 1  ISSUES PERTAINING TO GOVERNMENT OF CHHATTISGARH  S.No Name of the company and location Issues in Brief Action to be Taken 1 NMDC Ltd. NMDC Iron & Steel Plant at Nagarnar, Chhattisgarh 1.  Request for acquisition of about 250 acres of additional land for NMDC’s proposed pellet plant and other associadated activities at Nagarnar. Request has been sent to District Collector, Bastar District in March, 2011. Chhattisgarh State Government to expedite the matter.      2. For providing Power Supply to the Integrated Steel Plant at Nagarnar, Chhattisgarh state Power Transmission Corporation Limited (CSPTCL) has to construct:‐ a) 400 KV line from Raipur to Jagdalpur b) 400/220 KV substation at Jagadalpur c) 220KV line from Jagdalpur to Nagarnar. For these FC has to be obtained by the State Govt at the earliest to ensure their completion by March,2015 for starting commissioning activities of the plant. State Govt. to expedite the processing   3. Early clearance of Forest diversion proposals for the proposed water pipeline for the Nagarnar plant.  State Govt. to expedite the matter  Mining Lease (ML) granting for Sadartera Dolomite Block   4. ML application for Sadartera Dolomite Block. All required documents have been submitted to State’s Forest Deptt. on 10.1.2012  Request for early grant of ML for the required area. 

Upload: ngohanh

Post on 25-Apr-2018

214 views

Category:

Documents


1 download

TRANSCRIPT

  1

 

ISSUES PERTAINING TO GOVERNMENT OF CHHATTISGARH  

S.No  Name of the company and location 

Issues in Brief  Action to be Taken 

1  NMDC Ltd. 

NMDC Iron & Steel 

Plant at Nagarnar, 

Chhattisgarh 

1.  Request for acquisition of about 250  acres  of  additional  land  for NMDC’s proposed pellet plant and other  associadated  activities  at Nagarnar. Request has been sent to District Collector, Bastar District  in March, 2011. 

Chhattisgarh  State Government to expedite the matter.    

    2.  For  providing  Power  Supply  to the  Integrated  Steel  Plant  at Nagarnar, Chhattisgarh state Power Transmission  Corporation  Limited (CSPTCL) has to construct:‐ 

a) 400 KV  line  from Raipur  to Jagdalpur 

b) 400/220  KV  substation  at Jagadalpur 

c) 220KV  line  from  Jagdalpur  to Nagarnar. 

For these FC has to be obtained by the  State  Govt  at  the  earliest  to ensure  their  completion  by March,2015  for  starting commissioning  activities  of  the plant. 

State  Govt.  to  expedite the processing 

    3.  Early  clearance  of  Forest diversion  proposals  for  the proposed  water  pipeline  for  the Nagarnar plant.  

State  Govt.  to  expedite the matter 

  Mining Lease (ML) granting for Sadartera Dolomite Block 

 

 4.  ML  application  for  Sadartera Dolomite  Block.  All  required documents have been submitted to State’s Forest Deptt. on 10.1.2012  

Request  for  early  grant of  ML  for  the  required area. 

  2

2  RINL  Pending PL/ML Application  Two  PL/ML  applications are pending with the State Government 

3  Monnet  Ispat  & Energy Ltd.  

1.5 MTPA 

Integrated Steel 

Plant at Raigarh, 

Chhattisgarh 

Land  acquisition  for  Rajgamar Dipside  (South  of  Phulkadih  Nala) Coal  Block.    Total  mining  Lease Hold Area  is 625 Ha, out of which 450 Ha of area already acquired by SECL  under  CBA  Act.    Request  for transfer  of  land  by  SECL  pending since  21/1/2011.    In  this  process, joint  survey  of  the  mine  by  the surveyors of Monnet and SECL has been  completed  on  15/2/2012.  Detailed Land schedule  is prepared and further action for surrender of Mineral Rights  for overlapped  land is pending with SECL. 

SECL  should be  advised  to transfer  the  land immediately as  the mining lease  can  be  signed  only after land acquisition.    

4  Jindal  Steel  & Power Ltd. 

Expansion  Project 

at Raigarh Plant  

Total  land requirement  is 1244.932 Ha. Out of which 799.101 ha land is in possession 

Iorn Ore Linkage 

 

 Support  is  required  from the State Govt. in acquiring the remaining 465.831 Ha. 

Recommendations of State Govt  either  for  mineral concession  (ML/PL)  for iron  ore  or  JVwith  State Govt.  agency  for  getting linkage.  

    Water Allocation 

Issue  for  allocation  of  balance 88.0MCM of water  is pending with Water  Resources  Department, Govt. of Chhattisgarh since long. 

  

    Draft  EIA  Reports  submitted  to CECB  to  conduct  public  hearing  in March  2012  and  April,  2012  for  1 MTPA  and  7  MTPA  expansion projects respectively. The dates for holding public hearing are yet to be fixed. 

Public  hearing  to  be  held at the earliest 

5.  Jayaswal  Neco Industries Ltd. 

Gare  Palma  IV/8 

Application  for  grant  of  Mining Lease  

Pending  with  State Government    of Chhattisgarh  since 

  3

Coal  Block, Tamnar,  Raigarh, Chhattisgarh 

14.11.2011 

  Laindongri Iron Ore Mine,  Village Barbaspur,  District Kanker 

Grant order for execution of Mining Lease  

Pending  with    the  State Government  of Chhattisgarh for more than 18 months 

  Metabodli  and Chhotedongar  Iron Ore  Mine,  District Kanker  and Narayanpur, Chhattisgarh  

 Execution of Mining Lease for both the mines  

 Work  cannot  be  started due  to  severe  law  and order situation. 

 

  Green field 1 MTPA project  at  village Dagori,  Distt. Bilaspur, Chhattisgarh 

Land acquisition issues  Support  is  required  from the State Govt 

6.  Godawari Power & Ispat  Limited, Rajnandgaon, Chhattisgarh  

Land acquisition  issues In principle approval received from State Government of Chhattisgarh   Allotment of Government Revenue land measuring area of 9.635 hect.  Allotment  of  private  land  area  of 196.006 hect. 

 Chhattisgarh  State Government  to  take decision  

    Water Allocation 

Application  for  allotment  of  17.67 mcm water  

 Pending  with  Water Resource  Department, Government  of Chhattisgarh. 

7.  Vandana  Ispat Limited  Village Anjora/Kopedih, Rajanadgoan, Chhattisgarh 

Diversion  of  land/change  in  Land use 

Pending  with  District  Collectorate, Rajnandgoan,  Govt. of Chhattisgarh 

8.  Shri Bajrang Power & Ispat Ltd 

Dharsiwa‐Tilda  Road,Raipur Chhattisgarh  

Application  for grant of PL  for  Iron Ore 

Pending  with  State Government 

  4

9.  Essar  Steel  India Ltd. 

Vizag 

Laying  of    Iron Ore  slurry  pipeline between Kirandul and Vizag 

 

Matter is under considered with  Chhattisgarh  State Government. 

10.  TATA STEEL LIMITED  

Chhattisgarh  Steel Plant  

5.5 MTPA Integrated Steel plant at Baster. 

 

Land  has  been  acquired  by  the Government  of  Chhattisgarh  and transferred  to  Chhattisgarh  State Industrial  Development Corporation  (CSIDC)  for  allotment to TSL on 99  years  lease.   TSL has requested  for  demarcation  of  the said  land  before  taking  possession of the same 

Physical possession of the acquired land  for  the  Plant  to  TSL  pending more than two years 

State  Government  should expedite  demarcation  of land  after  resolution  of issues. 

 

 

 

To be expedited 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  5

 

ISSUES PERTAINING TO GOVERNMENT OF JHARKHAND   

 

S.No  Name of the company and location 

Issues in Brief  Action to be Taken 

1  SAIL 

 

Issues  in  SARANDA  FOREST DIVISION for which Stage – II Forestry  Clearance  of  SAIL Mines  (KIRIBURU, MEGHAHATUBURU,  GUA  & CHIRIA) are pending: 1. Early  approval  of 

Integrated  Wildlife Management  Plan  of Saranda,  Singhbhum (West)  

2. Submission  of  phased plan  for  future  use  of remaining  unbroken area  within  all  existing leases  in  Saranda  Forest Division  by  Government of Jharkhand to MoEF  

3. Submission  of  the Catchment  Area Treatment  (CAT)  Plan  of Koyna‐Karo  catchment area  in  Saranda  Forest Division  by  Government of Jharkhand. 4. State Government  to identify  inviolate  area  in SARANDA  free  from mining  and  depict  them on  map  with  digitized boundaries. Map  should also depict mining  areas under consideration. 

Government  of  Jharkhand  to expedite compliance of these Stages‐I  forest  clearance conditions  before  grant  of Stage‐II  forest  clearances  for Kiriburu,  Meghahatuburu, Gua and Chiria  leases of SAIL by MoEF.   Non  compliance  of  Stage‐I forest  clearance  conditions may  close mining  operations at  Gua  mines  beyond 13.8.2014 (subject to grant of +1  WP  beyond  13.8.13  by MoEF)  till  grant  of  Stage‐II forest clearance. 

2.  NMDC 

Sasangda  Iron Ore  

NMDC applied for PL for Iron ore mine over  an  area of 1.1546  sq. km.  on  21.5.07.  As  per  the 

State  Government  to  grant  the PL  so  that  the  exploration work in the area could be started. 

  6

Block  agreement  with  the  State Government  the  deposit  will  be developed by the JV Co. of NMDC and  JSMDC  (60:  40)  ratio. Ministry  of  Mines  already granted  its  prior  approval  for grant of PL in favour of JV.   

    NMDC applied  for PL and ML  for Ghatkuri  Iron  Ore  Deposit  on 18.4.2007. 

Grant of the PL and ML  in favour of NMDC.  

    NMDC has applied  for 7 MLs/PLs for  iron ore mines, 2 MLs/PLs for gold  mines,  and  5  MLs/PLs  for bauxite  mines  in  the  Jharkhand State.  

State Government to take further necessary action.  

3.  RINL   Grant  of  07 Nos  of  PLs  for  Iron Ore mines   

Decision on PL applications are to be  expedited  by  the  State Government.  

4.  Tata Steel Limited. 

Jamshedpur  Steel Plant  

 Eastern  Road  Corridor  at Jamshedpur  to  provide  safe  and smooth  uninterrupted connectivity  with  the  National Highway.  Government  of Jharkhand has given  ‘in Principle’ approval  to  execute  the  project as a PPP with them  

State Government to expedite 

    Renewal  of  ML    and  FC  of Noamundi Iron Ore Mine  

ML  of  Noamundi  Iron Ore Mine has  expired  and  is  presently operating  under  “Deemed provision.   

Renewal  of  the ML    and  FC  for Noamundi Iron Mine by the State Government 

    Application  for  grant  of  Forest Clearance  for Kotre Basantpur & Pachmo Coal Blocks 

Pending  with  State  Government of Jharkhand 

    Expansion from  5 to 10 MTPA for  Brown  Field  Integrated  Steel Plant 

Proposal  pending with  Secretary Industries (Govt of Jharkhand)   

5.  Jindal  Steel  & Power Ltd. 

a)    Patratu      

Transfer of Govt. Land by way of Lease  Settlement  is  under process for 188.03 Acres. 

State Govt. to provide assistance in land acquisition 

  7

Project, Jharkhand  Acquisition  of  private  land through  Land  Acquisition  under process for 753.93 Acres. 

    Iron Ore Linkage   Recommendation  from Jharkhand  Govt.  is  pending  for mineral concessions  for  Iron and Manganses Ores.  

    Allocation of Iron Ore mine  To  develop  Iron  Ore  Mines  in Joint  Venture  with  State  Govt. Agency  so  as  to meet  Iron  Ore requirement of Steel Plant. 

    Coking Coal and Non Coking Coal:

 

Part  of  Amarkonda‐Murgadangal non  coking  coal  block  has  been allocated  on  17.01.2008  by Ministry of Coal, Govt. of India to cater  the  requirement  of  1000 MW Captive power plant. 

This  is a  regionally explored coal block  and  needs  further exploration work  to  be  done  by us  to  prepare Geological  Report and Mining Plan. Due to local law and  order  problems,  JSPL  is unable to start exploration work. The company has already applied for  long  term  coal  linkage  to Ministry  of  Coal  on  6.6.2011  for the  1320  MW  CPP  for  the intervening  period  till  the  coal mine is developed. 

6.  JSW  Steel  Ltd Sonahatu  Block Ranchi, Jharkhand   

Govt.    of  Jharkhand  have  issued  an order deallocating 92.50 MCM  of  water  for  its  10  MTPA Greenfield plant. 

State  Government  to  withdraw deallocation order.  

    Speedy  transfer  of  Govt  land (GM‐Jungle  Jhari)  in Gumla Distt in  favour  of  JSW  JSL  for compensatory  afforestation  (CA) purpose  for  Stage‐I  FC compliance  for   Ankua  Iron   Ore and Rohne Coal Mining projects.  

State  Govt.  of  Jharkhand  to provide assistance for transfer of land for CA purpose.  

7.  Jayaswal  Neco Industries  Ltd. Moitra Coking Coal Block,  Hazaribag, Jharkhand 

Application  for  stage‐I  Forest Clearance  

 

 

 

Pending  with  the  State Government  of Jharkhand 

  8

    Request for land acquisition   Pending    before  the  State Government  of  Jharkhand  since 10.7.2005 

8.  Monnet Ispat  and Energy Limited 

Bokaro, Jharkhand 

Land acquisition  issue  Due to unavailability of RoR, land acquisition  is pending with State Government.  

Allocation of land is pending with State Government.  

    Allocation of water  Pending with State Govt.  

 

     Request  for  alternate  iron  ore mine  in  lieu  of  allocation  of Ghatkuri  iron ore mines which  is now reserved for PSUs 

State  Government  should provide required help.  

9  BHUSHAN POWER & STEEL LTD 

Jharkhand  Steel & Power Project 

Land acquisition  Issues  

Land acquisition related issues are the most diffcult being faced by the Company towards implementation of its steel project. As per TEFR, total land requirement was of 3258 acres. 

Based  on  our  original application  dated  1.7.2008  to Secretary,  Revenue  and  Land Reforms, Govt. of  Jharkhand,  for acquisition of land, the same was forwarded by Dy. Commissioner, East Singhbhum  (Jamshedpur)  to Secretary  (Revenue  &  Land Reforms) in May, 2010. However, due to constraints being faced for procurement  of  land  and  our keenness  to  implement  the project,  the Company decided  to initially  proceed  with implementation of 1.0/1.2 MTPA Steel  Plant  and  100 MW  Power Plant in phase‐I over 578 acres of land. The work  for Phase –II will start concurrently as soon as  the land is procured.  

Till date over 380 acrs of private  land  has  already  been purchased.  

State Government to expedite.  

  9

Application  for acquisition  of  further  196.49 acres  of  Private  land  for  Phase‐I was  made  on  14.6.2012  with Principal  Secretary,  Revenue  & Land  Reforms,  Jharkhand. Agreement  for  same  has  also been  signed  on  31.12.2012. However  the  processing  of further  notification  under  4(1) etc is still under process.  

Application  for Government  land  59.98  acres was  made  to  the  Principal Secretary,  Revenue  and  Land Reforms,  Jharkhand on 4.7.2011. Currently the same  is  lying  in the office  of Dy.  Commissioner,  East Singhbhum  for  further processing.  

As  required  for acquisition  of  private  land  and Govt.  land,  the  statutory  Gram Sabhas  have  already  been successfully conducted. 

Application for Scheduled Tribe  land  62.07  acres  stands filed in the court of Dy.  

Commissioner  for awarding the land in their favour. 

10.  Arcelor Mittal  India Limited 

Jharkhand 

 

Forest  Clearance  application  in respect of 662.95 Ha Karampada PL  area  pending  since  25.2.2011 and permission for test drilling.  

State  Govt.  to  grant permission  for  exploratory drilling and FC for land.  

     Applied for acquisition of 2210 acres of land in Nov’ 11 under the Jharkhand Voluntary Land Acquisition Rules 2010   

Government of Jharkhand may be requested to acquire land expeditiously.  

 

 

 

 

  10

 

ISSUES PERTAINING TO GOVERNMENT OF ODISHA  

 

S.No  Name of the company and location 

Issues in Brief  Action to be Taken 

 

SAIL 

Bolani & Barsua Iron ore Mines 

Anomaly in the levy of royalty on iron ore in the State of Odisha 

1. After  the  issue  of  circular dated  07.09.10  of Commissioner‐cum‐Secretary, Govt. Of Odisha, Dept. of Steel and  Mines,  the  royalty  on both  iron ore  lump as well as on fines from Bolani & Barsua mines  of  SAIL  are  being charged at the rate of lump on the  assumption  that  these mines  are  producing calibrated  lump  Ore  (CLO‐ input  for  DRI  route  of  iron making).  

2. Further,  from  Sep’2012 onwards,  under  Orissa Minerals  Rules,  2007,  for being exempted from stacking and  sampling  of  iron  ore, royalty on both  iron ore  lump and  fines  from  Bolani  & Barsua mines of  SAIL  is being charged  at  the  royalty applicable  to highest grade of iron  ore  lump.  On  these accounts an additional burden of  about  Rs.248  crore  has impacted  the  bottom  lines  of SAIL till May’13.  

1. To  review  the system  of  charging of  royalty  for  fines at  the  rate  of  lump at Bolani and Barsua mines  during August’2009  till August’2012  on  the pretext of CLO being produced.  

 

2. To  review  the system  of  charging of  royalty  for  fines at  the  highest  rate of royalty applicable for  lumps under the provisions  of exemption  from stacking  and sampling  for  Bolani and  Barsua  mines since September’2012 onwards.  

  SAIL, Thakurani Block‐A, 277.683 Ha 

Grant  of  Prospecting  License(PL) for Thakurani Block A(277.683 ha)  

Govt of  India  in consultation with 

Pending  with  State Governmwent 

  11

Govt.  of  Orissa  had  reserved 277.683  Ha  in  Block  –A  for  50 years  for  SAIL  for  undertaking exploration  vide  Gazette notification  dated  4.2.04.  Against this Notification, SAIL had applied for Grant of PL for Thakurani Block – A  (277.683 ha)  in Apr’04.  Since then  the  application  is  pending with State Government. Utkal  B‐1  coal  block  allocated  to  the Company  can meet  coal  requirement of  the  project  for  only  2  MTPA capacity  DRI  plant  only.  Execution  of Mining Lease Deed is pending for close to 1 year 8 months 

 

 

 

Govt.  of  Odisha  to expedite  execution  of ML  and  allotment  of additional coal blocks 

Allocation of captive  iron ore mine  for the  integrated  steel  plant  or  JV  with OMC 

Pending  with  State Government.  

Lying  of  balance  stretch  of  3.4  Km water pipeline  for Angul plant delayed due to  local resistance 

 

State Government to assist in laying of pipeline 

 

 

Revalidation  of  water  usage  approval which expired in August,2011 

 

State Govt. to revalidate 

 

Requirement  of  additional  land  (520 Ac) for water reservoir 

Proposal  to be  cleared by State. 

2  Jindal  Steel  & Power Ltd. 

Angul Project, Odisha 

Construction  of  new  road  from  Banarpal  to  Angul  town  by‐pass  road from  north  of  Angul  town  for congestion free movement of coal from mines 

Pending  with  State Government. 

  12

3.  Bhushan  Steel Ltd 

Grant  of  Mining  Lease  for  Iron  Ore Mines 

 Commissioned  3  MTPA  Integrated Steel  Plant.  The  Plant  capacity will increase to 5.6 MTPA by end of this month, i.e. March, 2013 

A  steel  plant  of  such  a  large  capacity cannot be operated without allocation of Captive Iron Ore Mines.  

Grant  of  Iron  Ore  Mining lease  to  cater  to requirement of Iron Ore for 5.6 MTPA  integrated  Steel plant.  

Till  such  times  mines  are allocated  and  become operational,  OMC  (an Odisha  Government  State Undertaking)  should  be directed  to  accord  a dedicated  linkage  of required  quantity  of  iron ore  to  BSL  at  reasonable price from their mines. 

    Truck  Unions  and  Transporters  are literally  blackmailing  the  consumers  in the  state  of  Odisha.  Per  ton transportation  rate  in Barbil  is  highest in  the  world.  A  guideline  for  freight charges in this regard was issued by the Odisha Government  but  it’s  not  being followed. 

The  guideline  should  be enforced by the state govt. strictly. 

 

 

4  Bhushan  Power &  Steel  Ltd. Odisha 

Execution of Jamkhani Coal Block  

 

Pending  with  Department of  Steel  and  Mines, Government of Odisha. 

 Matter may be expedited. 

    Execution  of Mining    Lease  of  Bijahan Coal Block  

Pending  with  Department of  Steel  and  Mines, Government of Odisha  

5  RINL  Application for ML  5  ML  applications  are pending  with  the  State Government  for  allotment of  iron  ore  mines.  To  be expedited.  

6  Monnet Ispat 

Angul, Odisha  

Captive iron ore mine  State    Government  should  provide required help  

7  Posco‐India Private Ltd.  

12  MTPA Integrated  Steel 

Prospecting  Licence  (PL)  In  2006,  the 

Govt. of Odisha recommended POSCO’s 

PL  application  dated  July,  2005  to  the 

Central  Govt  for  the  grant  of  PL  in 

The MoM  should  take  the 

decision  at  the  earliest  so 

that  POSCO  can  start  the 

prospecting  mining 

  13

Plant 

Jagatsinghpur, 

Odisha 

Sundergarh.  After  hearing  all  pending 

applicants  as  per  the  order  of  the 

Revisional Tribunal, the Govt. of Odisha 

again  recommended  POSCO’s  PL 

application  in  2009.  The 

recommendation  was,  however, 

quashed  by  the  Odisha  High  Court  in 

2010.  Finally,  on  10th  May  2013,  the 

Hon’ble  Supreme  Court  set  aside  the 

Odisha High Court’s order and remitted 

the matter to the Central Govt to take a 

decision  on  an  early  date  and 

communicate the same to the Govt. of 

Odisha. 

activities  

Essar  Steel Limited 

Paradip Odisha 

Allocation of Captive mines   Pending  with  State Government 

  Grant of Priority C status for movement of Iron Ore Fines from Dhamra to ISP at Hazira.  

State    Government  should  provide required help  

Essar  Steel Limited 

Vizag 

Laying  of    Iron  Ore  slurry  pipeline between Kirandul and Vizag 

 

Matter  is  under consideration  with  Odisha State Government. 

 

OMDC  Renewal of mining leases of:‐ 

Kolha‐Roida Iron Ore & Mn. 

Mines (254.942 Ha.). 

Thakurani Iron Ore & Mn. 

Mines (778.762 Ha.). 

Dalki Mn. Manganese Mines 

(266.77 Ha.).  

Bhadrasahi Iron Ore & Mn. 

Mines (998.70 Ha.). 

Belkundi Iron Ore & Mn. Mines 

(1276.798 Ha.) 

Bagiaburu Iron Ore Mines 

(21.52 Ha.). 

Govt. of Odisha to expedite the matter 

  14

ii) Permission to operate Kolha‐

Roida Iron Ore & Mn. Mines 

which has got all Statutory 

Clearances since 23.07.2012. 

iii)   Permission for dispatch / Sale 

of Mined out ores in various 

stock areas of all the above 

mining leases. 

 

10  VISA STEEL LIMITED  

District Jajpur, Kalinganagar (Odisha) 

 Allotment  of  306  Ac  of  land  for  solid waste disposal 

 State  Government  to expedite.  

    Supply of adequate quantity of Iron Ore and  Chrome  Ore  at  reasonable  price under long term agreement from OMC. 

State Government to help . 

 

 

    Visa  Steel  signed  MoU  with  Odisha Govt. in 2003. Allotment of captive iron ore mine pending since 2005  

State  Government  to expedite  allocation  of captive iron ore mine.   

    Price fixing mechanism for proposed e‐auction of  iron ore and casting one for chrone  ore  by  OMC  needs  to  be modified  for  viability  of  the  user industry.  

State  Government  to  take  favourable decision 

    Allotment  of  additional  675  acres  of adjoining  land  for  expansion  of  steel capacity to 2.5 MTPA at Kalinganagar. 

State  Government  to speed up the process 

 

 

  15

ISSUES PERTAINING TO GOVERNMENT OF MAHARASHTRA

S.No Name of the

company and

location

Issues in Brief Action to be Taken

1.  SAIL (CFP) Chandrapur, Maharashtra 

Issue  of  Prospecting License(PL)  of Manganese  ore  for Chandrapur Ferro Alloy Plant  (CFP)  in  four areas  namely  Tekadi, Hiwra,  Paonar  Khairi and Gonditola  

 

The  areas  for  Prospecting  License (PL) may  be  allocated  to  SAIL  on priority  for  the  viability  of  the CFP/SAIL.  

2  JSW Ispat Steel 

Ltd., Dolvi, Tal‐Pen, 

Dist. Raigad, 

Maharashtra

a)       Land Acquisition of internal land area of 4.16.30 Hect required for expansion of the plant.   

 

Government  should  help  in  land acquisition  where  minority  land holders  where  land  is  embedded  are holding back  

    b)        Issuance of LoI for 

Iron Ore Mine  in 

Gadchiroli District for 

which prior approval 

under Section 5(1) of 

MMDR Act 1957 

already granted 

 

Government should expedite the matter

  16

ISSUES PERTAINING TO GOVERNMENT OF WEST BENGAL

S.No  Name of the 

company and 

location 

Issues in Brief  Action to be Taken 

1.  JSW Steel Ltd Salboni, West Bengal

Reservation of Ghatkuri Mines, Jharkhand for the Steel plants coming up in the State of West Bengal. In the year 2006, Govt of Jharkhand has reserve the area for the PSU u/s 17 A (2) of MMDR ACT, 1957.

To be expedited.

2.  Jai Balaji Industries Limited.

Brown Field Mangalpur, P.O Bakhtarnagar, Distt. Burdwan, West Bengal

Grant of NOC for expansion Pending with State Government.

  Greenfield Project at Raghunathpur, Distt Purulia, WB

Land Deed is not executed

Grant of NOC

Execution of Agreement for water requirement

Early execution of Land Deed from Government of West Bengal Pending with State Government. Early execution of Agreement Pending with State Government

 

  17

ISSUES PERTAINING TO GOVERNMENT OF KARNATAKA

S.No  Name of the 

company and 

location 

Issues in Brief  Action to be Taken 

1  NMDC Ltd. 

 

 

 

Granting  of  ML  in  the 

Ramandurg  iron  ore  mine 

to  NMDC  primarily  to 

ensure  feeding  of  iron  ore 

on  sustained  basis,  to  the 

steel plant proposed  to be 

set up by NMDC at Bellary 

in  pursuance  of  MoU 

singed  between  Govt.  of 

Karnataka and NMDC 

To be expedited

2.  RINL Application for captive  iron 

ore mine 

One  ML  application  is  pending  for 

consideration 

3.  Arcelor Mittal India Ltd.  Bellary, Karnataka

 Application for captive iron 

ore  mining  pending  with 

the State Govt.   

 State Govt. to expedite processing.  

 

 

 

 

 

 

 

 

 

 

 

 

  18

 

ISSUES PERTAINING TO GOVERNMENT OF ANDHRA PRADESH

S.No  Name of the 

company and 

location 

Issues in Brief  Action to be Taken 

1.  RINL  Water : RINL made Tripartite agreement with Govt. Of Andhra Pradesh and Visakha Industrial Water Supply Company (VIWSCO) to meet its raw water requirement. The agreement envisages increase in water quantity to meet expansion requirement by making a supplementary agreement. RINL is pursuing for supplementary agreement for enhancing water quantity up to 45mgd to meet the requirement for 7.3 mtpa

State Government of Andhra Pradesh to provide required help

    Power : 1. Eastern Power Distribution Company of A.P (APEPDCL) had enforced Restriction & Control (R&C) measures, even for drawl of power within the Contracted Maximum Demand, with effect from September’12 onwards. RINL had also taken up the matter of exemption of R&C measures with the Hon’ble Chief Minister of AP and other officials for kind consideration. A writ petition is also filed at Hon’ble AP High court seeking relief from imposition of R&C

Since, RINL is a continuous manufacturing Plant with captive power generation and highly thermal sensitive units, help required from State Govt. of Andhra Pradesh to

- exempt RINL from R&C measures for safe operation of the plant,

- waiver of penal charges imposed on RINL towards R & C measures & surcharges, which include penal charges on account of momentary surges in power import due to disturbances in captive power generation

- regularize RINL’s request for enhancement of Contracted Maximum Demand, from 135 MVA to 235 MVA, to ensure commissioning of expansion units.

  19

measures. APEPDCL has levied 118.78 crores towards penal charges on account of R & C measures for the period Sept’12 to May’13 and cumulative surcharge of 5.75 crores for delay in non-payment of the penal charges. 2. RINL had filed an application in Oct.’07 for enhancement of contract demand to 400MVA in phased manner for meeting 6.3 MTPA expansion requirements from existing 135 MVA at 3.0 MTPA stage. APTRANSCO agreed to take up the power requirement in 4 phases at a cost of 86.33 crores. RINL paid 63.02 crores for phase 1, 2 & 3. The phase 1 works have been completed by APTRANSCO and clearances have been given by APTRANSCO and APEPDCL to enhance the Contract Maximum Demand by 100 MVA from 135 MVA to 235 MVA).

    Revenue loss to the tune of 3.15 crores towards energy export during Jan & Feb.’07

During the power crisis during Jan & Feb’ 2007, RINL maximised its captive generation by changing the fuel mix to export power to grid based on the written request from CMD / APEPDCL.

In spite of agreed price @ 3.24 per unit towards the export for the period, the

Support from State Govt. of Andhra Pradesh is needed for the Payment of 3.15 Crores to RINL from APTRANSCO / APPCC towards energy export during Jan & Feb.’07.

  20

APTRANSCO / APPCC initially paid @ 3.24 per unit, later adjusted to the @ 1.75 per unit, resulting in loss of revenue amounting to 3.15 crores.

    Expressway alignment

Visakhapatnam–Kakinada Petroleum, Chemicals and Petro-Chemicals Investment Region Special Development Authority (VK-PCPIR SDA) proposed Expressway alignment (75 M corridor) connecting Kakinada Port to Gangavaram Port, along Visakhapatnam coast or across RINL land premises. Considering future expansion, captive port, desalination plant, safety and security aspects, RINL-VSP informed that above alignments are not feasible and suggested to take up alignment along western boundary of VSP.

GoAP to consider the alignment as suggested by VSP.

    Allocation of Land RINL requested GoAP to allocate about 800 acres of land nearer to VSP to facilitate re-location of green belt so that existing green belt land adjacent to Plant premises may be used for establishing expansion units.

GoAP to expedite allocation of land.

    Double lane road VSP’s Hyderabad stockyard is located at

Support from GoAP for widening of single lane road to a double lane

  21

Patancheru and connected by single lane road from National Highway, which is to be widened to a double lane road.

road.

    Govt of Andhra Pradesh has issued a Memo stating that RINL’s application for ML/PL in two areas in Warangal and Karimnagar districts would be processed.

To be expedited

2  M/S Kamineni 

Steel & Power 

India Pvt. Ltd.  

 

 

Non‐allocation of Water  to their Steel Plant 

To be expedited

3.  Essar  Steel Limited 

Vizag 

Laying  of    Iron  Ore  slurry pipeline  between  Kirandul and Vizag  

Matter  is  under  considered  with Odisha State Government.