Guangzhou-Shenzhen-Hong Kong Express Rail LinkIp Mei Sz, Grace (52222294)Lai Kwok Yiu, Antonio (52221746)Lau Hiu Tung, Winnie (52221377)
![Page 2: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/2.jpg)
Outline
Content of XRL
Civic engagemen
t process
Application of theory Conclusion
![Page 3: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/3.jpg)
Content of XRL
![Page 4: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/4.jpg)
Status quo
•Existed railway system was backward▫Both passenger and goods use the same
railway
•The capacity of existed railway system was not enough▫The amounts of passenger doubling every
ten years since 1988
![Page 5: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/5.jpg)
Aims
•Strengthen the transportation linkage between HK and China
•Further develop position of Hong Kong as a gateway out of the Pearl River Delta
•Achieve a better economic cooperation between the HK and China
•Referenced the success of Europe and Japan▫Construction of XRL as a key factors of
regional development
![Page 6: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/6.jpg)
Other interesting reasons• PRC government announced the 11th five-year
plan▫Mention about the situation of HK▫Emphasized the construction of XRL▫However, the construction did not included HK
• Some professional considered HK would be marginalized▫E.g. Hong Kong Institute of Asia-Pacific Studies
from The Chinese University of Hong Kong• Stimulate the perception of CE
▫Construction of XRL became one of the Ten Major Infrastructure Projects
![Page 7: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/7.jpg)
Detail• Known as Guangshengang XRL• One of the Ten Major Infrastructure Projects by Donald Tsang
Yam-kuen
• 66.9 billion for budget• 26 km for the length of system
• Connection▫ Kowloon, Hong Kong in the south▫ Panyu, Guangzhou, Guangdong in the north
• Top speed▫ Guangshen section: 350 km/h (220 mph)▫ Hong Kong section: 200 km/h (120 mph)
![Page 8: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/8.jpg)
Benefits
•Reduce the travel time▫Journey time from HK to Guangzhou
reduced from 100 minutes to 48 minutes▫Only 10 hours for going Beijing
•Inspire the economic activities near the station or HK further
•Created job opportunities▫5, 500 during construction▫10, 000 in it’s operation
![Page 9: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/9.jpg)
Implement agency
Government MTR
![Page 10: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/10.jpg)
Time table of XRL
2007
•As a item of Ten Major Infrastructure Projects
2008
•Executive Council start to discuss the construction of XRL
•MTR started the consultation
2010
•Legislative Council approve the funding application
•Construction initiation
2015
•Proposed to finish
![Page 11: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/11.jpg)
The votes of XRL
•55 billion in funding XRL Project•11.8 billion in funding in others related to
XRLAgree Disagre
eNo. of votes
31 21
![Page 12: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/12.jpg)
Supporter
•Government•MTR•Business Sector
▫Construction industry▫Tourism▫The property developer
•Functional Constituencies
![Page 13: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/13.jpg)
Reasons of support
•Government▫Benefit to economic development▫Avoid HK to be marginalized▫Match the development of China
•MTR▫Interest group
•Business Sector▫Create job opportunities
•Functional Constituencies▫Reflect the opinion of voters
![Page 14: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/14.jpg)
Pro XRL Activity
•Rally outside the legislative council
•Establish Facebook group
![Page 15: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/15.jpg)
Opponent
•Post 80s•Local residents
▫Choi Yuen Tsuen▫Tai Kok Tsui
•Pan-democratic parties ▫Democratic Party▫Civic Party▫League of Social Democrats
![Page 16: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/16.jpg)
Reason of opposition
•Post 80s▫Not real high speed railway▫Could not benefit the resident of north NT▫The price of the ticket would be too high▫Government rejected the suggestion of the
public▫Lack of public consultation▫Lack of democratic elements
![Page 17: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/17.jpg)
Reason of opposition
•Local residents▫Choi Yuen Tsuen
Unwilling to move Due to sense of belonging
Insuffience indemnification▫Tai Kok Tsui
Fear the construction would influence the structure of building
![Page 18: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/18.jpg)
Reason of opposition
•Pan-democratic parties▫Reflected the opinion of voters▫Too expensive▫Force some people to leave their district▫Not enough consultation▫Lack of planning details
![Page 19: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/19.jpg)
Anti XRL activity
•Demonstration (4 Jan 2010, 15 Jan 2010)•Rally outside the legislative council (8Jan
2010)•Ascetic ( 苦行 ) Start from Monday (4 -7
Jan 2010) •Establish Facebook group
![Page 20: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/20.jpg)
Civic engagement process
![Page 21: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/21.jpg)
4 Stages of Consultation (MTR)
• May – Aug 2008
First stage
• Sept – Nov 2008
Second stage • Dec
2008 –April 2009Third stage
• May – Sept 2009
Forth stage
![Page 22: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/22.jpg)
2 monthsStatutory Consultation
200828 Nov.
200929 Jan
![Page 23: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/23.jpg)
Consultation Meeting (District Council) 2008
![Page 24: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/24.jpg)
Consultation Meeting (District Council) 2009
![Page 25: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/25.jpg)
Application of theory
![Page 26: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/26.jpg)
Distributive (Lowi)
Definition
• Government distribute a good or service to some portion of the population
• Typically paid for through general tax revenues
Application
• The XRL is a service for public
• No specific tax
![Page 27: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/27.jpg)
Five elements of policy design (Birkland)
•Strengthen the linkage between Hong Kong and China
The goals of the policy
•Construction of XRL
•Enhance the competitiveness of Hong Kong
The causal model
•Construction of infrastructure
The tools of the policy
•The public
The targets of the policy
•HK government give the implementation to MTR through service concession agreement
Implementation of the policy
![Page 28: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/28.jpg)
Rationalist model of decision making
•Clear definition of goals▫Refers to the aims of XRL
•Alternatives and consequences▫Location▫Route▫Construction method
•Best solution▫In the government’s stand point
![Page 29: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/29.jpg)
Criticism
•Bounded rationality▫The data provided by government were
only a estimation▫Possible outcomes and alternatives might
be neglected
![Page 30: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/30.jpg)
The Stages Model
Issue emergence• The transportation linkage between HK and China was not strong enough
Agenda setting Alternative selection• Construction method
• Location of station
Enactment• January 2010 approved funding
Implementation• April 2010 construction initiated
Evaluation
![Page 31: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/31.jpg)
Conclusion
![Page 32: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/32.jpg)
Conclusion
•XRL could bring long term benefit to HK•Consensus have not been established
before legislative council approved funding
•Increase of political participation of public
![Page 33: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/33.jpg)
Thank you!!!
![Page 34: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/34.jpg)
Reference• Lowi, T. J. (1972). Four Systems of Policy, Politics,
and Choice. Public Administration Review, 32 (4), 298-310.
• Birkland, T. A. (2005). An Introduction to the Policy process: Theories, Concepts, and Models of Public Policy Making. New York: M.E. Sharpe, Inc.
• Yuen, Y. M., Shen, J. F. & Zhang, L. (2006). China’s 11 th Five-year Plan: Opportunities and Challenges for Hong Kong. Retrieved February 20, 2011 from The Chinese University of Hong Kong, Hong Kong Institute of Asia-Pacific Studies Web site: http://www.bauhinia.org/publications/China11FYP-HK-FR-english.pdf
![Page 35: Guangzhou-Shenzhen-Hong Kong Express Rail Link](https://reader035.vdocuments.pub/reader035/viewer/2022062308/55894aa0d8b42a4b648b46ed/html5/thumbnails/35.jpg)
Reference
•朱凱迪 (2009). 行政主導釋義 ( 廣深港高鐵及石崗菜園村系列 ). Retrieved February 26, 2011 from, Web site: http://www.inmediahk.net/node/1002679
•朱凱迪 (2009). 仲衰過假諮詢 ( 廣深港高鐵與石崗菜園村系列 ). Retrieved February 4, 2011 from, Web site: http://www.inmediahk.net/node/1002532