imac vii meeting status of infrastructure emre kazancı on behalf of tarla team
TRANSCRIPT
IMAC VII Meeting
Status of Infrastructure Emre Kazancı
On Behalf of TARLA Team
07-08/09/2015 IMAC VII Meeting 2
• Completed Construction Works• New constructions• Modifications • Experimental Stations and Clean Room
• Electricity
• Ionized Air Conditioning
• Radiation Shielding Doors
• Compressed Air
• Water Cooling System
• Segmentation of Laboratory Rooms
• Conclusion
Outline
07-08/09/2015 IMAC VII Meeting 3
Construction Works
• A,B Administrative Building• C Accelerator Building• D Water Cooling Building• E Security• F Generator and main
transformer room• G UPS room• H Mechanical Workshop• I Contamination Storage
New Construction
07-08/09/2015 IMAC VII Meeting 4
• Water cooling building and piping tunnelHouses pumps, tanks, circulators, heat exchangers etc.
• Mechanical workshopProduction and repair of mechanical systems up to a certain level
• Contaminated material storageTo safely store activated equipment (solid)
• Security office Controlled, single entrance to facility site for human and machine safety
• Waste-water storage (planned, in tender progress)• To safely store activated water produced by water cooling system
New Constructions
07-08/09/2015 IMAC VII Meeting 5
Water Cooling BuildingThe building is dedicated for water cooling plant
Connected to the laboratory by a 2x2m wide tunnel beneath road level
Total height 5.5 m (2m below road level)
07-08/09/2015 IMAC VII Meeting 6
Mechanical WorkshopA two story workshop with gross area of 200 m2 for manufacturing and maintenance
• Crane 5ton• Driller• Cold Saw• Compressor• Band Saw• Guillotine shear • Hand Tools
• CNC milling machine• CNC turning machine• Turning machine• Milling machine• 3 Axis goniometer• Hydraulic Press• Pipe bending machine• TIG welding machine
07-08/09/2015 IMAC VII Meeting 7
Contaminated Material Storage, Security Office
07-08/09/2015 IMAC VII Meeting 8
Waste-water storage
• Designed, in tender progress
• Will be located next to water cooling building, buried underground
• Trapped access without radiation shielding door from water cooling building
• Total volume of circulating water in radiation area is 1.8 tones. (beamline and three dumps)
• 3x2 tones all metal modular SS tanks plus 2 tones dispose chamber
• Automatic activated water draining and tank to tank transfer via dedicated piping and pump
• Human contact to water only at clearance volume of piping tunnels between caves
07-08/09/2015 IMAC VII Meeting 9
Modifications
Switched position of CB2 and one layer of radiation shielding blocks
A small control office is built inside He cooling room
Door position of He cooling room is changed because CB1 and dewar is located at the entrance hall of former one
Location and size of former sectional door is changed to allow entrance of CB1 and WWP
07-08/09/2015 IMAC VII Meeting 10
Before
After
Ionized air ducts are reorganized regarding radiation security
• Former distribution was covering almost whole area on the roof
• No trespassing was allowed• Foam duct material, unsafe for radiation• Glued to the ground, no maintenance without
damaging neighboring ducts • Input and exhaust ports were at the same
elevation with beamline
07-08/09/2015 IMAC VII Meeting 11
Air conditioning units located at corridor are moved to terrace • Gained a larger working area• Ease of maintenance• Reduce mechanical vibrations near RF amplifiers and
LLRF• Less complex air duct distribution and homogeneous air
flow
Before After
07-08/09/2015 IMAC VII Meeting 12
• UPS units are moved to former e-gun building
• Reduced cooling costs• Increased number of UPS units• More organized and simpler cabling for electricity grid• Gained more working area inside laboratory• Reduced electricity related security risks
• Power distribution inside laboratory building is reorganized accordingly
Before After
07-08/09/2015 IMAC VII Meeting 13
• Trapped entrance to radiation halls are removed in order to use concrete doors instead of lead doors
• A cheaper solution• More working area• Easier access for big systems• Better radiation security
07-08/09/2015 IMAC VII Meeting 14
Additional cable halls are drilled to radiation area roof (31 in total)
Two stairs are built to radiation area roof
Terrace of laboratory is reorganized as ionized/non-ionized air ventilation plant and storage
07-08/09/2015 IMAC VII Meeting 15
• Former two-story, 6 room experiment station area is demolished in order to build 5 new stations in a single story with elevated height and a clean room according to demands of experiment community
Experiment Stations and Clean Room
07-08/09/2015 IMAC VII Meeting 16
Electricity• One of the main parts
of TARLA infrastructure
• Electricity system is totally reorganized during modifications
• 2MVA + 1MVA backup• 3 x 1000kVA Transformers• 3 x 1100kVA Generator• 6 x 300kVA UPS• Busbar Distribution
07-08/09/2015 IMAC VII Meeting 17
• Load and voltage fluctuation ±5%
• Frequency fluctuation ±1 Hz
• Harmonic distortion isolation for RF system feed (under development)
• Local PLC system for generator synchronization to UPS phase
• Local controller for UPS switching
• SCADA system for grid monitoring and shutter control (under development)
• Synchronized loading of generators <1 min.
• UPS feed duration under %125 load >10 min.
• Coupled grounding for facility and electricity system
• Grounding trays furnished to caves
• No ungrounded power panel or plug.
• Average grounding resistance throughout facility of 0.06 Ω
Three distinct busbar installations for power distribution of 1kA, 1.6kA and 4kA carrying capacity which are connected in parallel to UPS
07-08/09/2015 IMAC VII Meeting 18
Ionized Air Conditioning
• Design and installation of PLC controller for dampers, motors and valves will be done according to safety and hazard analysis which is under the scope of PSS contractor
• Single inlet and outlet coupled to distribution ducts via air dampers. • Distinct air ducts for each hall, no risk of air mixing during operation.• Staff may freely be present in any hall even if the rest of halls are in operation
• Air ducts, inlet coil, exhaust port and dampers are installed
• Design of chimney and filter unit is ongoing
07-08/09/2015 IMAC VII Meeting 19
• 40500 m3/h total air flow rate which corresponds to 25 circulations/hour.
• Combination of bag/HEPA (H14)/carbon filters for exhaust
• 5m chimney height above highest point of roof (17.5m above ground level)
• 900 mbar pressure inside caves (~950 mbar outside)
• Frequency driven suction motor at exhaust port to enable different operation modes
07-08/09/2015 IMAC VII Meeting 20
Radiation Shielded Doors
• Instead of lead composite doors, concrete doors in same thickness with walls are decided.
• Better radiation security
• Easier access for big machines like SRF modules
• Cheaper construction
07-08/09/2015 IMAC VII Meeting 21
• General design is complete
• Total weight is about 130 ton/door
• Dimensions are 3.30x2.25x4.35m
• Construction department approved static calculations for basement
• A hole of 40 cm depth will be dig for traction and actuator system
• Detailed design including static calculations, mechanical design and actuator system design will be done by contractor
• PLC based controller will be done according to the «hazard and risk assessment» of PSS contractor
07-08/09/2015 IMAC VII Meeting 22
Compressed Air
• ATLAS Copco GA 7 VSD+• 5.5-12.5 bar pressure• 7.2-14.2 l/s flow rate• Screw type, frequency controlled
• FD15 drier• Dew point of -400C• Operating pressure up to 16 bar• 15 l/s flow rate
• Tank• 500liters
Installed for He plant primarily but capable of feeding enough pressure/flow for whole facility
Cu piping is installed for He plantAl piping will be used for radiation halls due to lesser contamination
07-08/09/2015 IMAC VII Meeting 23
Water Cooling System
• Water cooling system is composed of;
• a central cooling plant which provides cooling capacity
• three separate circulations; beamline components, beam dumps and radiation non-related systems
• support systems
• Installation is divided into two stages;
• First stage covers central cooling plant, majority of support systems and radiation non-related circulations
Commissioning phase
• Second stage covers beamline /beamdump cooling circulations and waste-water treatment
Design complete/in tender progress
07-08/09/2015 IMAC VII Meeting 24
07-08/09/2015 IMAC VII Meeting 25
• First Stage Covers;
• 1 Hybrid type closed cycle cooling tower, 850.000kcal/h
• 3 Chiller Units 425.000kcal/h each
• 2 Main heat exchangers (1 backup)
• 4 storage tanks• 1x15 ton feed water• 1x1 ton filtered water• 1x5 ton 7/120C chiller buffer• 1x2 ton conditioned water
• 4 frequency driven circulation pumps
• 3 fixed speed mixing pumps• 2 main 3-way mixing valves• 2 2-way by-pass valves• Automation and control system
07-08/09/2015 IMAC VII Meeting 26
07-08/09/2015 IMAC VII Meeting 27
Flow rate Nom. Input Temp Temp rise Conductivity pH Nom. Input
pressure Pressure drop
Radiation non-related systems
~3-30 m3/h 22+/-30C <150C -- -- 6+/-1bar <3 bar
Beamline ~0.2-2.7 m3/h 29+/-10C <150C 1-5 MΩ 8-8.5 6+/-0.5bar <3 bar
Beamdumps 2x4.6 m3/h 29+/-30C <150C 1-5 MΩ 8-8.5 6+/-0.5bar <4 bar
07-08/09/2015 IMAC VII Meeting 28
Segmentation of Laboratory Rooms
1st floor
Sample preperation
room
Small workshop
Acc Hall FEL Hall
Tr room
Proposed area for exp. Stations and clean room
Brems. Hall
He Plant
Clean room
RF and electronic rooms
07-08/09/2015 IMAC VII Meeting 29
2nd floor
serversSystem room
Electronic storage
Electronic workshop
Control room
Diagnostic lab
07-08/09/2015 IMAC VII Meeting 30
Conclusions• Infrastructure is the key point of an accelerator facility
• Without proper and reliable infrastructure actual progress can not be met
• Late 2014 and majority of 2015 is spent on infrastructure studies
• Complete missing parts• Fix problems
• Infrastructure studies are almost completed.
• Technical specification documents are prepared for the rest, we are waiting for the tender procedures to be completed
IMAC VII Meeting
Thank You