KERTAS 3A: CASE STUDY:
STESEN MINYAK PETRONAS DI PENCHALA LINK (KATEGORI PROJEK BERSKALA KECIL BUKAN KEDIAMAN)
Bengkel Pengenalan OSC 3.0 untuk ‘Principal Submitting Person’ dan ‘Submitting Person’
Ir Bashir Ahamed Maideen, FGDCP 17 Mei 2014
SMALL SCALE PROJECT
DEWAN BANDARAYA KUALA LUMPUR
INTRODUCTION
I. Commercial building of not more than 3 storeys height on land area not exceeding 1 acre, such as: a. Fast Food Outlet b. Car showroom, office equipment or furniture exhibition area c. Factory, warehouse, stores d. Kindergarten, childcare centre e. Club house
II. A public amenity building of not more than 3 storeys height on land area not exceeding 1.5 acre (multi-purpose hall, public facility building, place of worship).
III. A petrol station on land area not exceeding 1.5 acre. IV. A Shop building of not more than 3 storeys height. V. A power supply sub-station building of not more than 3
storeys height on land area not exceeding 1.5 acre.
1
SMALL SCALE PROJECT CRITERIA – OSC 1SUBMISSION
INTRODUCTION
In compliance with the existing LOCAL PLAN.
In accordance to the express conditions stated in the land title.
The land matters does not requires the approval from the state EXCO.
Development on land with Class 1 slope category (less than 15 degree)
5
Development outside Heritage Zone
• Water demand not exceeding 10,000 liter per day.
• The length of pipe connection not exceeding 30m from the existing water supply pipe line.
• The water supply pipe diameter not exceeding 150mm.
2
3
4
5
6
7
SMALL SCALE PROJECT CRITERIA – OSC 1SUBMISSION
INTRODUCTION
SMALL SCALE PROJECT CRITERIA – OSC 1SUBMISSION
• The electricity power demand not exceeding 1000kVA with a distance of less than 500m from source of supply (Data validity period of 3 months).
• Sewerage system to be connected to public sewer line; or a septic tank designed for capacity of not more than 150 PE.
• With telecommunication infrastructure facilities.
8 9
10
THE PHASES / STAGES
S1: Stage 1 Pre Construction
S2 : Stage 2 During Construction
P2 P3 P4
Notice of Commence-
ment of works -
B Form & PDC 6
PSP/SP Submit Plan to Internal
and External Department/ Agencies
Interim Inspections
Process 2 Process 3 Process 4
OSC 1 SUBMISSION : DEALING WITH CONSTRUCTION PERMITS IN KL
OSC 1
Submission
Pre- Consultation
TNB & SYABAS
P1
Process 1
Start
S3: Stage 3 Post Construction
Process 6
P6
Owner/PSP Apply Final Inspection
R&D, BOMBA and
IWK
End
PSP Deposit CCC
F Form and G1 to G21
Forms
Process 5
P5
Owner/PSP Apply Utility
Final Inspection & Connection NFP, Water
and Electricity
10 Procedures and 100 days
OSC 1 SUBMISSION : DEALING WITH CONSTRUCTION PERMITS IN KL
Pre-Construction 1 Procedures, 51 days
OSC
JPRB Planning Permission & Landscape Permission
Submission by SP
JRBB Building Plan including: -Car Park -MSMA & SPAH
JPIF
-Earthwork -Road & Drainage -Street Lighting -Road Excavation Permit (JKAWS)
OSC Meeting
Approval Issued to PSP
Red
arr
ow
s sh
ow
flo
w o
f co
mm
ents
/rec
om
men
dat
ion
s
JPRB Prepare
Approval Document
JRBB Prepare
Approval Document
JPIF Prepare
Approval Document
TNB Electrical Detail Design
BOMBA Prepare
Approval Document
IWK Prepare
Approval Document
SKMM Prepare
Approval Document
BOMBA Plan Endorsement -Architectural -M&E
IWK Sewerage Planning &
Design
SKMM Communication
Infrastructure Plan
SYABAS Detail Design
TNB Load data and power source
SYABAS Pressure Test and Tee off
point
Submission by PSP
Pre-Consultation
OSC
SYABAS Prepare
Approval Document
TNB Prepare
Approval Document
2 days 14 days 14 days 14 days 7 days
1
Process 2 PSP/SP Submit
Plan Internal and External
Process 1 Pre-Consultation TNB & SYABAS
Notes :
World bank did not consider Pre-
consultation as Procedure.
PPSPPA
JPRB – Jab. Perancangan Bandar JRBB – Jab. Rekabentuk Bandar dan Bangunan JPIF – Jab. Perancangan Infrastruktur JKAWS – Jab. Kerja Awam dan Saliran PPSPPA – Perbadanan Pengurusan Sisa Pepejal dan Pembersihan Awam
OSC 1 SUBMISSION : DEALING WITH CONSTRUCTION PERMITS IN KL
Form B Building
IWK Commence-
ment of Work PDC 6
OSC
1 day
Pre-Construction 1 Procedure, 1 day
2
JKAWS Payment for
Road Excavation
Process 3 Notice of Commencement of works.
Form B E/work
PSP
JPRB – Jab. Perancangan Bandar JRBB – Jab. Rekabentuk Bandar dan Bangunan JPIF – Jab. Perancangan Infrastruktur JKAWS – Jab. Kerja Awam dan Saliran PPSPPA – Perbadanan Pengurusan Sisa Pepejal dan Pembersihan Awam
NFP Telecommunication
Connection
TNB Final Inspection &
Letter Clearance
SYABAS Inspection and Connection to
Public pipe
SYABAS Received
T & C Report from SP
OSC 1 SUBMISSION : DEALING WITH CONSTRUCTION PERMITS IN KL
7 days
Post-Construction 4 Procedures, 31 days
3
7days + 1day
OSC Request by
PSP
TNB Electricity
Connection
4 5 6
2 days
Process 5a Apply Utility Final Inspection & Connection - NFP, Water Supply and Electricity
SYABAS Meter
Connection& Clearance Letter
14 days
Issuance of Clearance
To PSP
JPIF Road &
Drainage (risk-based inspection)
Notification & Request by
PSP OSC
BOMBA Inspection Letter of
Clearance
IWK Testing &
Commissioning Letter of
Clearance
OSC 1 SUBMISSION : DEALING WITH CONSTRUCTION PERMITS IN KL
2 days 14 days
Post-Construction 3 Procedures, 16 days
7
8
9
Process 5b Owner / PSP Apply Final Inspection - R&D, BOMBA and IWK
DBKL Deposit
CCC
OSC 1 SUBMISSION : DEALING WITH CONSTRUCTION PERMITS IN KL
1 day
PSP Deposit
CCC
Post-Construction 1 Procedures, 1 day
BAM/BEM Deposit
CCC
10
TOTAL 10 PROCEDURES AND 100 DAYS
OSC
Process 6 PSP Deposit CCC - F Form and G1 to G21 Forms
KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN 1 FEBRUARI 2014
OSC 1SUBMISSION 1st PROJECT IMPLEMENTATION
Project: Petronas Petrol Station
Penchala Link (PPS Penchala Link)
Location: Sungai Penchala KM 2.95
(Before Bkt Kiara Toll)
Status Tanah: Stesen Minyak
Zoning: ok
• Developer : Petronas Dagangan
Sdn Bhd
• Local Authority : DBKL
• PSP: BDA Architect
• SP: Nadi Consult Era Sdn Bhd
• Contractor: Dua Medan Cons. S.B.
SITE LOCATION
Site located at Penchala Link KM2.95, Selepas Tol Bukit Kiara
SITE LOCATION
KELULUSAN TERIMA
MAJLIS PENYERAHAN KELULUSAN
Majlis Penyerahan Dokumen Cadangan Pembangunan Stesen Minyak kepada Tetuan
Petronas Dagangan Bhd telah diadakan pada 24 Julai 2012 di Menara DBKL
GAMBAR SIAP
72 hari 10 Prosedur
19
Model Baru OSC 1 Submission di
Kuala Lumpur terbukti berkesan
P2 P3
To Start Construction
B Form & PDC 6
PSP/SP Submit Plans
To all Internal and External Department/
Agencies
Process 2 Process 3
Pre- Consultation TNB, Syabas
& SKMM
P5
Owner/PSP Apply Utility
Final Inspection & Connection NFP, Water
and Electricity BOMBA and
IWK, Notification
for R&D
P1
Process 1
PSP Deposit CCC
F Form and G1 to G21
Forms
9 Procedures and 48 days
Interim Inspections
Process 4 Process 5 Process 6
P6
END START P6 P5 P4 P3 P2 P1
Procedure - 0 0 day
Procedure - 1 30 days
Procedure - 1 1 day
Self Regulation
Procedures - 6 16 days
Procedure - 1 1 day
P4
OVERALL PROCESSES OSC 1 SUBMISSION
New OSC Submission Process for Big Scale Project
A source of valuable technology…
During the working session to improve DCP ranking,
FGDCP discovers many areas and opportunities for
improvements. Improvements were made to reduce
number of procedures, time and cost…
Thus ‘valuable technology’, that is ‘efficient methods’ in the
process and procedure are discovered.
The OSC 1Submission model was tested with real projects,
now the ‘technology’ discovered is going to be implemented
for big scale projects – KLis BEST & OSC 3.0
KUALA LUMPUR INTEGRATED SUBMISSION
BE EFFICIENT, SYSTEMATIC &
TRANSPARENT
P2a P3
Pemberitahuan Mula Kerja
• BORANG B (BGN & KERJA TANAH)
• PDC 6
Pertimbangan Kelulusan
Pembangunan • KM • KERJA TANAH • PRE-COMP • KONSEP INFRA • PERIHAL TANAH • LALUAN
ANGKUT BAHAN – JPB
• LALUAN UTILITI
Proses 2 Proses 4
Pra Rundingan • REKABENTUK
P5
Pemeriksaan Interim
P1
Proses 1
Pemeriksaan Akhir
Peringkat I & Peringkat II
23/24 PROSEDUR DAN 145 HARI
Kelulusan Pelan Perincian II
• BOMBA M&E • IWK • SYABAS • TNB
Proses 5 Proses 6 Proses 7
P6
PERINGKAT – PERINGKAT PEMBINAAN KL IS BEST
AKHIR MULA P6 P5 P4 P3 P2 P1 P7
Pendepositan CCC dan
Borang-Borang G
Proses 7
P7
Prosedur - 1
Hari - 14
Prosedur - 1
Hari - 45
Prosedur - 1
Hari – 4 Prosedur - 1
Hari - 1
Prosedur - 7
Hari - 8
Prosedur - 8
Hari - 30
Prosedur - 1
Hari - 1
P4 P2b
Kelulusan Pelan Perincian I
• Pelan Bangunan BORANG A
• PJ – R&D • STREET
LIGHTING • BOMBA
(PASIF) • PDC 2
Proses 3
Prosedur - 1
Hari - 30
Mula kerja tanah
Towards Government 3.0
Open Government (Transparency, Participation and
Collaboration) :
Should we make Operational data Transparent.
Real-time traffic management everyone devices.
Citizen-to-government to consumer-device to
government-infrastructure
Government IT applications run side by side with
consumer applications (and share data) on what we
call today the “public cloud”
LATEST INNOVATION BY DBKL
COLOUR CODING TRACKING SYSTEM
COLOUR CODING TRACKING SYSTEM
COLOUR CODING TRACKING SYSTEM
COLOUR CODING TRACKING SYSTEM
Received e-mail notification through KL Trax
Thank You…