LapierreD
enis & Sharon
34 Eldorado Avenue
London, ON
N5W
1S5lapierredenis@
hotmail.com
Mr. &
Mrs.
Marker
Ron &
Bev
1545 Gore R
oadLondon, O
NN
5W 1T9
Ms.
VanA
melsfort
Willa
30 Braesyde A
venueLondon, O
NN
5W 1V
3
Ms.
FortinK
athleenfortin@
bodyreflex.com
Mr.
Rom
anczukG
reg73 Eldorado A
venueLondon, O
NN
5W 1S8
gregromanczuk@
hotmail.com
Ms.
Mikicinski
Anna
44 Dengate C
rescentLondon, O
NN
5W 1V
8anna.m
Ms.
Barnes
Shirley6 Eldorado A
venueLondon, O
NN
5W 1S5
Mr.
Walm
sleyPaul
1488 Gore R
oadLondon, O
NN
5W 1T7
pd_walm
sley@hotm
ail.com
Mr. &
Mrs.
Powell
Alfred &
Judith46 Eldorado A
venueLondon, O
NN
5W 1S5
Mr. &
Mrs.
Bell
Gord &
Gail
105 Selkirk StreetLondon, O
NN
5W 1W
1
Mr. &
Mrs.
Hill
Sherman &
Donna
81 Strathcona Drive
London, ON
N5W
1P9
Mr.
Donelly
James D
avid33 D
engate Crescent
London, ON
N5W
1V7
jim_donnelly@
bell.net
Ms.
Vidal
Carol
1616 Gore R
oadLondon, O
NN
5W 1T8
Mr.
Marczenko
Andrew
1536 Gore R
oadLondon, O
NN
5W 1T8
Ms.
Nydam
Laura1595 G
ore Road
London, ON
N5W
1T9
Mr.
Berm
anR
onald30 C
oldstream C
rescentLondon, O
NN
5W 1T6
randhberman@
hotmail.com
Mr. &
Mrs.
IrelandR
obert Thomas &
Laurie93 C
oldstream C
rescentLondon, O
NN
5W 1T5
Mr. &
Mrs.
Disher
Cam
& B
renda86 Eldorado A
veLondon, O
NN
5W 1S5
Mr. &
Mrs.
FroudeM
arg and Stan28 B
raesdye Avenue
London, ON
N5W
1V3
mjfroude@
hotmail.com
Mr. &
Mrs.
Jawniuk
Michael &
Ruth
107 Selkirk StreetLondon, O
NN
5W 1W
1
Vachhani
Mital
19 Pilkington Crescent
Thornhill, ON
L4J 6B7
Grada
Ligia64 B
renneman D
riveB
aden, ON
N3A
4M9
Mr.
Willits
Murray
1602 Gore R
oadLondon, O
NN
5W 1T8
Ms.
Greenw
oodB
etty70 Eldorado A
venueLondon, O
NN
5W 1S5
Mr.
Frampton
James
45 Dengate C
rescentLondon, O
NN
5W 1V
7
Mr.
PolhillB
ud16 W
eeedsmuir
London, ON
N5W
1K5
Mr.
LobodzinskiB
ud41 D
engate Crescent
London, ON
N5W
1V7
Michienzi
A147 M
onyebello Drive
London, ON
N5W
1S1
Mr.
Bungay
G78 Eldorado D
riveLondon, O
NN
5W 1S5
Ms.
Jawniuk
Ruth
107 Selkirk StreetLondon, O
NN
5W 1W
1
Ms.
Maksy
Donna
62 Eldorado Avenue
London, ON
N5W
1S5
Ms.
Hache
Jean50 Eldorado A
venueLondon, O
NN
5W 1S5
TillaartC
hris1520 G
ore Road
London, ON
N5W
1T8
Ms.
Berm
anA
llisonA
boriginal Affairs and N
orthern Developm
ent Canada
Consultation and A
ccomm
odations Unit
Program O
fficer300 Sparks Street
Ottaw
a, Ontario
K1A
0H4
613-943-5488U
CA
-CA
U@
aadnc-aandc.gc.caM
r.Ford
JohnLondon Transit C
omm
issionD
irector of Transportation & Planning
450 Highbury A
venue North
London, ON
N5W
5L2519-451-1340 x 327
Rem
ove from L
ist
Residents R
equesting to be Kept Inform
ed
Pro. N
o. 12-6524
�������������� ����������������������������������������������������
������� ������������������� ��!�"#$%���$"&'(")� �����$�
4. NOTICE OF STUDY COMMENCEMENT
The notice and comment form were sent to the contact list on September 12, 2012. Special covering letters were sent to Aboriginal Affairs and Northern Development Canada (AANDC) and the Ministry of Aboriginal Affairs (MAA) requesting information related to First Nations.
The City distributed the notice and comment form to property owners in the area on September 11, 2012, as shown on the map at the end of this section. A short version of the notice was published in the September 13 and 20, 2012 editions of the Londoner and on the City’s website under the “Public Notices” section.
Twenty-seven responses were received to the notice. The following tables summarize the comments as well as how each one was addressed.
Agency Comments Contact Comment Response
AgencyMinistry of AboriginalAffairs
GilesBenaway
First Nations contacted as part of this study is comprehensive and the Ministry does not recommend contacting any others.
Remove MAA from contact list as it has no additional interest in the study.
Removed from contact list.
Ministry of theEnvironment, SouthwesternRegion
BillArmstrong, RegionalEnvironmental Planner
There has been significant public interest/concern in and around Pottersburg Creek in the past, including bank erosion along the creek, south of Hamilton Road. The City will be initiating a separate EA to address this issue (Hamilton Road EA).
Current Gore Road EA should not limit alternatives/opportunities that will be reviewed as part of the Hamilton Road EA.
The study team is aware of the ongoing issues and sensitivities regarding Pottersburg Creek and will coordinate with the City’s Hamilton Road EA team throughout this study.
London TransitCommission (LTC)
Katie Burns
London Transit has a bus route on Gore Road that crosses the bridge, which will be maintained following construction. The design should consider pedestrian access.
The new bridge will accommodate buses and will include sidewalks on both sides. The study team will be in contact with LTC once construction staging is further developed to discuss opportunities to minimize disruption to LTC service during construction.
�������������� ����������������������������������������������������
������� ������������������� ��!�"#$%���$"&'(")� �����"�
Agency Comments Contact Comment Response
Local StakeholdersNatureLondon
Sandy Levin, Chair
Requests to be kept informed via email, including Public Information Centre (PIC) information.
Updated throughout study.
Comments from the General Public Key Issue Comment Response
TrafficImpacts
Braesyde Avenue should be blocked from traffic during construction.
Signs indicating ‘local traffic only’ were ignored the last time there was construction at the bridge and Braesyde Avenue was used as an unofficial detour.
Braesyde Avenue does not have sidewalks and there are many pedestrians who use the road, including children.
It is not feasible to maintain traffic on the bridge during construction.
A signed detour route will be set up during construction that follows Hamilton Road and Clarke Road.
The City has used temporary traffic calming measures such as speed humps on area roads to help reduce speeds and make the routes less desirable for cut-through traffic. The need for similar traffic calming measures will be reviewed as part of this study.
Against permanently closing the bridge.
The current study is to replace the existing bridge and permanent closure will not be recommended.
RoadwayDesign Issues
Requested a grade reduction or traffic signal be installed on the west side of the bridge.
Currently, when stopped at Montebello Drive and pulling out onto Gore Road the grade prevents drivers from seeing oncoming traffic (east to west bound).
Bridge will be raised approximately 1.5 m, which will help to address existing sightline concerns.
Bridge and roadway grade leading to the bridge should be raised 4 to 6 feet to reduce walkway complications – vehicles must stop quickly for pedestrians which they are unable to do during bad weather.
Bridge will be raised approximately 1.5 m, which will help to address existing sightline concerns.
Bridge should include on-road cycling lanes.
The bridge will be wide enough to accommodate future on-road cycling lanes, however they will not be painted as Gore Road does not currently include cycling lanes.
New bridge should have wider sidewalks.
Sidewalks will be provided on both sides of the bridge.
�������������� ����������������������������������������������������
������� ������������������� ��!�"#$%���$"&'(")� �����%�
Comments from the General Public Key Issue Comment Response
Improvement OpportunitiesIdentified
Identified an area approximately 100 m south of the bridge that is low-lying, swampy and a breeding ground for mosquitos. Suggested the area could be filled in with excess materials from the project to enhance the pathway and minimize the breeding area for mosquitos.
Due to Upper Thames River Conservation Authority regulations along Pottersburg Creek, there are no opportunities to place any excess fill along the banks of the creek.
Improvements at the Hamilton Road/Gore Road intersection are required.
The current study is to replace the bridge and is not looking at changes to the Gore Road/Hamilton Road intersection. Comments regarding the need for intersection improvements were provided to the City for consideration.
Property-SpecificIssues
Currently on septic and would like the opportunity to connect to sewers if possible.
There is an opportunity for the homeowner to connect to the sanitary sewer, at the homeowner’s expense, during construction. Details will be confirmed with the City during the design phase.
Will this project affect property taxes and value of homes in the area?
This project is being completed through the City’s capital works budget and will not impact property taxes from area residents. In addition, as this is a replacement project, changes to property values in the area are not anticipated.
Gore Road Bridge Replacement Class Environmental Assessment
Notice of Study Commencement
Due to the age and existing condition of the bridge, the City of London is completing a Class Environmental Assessment (EA) to replace the Gore Road Bridge. The bridge was constructed in 1940 and crosses Pottersburg Creek in southeast London.
The Municipal Class Environmental Assessment (EA) (October 2000, amended in 2007 and 2011) categorizes the Gore Road Bridge Replacement as a Schedule ‘B’ project. This type of project is approved under the Environmental Assessment Act, provided it follows Phase 1, “Problem/Opportunity Identification” and Phase 2, “Alternative Solutions” of the Class EA process and is “screened”. Based on the objective of avoiding or minimizing adverse environmental impacts, the screening process will involve:
• Identify and evaluate alternatives for replacing the bridge • Complete environmental inventories and assess impacts of the recommended alternative. Opportunities to limit
impacts will be reviewed • Public and agency consultation throughout the study • Document the study in a Project File. The file will be available for a 30-day public review period.
A Public Information Centre will be held to present the recommended alternative. A subsequent notice will include the date, time and location of the meeting.
PUBLIC COMMENTS INVITED At any time during this study, interested persons have an opportunity to provide comments, questions and concerns to the study team. Information will be collected in accordance with the Freedom of Information and Protection of Privacy Act. Unless otherwise stated in the submission, all personal information such as name, address, and property location will become part of the public record and will be included in the final report.
To provide comments or for further information on this project please contact:
Sabrina Stanlake, RPP Karl Grabowski, P.Eng. Planner Transportation Design Engineer Dillon Consulting Limited City of London Box 426, London, Ontario, N6A 4W7 P.O. Box 5035, London, Ontario, N6A 4L9 Tel: 519-438-1288, Ext. 1235 Tel : 519-661-2500, Ext. 5071 Fax: 519-672-8209 Fax : 519-661-2355 Email : [email protected] Email: [email protected]
Gore Road Bridge Replacement Class Environmental Assessment
Notice of Study Commencement
The City of London is completing a Class Environmental Assessment (EA) to replace the Gore Road Bridge over Pottersburg Creek in southeast London. The Municipal Class Environmental Assessment (EA) (October 2000, amended in 2007 and 2011) categorizes the Gore Road Bridge Replacement as a Schedule ‘B’ project. Additional information on the study is available on the City’s website at http://www.london.ca/d.aspx?s=/Transportation/trans_planning.htm
To provide comments or for further information please contact:
Sabrina Stanlake, RPP Karl Grabowski, P.Eng. Planner Transportation Design Engineer Dillon Consulting Limited City of London Box 426, London, Ontario, N6A 4W7 P.O. Box 5035, London, Ontario, N6A 4L9 Tel: 519-438-1288, Ext. 1235 Tel : 519-661-2500, Ext. 5071 Fax: 519-672-8209 Fax : 519-661-2355 Email : [email protected] Email: [email protected]
1/1https://groups.google.com/a/dillon.ca/forum/?hl=en&fromgroups=#!topic/goreroadbridge/Eatltm2W4SY
Welcome to the new Google Groups! Welcome to the new Google Groups! Learn about the Learn about the new features you’ll findnew features you’ll find..
Groups POST REPLYPOST REPLY
©2012 Google Privacy - Terms of Service -
Google Home
My groups
Home
My discussions
Starred
Recently viewed
Gore Road Bridge
Hwy3and4
Highbury Interchange
Click on a group’s staricon to add it to your
favorites
Favorites
Gore Road Bridge ›
Notice of Study Commencement1 post by 1 author in Gore Road Bridge
Post replyKathy & Earl Fortin Sep 13 (6 days ago)
Thank you for your notice re: Gore Road Bridge. We had hoped that it was notice of changes to be made at the corner of HamiltonRoad and Gore Road. Not sure why the “bridge” is requiring changes but it obviously has come to someone’s attention, so wewould appreciate being informed regarding this project.
It would be helpful if we could be informed by e-mail at [email protected].
Thank you Kathleen Fortin
Reply
Search for topics [email protected]
+You Search Images Mail Drive Calendar Sites Groups Contacts More
10/ 2/ 12 Dillon Consult ing M ail - G or e Road Br idge Replacement
1/ 2ht t ps: / /mail. google. com /mail/ u/ 0/ ?ui=2&ik=e683f 2a15e&view=pt &sear ch=inbox&t h=13a1f 2ebd9667de1
Mulcahy, Sandy <[email protected]>
Gore Road Bridge Replacement1 message
Margaret Froude <[email protected]> Mon, Oct 1, 2012 at 9:54 PMTo: [email protected], [email protected]
I am emailing you in response to your letter regarding Notice of Study Commencement - Gore Rd BridgeReplacement. We would most definitely like to be kept informed regarding this project, especially around the date and timeframe for this replacement. We do understand the need for this replacement, and would like additional information around the closure of GoreRd and what has been done around the issue of re routing traffic. Has any sort of traffic analysis taken place with regards to the amount of traffic using this road? This should be a measurement as to the percentage of traffic from Hamilton Rd that would normally use the GoreRd corridor to Clarke Rd and vice versa. What is the plan for re routing traffic? which includes all sizes of transports trucks, delivery trucks, city buses,school buses and cars etc. Currently Braesyde Ave has a 'no' truck signage, we also have no parking on one side of the street no curbs,gutters or sidewalks. All or most students arrive by school bus to the London District Christian School, and we also have three additional school buses that pick up students for theThames Valley and the London District Catholic school boards. If the high school hosts has any kind of celebration, cars are parked (one side of the road).. all the way downBraesyde Ave leaving very little room for travel.. this would be a concern for traffic jam and happens currently without any additional routed traffic. We have lived here since 1976, and this road is simply tar and stone. Prior to the development of WhitlowEstates, the Hamilton Rd city bus use to travel via Braesyde Ave which has left us with a poor road, little water runoff, puddling after a rainfall and has not seen anymaintenance other patch work over time. Local traffic was also increased when the condo's were built on Hamilton Rd, which has also added tothe deteriorated state ... you see Braesyde Ave was/is the cut through to Gore Rd and the easiest access for these folks. Extra traffic routed via Braesyde Ave to avoid the bridge work, would seriously impact this street and safety. Deteriorating this road even further. We had this sort of re routing happen when there was an emergency closure of Gore Rd, and it was terrible.
10/ 2/ 12 Dillon Consult ing M ail - G or e Road Br idge Replacement
2/ 2ht t ps: / /mail. google. com /mail/ u/ 0/ ?ui=2&ik=e683f 2a15e&view=pt &sear ch=inbox&t h=13a1f 2ebd9667de1
There is a sharp curve in this road right in front of the high school, 30 km is just too fast and drivers were caught off guard or didn't pay attention, or simply angry aboutthe detor. The barricades were placed at each end of the street to close Braesyde to local traffic only, but still many many vehicles disregarded these signs, and no one policedthem, in fact most times the signs were knocked over or removed all together. Suggestions would be to barricade at Clarke Rd to local traffic... to stop anyone from entering from Gore Rdand barricade on Braesyde/Hamilton Rd.. with option to have it monitored. As you can see, our biggest issue is the additional unwanted traffic day and night and constant noise, plus thesafety of our school children and young adults in the group home that walk our street and board school buses. Hopefully, most of what I have described above has already been part of your planning, and we look forward toyour response Best Regards Marg and Stan Froude28 Braesyde Ave
1/1https://groups.google.com/a/dillon.ca/forum/?hl=en&fromgroups=#!topic/goreroadbridge/MI1DWgOnLHY
Welcome to the new Google Groups! Welcome to the new Google Groups! Learn about the Learn about the new features you’ll findnew features you’ll find..
Groups POST REPLYPOST REPLY
©2012 Google Privacy - Terms of Service -
Google Home
My groups
Home
My discussions
Starred
Recently viewed
Gore Road Bridge
Hwy3and4
Highbury Interchange
Click on a group’s staricon to add it to your
favorites
Favorites
Gore Road Bridge ›
Gore Road Bridge Replacement1 post by 1 author in Gore Road Bridge
Post replyGreg Romanczuk Sep 13 (6 days ago)
Sabrina, I would like to be kept informed regarding the above project via email. The following is my info: Greg & Anna Romanczuk 73 Eldorado Avenue London, ON N5W1S8 [email protected] Will renderings of the concepts be available online in the future? Thank you, Greg Romanczuk
Reply
Search for topics [email protected]
+You Search Images Mail Drive Calendar Sites Groups Contacts More
�������������� �����������������������������������������������*����
������� ������������������� ��!�"#$%���$"&'(")� � �����$�
5. EXISTING CONDITIONS
Gore Road, in the southeast end of the City of London, is designated an arterial road in the Official Plan and crosses Pottersburg Creek.
Lands adjacent to Pottersburg Creek are part of the City’s Natural Heritage system, with the creek joining the south branch of the Thames River south of Hamilton Road.
East and west of the bridge, the lands are designated residential in the Official Plan, and include a mix of low and medium density housing west of the bridge, between Gore Road and Hamilton Road, as shown on the attached Schedule A to the Official Plan. The land south of Gore Road, east of the Hamilton Road intersection is designated a Neighbourhood Commercial Node and is currently being redeveloped for a restaurant. The area north and east of the bridge, from Firestone Boulevard to Clark Road is designated Light Industrial and Auto-Oriented Commercial Corridor and is primarily a mix of light manufacturing and retail uses. The Dutch Canadian Society Hall is located northwest of the Gore Road and Clarke Road intersection.
The City’s Thames Valley Parkway, a 30 kilometre asphalt pathway, extends along the Thames River throughout the City. There is an existing asphalt pathway along Pottersburg Creek that extends from Kiwanis Park south, along the west side of the creek to connect with the Thames Valley Parkway south of Hamilton Road. The pathway along Pottersburg Creek includes an at-grade crossing at Gore Road and Hamilton Road.
The following series of memos and reports provides information on the existing structure, municipal infrastructure and natural environment within and adjacent to the study area:
� Roadway and Municipal Preliminary Design � Kiwanis Park Pathway Preliminary Design � Hydraulics Analysis � Preliminary Structural Design Report � Heritage Impact Assessment � Environmental Impact Study � Official Plan Schedules.
130 Dufferin Avenue, Suite 1400, London, Ontario, N6A 5R2 – Phone 519-438-6192 – Fax 519-672-8209
TECHNICAL MEMORANDUM
TO: Project File
FROM: Jason Johnson, P.Eng.
DATE: June 10, 2013
SUBJECT: Roadway and Municipal Preliminary Design Gore Road Bridge Replacement – Class Environmental Assessment
OUR FILE: 12-6524
The following memo provides information related to the civil aspects of this Class Environmental Assessment (Class EA). The recommended design for the Gore Road corridor is shown in the attached figures.
ROADWAY DEVELOPMENT PHASES
The following roadway development phases were considered as part of the preliminary design:
� Immediate – roadway improvements to suit immediate bridge replacement requirements, and matching ultimate profile for the bridge structure only. This phase includes widening for the potential ultimate cross section across the new structure, while tying in to the existing conditions east and west of the structure
� Interim – roadway improvements to be considered in the future for the sake of improving roadway design away from the bridge. The interim phase relates to improvements in sight lines, particularly related to turning movements from Montebello Drive onto Gore Road or residents entering or exiting driveways in the vicinity
� Ultimate – conceptual design to be considered in the long-term. This future phase may include widening Gore Road to two lanes, plus a left turn lane for Montebello Drive and Braesyde Avenue. The left turn lane would extend across the structure for continuity to the driver.
The Class EA only considers the work being done under the “immediate” phase. Improvements under the “interim” and “ultimate” phases will require a separate Class EA be completed.
ROADWAY DESIGNATION AND USAGE
Gore Road is currently designated an arterial roadway in Schedule ‘C’ of the City’s Official Plan with an annual average daily traffic (AADT) of 13,000 vehicles per day and is anticipated to remain as a two-lane cross section for the foreseeable future. Based on the City’s Bicycle Master Plan, the roadway is also designated a secondary commuter route. Gore Road is a designated transit route used by London Transit Commission (LTC). The current posted speed is 50 km/hr.
���3�!����4�����,�������������!������������������������,����������� �����������������������������������"��
130 Dufferin Avenue, Suite 1400, London, Ontario, N6A 5R2 – Phone 519-438-6192 – Fax 519-672-8209
CROSS SECTION
The proposed cross section across the structure is 13.0 m wide (edge of pavement to edge of pavement). The main features of the roadway cross section, across the structure, include one lane of traffic in each direction, on-road bicycle lanes, curb and gutter and sidewalks. Barrier curb and gutter is recommended to enhance roadside safety.
SIGHTLINES
Sightlines were reviewed for the posted speed of 50 km/hr (design speed of 60 km/hr) and it was confirmed that adequate stopping distances are provided for through traffic. Sightlines were also reviewed for traffic turning left onto Gore Road from Braesyde Avenue and it was confirmed that adequate site distances are provided. The limits of construction do not extend to the Montebello Drive intersection and so sightlines for turning movements at this intersection were not considered as part of this project. Improvements to sight lines in this area could be addressed under a separate project.
SIDEWALKS
A sidewalk currently exists on the north side of Gore Road. This sidewalk crosses Pottersburg Creek via a pedestrian bridge attached to the existing bridge and provides access to the trail to the north, just west of the existing bridge. There is no sidewalk on the south side of Gore Road and access to the trail south of Gore Road is via the shoulder. There is currently an at-grade pedestrian crosswalk at Gore Road, just west of the bridge connecting the north and south sections of the trail.
The sidewalk on the north side of Gore Road will be reinstated. The existing pedestrian bridge will be removed and the new structure will accommodate the additional sidewalk width. A new sidewalk will be installed on the south side of Gore Road, between Braesyde Avenue and just west of the new structure, to provide pedestrians from the Braesyde Avenue area with a link to the trail on the south side of the roadway. A short retaining wall may be required on the south side of Gore Road, behind the sidewalk, just west of Braesyde Avenue. This will allow the new cross section to match into the existing slope in the area.
ACTIVE TRANSPORTATION
The roadway is designated as a secondary commuter route, which includes a shared lane for cyclists and vehicles (painted as “Share the Road”). The bridge cross section is wide enough to accommodate separate bike lanes if constructed in the future on Gore Road.
SANITARY SEWERS
Sanitary sewers currently exist on Gore Road east and west of the structure. The sewers outlet to the Pottersburg Trunk sewer, a 900 mm diameter concrete sewer, located along the west banks of Pottersburg Creek. There are multiple sanitary maintenance holes on the south side of the structure where the sewer from the east crosses the creek via a syphon. Flows from the Braesyde Avenue area connect to the Pottersburg trunk sewer at a manhole on the southwest corner of the bridge via a pipe bridge over the
���3�!����4�����,�������������!������������������������,����������� �����������������������������������%��
130 Dufferin Avenue, Suite 1400, London, Ontario, N6A 5R2 – Phone 519-438-6192 – Fax 519-672-8209
creek. Flows from the west discharge to the Pottersburg trunk sewer through a manhole on the north side of Gore Road. Grading will be provided for the construction of overland access roads so that all manholes can be accessed for maintenance. All existing sanitary infrastructure, including the pipe bridge and siphon, will remain in place at the end of the project.
STORM SEWERS
Storm sewers currently exist on the west side of the structure with an outlet at the northwest corner of the bridge. Sewers servicing the residential area to the northwest and Gore Road, from the bridge to Montebello Drive, connect to this outlet. The storm sewer on Gore Road is undersized and a new storm sewer and outlet are proposed as part of the immediate phase of work.
The new storm sewer will be installed in a standard location offset 3.0 m from the center of Gore Road, west of the bridge, and is sized to convey flows from as far west as the Hamilton Road and Gore Road intersection in the future. Catch basins will be installed at standard intervals and will outlet to the new sewer. The proposed outlet is a pre-cast concrete headwall. The storm sewers from the residential area to the northwest and Gore Road will connect to a manhole, just upstream of the headwall, combining into a single outlet at Pottersburg Creek. Compared to the two existing outlets in parallel, this will decrease the probability of erosion.
There are currently no storm sewers servicing Gore Road east of the bridge. A new storm sewer and outlet are proposed. The outlet will be installed northeast of the bridge. The storm sewer will be installed in a standard location offset 3.0 m from the center of Gore Road, east of the bridge and sized to convey flows in the future from as far east on Gore Road as the mid-point between Braesyde Avenue and Firestone Boulevard. In addition, the system on the east will be sized to accommodate tying in a future system serving a portion of Braesyde Avenue. Catch basins will be installed at standard intervals and will outlet to the new sewer. The proposed outlet is a pre-cast concrete headwall.
The addition of the storm sewers and curbs will greatly reduce the volume of overland flow in the vicinity of the bridge and eastward to the intersection with Braesyde Avenue. Remaining overland flows will be conveyed into the creek through ditches and swales, and scour will be managed by the flattening of embankment slopes to 2:1 at the steepest, and the use of riprap slope protection where appropriate.
WATERMAIN
A 300 mm diameter watermain exists on the north side of Gore Road along the north edge of pavement crossing under Pottersburg Creek. Existing line valves are located east and west of the bridge on Gore Road at Braesyde Avenue and Montebello Drive. There are no record drawings for the main but it is suspected to be cast iron and installed in the 1950s or 1960s. A new 300 mm diameter watermain will be installed to the limits of the new bridge construction. The new main will be attached to the side of the new bridge and will tie back into the existing line at the limits of the reconstruction.
���3�!����4�����,�������������!������������������������,����������� �����������������������������������)��
130 Dufferin Avenue, Suite 1400, London, Ontario, N6A 5R2 – Phone 519-438-6192 – Fax 519-672-8209
CONSTRUCTION
Construction is currently scheduled for 2014. Gore Road will be closed during construction between Montebello Drive and Braesyde Avenue, however, access to the houses fronting onto Gore Road east and west of the bridge will be maintained throughout construction. Traffic will be detoured around the project via Hamilton Road and Clarke Road. To hinder cut-through traffic, traffic calming measures will be considered on Braesyde Avenue between Hamilton Road and Gore Road.
There is also a bus route through the project limits and so coordination with the LTC will be required.
Pedestrian traffic will be maintained through the limits of the project for the duration. A temporary pedestrian bridge will be installed over Pottersburg Creek, north of the existing bridge and will be maintained until the new bridge is completed.
UTILITIES
There is an existing Hydro One transmission line that crosses from the south side of Gore Road to the north side, approximately 150 m west of the bridge. The line then continues easterly, parallel to the roadway, in a utility easement just north of the property line. No conflicts or relocations of this line are anticipated at this time.
There is an existing London Hydro distribution line running along the south side of Gore Road through the limits of construction. This line must be relocated prior to construction. There are also cable and phone utilities on this line that will require relocation at the same time.
LIGHTING
Existing illumination is mounted on London Hydro poles along the south side of Gore Road. With the proposed road widening, the London Hydro poles will be relocated further south, away from Gore Road. Preference for illumination on the proposed new structure will be to keep the lights mounted on the relocated London Hydro poles, providing they will meet the City of London’s illumination standards for a major road classification. If the required illumination cannot be achieved from mounting the lighting on the utility poles, base mounted street lighting poles and underground lighting service for the limits of the Road widening will be provided.
TECH
TO:
FROM:
DATE:
SUBJEC
OUR FIL
The KiwPottersburoccur at existing si
The propopass undeproviding
In generaldirected b
It is recom
� Pbyacthavcr
� Fththpous
� CalwR
130 Dufferi
HNICAL
Projec
Chris H
June 2
T: KiwanGore R
LE: 12-652
anis Park Parg Creek and an intersectioight lines on G
osed Gore Roer the bridge
g an aesthetic
l, the pathwayby the Environ
mmended the
otential pathwy the presencchieved for thhe bridge. Thvoid occasionrosswalk will
lusher truck ahe north and shat are too steoint to serve ased by Hydro
Continuity of tlong the south
west of the croRoad, in the w
in Avenue, Suite 1
L MEMO
ct File
Haines, P.Eng
24, 2013
nis Park PathwRoad Bridge R
24
athway in thcrosses Gore
on and does Gore Road fo
oad Bridge Re, allowing proute for the
y will be desnmental & Pa
crosswalk on
way flooding ce of overheahe roadway. Te pathway winal and seaso provide an a
access to exissouth sides oeep and too sas a reliable l
o One for main
the sidewalk h side of Goreosswalk, is no
westerly direct
1400, London, Ont
ORAND
g.
way PreliminaReplacement
he area of Ge Road at a cro
not have anyor eastbound t
Replacement pedestrians apathway.
igned to the Carks Planning
n Gore Road b
– It should bad transmissioThis profile rill not be highonal flooding
alternative rou
sting manholef Gore Road.soft for vehiclane for occasntenance of th
– The crosswe Road to croot planned sintion at the pro
tario, N6A 5R2 – P
DUM
ary Design – Class Envir
Gore Road Bosswalk to thy traffic contraffic, east of
includes an aand cyclists t
City of LondSection.
be retained fo
e noted that von lines, limiraise restrictioh enough, rel
g of the pathute
es – City flush The profile rles. The pathsional flusherhe overhead t
walk will alloss over to the
nce there is nooject limits to
Phone 519-438-61
ronmental As
Bridge currenhe west of the ntrol. The crof Montebello
allowance forto avoid the
don Multi-Use
or the followin
vertical clearaiting the amoon limits thelative to norm
h in periods o
her trucks reqraise for the
hway crosswar truck use. Thtransmission
ow pedestriane north side. Eo existing sidetie into.
192 – Fax 519-672
ssessment
ntly follows bridge. The c
ossing was loDrive.
r the Kiwanicrosswalk a
e Pathway St
ng reasons:
ance at the brount of profilelevation of
mal water levof high flows
quire access troadway will
alk provides ahese access plines
ns walking onExtension of tewalk on the
2-8209�
the west bancrosswalk doocated to opt
s Park Pathwat Gore Road
andards and a
ridge is constre raise that cthe pathway els in the cres. Maintainin
to the manholl create side sa controlled a
points could a
n the new sidethe south sidesouth side of
nk of es not timize
way to d and
as per
rainedcan be under
eek, to ng the
les on slopesaccess lso be
ewalk ewalk,f Gore
5�3��������6����-3�!�����������!������������������������,����������� �����������������������������������"��
130 Dufferin Avenue, Suite 1400, London, Ontario, N6A 5R2 – Phone 519-438-6192 – Fax 519-672-8209�
Removable bollards will be located across the pathway near the crosswalk to deter other vehicles from entering and to slow down cyclists as they approach the level crossing of Gore Road. The width and line painting of the level crossing will follow the Transportation Association of Canada’s Bikeway Traffic Control Guideline for Canada – Second Edition, with painted markings to separate pedestrians and cyclists. The combined width will also be suitable for the flusher trucks and turning features will be incorporated in the design.
The addition of the pathway requires a slightly longer bridge span than what would be required without it. In addition, retaining walls will be needed along the west shoreline of Pottersburg Creek to support the pathway near the bridge. Environmentally low impact solutions for achieving the retaining walls along the west shoreline will be investigated during detailed design. It is anticipated that the pathway under the bridge will require illumination.
There is an existing sanitary sewer pipe bridge across Pottersburg Creek downstream of the Gore Road Bridge. Alternatives were explored to climb the side slopes at the bridge to allow the pathway to pass over the pipe bridge and associated buried works, however the grades would be excessive. Therefore the pathway will remain close to the normal water level for a distance until it passes under the pipe bridge and then climb gradually up the banks of the creek to the west. Retaining walls to protect existing municipal works and structures in the area will be required along the pathway.
Pottersburg Creek is part of the City’s natural heritage system and an Environmental Impact Study is currently underway to assess the impacts and mitigation measures for the bridge replacement, and pathway extension.
The resulting pathway will be an aesthetic and functional enhancement to the Kiwanis Park Pathway system for pedestrians, cyclists and maintenance personnel.
130 Dufferin Avenue, Suite 1400, London, Ontario, N6A 5R2 – Phone 519-438-6192 – Fax 519-672-8209
TECHNICAL MEMORANDUM
TO: File
FROM: Hanna Ibrahim, C.E.T., Brian Huston, P.Eng.
DATE: March 13, 2013
SUBJECT: Gore Road Bridge – Hydraulic Analysis
OUR FILE: 12-6524______________________________________________________________________________
INTRODUCTION
The purpose of this memo is to provide a summary of the hydraulic performance of the existing Gore Road Bridge, over Pottersburg Creek, and the evaluation of the performance of the recommended replacement structure. This technical memo will form part of the Gore Road Bridge Replacement Environmental Assessment (EA) and Preliminary Design. As such, this memo is intended to provide hydraulic information to assist in the evaluation of the technically preferred bridge replacement alternative presented in the EA.
Located in the City of London, the existing Gore Road Bridge (Structure 4-BR-15) is a cast-in-place concrete tee beam bridge between Hamilton Road and Clarke Road. Gore Road is classified as an urban arterial roadway and the bridge location is shown in Figure 1.
����������������7!�����������!���������"��
130 Dufferin Avenue, Suite 1400, London, Ontario, N6A 5R2 – Phone 519-438-6192 – Fax 519-672-8209
Figure 1: Site Location
The hydraulic performance of the existing and proposed structures will be evaluated based on the design criteria summarized in Table 1. The design standards established as part of the preliminary design represents a combination of criteria outlined in the TAC Manual and the Canadian Highway Bridge Design Code.
Table 1: Design Criteria Parameter Design Standard
Road Category Arterial (urban) Return Period of Design Flow 1:100 year Minimum Freeboard Requirement Greater than or equal to 1.0 m Minimum Clearance Requirement Greater than or equal to 1.0 m
����������������7!�����������!���������%��
130 Dufferin Avenue, Suite 1400, London, Ontario, N6A 5R2 – Phone 519-438-6192 – Fax 519-672-8209
HYDRAULIC MODELING
Design Flow
A Pottersburg Creek Subwatershed Study was completed in 1995 by Paragon Engineering Limited. A HEC-RAS flow file was provided to Dillon by the Upper Thames River Conservation Authority (UTRCA), which included three flow change locations for the 100-year return period event peak flow. These flows are summarized in Table 2 and the cross-sections locations, also provided by UTRCA, are shown in Figure 2. These flows were used to evaluate the hydraulic performance of the recommended replacement bridge configuration for Gore Road, and to demonstrate that the recommended configuration results in no increase in water surface elevations.
Table 2: 100-Year Return Period Event Peak Flow Change Locations Location Peak Flow (m3/s)
Cross-Section 2.39 – Immediately Upstream of Trafalgar Street
55.5
Cross-Section 1.66 – Downstream Face of CN Rail Crossing 73.0Cross-Section 0.79 – Immediately Upstream of Gore Road 89.6
����������������7!�����������!���������)��
130 Dufferin Avenue, Suite 1400, London, Ontario, N6A 5R2 – Phone 519-438-6192 – Fax 519-672-8209
Figure 2: Cross-Section Locations
It is noteworthy that a Pottersburg Creek Subwatershed Study Update is currently underway, and includes updates to the hydrologic modeling that was completed in 1995. The update may result in a change in the 100-year peak flows. The update will be applied to the model during the detailed design phase of the project.
����������������7!�����������!���������(��
130 Dufferin Avenue, Suite 1400, London, Ontario, N6A 5R2 – Phone 519-438-6192 – Fax 519-672-8209
Geometry
In addition to the flow file, UTRCA provided Dillon with a geometry file. The model extends from approximately 450 m downstream of the Hamilton Road Bridge, to approximately 660 m upstream of the railway crossing. Together, these files formed the basis for the analysis of the recommended bridge configuration.
A topographic survey of Gore Road Bridge and Pottersburg Creek, in the vicinity of the bridge, was completed in October 2012. A review of the geometry file was completed and compared to the survey data.
� The Gore Road Bridge bounding sections and ineffective flow areas were not placed according to HEC-RAS convention. This is likely due to the conversion of the original model from HEC-2 to HEC-RAS
� The width of the bridge opening in the model was found to be approximately 22.5 m and the surveyed width is approximately 9.15 m
� The low point of the bridge soffit in the model is 246.40 m, both upstream and downstream, but was surveyed to be 246.26 m at the upstream face and 246.21 m at the downstream face.
The topographic survey data was used to revise the bounding sections and coding of the bridge in the HEC-RAS model. Figures 3 and 4 illustrate the bridge sections in the original geometry file provided by UTRCA and the revised sections based on the survey data respectively.
����������������7!�����������!���������'��
130 Dufferin Avenue, Suite 1400, London, Ontario, N6A 5R2 – Phone 519-438-6192 – Fax 519-672-8209
Figure 3: Original Geometry File Gore Road Bridge Sections
Figure 4: Revised Geometry File Gore Road Bridge Sections
����������������7!�����������!���������8��
130 Dufferin Avenue, Suite 1400, London, Ontario, N6A 5R2 – Phone 519-438-6192 – Fax 519-672-8209
SUMMARY OF EXISTING CONDITIONS
Figure 5 shows the downstream face of the existing bridge from the east side of the structure, looking in a westerly direction.
Figure 5: Existing Gore Road Structure (Downstream Face)
����������������7!�����������!���������9��
130 Dufferin Avenue, Suite 1400, London, Ontario, N6A 5R2 – Phone 519-438-6192 – Fax 519-672-8209
Figure 6 shows the upstream face of the existing bridge, from the east side of the structure, looking in a westerly direction.
Figure 6: Existing Gore Road Structure (Upstream Face)
����������������7!�����������!���������:��
130 Dufferin Avenue, Suite 1400, London, Ontario, N6A 5R2 – Phone 519-438-6192 – Fax 519-672-8209
Figure 7 illustrates the configuration of the channel and floodplain immediately downstream of the existing bridge. The banks of the channel are well vegetated and generally in a stable condition. The figure captures the water levels observed on May 22, 2012.
Figure 7: Channel Immediately Downstream of Existing Bridge
����������������7!�����������!���������$#��
130 Dufferin Avenue, Suite 1400, London, Ontario, N6A 5R2 – Phone 519-438-6192 – Fax 519-672-8209
Table 3 summarizes the water surface elevations (WSEL) and channel velocities immediately upstream and downstream of Gore Road Bridge, calculated by the revised existing conditions HEC-RAS model for the 100-year return period event peak flow.
Table 3: Existing Conditions Water Surface Elevations Cross-Section ID Peak Flow
(m3/s) WSEL (m)
1.62 73.00 249.791.59 73.00 249.611.47 73.00 249.141.24 73.00 247.641.12 73.00 247.571.01 73.00 247.210.92 73.00 247.230.79 89.60 247.240.77 89.60 246.82
0.7665 Existing Gore Road Bridge 0.763 89.60 245.610.76 89.60 245.700.72 89.60 244.920.61 89.60 245.210.50 89.60 245.170.46 89.60 245.15
As discussed previously, the upstream and downstream soffit elevations are 246.26 m and 246.21 m, respectively. The hydraulic analysis suggests that the existing structure is hydraulically inadequate considering the design criteria for clearance summarized in Table 1.
SUMMARY OF RECOMMENDED PRELIMINARY DESIGN OPTION
As part of the preliminary design process, several crossing alternatives were examined. The crossing alternatives were developed to comply with the hydraulic design criteria summarized in Table 1. Although several different structure alternatives were examined, each of the alternatives was similar in terms of general layout and configuration. Each alternative maintained or increased the hydraulic opening of the bridge compared to existing conditions in order to achieve the required clearance from the design high water level to the underside of the new structure. All of the alternatives also required modifications to the approach grades on Gore Road in order to
����������������7!�����������!���������$$��
130 Dufferin Avenue, Suite 1400, London, Ontario, N6A 5R2 – Phone 519-438-6192 – Fax 519-672-8209
achieve minimum clearance, or improve existing deficiencies relating to the design criteria for the roadway.
Each alternative took into consideration the future widening of the roadway, the structure’s ability to be widened to accommodate those lanes in several stages, potential environmental impacts to Pottersburg Creek and the structure’s ability to convey the 250-year return period event peak flow without adversely impacting private lands and public infrastructure. Although conveyance of the 250-year return period event peak flow is not included in the base design criteria for the structure, it was a consideration for future conditions. The proposed structure has a soffit elevation which is approximately 0.89 m higher than the existing bridge soffit elevation, and will provide 1.0 m of vertical clearance to the proposed 100-year return period event WSEL.
The recommended preliminary design alternative addresses the hydraulic deficiencies of the existing structure through improvements to the roadway profile and the raising of the soffit elevation of the new bridge. Table 4 summarizes the calculated WSEL and channel velocities immediately upstream and downstream of Gore Road Bridge for the 100-year return period event peak flow.
Table 4: Proposed Conditions Water Surface Elevations Cross-Section ID Existing WSEL
(m) Proposed WSEL
(m) Change in WSEL
(m) 1.62 249.79 249.79 0.001.59 249.61 249.61 0.001.47 249.14 249.14 0.001.24 247.65 247.65 0.001.12 247.57 247.59 +0.021.01 247.21 246.86 -0.350.92 247.23 246.27 -0.960.79 247.24 246.23 -1.020.772 246.82 245.76 -1.060.77 N/A
0.7665 N/A0.763 245.61 245.72 0.000.76 245.70 245.70 0.000.72 244.92 244.92 0.000.61 245.21 245.21 0.000.50 245.17 245.17 0.000.46 245.15 245.15 0.00
����������������7!�����������!���������$"��
130 Dufferin Avenue, Suite 1400, London, Ontario, N6A 5R2 – Phone 519-438-6192 – Fax 519-672-8209
Table 4 illustrates that the calculated WSEL are similar downstream of the existing and proposed structures, and upstream of Gore Road at cross-sections beyond the influence of the hydraulic opening. Cross-sections 0.7665 and 0.772 represent the existing and proposed bridge structures respectively, and the 0.02 m increase in WSEL at cross-section 1.12 can be attributed to the geometry changes in the downstream cross-sections up to the bridge, such as channel slope and reach lengths (no changes were made to the geometry upstream of cross-section 1.12).
A freeboard in excess of 1.0 m will be provided for the proposed structure, and 100-year return period event WESL are not adversely impacted. During detailed design, vertical clearance requirements will be confirmed in conjunction with incorporating the hydrologic and hydraulic updates from the Pottersburg Creek Subwatershed Study Update.
DILLON CONSULTING LIMITED LONDON, ONTARIO
���___________________________ _________________________ Hanna Ibrahim, C.E.T. Brian Huston, P.Eng Partner
Proposal forReview and Analysis of "RiskManagement Measures" for LiquidE f f l u e n t s , S t o r m wa t e r a n dTransportation and ConstructedPathways
Request for Proposals No.: SWP20070002
January 2007
Ontario Ministry of the Environment
Submitted by
Dillon ConsultingLimited
50-2800-6100
ment Measures” for Liquid Effluents, Storm Water, and Transportation and Constructed Pathways Final Draft Report June 8, 2007
Gore Road Bridge over Pottersburg Creek (No. 4-BR-15) – Bridge Replacement
Preliminary Structural Design Report (Final) ��!�"#$%�������������������� ��!��*��������12-6524��;�.������.!��Dillon ConsultingLimited
��!��*���������������������������������.���� ���6����������,�������������������!�;�������������������,�������������
�������� ������������������� ��!�"#$%�����������<�0�$"&'(")� �������
TABLE OF CONTENTS Page
1.0� INTRODUCTION ...............................................................................................................1�
2.0� PROJECT LOCATION .......................................................................................................1�
3.0� AVAILABLE INFORMATION ..........................................................................................1�
4.0� EXISTING STRUCTURE ...................................................................................................2�4.1� Structure ................................................................................................................2�4.2� Maintenance and Repair History ..........................................................................2�4.3� Condition of Structure ..........................................................................................2�4.4� Geometrics ............................................................................................................2�4.5� Traffic ...................................................................................................................2�4.6� Municipal Services ...............................................................................................3�4.7� Utilities ..................................................................................................................3�
5.0� EVALUATION OF ALTERNATIVES ...............................................................................4�5.1� Do Nothing, Closure or Rehabilitation Alternatives ............................................4�5.2� Replacement Alternatives .....................................................................................5�5.3� Recommended Alternative ....................................................................................6�
6.0� FOUNDATIONS .................................................................................................................7�
7.0� PROPOSED REPLACEMENT ...........................................................................................7�7.1� General ..................................................................................................................7�7.2� Hydraulic Opening ................................................................................................7�7.3� Cross-section .........................................................................................................7�7.4� Deck ......................................................................................................................8�7.5� Girders ..................................................................................................................8�7.6� Barrier System ......................................................................................................8�7.7� Abutments .............................................................................................................9�7.8� Bearings ................................................................................................................9�7.9� Slope Protection ....................................................................................................9�7.10� Approaches ...........................................................................................................9�7.11� Deck Drainage ......................................................................................................9�7.12� Corrosion Protection ...........................................................................................10�7.13� Accelerated Bridge Construction ........................................................................10�
8.0� CONSTRUCTION STAGING ..........................................................................................10�
9.0� MISCELLANEOUS ..........................................................................................................11�9.1� Design Code ........................................................................................................11�9.2� Access to Site ......................................................................................................11�9.3� Utilities ................................................................................................................11�9.4� Entrances and Intersections ................................................................................11�9.5� Environmental Considerations ............................................................................12�9.6� Heritage Evaluation ............................................................................................12�9.7� Illumination .........................................................................................................12
��!��*���������������������������������.���� ���6����������,�������������������!�;�������������������,�������������
�������� ������������������� ��!�"#$%�����������<�0�$"&'(")� ��������
Page9.8� Property ...............................................................................................................12�9.9� Survey .................................................................................................................12�9.10� Aesthetics ............................................................................................................12�
10.0� SUMMARY AND RECOMMENDATIONS ....................................................................13�
LIST OF TABLES
Table 1: Bridge Alternatives Analysis Summary ........................................................................... 6�Table 2: Cross-Section Alternatives ............................................................................................... 8�Table 3: Types of Reinforcing Steel in Structure ......................................................................... 10�
LIST OF APPENDICES
Appendix A Alternatives Analysis Table Appendix B Preliminary General Arrangement Drawing Appendix C Preliminary Construction Cost Estimate Appendix D Existing Water and Sewer Drawings
��!��*���������������������������������.���� ���6��<�0�)&�&$(�����������,�������������������!�;�������������������,�������������
�������� ������������������� ��!�"#$%�����������<�0�$"&'(")� �����$�
1.0 INTRODUCTION
This report addresses the structural design for the replacement of Gore Road Bridge(Bridge Inventory No. 4-BR-15). It is our understanding the bridge replacement is required due to its age and condition.
2.0 PROJECT LOCATION
Gore Road Bridge, over Pottersburg Creek, (Bridge Inventory No. 4-BR-15) is located within theCity of London, on Gore Road east of Hamilton Road with Montebello Drive to the west and Braesyde Avenue to the east.
3.0 AVAILABLE INFORMATION
The following reference documents are available: � 2011 Biannual Inspection Report, Bridge Inventory No. 4-BR-15, January 2, 2012 � Existing water and sewer drawings (see Appendix D)� Pedestrian count data (email from Mark Ridley to Jane Fullick of July 3, 2012) � “Heritage Impact Assessment: Gore Road Bridge Replacement”, Archaeological Services
Inc., 12EA-156, December 2012 � “Geotechnical Investigation, Gore Road Bridge Replacement”, 12-1132-0091-R01, Golder
Associates, November 2012 � Traffic data for Gore Road at Firestone Boulevard (2006) and Hamilton Road (2009), City of
London� Analytical Testing, Gore Road Bridge Replacement”, 12-1132-0091-L01, Golder Associates,
April 2012 � Hydro One conductor elevations and clearance criteria (email, January 31, 2013) � Upper Thames River Conservation Authority (UTRCA) Fill and Flood Line Mapping,
Sheet No. 85-58, 1991 � UTRCA hydraulic data.
The original construction drawings for the existing bridge are not available.
��!��*���������������������������������.���� ���6��<�0�)&�&$(�����������,�������������������!�;�������������������,�������������
�������� ������������������� ��!�"#$%�����������<�0�$"&'(")� �����"�
4.0 EXISTING STRUCTURE
4.1 Structure
Gore Road Bridge is a single span, cast-in-place reinforced concrete tee bridge, constructed in 1940. The bridge spans approximately 14 m with a skew angle of approximately 50 degrees, providing a clear opening perpendicular to the abutments of 9.15 m. The overall width of the bridge is approximately 9.5 m with concrete parapets on each side. A cantilevered wooden sidewalk was constructed along the north side of the bridge and replaced in 2008. The total depth of the structure is approximately 1.1 m.
4.2 Maintenance and Repair History
Since the original bridge construction, we are not aware of any significant maintenance or repairs, aside from the construction and replacement of the wooden sidewalk structure.
Minor maintenance and repairs include the installation of the guide rail, temporary concrete barriers at the southwest approach, frequent repairs to slope protection, sandblasting and painting.
4.3 Condition of Structure
Assessment of the existing structure was not included in the scope of work. A biannual visual inspection in accordance with the Ontario Structural Inspection Manual was completed for the City in 2011. The inspection identified a need for bridge replacement within the next five to ten years.
4.4 Geometrics
Gore Road Bridge carries one lane of traffic in each direction over Pottersburg Creek. The bridge is located on a straight roadway alignment, with a sagging vertical curve between Montebello Drive and Braesyde Avenue.
4.5 Traffic
Gore Road is currently designated as an arterial roadway in Schedule ‘C’ of the City’s Official Plan with an annual average daily traffic (AADT) of 13,000 vehicles per day. Approximately 8% trucks were observed during a traffic count in 2006. The posted speed for this section of Gore Road is 50 km/h.
��!��*���������������������������������.���� ���6��<�0�)&�&$(�����������,�������������������!�;�������������������,�������������
�������� ������������������� ��!�"#$%�����������<�0�$"&'(")� �����%�
Based on the City’s Bicycle Master Plan, the roadway is also designated as a secondary commuter route. Gore Road is a designated transit route used by London Transit Commission.
4.6 Municipal Services
There is a sanitary sewer siphon running below the creek, located south of the bridge and parallel to the road. Access to the manholes at each end of the siphon, and avoidance of conflict between the bridge footings and the siphon, are constraints to the replacement bridge configuration and location.
A buried watermain runs parallel to the roadway, crossing below the creek. Tentative plans include the abandonment of the watermain and replacement with an insulated watermain hung from the replacement bridge.
There is a storm sewer system with an outfall to the creek at the west bank of the river upstream of the bridge. A new storm sewer system is being considered for the replacement configuration, requiring a new outfall upstream of the bridge, on the east bank of the river.
4.7 Utilities
There is a Hydro One electrical transmission line running parallel to Gore Road along the north side of the road and crossing to the south side of the road, as the line approaches Montebello Drive to the west. Three transmission towers are located within the proposed project limits, and the tower bases are not encroached by the roadway embankment. Hydro One completed field measurements of the existing conductor locations in January 2013, and calculated maximum sag for the purpose of establishing clearance limits for the conductor spans in the area. Based on these calculations, raising the profile will not encroach into the conductor vertical clearances in the final condition.
During construction, a clearance of 3.0 m must be maintained from each conductor in any direction. Due to planned road alignment and widening at the bridge, it is anticipated that the use of cranes to erect the facia girder(s) at the north side of the bridge will not be practical. Two options exist. One option is to de-energize the nearest conductor for a short duration to allow cranes to encroach into the zone. The other option is to erect the facia girders near the centreline of the bridge and use low-clearance equipment to move the girders into position using several short lifts, or to slide the girders into position.
There is also a London Hydro distribution line running along the south side of Gore Road. A few poles in the vicinity of the bridge will have to be relocated to accommodate the wider roadway
��!��*���������������������������������.���� ���6��<�0�)&�&$(�����������,�������������������!�;�������������������,�������������
�������� ������������������� ��!�"#$%�����������<�0�$"&'(")� �����)�
cross-section and embankments. The relocations will also affect Rogers Cable and Bell Canada utilities mounted on the poles.
5.0 EVALUATION OF ALTERNATIVES
5.1 Do Nothing, Closure or Rehabilitation Alternatives
Based on the condition and age of the existing structure, a “do nothing” alternative is not recommended for the following reasons:
� Permanent closure of the bridge within five to ten years is likely � Closure at the bridge would increase traffic on Hamilton Road, Clarke Road and potentially
within the local neighbourhoods � Bridge is used by approximately 4400 vehicles per day � Bridge is used by approximately 100 pedestrians per day � Closure would require significant out-of-the-way travel for pedestrians � Transit routes would be affected.
Rehabilitation of the bridge is not recommended for the following reasons: � Bridge is 73 years old, near the end of its useful life and has significant deterioration � Cost to rehabilitate is about 60 to75% of replacement cost, adding approximately 20% of the
service life of a replacement bridge � Drawings not available, adding risk and uncertainty that rehabilitation will meet all safety
and performance criteria � Risk of significant cost increase during rehabilitation due to unknown condition of buried
components � Does not address deficient bridge opening for water flows on Pottersburg Creek � Difficult and expensive to address steep side slopes, with a history of failure, without
significant reconstruction � Wood sidewalk has on-going maintenance costs � No improvement of roadway geometrics/roadside safety.
Based on the City’s Official Plan, Gore Road is an arterial road that serves a significant role in the community, making permanent closure an impractical alternative. Therefore, a replacement bridge will be required.
��!��*���������������������������������.���� ���6��<�0�)&�&$(�����������,�������������������!�;�������������������,�������������
�������� ������������������� ��!�"#$%�����������<�0�$"&'(")� �����(�
5.2 Replacement Alternatives
Several replacement alternatives were considered, addressing the structure configuration and the structure type. In all cases, a single span bridge replacement was considered. Due to navigability and flow requirements, the use of culverts was not considered.
The large skew angle of the crossing was a significant factor in the design. The skew angle of the existing bridge is estimated at 50 degrees. Since the creek is generally curved in the vicinity of the bridge, the skew angle for the replacement bridge was able to be reduced to approximately 39 degrees, which remains significant.
The span length included an allowance for a future trail passing under the bridge on the west side. The trail would be 3.0 m wide plus a 1.0 m allowance for a retaining wall system.
Refer to Appendix A for a structure alternatives comparison summary table.
Superstructure Types The following superstructure types were considered:
� A concrete rigid frame was considered due to its low maintenance characteristics and relatively shallow structure depth, reducing the amount of profile raise required. However, the span of the bridge exceeds the normal limits for this type of bridge and the construction would require extensive temporary in-water work
� A large buried structure (similar to an oversized culvert) comprising a span of concrete box girders was considered, with an aim to eliminate the skew of the bridge. However, conflict with the siphon, cost considerations and abutment type limitations eliminated this option
� A slab-on-girder bridge was considered since it avoids temporary work in the water for construction of the superstructure. It can accommodate longer spans and is a very conventional and cost-effective bridge type. Both concrete and steel girders are feasible for the site. Steel girders are recommended, since the girder depth (and roadway profile raise) can be reduced and the lighter girder weight may assist in erection below the transmission line on the north side.
��!��*���������������������������������.���� ���6��<�0�)&�&$(�����������,�������������������!�;�������������������,�������������
�������� ������������������� ��!�"#$%�����������<�0�$"&'(")� �����'�
Table 1: Bridge Alternatives Analysis Summary
Rigid Frame Bridge Slab-on Girder Bridge (Recommended) Pros � Shallow superstructure depth
means less change in roadway profile
� Durable, jointless, low-maintenance design
� Accommodates high skew�
� Longer spans possible � No falsework in the water � Faster construction � Steel and concrete girders possible � Semi-integral abutment is lower
maintenance than jointed bridge � Accommodates many skews
Cons � Span limitations � Falsework in the water during
construction� Slower construction duration
� Deeper bridge than rigid frame
A slab-on-girder bridge using steel girders is recommended.
Abutments Current design standards encourage the elimination or reduction of expansion joints where possible, to reduce maintenance costs arising from joint replacements and damage caused by leaking joints.
Soil conditions at this site are not well suited to the use of an integral abutment bridge because the soil is too firm to install piles without significant risk of problems in the field. Pre-augering of holes for the pile installation was considered, but the augering procedure also had significant risks that could make construction problematic.
It is important to note the soil bearing capacity is well suited to using spread footings with semi-integral abutments. Semi-integral abutments do not have deck expansion joints, which is the primary maintenance item found on traditional abutments.
Semi-integral abutments on spread footings are recommended.
5.3 Recommended Alternative
The recommended replacement approach is a single span bridge with a concrete deck on steel girders supported by a semi-integral abutment on spread footings.
��!��*���������������������������������.���� ���6��<�0�)&�&$(�����������,�������������������!�;�������������������,�������������
�������� ������������������� ��!�"#$%�����������<�0�$"&'(")� �����8�
6.0 FOUNDATIONS
The foundation alternatives considered were based on the following report: � “Geotechnical Investigation, Gore Road Bridge Replacement”, 12-1132-0091-R01, Golder
Associates, November 2012.
7.0 PROPOSED REPLACEMENT
This section presents a description of the proposed replacement superstructure, with discussion of alternatives that may be considered to accelerate construction.
7.1 General
The recommended replacement approach is a single span bridge with a concrete deck on steel girders, supported by a semi-integral abutment on spread footings.
7.2 Hydraulic Opening
A hydraulic and hydrology study has been undertaken by Dillon for this project and is addressed in a separate technical memo. To meet the Canadian Highway Bridge Design Code (CHBDC), the soffit of the bridge must be a minimum of 1.0 m above the 1:100 year high water level. In addition, navigable clearance measured relative to the normal water level must also be achieved, based on a review by Transport Canada. At Gore Road Bridge, the high water clearance is the governing constraint, and thus the soffit of the bridge was set at EL 247.1 m or higher.
The width of the bridge opening is larger than the existing bridge based on the use of an open abutment style on the east end (i.e., use of a foreslope versus a vertical wall) and the addition of the pathway on the west end. These changes serve to increase the hydraulic opening significantly compared to the previous opening which was deficient.
An update to the Pottersburg Subwatershed Study is underway and is anticipated to be released in the summer of 2013. Results of this update should be incorporated into the model used for the final design of the bridge and adjustments made accordingly.
7.3 Cross-Section
The roadway portion of the cross-section of the new bridge will accommodate a 13 m wide roadway surface to allow for several potential future lane configurations, as shown in Table 2 below.
��!��*���������������������������������.���� ���6��<�0�)&�&$(�����������,�������������������!�;�������������������,�������������
�������� ������������������� ��!�"#$%�����������<�0�$"&'(")� �����9�
Table 2: Cross-Section Alternatives
Existing Configuration Proposed Configuration Future Configuration
Wood sidewalk Barrier-----0.5 m west bound shoulder 3.5 m west bound lane -----3.5 m east bound lane 0.5 m east bound shoulder -----Barrier
-----Barrier2.0 m west bound sidewalk 2.0 m west bound bike lane/shoulder4.5 m west bound lane -----4.5 m east bound lane 2.0 m east bound bike lane/shoulder2.0 m east bound sidewalk Barrier
-----Barrier2.0 m west bound sidewalk 1.5 m west bound bike lane/shoulder3.5 m west bound lane 3.0 m median for turning lane(s) 3.5 m east bound lane 1.5 m east bound bike lane/shoulder2.0 m east bound sidewalk Barrier
Refer to the Preliminary General Arrangement drawing in Appendix B for replacement details.
7.4 Deck
A 225 mm thick cast-in-place concrete deck forms the base case for the replacement design.
7.5 Girders
Steel plate girders or Welded Wide-Flange shapes approximately 1.0 m deep are recommended. Atmospheric Corrosion Resistant Steel is recommended, rather than painting, to reduce maintenance costs.
7.6 Barrier System
The proposed bridge would have PL-1 parapets and single railing.
To enhance aesthetics, we recommend an architectural texture on both sides of the parapet, achieved using form liner panels. An alternative would be to use a 4-box steel railing instead of the parapet and single railing. The railing alternative is more attractive when painted, but has increased maintenance compared with galvanizing or using the concrete parapet.
The parapets could accommodate conduits for future use, if required by the City.
��!��*���������������������������������.���� ���6��<�0�)&�&$(�����������,�������������������!�;�������������������,�������������
�������� ������������������� ��!�"#$%�����������<�0�$"&'(")� �����:�
7.7 Abutments
Refer to the Preliminary General Arrangement drawing in Appendix B for replacement details representing the base case for comparison.
7.8 Bearings
The bridge would have steel laminated elastomeric bearings.
7.9 Slope Protection
The abutment for slopes and side slopes will require riprap to prevent scour.
Retaining Walls A retaining wall will be required at the southwest corner of the bridge, to accommodate the manholes in the area for the sanitary sewer siphon. It is recommended that this retaining wall be constructed separately from the bridge to allow future alterations as needed.
For the case of a trail passing under the bridge, a small retaining wall along the west shore line would be required. It is recommended that this be constructed with the bridge to simplify future works since access will be easier before the superstructure is constructed, and this work could be included in the regulatory submissions for the bridge replacement. It is anticipated that the incremental cost of constructing this wall with the bridge would be lower than constructing it at a later date.
The northwest corner slope would also require a retaining wall to accommodate a future trail and it is recommended that this be completed at the time of the bridge construction to reduce future excavations near the bridge, throwaway costs due to rework in the area and potential regulatory permits for work near the creek.
7.10 Approaches
Approach slabs constructed on cast-in-place concrete measuring 6.0 m long are recommended.
7.11 Deck Drainage
Based on the length of structure, vertical profile and roadway cross fall, deck drains will not be required.
��!��*���������������������������������.���� ���6��<�0�)&�&$(�����������,�������������������!�;�������������������,�������������
�������� ������������������� ��!�"#$%�����������<�0�$"&'(")� �����$#�
7.12 Corrosion Protection
The recommended types of reinforcing steel for the structure are summarized in Table 3.
Table 3: Types of Reinforcing Steel in Structure
Locations Black Stainless Glass Fibre Reinforced Polymer
Abutments – front, side and back faces Yes --- ---Abutments – ballast walls and bearing seats --- Yes ---Wingwalls – outside face Yes --- ---Wingwalls – inside face within top 500 mm --- Yes ---Wingwalls – other Yes --- ---Approach slabs – bottom Yes --- ---Approach slabs – other --- Yes ---Footings Yes --- ---Deck – typical --- --- YesDeck – at semi-integral abutment details --- Yes ---Barriers --- --- YesCurbs and sidewalks – high abrasion areas --- Yes ---Curbs and sidewalks – other --- --- Yes<���=��>��������3-��������*�������.�����2���������������-���������������+������������������-����.�����0
7.13 Accelerated Bridge Construction
Accelerated Bridge Construction (ABC) approaches could be considered during detailed design. These approaches could include the use of stay-in-place concrete deck forms, full-depth precast concrete deck panels, precast abutment breastwalls with post-tensioning or other techniques. In general, ABC techniques have a cost premium which must be justified against user costs. In this case, the use of ABC techniques is not expected to yield sufficient gains in construction duration to justify the cost premium and the detour routes are relatively short.
8.0 CONSTRUCTION STAGING
Based on the poor condition of the existing bridge and its narrow width, staged construction is not recommended. The bridge must be closed for the entire duration of construction, with detour routes established for the public and transit users.
Pedestrian traffic will be maintained through the limits of the project for the duration. A temporary pedestrian bridge will be installed over Pottersburg Creek, north of the existing bridge and will be maintained until the new bridge is completed.
��!��*���������������������������������.���� ���6��<�0�)&�&$(�����������,�������������������!�;�������������������,�������������
�������� ������������������� ��!�"#$%�����������<�0�$"&'(")� �����$$�
Timing for the removal of the existing abutments, construction of the new retaining walls and abutments will be affected by regulatory limitations for the protection of aquatic species.
9.0 MISCELLANEOUS
9.1 Design Code
The structural design would be carried out in accordance with the CHBDC (CAN/CSA-S6-06), S6S6-10 – Supplement 1 to CAN/CSA-S6-06, S6S2-11 – Supplement 2 to CAN/CSA-S6-06 and City standards. Additional reference will be made to manuals, guides and standards by the Ontario Ministry of Transportation, where appropriate, to assist in the design for the City.
9.2 Access to Site
The site is readily accessible from Gore Road to the east and west.
Provision must be made to accommodate using construction vehicles and cranes near the existing overhead electrical transmission line (to be specified during detailed design).
9.3 Utilities
A new watermain is planned for the replacement bridge, located between girders to protect it from weather and debris flows, and to avoid detracting from the bridge aesthetics.
Embedded utility conduits are possible at this bridge, however none are planned.
9.4 Entrances and Intersections
The intersection with Montebello Drive to the west will not be changed under the proposed project. Limited work will be completed at the intersection with Braesyde Avenue to the east. Two properties to the east of the bridge will require adjustments to the driveway entrances onto Gore Road.
��!��*���������������������������������.���� ���6��<�0�)&�&$(�����������,�������������������!�;�������������������,�������������
�������� ������������������� ��!�"#$%�����������<�0�$"&'(")� �����$"�
9.5 Environmental Considerations
This structural design report is being completed as a component of a Class B Municipal Class Environmental Assessment process. An Environmental Impact Statement is also to be completed in conjunction with this project.
9.6 Heritage Evaluation
A Cultural Heritage Evaluation was completed by Archaeological Services Inc. in 2012.
9.7 Illumination
Existing illumination is mounted on London Hydro poles along the south side of Gore Road. With the proposed road widening, the London Hydro poles will be relocated further south away from Gore Road. Preference for illumination on the proposed new structure and road widening will be to keep the lights mounted on the relocated London Hydro poles, providing they will meet the City of London’s illumination standards for a major road classification. If the required illumination cannot be achieved from mounting the lighting on the utility poles, base mounted street lighting poles and underground lighting service for the limits of the road widening will be provided.
Embedded conduit in the south side of the structure for illumination will also be provided.
Temporary illumination for the pedestrian detour route will be provided for the duration of the construction staging.
9.8 Property
No property acquisition is anticipated for this project.
9.9 Survey
A topographic survey was completed by the City of London in 2012.
9.10 Aesthetics
Based on the design speed of 60 km/h, a PL-1 barrier is required. The proposed bridge would have a two-tube railing system, on a concrete parapet, with an architectural texture achieved using form liner panels.
��!��*���������������������������������.���� ���6��<�0�)&�&$(�����������,�������������������!�;�������������������,�������������
�������� ������������������� ��!�"#$%�����������<�0�$"&'(")� �����$%�
10.0 SUMMARY AND RECOMMENDATIONS
The recommended replacement for the Gore Road Bridge at Pottersburg Creek (Bridge Inventory No. 4-BR-15) is to construct a single-span steel girder bridge on semi-integral abutments.
Our opinion of the probable cost for the construction of the recommended alternative is $1.44 million, plus taxes, for the bridge and temporary pedestrian crossing only, exclusive of municipal road and sewer work, utilities, trails and retaining walls. Costs for design, regulatory approvals, contract administration and contingencies have not been included (Appendix C).
DILLON CONSULTING LIMITED LONDON, ONTARIO
_______________________________Chris Haines, MBA, P.Eng. Structural Engineer
��!
��*��
���
�����
����
�����
����
����������.�
���
���6
��<�0�)&
�&$(
�������
����
,���
����
����
����
����
!�;���
����
����
��������
,������
������
� ������
� ��
�������
����
������ �
�!�"#$
%�����
������<
�0�$"&'(
")�
����
��&$�
Tab
le A
1: S
truc
ture
Alte
rnat
ives
Stru
ctur
e Ty
pe
Rig
id F
ram
e C
PCI g
irde
rs
(120
0 de
ep)
Stee
l Gir
ders
(100
0 de
ep)
Con
cret
e B
ox G
irde
rs(9
00 d
eep)
Pr
efer
red
Alte
rnat
ive
Alte
rnat
ive
1 2
34
--
Subs
truct
ure
Type
R
igid
Fra
me
Sem
i-int
egra
l Abu
tmen
t Se
mi-i
nteg
ral A
butm
ent
Sem
i-int
egra
l Abu
tmen
t --
Sk
ew39
°39
°39
°39
°--
Span
± 23
.6 m
to fa
ce
± 25
m
± 25
m
± 25
m
--St
ruct
ure
dept
h (e
xclu
ding
asp
halt
and
cros
s-fa
ll)
± 1.
3 m
@ a
but f
ace
± 0.
6 m
@ m
idsp
an
± 1.
5 m
±
1.3
m
± 1.
1 m
--
Prof
ile ra
ise
± 1.
56 m
±
1.76
m
± 1.
56 m
±
1.36
m
4N
umbe
r of g
irder
s N
/A8
at 2
.25
m
8 at
2.2
5 m
14
(tip
to ti
p)
--Jo
ints
N
o N
oN
oN
o--
Win
gwal
l typ
e A
ttach
ed
Atta
ched
A
ttach
ed
Atta
ched
--
Po
tent
ial P
CB
Dis
turb
ance
Y
esY
esY
esY
es--
Trai
l Allo
wan
ce
Yes
Yes
Yes
Yes
--Te
mp
Wor
ks in
Wat
erco
urse
Si
gnifi
cant
Min
orM
inor
Min
or2,
3, 4
Tr
ail R
etai
ning
wal
ls re
quire
d Y
esY
esY
esY
es--
M
unic
ipal
Con
flict
s Lo
wLo
wLo
wLo
w--
Tran
smis
sion
Lin
e C
lear
ance
(con
stru
ctab
ility
) Lo
w
Mod
erat
e/H
igh
Low
M
oder
ate
1, 3
Tran
smis
sion
Lin
e C
lear
ance
(ulti
mat
e)
Acc
epta
ble
Acc
epta
ble
Acc
epta
ble
Acc
epta
ble
--
Dec
k A
rea
(m2 )
450
m2
450
m2
450
m2
450
m2
--
Cos
t/m2
$3,7
50/m
2 $2
,750
/m2
$3,0
00/m
2 $3
,500
/m2
--
Estim
ated
Cos
t – b
ridge
$1
.68
mill
ion
$1.2
5 m
illio
n $1
.35
mill
ion
$1.6
0 m
illio
n --
Estim
ated
Cos
t – p
rofil
e ra
ise
(rel
ativ
e)
$0.0
4 m
illio
n $0
.11
mill
ion
$0.0
4 m
illio
n --
---
Estim
ated
Cos
t – re
tain
ing
wal
ls fo
r tra
il
Sam
e Sa
me
Sam
e Sa
me
--
Estim
ated
Cos
t – to
tal
$1.7
2 m
illio
n $1
.36
mill
ion
$1.3
9 m
illio
n $1
.60
mill
ion
2, 3
Ex
tent
of E
xist
ing
Brid
ge R
emov
al
Com
plet
e C
ompl
ete
Com
plet
e C
ompl
ete
--
Flus
her T
ruck
Acc
ess
Acc
epta
ble
Diff
icul
tA
ccep
tabl
eA
ccep
tabl
e 1,
3, 4
W
ater
mai
n m
ount
ing
Side
Bet
wee
n gi
rder
s B
etw
een
gird
ers
Side
2,
3C
onst
ruct
ion
Dur
atio
n Lo
ngA
vera
geA
vera
geA
vera
ge2,
3, 4
3ov
eral
l
<���=�
�����*�
�����
,�����
����
��*����
����������
�,�
����
��*����
-��.���
������
����
����
�!���
�����
�����
���
����
�����
�����+�
������
�������
����
�����
������
����
�����������0�
��!��*��������������������������������.���� ���6��<�0�)&�&$(��&��������,������������������!�;�������������������,�����������
Preliminary Construction Cost Estimate - Bridge
Item TotalCode Estimated Cost
0212-0010 Earth Borrow M3 3500.0 $5.00 $17,5000405-0010 Pipe Subdrains M 50.0 $35.00 $1,7500510-9010 Removal of Bridge Structure LS 1.0 $100,000.00 $100,0000511-0010 Rip Rap M2 1000.0 $45.00 $45,0000902-0010 Earth Excavation for Structure M3 950.0 $30.00 $28,5000902-0030 Unwatering Structure Excavation LS 1.0 $100,000.00 $100,0000904-0050 Concrete in Footings M3 130.0 $500.00 $65,0000904-0085 Concrete in Substructure M3 160.0 $750.00 $120,0000904-0105 Concrete in Deck M3 177.0 $1,200.00 $212,4000904-0125 Concrete in Parapet Walls M3 17.0 $1,775.00 $30,1750904-0135 Concrete in Approach Slabs M3 52.0 $800.00 $41,6000905-0010 Reinforcing Steel Bar T 56.0 $2,000.00 $112,0000905-0020 GFRP and Stainless Reinforcing T 15.0 $3,000.00 $45,0000908-0030 Parapet Wall Railing M 74.0 $105.00 $7,7700909-0031 Fabrication of Structural Steel T 45.0 $4,650.00 $209,2500909-0041 Delivery of Structural Steel T 45.0 $270.00 $12,1500909-0051 Erection of Structural Steel T 45.0 $1,780.00 $80,1000913-0040 Embedded Works in Structure M 45.0 $60.00 $2,7000914-0011 Bridge Deck Waterproofing M2 390.0 $35.00 $13,6500914-0031 Form and Fill Grooves M 70.0 $45.00 $3,1500914-0040 Membrane Reinforcement M 35.0 $70.00 $2,4500922-0010 Bearings EA 14.0 $1,000.00 $14,0000928-0055 Access to Work Area, Work Platform and Scaffolding LS 1.0 $50,000.00 $50,0000999-9100 Concrete Sealer M2 100.0 $55.00 $5,500
PCB Waste (Allowance) LS 1.0 $30,000.00 $30,000Watermain pipe supports and sleeves LS 1.0 $10,000.00 $10,000Temporary Pathway Electrical LS 1.0 $15,000.00 $15,000Temporary Pedestrian Bridge Rental & Delivery LS 1.0 $15,000.00 $15,000Temporary Pedestrian Bridge Erection LS 1.0 $10,000.00 $10,000Temporary Pedestrian Bridge Removal & Shipping LS 1.0 $10,000.00 $10,000Wood gangway & misc. fencing LS 1.0 $12,000.00 $12,000Approach Embankment - fill & removal M3 300.0 $50.00 $15,000
TOTAL (taxes, contingencies, fees additional) $1,436,700
Item Description Unit Quantity Unit Cost
������� �����������������&� ��!�"#$%�&���������<�0�$"&'(") ������ &$��������