joju - bpr 4
TRANSCRIPT
-
8/3/2019 Joju - BPR 4
1/12
BUSINESS PROCESSRE - ENGINEERING
Re Engineering
( Implementation Phase )
-
8/3/2019 Joju - BPR 4
2/12
The key stages in implementingBusiness Process Re-engineering (BPR)
Successful re-engineering requires a clear understanding
that:
organizations should be process--not function--driven;
processes must be built around the customer; and
staff involvement at all stages of design, planning, implementation
and maintenance is a prerequisite for success--staff are the
"cement" who bind everything together.
-
8/3/2019 Joju - BPR 4
3/12
Although there have been many BPR-driven successes,
there has also been criticism of the relatively high failure
rate as well, where companies have not obtained theexpected results.
Reasons put forward for failure include: confusing
downsizing with changing the way things are done; too
much emphasis on reducing staff, poor redesign of
processes; continuing with a departmental, rather than a
process-driven, customer-focused culture; introducing newtechnology in isolation; and failing to involve staff at every
stage.
-
8/3/2019 Joju - BPR 4
4/12
Implementation Phase(Hammer & Champy)
Plan the implementation
Appoint a project co-ordinator or team.
Decide if implementation will be carried out in one
major effort or in two or more phases.
Decide on a start and finish date. If possible choose
slack periods.
Decide which existing and new processes and systems
will be run in parallel before old ones are dropped.
Prepare a detailed, prioritized day-by-day schedule for
key staff, and an outline plan for everyone else.
-
8/3/2019 Joju - BPR 4
5/12
Contd Ensure that key staff are fully briefed and that training has been
given where appropriate.
Ensure that key external partners, such as suppliers, are fully
briefed as to how, and from when, the changes will affect their
operations.
Notify key customers, and other key partners that normal service
will be resumed as soon as possible. Put details on the corporate
web site (if one), with contact names and details.
Allow sufficient time for testing, settling in, tweaking, trouble-
shooting and general "hand-holding". This is likely to be a
particularly stressful time to those at the sharp edge.
Issue regular progress reports.
-
8/3/2019 Joju - BPR 4
6/12
Implementation Timeline
Depict each major step in theimplementation of the solution on a timeline.Major steps should include: development,
testing, training, initial implementation, androllout.
Consider any impacts to the organization
from a productivity or operational viewpoint.
-
8/3/2019 Joju - BPR 4
7/12
Contd..
Most implementation plans get dictated by the systems development
schedule because it is usually the least flexible and has the most
dependencies.
However, it is important that your team think about each solution
element, and define an implementation timeline that will maximize
benefits while having the fewest impacts on the organization.
The implementation focus will enable you to prioritize the steps in the
implementation.
-
8/3/2019 Joju - BPR 4
8/12
Example
For example, if the focus is to streamlinethe operation, then the priority would be to
implement the automated functions quickly. In order to help you to focus your
implementation, link your costs and benefits
to the timeline
-
8/3/2019 Joju - BPR 4
9/12
Effective communication
Effective communication is considered a major key
to successful BPR-related change efforts
Communication is needed throughout the change
process at all levels and for all audiences even
with those not involved directly in the re-
engineering project
-
8/3/2019 Joju - BPR 4
10/12
Effective communication between stakeholders inside and
outside the organization is necessary to market a BPR
programme and to ensure patience and understanding of
the structural and cultural changes needed as well as the
organization's competitive situation
Communication should take place BPR implementation
process frequently and in both directions between those in
charge of the change initiatives and those affected by
them
Communication should be open, honest, and clearespecially when discussing sensitive issues related to
change such as personnel reductions
-
8/3/2019 Joju - BPR 4
11/12
Success of Implementation
Following the publication of BPR by Hammer& Champy, Davenport & Short manyorganizations have successfully
implemented and achieved dramaticbenefits from BPR.
Companies such as Ford Motors, CIGNA,and Wal-Mart are some of the organizationsrecognized for successful implementation ofBPR
-
8/3/2019 Joju - BPR 4
12/12
THANK
YOU