DAFTAR HARGA SATUAN PEKERJAAN TRIWULAN II TAHUN 2012 1 DAFTAR HARGA SATUAN BAHAN DAN UPAH KABUPATEN GRESIK TAHUN ANGGARAN 2012 ( TRIWULAN II ) WILAYAH GRESIK TENGAH/KOTA NO NAMA BAHAN SATUAN HARGA SATUAN TERENDAH TERTINGGI 1 2 3 4 5 1 BAHAN PASIR : a. Pasir Urug M3 160,000 180,000 b. Pasir Cor/Pasang M3 180,000 300,000 c. Sirtu M3 140,000 160,000 2 BAHAN TANAH : a. Tanah Urug M3 60,000 70,000 b. Pedel M3 110,000 135,000 3 BAHAN BATU : a. Batu Karang 10/15, 15/20 M3 115,000 125,000 b. Batu Belah 10/15, 15/20 M3 120,000 130,000 c. Batu Pecah 5/7 M3 130,000 140,000 d. Batu Pecah 3/5 M3 140,000 160,000 e. Batu Pecah 2/3 M3 200,000 225,000 f. Batu Pecah 1/2 M3 225,000 375,000 g. Batu Pecah 1/1 M3 225,000 250,000 h. Batu Pecah 0.5/0.5 M3 140,000 160,000 4 BAHAN BATU BUATAN : a. Batu Bata Merah Klas I Buah 600 700 b. Batu Bata Merah Klas II Buah 500 600 c. Batu Bata Putih (Bt. Juring) Buah 1,400 1,500 d. Batu Umpak ( 30 x 30 ) Buah 7,000 8,000 e. Paving Stone : K175 ==> - tebal 6 cm Polos M2 47,000 50,000 - tebal 8 cm Polos M2 55,000 60,000 - tebal 6 cm Warna M2 65,000 70,000 - tebal 8 cm Warna M2 73,000 76,000 K300 ==> - tebal 6 cm Polos M2 45,000 53,000 - tebal 8 cm Polos M2 55,000 61,533 - tebal 6 cm Warna M2 57,000 77,830 - tebal 8 cm Warna M2 69,000 87,633 K350 ==> - tebal 6 cm Polos M2 45,000 53,000 - tebal 8 cm Polos M2 54,000 60,000 - tebal 6 cm Warna M2 56,000 72,000 - tebal 8 cm Warna M2 68,000 72,000 K400 ==> - tebal 6 cm Polos M2 48,000 57,000 - tebal 8 cm Polos M2 61,000 67,000 - tebal 6 cm Warna M2 62,000 69,000 - tebal 8 cm Warna M2 74,000 80,000 K500 ==> - tebal 8 cm Polos M2 78,000 91,676 f. Uskup K300 ==> - tebal 6 cm Polos M2 2,600 3,000 - tebal 8 cm Polos M2 3,000 3,500 - tebal 6 cm Warna M2 3,000 3,500 - tebal 8 cm Warna M2 3,500 4,000 K350 ==> - tebal 6 cm Polos M2 2,800 3,400 - tebal 8 cm Polos M2 3,300 3,800 - tebal 6 cm Warna M2 3,200 3,700 - tebal 8 cm Warna M2 3,800 4,200 K400 ==> - tebal 6 cm Polos M2 3,000 3,500 - tebal 8 cm Polos M2 3,600 4,100 - tebal 6 cm Warna M2 3,400 3,900 - tebal 8 cm Warna M2 4,100 4,600 K500 ==> - tebal 8 cm Polos M2 g. Paving Block

Upload: caroline-gordon

Post on 29-Oct-2014

457 views

Category:

Documents


2 download

DESCRIPTION

Daftar Harga Satuan Gresik Kota

TRANSCRIPT

Page 1: Harga Satuan

DAFTAR HARGA SATUAN PEKERJAAN TRIWULAN II TAHUN 2012 1

DAFTAR HARGA SATUAN BAHAN DAN UPAH

KABUPATEN GRESIK TAHUN ANGGARAN 2012

( TRIWULAN II )

WILAYAH GRESIK TENGAH/KOTA

NO NAMA BAHAN SATUAN HARGA SATUAN KET

TERENDAH TERTINGGI

1 2 3 4 5 6

1 BAHAN PASIR :

a. Pasir Urug M3 160,000 180,000

b. Pasir Cor/Pasang M3 180,000 300,000

c. Sirtu M3 140,000 160,000

2 BAHAN TANAH :

a. Tanah Urug M3 60,000 70,000

b. Pedel M3 110,000 135,000

3 BAHAN BATU :

a. Batu Karang 10/15, 15/20 M3 115,000 125,000

b. Batu Belah 10/15, 15/20 M3 120,000 130,000

c. Batu Pecah 5/7 M3 130,000 140,000

d. Batu Pecah 3/5 M3 140,000 160,000

e. Batu Pecah 2/3 M3 200,000 225,000

f. Batu Pecah 1/2 M3 225,000 375,000

g. Batu Pecah 1/1 M3 225,000 250,000

h. Batu Pecah 0.5/0.5 M3 140,000 160,000

4 BAHAN BATU BUATAN :

a. Batu Bata Merah Klas I Buah 600 700

b. Batu Bata Merah Klas II Buah 500 600

c. Batu Bata Putih (Bt. Juring) Buah 1,400 1,500

d. Batu Umpak ( 30 x 30 ) Buah 7,000 8,000

e. Paving Stone :

K175 ==> - tebal 6 cm Polos M2 47,000 50,000

- tebal 8 cm Polos M2 55,000 60,000

- tebal 6 cm Warna M2 65,000 70,000

- tebal 8 cm Warna M2 73,000 76,000

K300 ==> - tebal 6 cm Polos M2 45,000 53,000

- tebal 8 cm Polos M2 55,000 61,533

- tebal 6 cm Warna M2 57,000 77,830

- tebal 8 cm Warna M2 69,000 87,633

K350 ==> - tebal 6 cm Polos M2 45,000 53,000

- tebal 8 cm Polos M2 54,000 60,000

- tebal 6 cm Warna M2 56,000 72,000

- tebal 8 cm Warna M2 68,000 72,000

K400 ==> - tebal 6 cm Polos M2 48,000 57,000

- tebal 8 cm Polos M2 61,000 67,000

- tebal 6 cm Warna M2 62,000 69,000

- tebal 8 cm Warna M2 74,000 80,000

K500 ==> - tebal 8 cm Polos M2 78,000 91,676

f. Uskup

K300 ==> - tebal 6 cm Polos M2 2,600 3,000

- tebal 8 cm Polos M2 3,000 3,500

- tebal 6 cm Warna M2 3,000 3,500

- tebal 8 cm Warna M2 3,500 4,000

K350 ==> - tebal 6 cm Polos M2 2,800 3,400

- tebal 8 cm Polos M2 3,300 3,800

- tebal 6 cm Warna M2 3,200 3,700

- tebal 8 cm Warna M2 3,800 4,200

K400 ==> - tebal 6 cm Polos M2 3,000 3,500

- tebal 8 cm Polos M2 3,600 4,100

- tebal 6 cm Warna M2 3,400 3,900

- tebal 8 cm Warna M2 4,100 4,600

K500 ==> - tebal 8 cm Polos M2

g. Paving Block

Page 2: Harga Satuan

DAFTAR HARGA SATUAN PEKERJAAN TRIWULAN II TAHUN 2012 2

NO NAMA BAHAN SATUAN HARGA SATUAN KET

TERENDAH TERTINGGI

1 2 3 4 5 6

K300 ==> - Inter block 4.6 Polos M2 48,500 51,000

- Inter block 4.8 Polos M2 61,900 64,000

- Inter block 4.6 warna M2 63,950 68,000

- Inter block 4.8 warna M2 61,750 86,000

K400 ==> - Inter block 4.6 Polos M2 52,000 57,000

- Inter block 4.8 Polos M2 66,600 70,000

- Inter block 4.6 warna M2 63,950 69,000

- Inter block 4.8 warna M2 81,750 88,000

- Corso 20.20.6 polos M2 57,825 64,000

- Corso 20.20.8 polos M2 82,575 89,000

- Corso 20.20.6 warna M2 74,625 80,000

- Corso 20.20.8 warna M2 106,375 110,000

- Dalles siera 50.50.6 polos M2 63,500 70,000

- Dalles siera 50.50.6 warna M2 82,500 89,000

- Segmento polos M2 85,700 92,000

- Segmento warna M2 110,550 125,000

h. Batako Buah 2,900 3,750

g. Kanstine :

- Uk : 10 x 20 x 40 Buah 7,000 33,500

- Uk : 15 x 25 x 40 Buah 17,500 50,700

- Uk : 15 x 30 x 50 Buah 20,000 59,400

- Uk : 18 x 30 x 60 Buah 25,000 38,000

- NK Uk : 18 x 21 x 30 x 50 Buah 75,000 79,000

- IV 20 Buah 39,000 49,000

- BDC M 21X5 Buah 37,000 43,000

- BDC 31X5 Buah 58,000 68,000

h. Roster : * Natural / polos Buah 12,000 13,000

* Warna Buah 12,500 15,000

5 BAHAN SEMEN/PC :

a. Semen/PC 40 Kg (SG) Zak 48,500 49,500

b. Semen/PC 50 Kg (SG) Zak 60,000 62,000

c. Semen/PC 40 Kg (holcim) Zak 45,000 46,000

d. Semen Putih Zak 70,000 75,000

e. Semen Warna Kg 10,000 20,000

6 BAHAN KAPUR :

a. Kapur Bubuk/Pasang Zak 5,000 6,000

7 BAHAN BESI :

a. Besi Beton Polos : - Ø 6 mm Lonjor 8,000 9,000

- Ø 8 mm Lonjor 8,000 9,000

- Ø 10 mm Lonjor 8,000 9,000

- Ø 12 mm Lonjor 8,000 9,000

b. Besi Beton Ulir : - Ø 8 mm Lonjor 8,500 10,000

- Ø 10 mm Lonjor 8,500 10,000

- Ø 12 mm Lonjor 8,500 10,000

c. Besi Siku Kg 9,500 11,000

d. Besi Profil canal Kg 10,000 12,000

e. Besi Profil WF Kg 10,000 12,000

f. Angker/Baut Kg 11,000 13,000

g. Mur Baut 1/2", 5/8", 7/8" Kg 11,000 15,000

h. Besi Plate Strip Kg 11,000 13,000

i. Besi Bulat st. 60 Kg 11,000 13,000

j. Pipa Kg 55,000 70,000

k. Niple Kg 9,000 12,000

l. Splite Pen Kg 9,000 12,000

m. Gembok Kg 15,000 22,000

n. Drucklager Kecil/ Besar Kg 155,000 175,000

o. Naf + Ring Kg 55,000 75,000

q.Rolling Dor M2 275,000 300,000

8 BAHAN KAWAT :

Page 3: Harga Satuan

DAFTAR HARGA SATUAN PEKERJAAN TRIWULAN II TAHUN 2012 3

NO NAMA BAHAN SATUAN HARGA SATUAN KET

TERENDAH TERTINGGI

1 2 3 4 5 6

a. Kawat Beton Kg 15,000 17,000

b. Kawat Galvanis Kg 17,000 19,000

c. Kawat Kasa/nyamuk aluminium Meter 20,000 25,000

d. Kawat Harmonika Meter 25,000 30,000

9 BAHAN PIPA PVC (AW) :

a. Pipa PVC dia 3/4" M' 6,500 7,500

b. Pipa PVC dia 1" M' 7,500 8,500

c. Pipa PVC dia 1,5" M' 12,000 15,000

d. Pipa PVC dia 2" M' 20,000 23,000

e. Pipa PVC dia 2,5" M' 25,000 27,000

f. Pipa PVC dia 3" M' 35,000 38,000

g. Pipa PVC dia 4" M' 51,000 57,000

h. Keni PVC dia 3/4" M' 1,500 2,500

i. Keni PVC dia 1" M' 2,000 3,000

j. Keni PVC dia 1.5" M' 3,000 5,000

k. Keni PVC dia 2" M' 6,000 10,000

l. Keni PVC dia 2.5" M' 7,000 11,000

m. Keni PVC dia 3" M' 9,000 13,000

n. Keni PVC dia 4" M' 11,000 16,500

10 BAHAN ALAT TUKANG

a. Timba Plastik Buah 7,000 9,000

b. Gergaji Buah 20,000 25,000

c. Gergaji Besi Buah 45,000 55,000

d. Pisau Besar Buah 15,000 20,000

e. Rol Meter 50 m Buah 40,000 45,000

f. Palu/ Bodem Buah 20,000 25,000

g. Ganco Buah 45,500 60,000

h. Keranjang Buah 8,000 10,000

i. Ember Buah 7,000 15,000

j. Cetok Buah 15,000 20,000

k. Kasut Kayu Buah 12,500 40,000

l. Linggis Buah 45,000 65,000

m. Cangkul Buah 25,000 34,000

n. Kotak Adukan Buah 20,000 25,000

o. Kayu Pemikul/ Tampar Buah 10,000 15,000

11 BAHAN PAGAR :

a. Pagar BRC

- Type UCP.UK : 0,90 M x 2,40 M Lembar 270,000 285,000

- Type HOTDIP UK : 0,90 M x 2,40 M Lembar 310,000 350,000

b. Pintu Pagar BRC :

- Swing UCP Lembar 360,000 390,000

- Dorong UCP Lembar 375,000 400,000

- Swing HOTDIP Lembar 395,000 430,000

- Dorong HOTDIP Lembar 420,000 455,000

c. Tiang Pagar BRC :

- Diameter 1,5 " UCP M' 85,000 95,000

- Diameter 2 " HOTDIP M' 90,000 100,000

12 BAHAN PIPA BESI (Medium) :

a. Pipa Besi Galvanis dia 0,5" M' 20,000 25,000

b. Pipa Besi Galvanis dia 3/4" M' 25,000 30,000

c. Pipa Besi Galvanis dia 1" M' 30,000 40,000

d. Pipa Besi Galvanis dia 1,5" M' 40,000 50,000

e. Pipa Besi Galvanis dia 2" M' 55,000 65,000

f. Pipa Besi Galvanis dia 2,5" M' 65,000 75,000

g. Pipa Besi Galvanis dia 3" M' 75,000 90,000

13 BAHAN BUIS BETON :

A. BUIS BETON BULAT ( O ) :

a. Buis Beton o dia 20 cm Buah 40,000 45,000

b. Buis Beton o dia 30 cm Buah 50,000 55,000

Page 4: Harga Satuan

DAFTAR HARGA SATUAN PEKERJAAN TRIWULAN II TAHUN 2012 4

NO NAMA BAHAN SATUAN HARGA SATUAN KET

TERENDAH TERTINGGI

1 2 3 4 5 6

c. Buis Beton o dia 40 cm Buah 55,000 65,000

d. Buis Beton o dia 60 cm Buah 75,000 80,000

e. Buis Beton o dia 80 cm Buah 80,000 85,000

f. Buis Beton o dia 1,00 M Buah 85,000 95,000

B. BUIS BETON U :

a. Buis Beton dia 20 cm Buah 45,000 50,000

b. Buis Beton dia 30 cm Buah 55,000 60,000

c. Buis Beton dia 40 cm Buah 65,000 70,000

d. Buis Beton dia 60 cm Buah 70,000 75,000

e. Buis Beton dia 80 cm Buah 75,000 85,000

f. Buis Beton dia 1,00 M Buah 85,000 90,000

14 BAHAN LANTAI :

a. Keramik :

- Ukuran 10 x 20 cm M2 32,000 35,000

- Ukuran 20 x 20 cm M2 38,000 42,000

- Ukuran 20 x 25 cm M2 36,000 45,000

- Ukuran 25 x 30 cm M2 45,000 49,000

- Ukuran 30 x 30 cm M2 30,000 35,000

- Ukuran 30 x 30 cm M2 38,000 41,000

- Ukuran 40 x 40 cm M2 39,000 43,000

- Ukuran 40 x 40 cm M2 48,000 52,000

15 BAHAN SANITAIR :

a. Kloset Jongkok Porselin Unit 98,000 115,000

b. Kloset Duduk Porselin Unit 300,000 450,000

c. Kloset Duduk Porselin Komplit Unit 850,000 1,000,000

d. Urinoir Unit 450,000 550,000

e. Wastafel Komplit 'Toto" Unit 300,000 325,000

f. Bak cuci Stainless Unit 230,000 350,000

g. Afour lantai Unit 10,000 85,000

h. Afour bak air Unit 8,000 28,000

16 BAHAN KRAN AIR :

a. Krom 1/2" Buah 40,000 60,000

b. Krom 3/4" Buah 18,000 35,000

c. Kuningan 1/2" Buah 47,500 60,000

d. Kuningan 3/4" Buah 55,000 60,000

17 BAHAN ATAP :

A. GENTENG :

a.Genteng flam pres jawa / lokal Buah 1,500 2,000

b.Genteng Karang Pilang / wisma Buah 2,500 3,500

c.Genteng wuwung jawa / lokal Buah 3,500 5,500

d.Genteng wuwung karang pilang / wisma Buah 9,000 10,000

e.Genteng Pelentong Buah 3,000 4,000

f. Genteng Nok Pelentong Buah 7,000 8,000

g.Genteng Beton Buah 4,500 6,000

h.Nok genteng Beton Buah 6,000 7,500

i. Nglayur Buah 2,500 3,000

j. Genteng Glazur KIA Buah 6,000 7,500

B. ASBES :

B. a. ASBES Gel Besar

a. Asbes Gel Besar Tebal 5 mm (1.80 x 1.05) Lbr 55,000 65,000

b. Asbes Gel Besar Tebal 5 mm (2.40 x 1.05) Lbr 80,000 90,000

c. Asbes Gel Besar Tebal 5 mm (3.05 x 1.05) Lbr 90,000 100,000

B.b. ASBES Gel Kecil

a. Asbes Gel Kecil Tebal 4 mm (1.50 x 1.05) Lbr 35,000 40,000

b. Asbes Gel Kecil Tebal 4 mm (1.80 x 1.05) Lbr 38,500 42,500

c. Asbes Gel Kecil Tebal 4 mm (2.40 x 1.05) Lbr 47,000 55,000

d. Asbes Gel Kecil Tebal 4 mm (3.00 x 1.05) Lbr 60,000 65,000

B.c. ASBES Plat/Datar

a. Asbes Plat/Datar datar tebal 4 mm (0,60x2.00) Lbr 15,000 20,000

Page 5: Harga Satuan

DAFTAR HARGA SATUAN PEKERJAAN TRIWULAN II TAHUN 2012 5

NO NAMA BAHAN SATUAN HARGA SATUAN KET

TERENDAH TERTINGGI

1 2 3 4 5 6

b. Asbes Plat/Datar datar tebal 4 mm (1.00x1.00) Lbr 15,000 20,000

c. Kalsiboard tb. 3.5 ( 1.20 x 2.40 ) Lbr 50,000 55,000

d. Kalsiboard tb. 4.5 ( 1.20 x 2.40 ) Lbr 65,000 72,000

B.d. ASBES Wuwung

a.Asbes wuwung gelombang besar tebal 5 mm Lbr 40,000 47,000

b.Asbes wuwung gelombang kecil tebal 4 mm Lbr 25,000 32,000

C. SENG :

a. Seng Gelombang bwg 32 (2.40 x 1.05 ) Lbr 55,000 65,000

b. Seng Gelombang bwg 32 (3.00 x 1.05 ) Lbr 65,000 85,000

c. Seng datar (0.2 x 90 x 100) Lbr 30,500 70,000

d. Seng Aluminium Lbr 70,000 75,000

18 BAHAN KAYU :

A. KAYU JATI :

a. Balok (8/12, 6/12) M3 12,000,000 13,000,000

b. Usuk (5/7, 4/6) M3 12,000,000 13,000,000

c. Papan (2/20) M3 12,000,000 13,000,000

d. Reng (2/3, 3/5) M3 12,000,000 13,000,000

B. KAYU MERANTI :

a. Balok (8/12, 6/12) M3 4,000,000 4,500,000

b. Usuk (5/7, 4/6) M3 4,000,000 4,500,000

c. Papan (2/20) M3 4,000,000 4,500,000

d. Reng (2/3, 3/5) M3 4,000,000 4,500,000

C. KAYU BANGKIRAI :

a. Balok (8/12, 6/12) M3 6,500,000 8,000,000

b. Usuk (5/7, 4/6) M3 4,500,000 6,500,000

c. Papan (2/20) M3 6,000,000 8,000,000

d. Reng (2/3, 3/5) M3 4,000,000 5,500,000

D. KAYU KAMPER :

a. Balok (8/12, 6/12) M3 6,500,000 7,500,000

b. Usuk (5/7, 4/6) M3 5,000,000 6,500,000

c. Papan (2/20) M3 7,000,000 8,000,000

d. Reng (2/3, 3/5) M3 5,500,000 6,000,000

E. KAYU BEKISTING

a. Meranti (MC) M3 3,500,000 4,000,000

19 BAHAN BAMBU :

a. Gedeg Guling M2 15,000 17,500

b. Bongkotan/tiang Buah 10,000 12,500

c. Bambu Petung Buah 25,000 30,000

20 BAHAN TRIPLEK :

a. 3 mm ( 2.40 X 1.22 ) Lembar 50,000 52,500

b. 4 mm ( 2.40 X 1.22 ) Lembar 62,000 68,000

c. 9 mm ( 2.40 X 1.22 ) Lembar 110,000 145,000

d. 12 mm ( 2.40 X 1.22 ) Lembar 150,000 155,000

e. 18 mm ( 2.40 X 1.22 ) Lembar 200,000 225,000

TEAK WOOD :

a. 3 mm ( 2.40 X 1.22 ) Lembar 90,000 95,000

b. 4 mm ( 2.40 X 1.22 ) Lembar 100,000 115,000

MILAMIN :

a. 3 mm ( 2.40 X 1.22 ) Lembar 70,000 85,000

b. 4 mm ( 2.40 X 1.22 ) Lembar 80,000 90,000

21 BAHAN ASPAL :

a. Aspal/ Bitumen Kg 7,000 8,500

b. Aspal Curah Kg 7,200 9,000

c. Coal Teer Kg 8,000 35,000

d. Lataston Ton 800,000 950,000

e. Laston Ton 775,000 900,000

f. Laston Atas (ATB) Ton 850,000 900,000

g. Prime Coat Liter 8,000 10,000

h. Tack Coat Liter 8,000 10,000

Page 6: Harga Satuan

DAFTAR HARGA SATUAN PEKERJAAN TRIWULAN II TAHUN 2012 6

NO NAMA BAHAN SATUAN HARGA SATUAN KET

TERENDAH TERTINGGI

1 2 3 4 5 6

22 BAHAN CAT :

a. Cat Tembok Kg 17,000 23,000

b. Cat Kayu Kg 45,000 50,000

c. Cat Besi Kg 53,000 56,000

d. Cat Brozen Kg 60,000 70,000

e. Meni Kg 20,000 22,500

f. Plamur Kg 18,000 25,000

g. Politur Kg 40,000 45,000

h. Kuas Kg 9,000 12,000

23 BAHAN MINYAK :

a. Minyak Tanah Liter 3,500 4,000

b. Solar Liter 4,500 4,500

c. Premium Liter 4,500 4,500

d. Pelumas/Olie Liter 22,000 25,000

e. Minyak Aspal Liter 3,500 4,500

f. Minyak Cat/Thinner A Liter 19,000 25,000

g. Minyak Cat/Thinner B Liter 10,000 18,000

h. Spirtus Liter 12,500 15,000

24 BAHAN KACA :

a. Kaca Polos 3 mm M2 55,000 65,000

b. Kaca Polos 5 mm M2 70,000 80,000

c. Kaca Polos 6 mm M2 120,000 130,000

d. Kaca Polos 8 mm M2 150,000 250,000

e. Kaca Ray Ben 3 mm M2 70,000 75,000

f. Kaca Ray Ben 5 mm M2 80,000 90,000

g. Kaca Ray Ben 6 mm M2 165,000 200,000

h. Kaca Ray Ben 8 mm M2 225,000 300,000

i. Kaca One Ray 3 mm M2 115,000 120,000

j. Kaca One Ray 5 mm M2 125,000 130,000

k. Kaca Rasa 5 mm M2 150,000 200,000

l. Kaca Krepyak/ Nako Lembar 12,500 15,000

m. Glass Block Buah 17,000 20,000

25 BAHAN PERALATAN KUNCI :

a. Kunci Merk Anchor Buah 35,000 45,000

b. Kunci Merk Kuda Terbang Buah 55,000 68,000

c. Kunci Merk Arch Buah 75,000 80,000

d. Kunci Merk Union Buah 100,000 110,000

e. Slot Merk Union Buah 6,500 8,500

f. Kunci Pembengkok Tulangan Buah 10,000 12,000

GRENDEL :

a. Pintu Buah 15,000 20,000

b. Jendela Buah 10,000 15,000

c. Grendel Tanam Buah 25,000 45,000

ENGSEL :

a. Pintu Pasang 30,000 50,000

b. Jendela Pasang 30,000 36,000

c. Engsel Pintu Alminium Pasang 59,000 62,500

d. Espanyolet/ kunci pintu almunium Pasang 30,000 35,000

Hak Angin Pasang 22,000 25,000

26 BAHAN PERALATAN LISTRIK :

A. LAMPU :

a. TL 20 W Buah 13,000 18,000

b. TL 40 W Buah 15,000 20,000

c. TL 60 W Buah 20,000 25,000

d. Pijar 25 W Buah 3,500 5,000

e. Pijar 40 W Buah 4,000 5,000

f. Pijar 60 W Buah 4,500 5,000

g. Pijar 100 W Buah 5,000 6,000

h. Mercuri 80 W Buah 26,000 30,000

Page 7: Harga Satuan

DAFTAR HARGA SATUAN PEKERJAAN TRIWULAN II TAHUN 2012 7

NO NAMA BAHAN SATUAN HARGA SATUAN KET

TERENDAH TERTINGGI

1 2 3 4 5 6

i. Mercuri 100 W Buah 35,000 45,000

j. Mercuri 200 W Buah 60,000 65,000

k. Mercuri 400 W Buah 65,000 70,000

B. KABEL :

a. Kabel NYA 1000 V 1,5 MM Meter 2,000 14,500

b. Kabel NYA 1000 V 2,5 MM Meter 3,500 24,500

c. Kabel NYA 1000 V 4 MM Meter 3,500 31,500

C. PERALATAN LISTRIK LAIN :

a. Saklar Buah 12,000 16,500

b. Stop Kontak Buah 15,000 20,000

c. Sekering Kast Buah 25,000 30,000

d. Isolasi Buah 5,000 7,500

e. Panel Box Buah 17,000 20,000

27 BAHAN PAKU :

a. Paku Reng/Usuk Kg 15,000 17,000

b. Paku Triplek Kg 17,500 20,000

c. Paku Seng/Payung Kg 20,000 23,000

d. Paku Asbes Kg 22,500 25,000

e. Paku Keling 3/4", 5/8", 7/8" Kg 7,500 8,500

28 BAHAN BETON :

a. Beton Ready Mix K-125 M3 475,000 525,000

b. Beton Ready Mix K-175 M3 505,000 560,000

c. Beton Ready Mix K-225 M3 530,000 590,000

d. Beton Ready Mix K-250 M3 550,000 620,000

e. Beton Ready Mix K-300 M3 575,000 640,000

f. Beton Ready Mix K-350 M3 580,000 630,000

g. Beton Ready Mix K-400 M3 600,000 660,000

h. Beton Ready Mix K-500 M3 800,000 825,000

29 BAHAN BETON PRA CETAK

1. TIANG PANCANG

a. K-500 ( 20 x 20 cm ) M 72,000 73,000

b. K-500 ( 25 x 25 cm ) M 105,000 106,000

c. K-500 ( 30 x 30 cm ) M 180,000 185,000

d. K-500 ( 35 x 35 cm ) M 200,000 205,000

e. K-500 ( 40 x 40 cm ) M 370,000 375,000

f. K-500 ( 45 x 45 cm ) M 400,000 405,000

g. K-500 ( 50 x 50 cm ) M 420,000 425,000

2. U-DITCH

a. 40 x 40 x 100 x 10 cm Buah 350,000 400,000

b. 50 x 50 x 100 x 10 cm Buah 425,000 450,000

c. 60 x 60 x 100 x 10 cm Buah 450,000 475,000

d. 80 x 80 x 100 x 10 cm Buah 650,000 670,000

e. 100 x 100 x 100 x 10 cm Buah 750,000 775,000

- TUTUP U - DITCH

a. 40 x 100 x 10 cm Buah 125,000 130,000

b. 50 x 100 x 10 cm Buah 150,000 160,000

c. 60 x 100 x 10 cm Buah 175,000 180,000

d. 80 x 100 x 10 cm Buah 225,000 230,000

e. 100 x 100 x 10 cm Buah 275,000 300,000

30 BAHAN LAIN-LAIN :

a. Kertas Gosok besi Lembar 3,000 3,500

b. Kertas Gosok kayu Lembar 3,000 4,000

c. Kertas Gosok tembok Lembar 3,000 4,500

d. Negatif Film Rol 27,500 28,000

e. Album Buah 37,500 38,000

f. Cuci Cetak Rol 17,500 18,000

g. Penggandaan ( 3 x ) Lembar 1,000 1,500

HARGA SATUAN UPAH KERJA

Page 8: Harga Satuan

DAFTAR HARGA SATUAN PEKERJAAN TRIWULAN II TAHUN 2012 8

NO NAMA BAHAN SATUAN HARGA SATUAN KET

TERENDAH TERTINGGI

1 2 3 4 5 6

WILAYAH GRESIK TENGAH / KOTAGresik, Kebomas, Manyar, Cerme, Duduk Samp., Benjeng, Balongpanggang

NO URAIAN SATUANHARGA SATUAN

KETERANGANTERENDAH TERTINGGI

1 2 3 4 5 61 MANDOR ORANG 75,000 80,000 10,000.00 2 KEPALA TK. GALI TANAH ORANG 70,000 75,000 9,375.00 3 KEPALA TK. BATU ORANG 70,000 75,000 9,375.00 4 KEPALA TK. KAYU ORANG 70,000 75,000 9,375.00 5 KEPALA TK. BESI ORANG 70,000 75,000 9,375.00 6 KEPALA TK. CAT ORANG 70,000 75,000 9,375.00 7 KEPALA TK. LISTRIK ORANG 70,000 75,000 9,375.00 8 KEPALA TK. PIPA ORANG 70,000 75,000 9,375.00 9 TUKANG GALI TANAH ORANG 67,500 70,000 8,750.00

10 TUKANG BATU ORANG 67,500 70,000 8,750.00 11 TUKANG KAYU ORANG 67,500 70,000 8,750.00 12 TUKANG BESI ORANG 67,500 70,000 8,750.00 13 TUKANG CAT ORANG 67,500 70,000 8,750.00 14 TUKANG PLITUR ORANG 67,500 70,000 8,750.00 15 TUKANG ASPAL ORANG 67,500 70,000 8,750.00 16 TUKANG PIPA ORANG 67,500 70,000 8,750.00 17 TUKANG LISTRIK ORANG 67,500 70,000 8,750.00 18 PEMBANTU TK. BATU ORANG 53,000 55,000 6,875.00 19 PEMBANTU TK. KAYU ORANG 53,000 55,000 6,875.00 20 PEMBANTU TK. BESI ORANG 53,000 55,000 6,875.00 21 PEMBANTU TK. CAT ORANG 53,000 55,000 6,875.00 22 PEMBANTU TK. LISTRIK ORANG 53,000 55,000 6,875.00 23 PEMBANTU TK. PIPA ORANG 53,000 55,000 6,875.00 24 PEKERJA ORANG 53,000 53,000 6,625.00 25 MASINIS / OPERATOR ORANG 75,000 80,000 10,000.00 26 PEMBANTU MASINIS / OPERATOR ORANG 60,000 65,000 8,125.00 27 MEKANIK ORANG 60,000 65,000 8,125.00 28 PEMBANTU MEKANIK ORANG 53,000 55,000 6,875.00 29 PENGEMUDI / SOPIR ORANG 60,000 65,000 8,125.00 30 PEMBANTU SOPIR/KERNET ORANG 53,000 55,000 6,875.00 31 PENJAGA API ORANG 53,000 55,000 6,875.00 32 PENJAGA MALAM ORANG 53,000 55,000 6,875.00 33 JURU PHOTO ORANG 53,000 60,000 7,500.00 34 JURU UKUR ORANG 53,000 60,000 7,500.00

Page 9: Harga Satuan

DAFTAR HARGA SATUAN PEKERJAAN TRIWULAN II TAHUN 2012 9

9,833

11,500

14,833

16,500

Page 10: Harga Satuan

DAFTAR HARGA SATUAN PEKERJAAN TRIWULAN II TAHUN 2012 10

PRINT