igcc with higher plant efficiency - jcoal 一般財団法人 … business confidential z...

25
IGCC with higher plant efficiency MITSUBISHI HEAVY INDUSTRIES, LTD. July, 2009 Note: This document is the property of and contains confidential proprietary information of MITSUBISHI HEAVY INDUSTRIES, LTD. This document shall not be reproduced, used, disclosed or transmitted in whole or in part unless authorized in writing by MITSUBISHI HEAVY INDUSTRIES, LTD. 高効率煤炭氣化複循環發電技術

Upload: buiduong

Post on 21-Mar-2018

223 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: IGCC with higher plant efficiency - JCOAL 一般財団法人 … BUSINESS CONFIDENTIAL z Specification Gasifier Dry feed, Air Blown, Two-Staged Entrained Bed Gas Clean-up MDEA (Methyl

IGCC with higher plant efficiency

MITSUBISHI HEAVY INDUSTRIES, LTD.

July, 2009

Note: This document is the property of and contains confidential proprietary information of MITSUBISHI HEAVY INDUSTRIES, LTD. This document shall not be reproduced, used, disclosed or transmitted in whole or in part unless authorized in writing by MITSUBISHI HEAVY INDUSTRIES, LTD.

高効率煤炭氣化複循環發電技術

kyoyopro
テキストボックス
Japan: Reference 3
Page 2: IGCC with higher plant efficiency - JCOAL 一般財団法人 … BUSINESS CONFIDENTIAL z Specification Gasifier Dry feed, Air Blown, Two-Staged Entrained Bed Gas Clean-up MDEA (Methyl

BUSINESS CONFIDENTIAL

Combined Cycle Power Plant Steam Turbine Gas Turbine

Geothermal Power Plant Boiler

MHIMHI’’ss products for Power Generation products for Power Generation and Chemicalsand Chemicals

POWER PLANTPOWER PLANT & & EQUIPMENTEQUIPMENT

Flue Gas CO2Recovery Plants

Refuse Incineration Plant Purified Terephthalic Acid PlantCompressor forEthylene Plant

CHEMICAL PLANTCHEMICAL PLANT & EQUIPMENT& EQUIPMENT

IGCC(Integrated

coalGasification Combined

Cycle)

Page 3: IGCC with higher plant efficiency - JCOAL 一般財団法人 … BUSINESS CONFIDENTIAL z Specification Gasifier Dry feed, Air Blown, Two-Staged Entrained Bed Gas Clean-up MDEA (Methyl

22

BUSINESS CONFIDENTIAL

MHI propose IGCC and CCS solution MHI propose IGCC and CCS solution as Clean Coal Technologyas Clean Coal Technology

1.1. IGCC Technology & Demonstration PlantIGCC Technology & Demonstration Plant

2.2. IGCC Commercial PlantIGCC Commercial Plant

3.3. Carbon Capture TechnologyCarbon Capture Technology

4.4. IGCC+CCS Commercial PlantIGCC+CCS Commercial Plant

Contents Contents

Page 4: IGCC with higher plant efficiency - JCOAL 一般財団法人 … BUSINESS CONFIDENTIAL z Specification Gasifier Dry feed, Air Blown, Two-Staged Entrained Bed Gas Clean-up MDEA (Methyl

33

BUSINESS CONFIDENTIALIGCC: Integrated Gasification Combined Cycle

2025

Gro

ss T

herm

al E

ffici

ency

(LH

V%)

Gro

ss T

herm

al E

ffici

ency

(LH

V%)

40

45

50

55

60

65

70

1990 1995 2000 2005 2010 2015

USC(coal)USC(coal)USC(coal)

2020

NGCC(Natural Gas)

NGCCNGCC(Natural Gas)(Natural Gas)

② IGCC②② IGCCIGCC

① Ultra High temp. GT(1,700oC)

①① Ultra High temp. GTUltra High temp. GT(1,700(1,700ooCC))

J type GTJJ type type GTGT

1,700oC GT1,7001,700ooC C GTGTHot gas

Clean-upSystem

MitsubishiMitsubishi’’s Clean Coal Technologys Clean Coal Technology

FuelFuel

COCO22GenerationGeneration((Power Station)Power Station)

COCO22CaptureCapture

COCO2 2 TransportationTransportation(Pipe (Pipe Line,etcLine,etc))

COCO22StorageStorageOcean &

Underground

MHI High efficiencyMHI High efficiencyPower PlantPower Plant

MHIMHICOCO22Capture Capture technologytechnology----Low Energy Low Energy CaptureCapture

MHI High Pressure MHI High Pressure COCO22Compressor Compressor for CCS Plantfor CCS Plant

2. CO2 Capture and Storage2. CO2 Capture and Storage1. Improvement of Thermal 1. Improvement of Thermal Efficiency of Power PlantEfficiency of Power Plant

A-USC(coal)AA--USC(coalUSC(coal))

Page 5: IGCC with higher plant efficiency - JCOAL 一般財団法人 … BUSINESS CONFIDENTIAL z Specification Gasifier Dry feed, Air Blown, Two-Staged Entrained Bed Gas Clean-up MDEA (Methyl

44

BUSINESS CONFIDENTIAL

Development History of IGCC in JapanDevelopment History of IGCC in Japan

PDU : Process Development UnitCRIEPI:Central Research Institute of Electric Power Industry

1980 1990 2000 20101985 1995 20051

10

100

1000

5

50

500

5000

Fuel

Cap

acity

( t/d

)

Clean Coal Power R&D, Ltd.2t/d PDU(CRIEPI)

200t/d Pilot Plant(Nakoso)

Commercial Plant1700t/d Demo. Plant(250MW class; Nakoso).

1. IGCC Technology & Demonstration Plant 1. IGCC Technology & Demonstration Plant

Page 6: IGCC with higher plant efficiency - JCOAL 一般財団法人 … BUSINESS CONFIDENTIAL z Specification Gasifier Dry feed, Air Blown, Two-Staged Entrained Bed Gas Clean-up MDEA (Methyl

55

BUSINESS CONFIDENTIAL

1. IGCC Technology & Demonstration Plant1. IGCC Technology & Demonstration Plant

Page 7: IGCC with higher plant efficiency - JCOAL 一般財団法人 … BUSINESS CONFIDENTIAL z Specification Gasifier Dry feed, Air Blown, Two-Staged Entrained Bed Gas Clean-up MDEA (Methyl

66

BUSINESS CONFIDENTIAL

SpecificationGasifier Dry feed, Air Blown, Two-Staged Entrained BedGas Clean-up MDEA (Methyl Di-Ethanol Amine )Gas Turbine D-class

(1,250℃ Class)

Coal feed 1,700t/day

Plant Efficiency 42%(LHV, Net)40.5%(HHV, Net)

Emission(16%O2, dry)

SOx : 8ppmV(actual:1ppm)NOx : 5ppmV(w/SCR)(actual:3ppm)

Dust : 4mg/m3N(actual:< 0.1mg/m3N)

MHI Supplied All the Key Components under Single Point Responsibility.

250MW IGCC Demonstration Plant250MW IGCC Demonstration Plant

High Temp.Filter

Gasifier

Air Booster

Gas Turbine Steam Turbine

Coal

MHRSGHRSG

WashingGypsumrecovery

Wet Desul -furization

Air

Limestone

ASUASU--N2N2

OO22NN22

Air

High Temp.Filter

Gasifier

Air Booster

Gas Turbine Steam Turbine

Coal

MHRSGHRSG

Gas C/UGypsumrecovery

Wet Desul -furization

Air

Limestone

1. IGCC Technology & Demonstration Plant1. IGCC Technology & Demonstration Plant

Page 8: IGCC with higher plant efficiency - JCOAL 一般財団法人 … BUSINESS CONFIDENTIAL z Specification Gasifier Dry feed, Air Blown, Two-Staged Entrained Bed Gas Clean-up MDEA (Methyl

77

BUSINESS CONFIDENTIAL7

IGCC/Gasification Technology Providers in the WorldIGCC/Gasification Technology Providers in the World

GEConoco-Phillips

Shell

MHI Gasifier

Syngas

Slag

CoalOxygen

MembraneWall

Reductor

Combustor

CoalAir

Coal

Slag Hole

Syngas

Oxygen-BlownAir-Blown

Slag

Membrane Waterwall RefractoryDry Coal Feed Slurry Feed

Siemens

2 Chamber / 2 Stage 1 Chamber / 1 StageSemi-2 Chamber / 2 Stage

1. IGCC Technology & Demonstration Plant1. IGCC Technology & Demonstration Plant

Page 9: IGCC with higher plant efficiency - JCOAL 一般財団法人 … BUSINESS CONFIDENTIAL z Specification Gasifier Dry feed, Air Blown, Two-Staged Entrained Bed Gas Clean-up MDEA (Methyl

88

BUSINESS CONFIDENTIAL

Buggenum (Netherlands)284MW 1994

Wabash River (U.S.)296MW 1995

Tampa (U.S.)315MW 1996

CCP R&D Co., Ltd. (Japan)CCP R&D Co., Ltd. (Japan)250MW250MW 20072007

Puertollano (Spain)318MW 1997

Coal IGCC Projects in the WorldCoal IGCC Projects in the World

Item Nuon Wabash River

TampaElectric ELCOGAS CCP R&D

Co. Ltd

Location NetherlandBuggenum

Shell

O2Dry

SiemensV94.2

284

U.S.Illinois

U.S.Florida

Jan. 1994

JapanNakoso

Gasifier E-GasTM Texaco(GE)

SpainPuertollano

Prenflo(shell)

Oxidant O2 O2 O2 AirCoal Feed Slurry Slurry Dry Dry

SiemensV94.3

Output(Gross ,MW) 296 315 318 250

MHI

Gas TurbineGE

7FAGE

7FAMHI

M701DA

Start of GT Syngas Firing Nov. 1997Aug. 1995 July 1996 Dec. 2007

1. IGCC Technology & Demonstration Plant1. IGCC Technology & Demonstration Plant

Page 10: IGCC with higher plant efficiency - JCOAL 一般財団法人 … BUSINESS CONFIDENTIAL z Specification Gasifier Dry feed, Air Blown, Two-Staged Entrained Bed Gas Clean-up MDEA (Methyl

99

BUSINESS CONFIDENTIAL

Excellent Operation results in First YearExcellent Operation results in First Year

SShowhoweded EExcellent xcellent Reliability and Performance!Reliability and Performance!Targeting 5,000hours Continuous Operation (2009)

0

10

20

30

40

50

Net Efficiency(%-LHV)

SOx(ppmV)

NOx(ppmV)

Dust(mg/m3N)

PerformanceDesign

0

10

20

30

40

50

Net Efficiency(%-LHV)

SOx(ppmV)

NOx(ppmV)

Dust(mg/m3N)

PerformanceDesign

Excellent PerformanceExcellent Performance

0

500

1,000

1,500

2,000

2,500

3,000

3,500

0 5 10 15 20Elapsed Year

Con

tinur

ous

Ope

ratio

n (h

ours

)

2007 W ( 296MW)1998

20071999P(335MW)

B( 284MW)

T(322MW)

2008

NakosoDemo. Plant

2005

2007

2000

1. IGCC Technology & Demonstration Plant1. IGCC Technology & Demonstration Plant

Page 11: IGCC with higher plant efficiency - JCOAL 一般財団法人 … BUSINESS CONFIDENTIAL z Specification Gasifier Dry feed, Air Blown, Two-Staged Entrained Bed Gas Clean-up MDEA (Methyl

1010

BUSINESS CONFIDENTIAL

Principle and Advantage of MHI Principle and Advantage of MHI GGasifierasifier

1. 2-Staged Gasification- Combustor / Reductor Configuration① Stable Syngas Production for Wide

Variety of Coal② Smooth Slag Discharge Capability③ No Necessity of Chemical Quench Gas

Water

(Combustion)Oxidizer

(Air)

Coal

Reductor

Combustor

(Gasification)Char

Slag

CoalOxidizer

(Air or O2)

2. Char Recycling System① Minimize Unburnt Carbon in Slag② No Black Water from Gasifier

Chemical Quenchat 2nd Stage

Temperature

Reductor

Combustor

1. IGCC Technology & Demonstration Plant1. IGCC Technology & Demonstration Plant

●Air-blown ⇒ Lower auxiliary power (Large Capacity ASU units are not necessary)

●Dry coal feed ⇒ Lower heat loss than slurry feed ⇒ Highest efficiency

Page 12: IGCC with higher plant efficiency - JCOAL 一般財団法人 … BUSINESS CONFIDENTIAL z Specification Gasifier Dry feed, Air Blown, Two-Staged Entrained Bed Gas Clean-up MDEA (Methyl

1111

BUSINESS CONFIDENTIAL

UnburnedCarbon 3~5% <0.1%

Volume 100%

0

20

40

60

80

100

石炭焚

フライアッシュ

IGCCスラグ

灰捨

て場

面積

比A

sh p

ond

area

ratio

[%]

40

20

0

60

80

100

8080

6060

[%][%]Slag

CombustorCombustor

Gasifier

CameraSlag Hole

Slag Water Bath Surface

Advantage in Slag TreatmentAdvantage in Slag Treatment

Camera

Slag Water Bath

PC BoilerFly Ash

(Powder)

GasifierMolten Slag

(Glassy Granular)Volume 40%

PC BoilerFly Ash

GasifierSlag

Advantage• Lower Slag Volume• No Leaching from Slag• Lower Unburned Carbon

1. IGCC Technology & Demonstration Plant1. IGCC Technology & Demonstration Plant

Page 13: IGCC with higher plant efficiency - JCOAL 一般財団法人 … BUSINESS CONFIDENTIAL z Specification Gasifier Dry feed, Air Blown, Two-Staged Entrained Bed Gas Clean-up MDEA (Methyl

1212

BUSINESS CONFIDENTIAL

0

10

20

30

40

0 10 20 30 40

Total Moisture (wt%-as received)

Ash

(wt%

-as

drie

d)

Dry Feed

Features of MHI Features of MHI GasifierGasifier

ApplicableZoneMHIMHI’’ss Gasification Gasification

ExperienceExperience

PulverizerExperience

Slurry FeedMHI Dry Feed System Brings ;• High Efficiency

- Low Heat Loss due to Moisture• Flexibility for Variety of Coal

- No Need to Make Slurry

Same Pulverizer as ConventionalBoiler Is Used ;

• Proven by Much Experiencein Variety of Coal

AirAir--BlownBlownO2O2--BlownBlown

1. IGCC Technology & Demonstration Plant1. IGCC Technology & Demonstration Plant

Page 14: IGCC with higher plant efficiency - JCOAL 一般財団法人 … BUSINESS CONFIDENTIAL z Specification Gasifier Dry feed, Air Blown, Two-Staged Entrained Bed Gas Clean-up MDEA (Methyl

1313

BUSINESS CONFIDENTIAL

Slag

Combustor

Reductor

Coal

Char

Coal

Same WW Structure as MHI’s 3,000 BoilersOffers Best Durability Reducing Maintenance Work

WW of Coal Firing BoilerMore than10 years Operation

Syngas, Char

Features of MHI Features of MHI GasifierGasifier

cf.Refractory Configuration(by Other Technology)

1. IGCC Technology & Demonstration Plant1. IGCC Technology & Demonstration Plant

Page 15: IGCC with higher plant efficiency - JCOAL 一般財団法人 … BUSINESS CONFIDENTIAL z Specification Gasifier Dry feed, Air Blown, Two-Staged Entrained Bed Gas Clean-up MDEA (Methyl

1414

BUSINESS CONFIDENTIAL

Gas Turbine Steam Turbine

Boiler625,778t/h

(2,976 units)

Gas Turbine62,478MW (486 units)

Steam Turbine182,939MW(1,987 units)

Developed to Gasifier Optimized for IGCC

Boiler

Origin of MHI IGCC Commercial Plant Origin of MHI IGCC Commercial Plant

Gas Purification System Developed to Gas C/Ufor IGCC

2. IGCC Commercial Plant2. IGCC Commercial Plant

Page 16: IGCC with higher plant efficiency - JCOAL 一般財団法人 … BUSINESS CONFIDENTIAL z Specification Gasifier Dry feed, Air Blown, Two-Staged Entrained Bed Gas Clean-up MDEA (Methyl

1515

BUSINESS CONFIDENTIAL

Features of Mitsubishi Gas TurbineFeatures of Mitsubishi Gas Turbine2. IGCC Commercial Plant2. IGCC Commercial Plant

155

10

15

20

25

3,000

2,000

1,000

1990 1995 2000 2005 Year

30

Unit NOS.

CapacityTo

tal N

os. o

f Ope

ratio

n U

nits

Tota

l Cap

acity

(MW

)

155

10

15

20

25

3,000

2,000

1,000

1990 1995 2000 2005 Year

30

Unit NOS.

CapacityCapacity

MHI Experience Low BTU gas GT

Experience of MHI GT

U.K. 13U.K. 13Total : 533unitsTotal : Total : 533533unitsunits

M501F× 69M701F×102

Total : 171units

M501FM501F×× 6969M701FM701F××102102

Total : Total : 171171unitsunits

M501D×20M701D×91

Total : 111units

M501DM501D××2020M701DM701D××9191

Total : Total : 111111unitsunits

M501G×51M701G×11

Total : 62units

M501GM501G××5151M701GM701G××1111

Total : Total : 6262unitsunits

U.K. 13U.K. 13Total : 533unitsTotal : Total : 533533unitsunits

M501F× 69M701F×102

Total : 171units

M501FM501F×× 6969M701FM701F××102102

Total : Total : 171171unitsunits

M501F× 69M701F×102

Total : 171units

M501FM501F×× 6969M701FM701F××102102

Total : Total : 171171unitsunits

M501D×20M701D×91

Total : 111units

M501DM501D××2020M701DM701D××9191

Total : Total : 111111unitsunits

M501D×20M701D×91

Total : 111units

M501DM501D××2020M701DM701D××9191

Total : Total : 111111unitsunits

M501G×51M701G×11

Total : 62units

M501GM501G××5151M701GM701G××1111

Total : Total : 6262unitsunits

M501G×51M701G×11

Total : 62units

M501GM501G××5151M701GM701G××1111

Total : Total : 6262unitsunits

G type

C/C efficiencyC/C efficiency

OriginalOriginal

F type

1100 1200 1300 1400 1500Temperature(℃)

50

55

60

C/C

Effi

cien

cy (L

HV%

)

UpUp--ratedrated

D type

G type

C/C efficiencyC/C efficiency

OriginalOriginal

F type

1100 1200 1300 1400 1500Temperature(℃)

50

55

60

C/C

Effi

cien

cy (L

HV%

)

UpUp--ratedrated

D type

• High Plant Efficiency by High Temp. GT• High Reliability from Abundant“Low BTU Gas Firing” GT

More than 1,223,000-More than 1,223,000Operating Hours5,268 MW2,990 MW2,278 MWCapacity

361323No. of UnitsTotalUnder ConstructionUnder OperationItem

> 1,223,000-> 1,223,000Operating Hours5,268 MW2,990 MW2,278 MWCapacity

361323No. of UnitsTotalUnder ConstructionUnderOperationItem

More than 1,223,000-More than 1,223,000Operating Hours5,268 MW2,990 MW2,278 MWCapacity

361323No. of UnitsTotalUnder ConstructionUnder OperationItem

> 1,223,000-> 1,223,000Operating Hours5,268 MW2,990 MW2,278 MWCapacity

361323No. of Units

TotalUnder ConstructionUnderOperationItem

Page 17: IGCC with higher plant efficiency - JCOAL 一般財団法人 … BUSINESS CONFIDENTIAL z Specification Gasifier Dry feed, Air Blown, Two-Staged Entrained Bed Gas Clean-up MDEA (Methyl

1616

BUSINESS CONFIDENTIALNote: Plant efficiency depends on site conditions including coalNote: Plant efficiency depends on site conditions including coal propertiesproperties..

SOx emissionSOx emission and acid gas cleanand acid gas clean--up process depends on the regional regulation. up process depends on the regional regulation.

MW

250MW

140140

330330

38

40

42

44

46

48

701DA G/T(1,250℃)

50

Net

Effi

cien

cy (L

HV

%)

Demo. Plant

501G G/T(1,500℃)

400

500

600

300

200

Gro

ss O

utpu

t

500MW

700Item Specification

Coal Bituminous Coal

Output Gross 500 MW

Net 450 MW

Gasifier Oxidizer AirCoal Feed Dry

Acid Gas Clean-up Wet MDEA

Gas Turbine M501G ×1(1 on 1)

Net Efficiency(LHV) 48%

Commercial Plant Typical Expected PerformanceCommercial Plant Typical Expected Performance3. IGCC Commercial size Plant3. IGCC Commercial size Plant

Commercial sizeCommercial size

IGCCIGCC W/0 CCSW/0 CCS

Page 18: IGCC with higher plant efficiency - JCOAL 一般財団法人 … BUSINESS CONFIDENTIAL z Specification Gasifier Dry feed, Air Blown, Two-Staged Entrained Bed Gas Clean-up MDEA (Methyl

1717

BUSINESS CONFIDENTIAL

PostCombustion(PCC for Boiler)

Pre Combustion( for IGCC)

OxyーFuel Combustion

EP CO2

Capture

CO2

Coal

AirBoiler

SolventAtmospheric

PressureCO215%

PC Boiler

EP

CO2

Coal

O2 Boiler

ASUCO2

CO2

Air

AGRGasifier

Coal

COShift

Solvent

CO2Capture

CO+H2O→CO2+H2

Air

PressurizedCO2 30~60%

IGCC

H2O

Cooling

IGCC: IIntegrated ntegrated GGasification asification CCombined ombined CCycleycle

PC Boiler

COCO22 Capture from fossil fuel firing plantCapture from fossil fuel firing plant3. Carbon Capture Technology

Page 19: IGCC with higher plant efficiency - JCOAL 一般財団法人 … BUSINESS CONFIDENTIAL z Specification Gasifier Dry feed, Air Blown, Two-Staged Entrained Bed Gas Clean-up MDEA (Methyl

1818

BUSINESS CONFIDENTIAL

Air

ASU-N2 G

Coal

N2

GT Comp

HRSG

Air

Air for Gasifier

O2

Air-BlownGasifier

Air Booster

AGR

ST

SRU

Combustor

Sulfur

G

AGRCO Shift

CO2Comp

Steam

CO+H2O CO2+H2

CO2 Sequestration

H2 Rich Syngas

<Pre Combustion><Pre Combustion>

3. Carbon Capture Technology

Typical System Configuration Typical System Configuration of IGCC with CO2 Captureof IGCC with CO2 Capture

Page 20: IGCC with higher plant efficiency - JCOAL 一般財団法人 … BUSINESS CONFIDENTIAL z Specification Gasifier Dry feed, Air Blown, Two-Staged Entrained Bed Gas Clean-up MDEA (Methyl

1919

BUSINESS CONFIDENTIAL

1985 1990 1995 2000 2005 20101975 198019701965

20

30

40

50

60

70

80

90

100

H2

CO

NTE

NTS

IN F

UEL

GA

S (v

ol %

)

Steam Injection

Refinery Gas

NoneCOG

N2 DilutionSyngas

NOx ControlKind of GasMark

MHI EXPERIENCE

51,400hrs Stand-by

Actual Combustion Test for National Project

152,800hrs

10

0

146,600hrs

108,200hrs

167,600hrs

143,800hrs

130,700hrs

153,200hrs

161,700hrs

SummaryNos. of Unit 12

Operating Hours >1,500,000

A Plant

B Plant

C Plant

D Plant

H PlantI Plant

K PlantJ Plant

E Plant 91,500hrs

G Plant 38,000hrs173,100hrsF Plant

Range ofAir blown syngas

w/ CO2 capture

HH22 Rich Gas Experience in MHI Gas TurbineRich Gas Experience in MHI Gas TurbineCarbon Capture Technology (Pre Combustion)Carbon Capture Technology (Pre Combustion)

3. Carbon Capture Technology

Page 21: IGCC with higher plant efficiency - JCOAL 一般財団法人 … BUSINESS CONFIDENTIAL z Specification Gasifier Dry feed, Air Blown, Two-Staged Entrained Bed Gas Clean-up MDEA (Methyl

2020

BUSINESS CONFIDENTIAL

UpdatingUpdating Australian Australian ZeroGenZeroGen ProjectProject

CoalCoal Australian Hard CoalAustralian Hard Coal

OutputOutput 530 MW gross530 MW grossGas Gas TurbineTurbine

M701G2 GTM701G2 GT((60Hz60Hz))(1 on 1)(1 on 1)

Carbon Carbon CaptureCapture 65 65 -- 90 %90 %

CO2 CO2 StorageStorage 200 200 -- 300 300 Mil.tonMil.ton/yr /yr

Gasifier

HRSG

AGR

・The Queensland state government has been promoting this PJ by recognizing IGCC & CCS is “a kind-of-must”technology in order to reduce GHG globally for the future.・ZeroGen Pty Ltd. decided that MHI joined her world-first commercial scale IGCC+CCS PJ.

・It was officially concluded and approved by CCC (Clean Coal Council) of the Queensland state government, by highly evaluating the successful result - its quality, reliability and operation ability - of the 250MW Nakosodemonstration PJ, to stop her Stage 1 demonstration PJ (120MW) and to step up directly to the commercial scale PJ (530MW) with MHI.

4. IGCC + CCS4. IGCC + CCS Commercial PlantCommercial Plant

Page 22: IGCC with higher plant efficiency - JCOAL 一般財団法人 … BUSINESS CONFIDENTIAL z Specification Gasifier Dry feed, Air Blown, Two-Staged Entrained Bed Gas Clean-up MDEA (Methyl

2121

BUSINESS CONFIDENTIAL

UpdatingUpdating Australian Australian ZeroGenZeroGen ProjectProject

2008 2009 2010 2011 2012 2013 2014 2015 2016

Key Mile StonesKey Mile Stones

PJ SchedulePJ Schedule

AwardPre-Study

Comm.FS Feed EPC

ScopingStudy

AwardFS

CommenciFEE

ngD

ContractEPC

Start Commissioning COD

Pre-Study

2008/10~12 Scoping Study2009/ 1~ 3 Pre-Study2009/ 6 Feasibility Study Awarded2010/ 6 FEED Study Contract (Scheduled)2012/ 1 EPC Contract (Scheduled)2015/ 9 Operation Start (Scheduled)

Project Shcdule

4. IGCC + CCS Commercial Plant 4. IGCC + CCS Commercial Plant

Page 23: IGCC with higher plant efficiency - JCOAL 一般財団法人 … BUSINESS CONFIDENTIAL z Specification Gasifier Dry feed, Air Blown, Two-Staged Entrained Bed Gas Clean-up MDEA (Methyl

2222

BUSINESS CONFIDENTIAL

ConclusionConclusion

1.250MW Demonstration Plant in Successful Operation⇒ Ensuring Quality/Performance of Commercial Plant

2.Commercial Scale IGCC Plant with Carbon Capture⇒ MHI is confident of our capability for successful

contribution and realization of commercial plant

Page 24: IGCC with higher plant efficiency - JCOAL 一般財団法人 … BUSINESS CONFIDENTIAL z Specification Gasifier Dry feed, Air Blown, Two-Staged Entrained Bed Gas Clean-up MDEA (Methyl

2323

BUSINESS CONFIDENTIAL

“Mitsubishi’s Contribution for Energy and Environment Solutions”

Page 25: IGCC with higher plant efficiency - JCOAL 一般財団法人 … BUSINESS CONFIDENTIAL z Specification Gasifier Dry feed, Air Blown, Two-Staged Entrained Bed Gas Clean-up MDEA (Methyl

2424

BUSINESS CONFIDENTIAL

Taiwan / DAH TARN Power StationTaiwan / DAH TARN Power Station

StageStage--11 StageStage--22●●ConfigurationConfiguration 3on1x 2Blocks 2on1x 4Blocks●●Plant OutputPlant Output 720MW x 2Blocks 708MW x 4Blocks

●●FuelFuel Main:Natural Gas Back up:Distillate Oil

Natural Gas

●●Gas TurbineGas Turbine M501F M501G

●●GeneratorGenerator Melco

●●Start of Commercial OperationStart of Commercial Operation 2006.6~2006.11 2007.9~2008.11●●CustomerCustomer TAIWAN POWER COMPANY

●●HRSGHRSG MHI

●●ConsortiumConsortium MC, CTCI

MHIMHI’’ss power plant in Taiwanpower plant in Taiwan