khsd road construction plan-keno city bypass road … · figure 2 conceptual road design ... this...

20
ROAD CONSTRUCTION PLAN –KENO CITY BYPASS ROAD KENO HILL SILVER DISTRICT MINING OPERATIONS QML0009 REVISION 1 November 2012

Upload: doxuyen

Post on 06-May-2018

215 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: KHSD Road Construction Plan-Keno City Bypass Road … · Figure 2 Conceptual Road Design ... This plan is intended to address construction, operation, and maintenance ... The Bypass

ROAD CONSTRUCTION PLAN – KENO CITY BYPASS ROAD 

KENO HILL SILVER DISTRICT MINING OPERATIONS 

QML‐0009 

REVISION 1 

November 2012 

 

Page 2: KHSD Road Construction Plan-Keno City Bypass Road … · Figure 2 Conceptual Road Design ... This plan is intended to address construction, operation, and maintenance ... The Bypass

  

ROAD CONSTRUCTION PLAN – KENO CITY BYPASS ROADQML‐0009 

Keno Hill Silver District Mining Operations NOVEMBER 2012 

 

KHSD_ROAD_CONSTRUCTION_PLAN‐KENO_CITY_BYPASS_ROAD_NOV2012        I 

 

TABLE OF CONTENTS 

1 INTRODUCTION ................................................................................................................................................................ 1

2 SITE DESCRIPTION ............................................................................................................................................................ 1

2.1 HISTORY ...................................................................................................................................................................... 12.2 GEOLOGY .................................................................................................................................................................... 22.2.1 PROPERTY GEOLOGY .................................................................................................................................................. 22.3 GENERAL ENVIRONMENTAL CONDITIONS ........................................................................................................................... 52.4 LIGHTNING CREEK ......................................................................................................................................................... 6

3 ROAD DEVELOPMENT OVERVIEW ........................................................................................................................................ 6

3.1 ONEK ACCESS BRIDGE .................................................................................................................................................... 6

4 SITE PREPARATION ........................................................................................................................................................... 7

4.1 CLEARING .................................................................................................................................................................... 74.2 HERITAGE RESOURCES PROTECTION ................................................................................................................................. 7

5 ROAD DESIGN AND SPECIFICATIONS ..................................................................................................................................... 7

5.1 HAUL ROAD SPECIFICATIONS ........................................................................................................................................... 75.1.1 HAUL ROAD DESIGN CRITERIA ...................................................................................................................................... 85.1.2 HAUL ROAD CONSTRUCTION GUIDELINES ....................................................................................................................... 95.1.3 HAUL ROAD MAINTENANCE ......................................................................................................................................... 95.1.4 HAUL TRUCK CLEANLINESS ........................................................................................................................................ 105.2 ACCESS TIE‐IN AND STAGING AREAS ............................................................................................................................... 105.3 ACCESS CONTROL ....................................................................................................................................................... 105.3.1 TEMPORARY ACCESS CLOSURE.................................................................................................................................... 105.3.2 PERMANENT ACCESS CLOSURE ................................................................................................................................... 11

6 BORROW SOURCES ........................................................................................................................................................ 11

7 GEOCHEMICAL EVALUATION ............................................................................................................................................ 11

8 GEOTECHNICAL TESTING .................................................................................................................................................. 11

Page 3: KHSD Road Construction Plan-Keno City Bypass Road … · Figure 2 Conceptual Road Design ... This plan is intended to address construction, operation, and maintenance ... The Bypass

  

ROAD CONSTRUCTION PLAN – KENO CITY BYPASS ROADQML‐0009 

Keno Hill Silver District Mining Operations NOVEMBER 2012 

 

KHSD_ROAD_CONSTRUCTION_PLAN‐KENO_CITY_BYPASS_ROAD_NOV2012        II 

 

9 BEST MANAGEMENT PRACTICES ....................................................................................................................................... 12

9.1 ENVIRONMENTAL MONITORING .................................................................................................................................... 12

LIST OF FIGURES 

Figure 1 Keno City Bypass Road Routing and Access Management ............................................................................ 14Figure 2 Conceptual Road Design ................................................................................................................................ 15Figure 3 Typical Conceptual Road Section ................................................................................................................... 16Figure 4 Typical Bridge Design ..................................................................................................................................... 17

 LIST OF TABLES 

Table 1 Keno Hill District Environmental Setting Summary ........................................................................................... 5Table 2 Road Design Criteria .......................................................................................................................................... 8Table 3 Design Vehicle Volvo A30E ................................................................................................................................ 9Table 4 Road Construction Best Management Practices ............................................................................................. 13

  

Page 4: KHSD Road Construction Plan-Keno City Bypass Road … · Figure 2 Conceptual Road Design ... This plan is intended to address construction, operation, and maintenance ... The Bypass

  

ROAD CONSTRUCTION PLAN – KENO CITY BYPASS ROADQML‐0009 

Keno Hill Silver District Mining Operations NOVEMBER 2012 

 

KHSD_ROAD_CONSTRUCTION_PLAN‐KENO_CITY_BYPASS_ROAD_NOV2012        1 

 

1 INTRODUCTION 

AlexcoKenoHillMiningCorp. (Alexco) continues todevelop themineral resources of theKenoHill SilverDistrict(KHSD).AspartofKHSDMiningOperations,AKHMwillcontinuetoestablishaccessandhaulroadsonthesite.Thisplanisintendedtoaddressconstruction,operation,andmaintenanceofsiteroadsdevelopedinsupportofAKHMminingactivitiesandwillbeadaptedasnecessaryfortheconstructionofspecificroads.Temporaryandpermanentclosureofroads isaddressed in theKenoHillSilverDistrictMiningOperationsReclamation and Closure Plan. The scope of this plan includes specifically the Keno City Bypass Road toaccommodateminetrafficassociatedwithLuckyQueenandOnekminingoperations.

2 SITE DESCRIPTION 

TheKHSDlieswithinthetraditionalterritoryoftheFirstNationofNa‐choNyakDun(FNNND)andnearthecommunitiesofKenoCityandMayo.TheKenoHillSilverDistrict is located incentralYukon(63°54'32"N,135°19’18”W;NTS105M/14&105M/13),354kmduenorthofWhitehorse.AccesstothepropertyisviatheAlaska, Klondike and Silver Trail Highways from Whitehorse to Mayo and an all‐weather gravel roadnortheastfromMayotoElsa(45km);atotaldistanceof452km.

TheKHSD is locatedonandaroundGalenaHill,KenoHill andSourdoughHill.Theproperty lies along thebroadMcQuestenRivervalleywiththreeprominenthills tothesouthof thevalley.LuckyQueenis locatedapproximately4kmnortheastofKenoCityandOnekissituatedabout500mnortheastofKenoCity.

TheKenoCityBypassRoadroutingisshowninFigures1and2.TheBypassRoadisrequiredtoaccommodatemine traffic associatedwith the LuckyQueen andOnekmine sites. Its routingdivertsmine traffic aroundKenoCityratherthanthroughthecommunity.

2.1 HISTORY 

TheKenoHillareawasoncehosttooneoftheworld’srichestsilverdeposits.In1903,thevillageofMayowasestablishedandthefirstsilverclaimwasstakedbyJacobDavidsononGalenaCreeknearpresentdayElsa.In1918KenoHillwasstakedandclaimedafterthediscoveryofasignificantsilverdeposit(Yukoninfo,n.d.).Asilverrushoccurredinthedistrictandin1919JohnKinmanfoundasilverveinaroundLightningCreek.Hiscabinbecameastoppingpointandeventually,KenoCity(YukonDevelopmentCorporation,2004). In1921the Treadwell Yukon Mining Company was formed, investing in various properties in the area. Elsa wasclaimedin1924,onGalenaHillbyCharlieBrefault.Itwasnotdevelopeduntil1935afterthemillwasmovedtothevicinity.In1947theUnitedKenoHillMinesLimited(UKHM)tookovertheTreadwellproperties,andbeganusingtheElsamilltoprocessore.ThedistrictwaslaterconsolidatedbyUKHMandUnitedKenoHillMineralsLimited(collectively“KenoHill”).

Together they became the second largest silver producers in North America and the fourth largest in theworldduring the late1950s.TheElsacommunitygrewtoapopulationofapproximately700 in the1980sduringthisboom.UnitedKenoHillMinesLtd.waseventuallyforcedintobankruptcyin1989duetothefallofmetal prices. The propertywas declared abandoned in 2001. In 2005 Alexco purchased the assets of the

Page 5: KHSD Road Construction Plan-Keno City Bypass Road … · Figure 2 Conceptual Road Design ... This plan is intended to address construction, operation, and maintenance ... The Bypass

  

ROAD CONSTRUCTION PLAN – KENO CITY BYPASS ROADQML‐0009 

Keno Hill Silver District Mining Operations NOVEMBER 2012 

 

KHSD_ROAD_CONSTRUCTION_PLAN‐KENO_CITY_BYPASS_ROAD_NOV2012        2 

 

UKHM and United Keno Hill Minerals Limited, collectively becoming “United Keno Hill Mines Limited(UKHM)”.TheYukonGovernmentapprovedthepurchaseagreementinDecember2007followingthereceiptofpermitsandapprovals.

2.2 GEOLOGY 

The Keno Hill Silver District is located in the western part of the Selwyn Basin in an area dominated bydeformedandmetamorphosedUpperProterozoictoMississippiansedimentaryrocksformedattheedgeofacontinentalmargin. During the Jurassic andCretaceous, the areawas subjected to compressional tectonicforcesproducing twomajor thrust sheets (Robert Service andTombstone) andwidespread folding. Earlylargescaledeformationproducedrecumbentfolds,resultinginlocalstructuralthickeningofstrata.Asecond(andpossiblythird)deformationaleventproducedgentlesouthwesterlyplungingsyn‐andantiformpairs.

TheRobertServiceThrustSheetinthesouthiscomposedofLateProterozoictoCambriansandstone,locallywith interbedded limestoneandargillite,aCambriantoMiddleDevoniansuccessionofsiltstone, limestoneandchert,andUpperDevonianargillite,chert,andchertpebbleconglomerate.Thelatterunituncomfortablyoverliesthelowerunits.

The Tombstone Thrust Sheet to the north consists of Devonian phyllite, felsic meta‐tuffs and metaclasticrocks, overlainbyCarboniferousquartzite. This latter rockunit is locally thickeneddue to folding andorthrustingandhoststhemineralizationoftheKenoHillSilverDistrict.

Intrusive rocks formed during four episodes of plutonism. Early Paleozoic fine‐grained diabase occurs asmetre‐scale dikes and sills in the Upper Proterozoic to Lower Cambrian rocks. During the Mid‐Triassic,gabbros todiorites formedpodsofvarioussizes,primarily in theDevonianandMississippianrocksof theTombstonethrustsheet. Athirdphaseofplutonismtookplacearoundninety‐twomillionyearsagointheearlyCretaceousandresultedinwidespreadandvoluminousTombstoneintrusionsofcommonlygranitictogranodioriticcomposition. Theyoungestmagmaticactivityoccurredaroundsixty‐fivemillionyearsago intheUpperCretaceousandresultedintheformationofperaluminousmegacrysticpotassiumfeldspargranite.

Inadditiontowherepolymetallicveinswereexploited,theareahostsanumberofoccurrences,andshowingsof tungsten, copper, gold, lead, zinc, antimonyandbarite. Tin, tungsten, andmolybdeniteoccurrencesarepossibly related to the suite of Cretaceous intrusion, whereas lead, zinc, and barite occur in stratiformcalcareoussedimentaryrocksofearlytomid‐Paleozoicagetypicalofsediment‐hosteddeposits.

2.2.1 Property Geology 

TheKenoHill District is underlain primarily by YukonGroupmetasedimentary rocks, locally divided intothree formations;UpperSchist,CentralQuartziteandLowerSchist. TheUpperSchist (HylandGroup,pre‐CambriantoCambrianage)overliesthequartzite inwhat is inferredtobeathrustcontact(RobertServiceThrust) and consists of quartz‐mica schist, quartzite, graphitic schist and minor limestone. The CentralQuartzite (Keno Hill Quartzite, Mississippian age) contains thick‐and thin‐bedded quartzite, massivequartzite, graphitic phyllite, graphitic schist, calcareous schist andminorTriassic greenstone. This unit isapproximately 700m thick and is host tomost of the past producing ore bodies. Structurally juxtaposedbelow the quartzite is the Lower Schist which has been correlatedwith the Devonian‐Mississippian Earn

Page 6: KHSD Road Construction Plan-Keno City Bypass Road … · Figure 2 Conceptual Road Design ... This plan is intended to address construction, operation, and maintenance ... The Bypass

  

ROAD CONSTRUCTION PLAN – KENO CITY BYPASS ROADQML‐0009 

Keno Hill Silver District Mining Operations NOVEMBER 2012 

 

KHSD_ROAD_CONSTRUCTION_PLAN‐KENO_CITY_BYPASS_ROAD_NOV2012        3 

 

Group.TheLowerSchistincludesgraphiticschist,argillite,thin‐beddedquartzite,calcareousschist,phyllite,slate,sericiteschist,minorthick‐beddedquartziteandlocallysignificantintervalsofTriassicgreenstone.Thegreenstone forms sillsand/orboudinsand consistsofmetadioriteandmetagabbro. Thesills andboudinsformbodiesuptoonekilometrelongandthirtymetresthick.Regional,greenschistfaciesmetamorphismofallunitsisbelievedtohaveoccurredintheMiddleCretaceous,about105millionyearsago.

Anumberofquartz‐feldsparporphyriticsillshaveintrudedthestratigraphyparalleltoschistosity.ThesillsaremostcommonintheLowerandUpperSchistsandcanreachthicknessesofuptofiftymetres;reportsofoccurrencesintheCentralQuartziteareinconclusiveandvague.Thequartz‐porphyrysillsarebelievedtobeofCretaceousage.

Structurally, the property is characterized by four sets of faults; many of which have been filled byhydrothermal minerals, forming veins. The oldest fault set consists of south dipping structures that aregenerally parallel to foliation and are apparently associated with the Tombstone Thrust Fault sincemovementwascontemporaneousorslightlylater.Locally,brittledeformationhasbeenobservedalongthesestructures.Asecondfaultset,knownas“longitudinalveins”strikesnortheasttoeastnortheastanddips

Page 7: KHSD Road Construction Plan-Keno City Bypass Road … · Figure 2 Conceptual Road Design ... This plan is intended to address construction, operation, and maintenance ... The Bypass

  

ROAD CONSTRUCTION PLAN – KENO CITY BYPASS ROADQML‐0009 

Keno Hill Silver District Mining Operations NOVEMBER 2012 

 

KHSD_ROAD_CONSTRUCTION_PLAN‐KENO_CITY_BYPASS_ROAD_NOV2012        4 

 

steeplysoutheast.Thelatestmovementalongthesefaultsissinistralwithoffsetslocallyreachingmorethan150 metres; however, more than one episode of movement commonly is indicated. Depending on thecompetencyofthehostrock,longitudinalveinscanbeuptothirtymetreswideinananatomisingsystemofsub‐veins. Essentially allmineralized rockwasmined from these longitudinal veins. A third set of faults,knownas“transversefaults”,isnorth‐weststrikinganddipssteeplytothenorth.Transversefaultstypicallydo not contain silver and lead mineralization but are commonly filled by quartz with trace to minorarsenopyrite,pyriteandjamesonite.

Ayoungersetoffaults,knownascrossfaults,strikenorthtonortheastwithadipofsixtydegreeswesttosouthwestandoffsetveinorlongitudinalfaultsbyupto2,000m.Inthewesternpartoftheproperty,dextralmovement is the most recent event along these structures, whereas in the eastern part of the propertysinistralmovementwithlessmagnitudeprevails.

AtKenoHill, the largest accumulation of oreminerals occurred in structurally prepared competent rocks,suchastheCentralQuartzite,resultinginareasofincreasedfluidflow.Incompetentrockslikephyllitestendtoproducefewerandsmaller,ifany,openspaces,limitingfluidflowandresultingmineralprecipitation.

Mineralization in the KenoHill Silver District is of the polymetallic silver‐lead‐zinc vein type. In general,commonganguemineralsincludemanganiferoussideriteandtoalesserextentquartzandquartzbrecciaaswell as calcite and other carbonates. Silver occurs in argentiferous galena and argentiferous tetrahedrite(freibergite).Insupergeneassemblages,silverisfurtherfoundasnativesilver,inpolybasite,stephanite,andpyrargyrite.Leadoccursingalenaandzincinsphalerite,whichisiron‐rich.Othersulphidesincludepyrite,arsenopyrite(locallygold‐bearing)andchalcopyrite.

The veins of the Keno Hill Silver District display characteristics associated with both mesothermal andepithermaldepositsanditisnotclearifacontinuumexistsorifseparateanddistinctmineralizingeventsareinvolved.Themostprominentexamplesofepithermalstylemineralizationarefoundinthewesternpartofthedistrict,althoughtheLuckyQueenmineonKenoHillproducednativesilverandrubysilverinquantity.Proximitytoamagmaticheatsourcehasoftenbeencalledupontoexplainthedistrictzonation,thoughthisisbynomeansacompleteexplanation.

Mineral zonation is common within base metal‐rich veins (zinc‐rich margin and silver/lead‐rich center).Changesinmineralogywithinindividualoreshootsislessclearlydocumented,althoughtherehaslongbeenaconvictionthatsilverand leadrichzonesoccurhigher in theveinswhilezincbecomesdominantatdepth.Anecdotalevidencesuggeststhatverticallystackedoreshootsmayrepeatedlyshowzoningofleadrichupperportionstozincdominantroots,butdataconfirmingthishasnotbeenfound.Ingeneral,Pb‐Znmineralizationappearstobenearlycontemporaneousinage.

Mechanismstriggeringdepositionoforeandganguemineralshavebeensuggestedbydistrictwidestudiesoffluidinclusionsandlightstableisotopes. Fluidboilingappearstohavebeenubiquitousandsomeevidenceexists for fluid mixing. The hydrothermal fluids responsible for mineral deposition contained significantquantities of CO2 which may have “boiled” during abrupt changes in pressure produced during fluidmovementfromconfinedfracturestomoreopenconduitsformedinquartzite.

 

Page 8: KHSD Road Construction Plan-Keno City Bypass Road … · Figure 2 Conceptual Road Design ... This plan is intended to address construction, operation, and maintenance ... The Bypass

  

ROAD CONSTRUCTION PLAN – KENO CITY BYPASS ROADQML‐0009 

Keno Hill Silver District Mining Operations NOVEMBER 2012 

 

KHSD_ROAD_CONSTRUCTION_PLAN‐KENO_CITY_BYPASS_ROAD_NOV2012        5 

 

Irrespective of stratigraphic formations or regionalmap units only a fewmajor rock types are commonlyencounteredintheareaoftheoldmineworkings.Theseare:

schistsandphylliteswithvariablecarboncontent;

chloriticphyllitesorschists;

quartzitesandphylliticquartzites;

sericite‐quartzphyllites;and,

greenstones.

2.3 GENERAL ENVIRONMENTAL CONDITIONS 

Table 1 summarizes existing environmental conditions in the KenoHill project area. The KenoHill SilverDistrictlieswithintheYukonPlateau–NorthEcoregion,justsouthoftheWerneckeMountains.Theterrainconsistsofconcordant,rolling,uplandareasseparatedbywidevalleys.Alpinemountainpeaksextendabovetheuplandslocally.Manyvalleysincludepeatlands,palsas,fensandmeadowsofsedgetussocks.Upperslopesmaybecoveredwithscreematerial,withtreelineoccurringat1,350to1,500m.Theareahasbeeninfluencedbythelatestglaciationbutshowsmoresubtleevidenceofanearliereventaswell.

Table 1 Keno Hill District Environmental Setting Summary 

Drainage Region  Stewart River drainage region 

Significant Watersheds  McQuesten River, Lightning Creek and Stewart River Watershed, Mayo River 

Ecoregion  Yukon Plateau (North) 

Study Area Elevation  900‐1350 m asl (Above Sea Level) 

Vegetation Communities  Northern boreal forests occupy  lower slopes and valley bottom; spruce, pine and alder;  grasses  and  sedges, mosses  occupy  forest  floor;  heavy moss  and  lichen growth  resident  as  ground  cover  understory  of  shrub willow;  open  and  forest fringe areas of willow and scrub birch, and various flowering plant species. 

Wildlife Species  Moose,  grizzly  and  black  bear,  caribou,  beaver,  wolf,  lynx, marten,  wolverine, western  tanager,  magnolia  warbler,  white‐throated  sparrow,  bald  eagle, furbearers and small animals.  

Committee  on  the  Status  of  Endangered  Wildlife  in  Canada  (COSEWIC)  listed species  include:  Common  Nighthawk  (Threatened);  Rusty  Blackbird  and  Olive‐Sided Flycatcher (Special Concern). 

Fish Species  Bering  and  Beaufort  Sea  salmonids  and  freshwater  species,  including:  Arctic grayling,  Arctic  char,  lake  trout,  trout  perch,  lake  whitefish,  broad  whitefish, burbot, inconnu, Arctic Cisco, Northern pike, slimy sculpin 

Page 9: KHSD Road Construction Plan-Keno City Bypass Road … · Figure 2 Conceptual Road Design ... This plan is intended to address construction, operation, and maintenance ... The Bypass

  

ROAD CONSTRUCTION PLAN – KENO CITY BYPASS ROADQML‐0009 

Keno Hill Silver District Mining Operations NOVEMBER 2012 

 

KHSD_ROAD_CONSTRUCTION_PLAN‐KENO_CITY_BYPASS_ROAD_NOV2012        6 

 

2.4 LIGHTNING CREEK  

Lightning Creek is situated within a narrow valley with a steep gradient flowing from the north side ofSourdoughHill intoDuncanCreek,whichdrains intotheMayoRiver.HopeandThunderGulches flow intoLightningCreekwithintheboundsoftheKenoHillSilverDistrict(KHSD).LightningCreekhasalsobeenthesite of extensiveplacerminingupstreamofKenoCitybothhistorically andatpresent time.TheLightningCreek drainage has also been affected by localized quartz mining activities including the Bellekeno Minewhichwasre‐openedbyAlexcoin2011.MineaditdrainagesfromBellekeno625(northsideofSourdoughHill) and Keno 700 (south side of KenoHill) eventually report to the Lightning Creek drainage. LightningCreekisnotableasitistheonlylargewatershedintheKHSDnotconnectedtotheSouthMcQuestenRiver.LightningcreekdrainsintotheDuncanCreekwatershedwhichflowssouthintotheMayoandStewartRiver.

3 ROAD DEVELOPMENT OVERVIEW 

TheKenoCityBypassRoadwillbedevelopedfromtheWerneckeRoad,crossingSignPostRoad,alongthehistoricOnekpowerline,totheOnek990Portal,crossingLightningCreekRoadandtheOnekAccessBridgeacrossLightningCreek to theBellekenoHaulRoad.TheBypassRoadwillbea single‐lane radio‐controlledroad,approximately2.1kmlongand6–9mwide.Someportionsoftheroadwillbewideenoughtosafelyaccommodate passing mine traffic. It will be developed with cut/fill construction, using the fill materialsupplemented by some additionalN‐AMLwaste rockmaterial (~15,000m3 in total required). TheN‐AMLwasterockwillbesourcedfromOnekorBellekeno.InitialdevelopmentoftheBypassRoadmayrequireN‐AML from the historic Onekwaste dump adjacent to the Bypass Road, until sufficient volumes of N‐AMLmaterialareavailablefromtheOnek990declinedevelopment.

Theroutingdoesnotcrossorcomewithin30mofanywatercourseorwaterbodyotherthanattheapproachtoLightningCreekandattheOnekaccessbridge.Ditchingalongtheroadwillfacilitateappropriatedrainage.Culvertswill be installed at the intersectionswithWernecke Road, Lightning Creek Road, BellekenoHaulRoadandSignPostRoadfordrainage.Additionalculvertsmaybeestablishedalongthebridgeapproaches.Theclearedvegetativedebrisandtopsoilwillbestockpiledalongtheroutinginnaturalclearedareasforroadreclamation.

3.1 ONEK ACCESS BRIDGE 

TheKenoCityBypassRoadroutingincludescrossingLightningCreek,whichwillrequireinstallationofthebridge.AKHMproposestoinstallaclearspan(singlespan)bridgeacrossLightningCreek.Thebridgewillbea single‐lane, steel girder prefabricated bridge, approximately 9m long and 4.4m wide. The bridge isdesigned tohave the flowcapacityof a1:100year floodevent; itwill be capableof supportingminehaultraffic(atleast100t).AnengineeredtypicalLightningCreekbridgedesignisprovidedinFigure3.

A6.5mwideaccessroadwillbeestablishedonthenorthandsouthsideofLightningCreektothebridgesite.Twooverflowculvertswillbe installedwithin the1:100year floodeventzone.Fillmaterial for theaccessroadandabutmentswillbesourced fromOnekandBellekenoN‐AMLwasterock. Thebanksandriparianareawillbeclearedwithabrushmowerorpushedasidewithadozer.

Page 10: KHSD Road Construction Plan-Keno City Bypass Road … · Figure 2 Conceptual Road Design ... This plan is intended to address construction, operation, and maintenance ... The Bypass

  

ROAD CONSTRUCTION PLAN – KENO CITY BYPASS ROADQML‐0009 

Keno Hill Silver District Mining Operations NOVEMBER 2012 

 

KHSD_ROAD_CONSTRUCTION_PLAN‐KENO_CITY_BYPASS_ROAD_NOV2012        7 

 

TheproposedsitefortheclearspanbridgedesigncrossingwasselectedbyAlexcoengineeringpersonnelandinconsiderationofriparianandflowregimeconditions.

Bardusan Placers Ltd. holds the placer claims at the site of the proposed Onek Access Creek Bridge. Theplacer rights holder has been contacted with respect to bridge location. The placer claim owner is notcurrentlyoperatinganyplacerminingactivityontheclaimsattheproposedbridgecrossinglocation. 

AKHMinstalledaclearspanbridgeonLightningCreek,approximately1.1kmdownstreamoftheproposedOnekAccessBridgesite(TypeBWaterLicenceMS10‐029).PursuanttotheNavigableWatersProtectionAct,Transport Canada determined that Lightning Creek is a Non‐Navigable waterway at the location of theexistingbridge(seeemailfromTransportCanada–YORDocument2009‐0030‐120‐1).Itwasdeterminedtobenotnavigablebecausethereisaculvertupstreamoftheexistingbridge.TheproposedOnekAccessBridgeislocatedapproximately586mupstreamoftheculvert.

TheOnekAccessBridgewillbelicencedunderanamendmenttotheexistingMS10‐029.

4 SITE PREPARATION  

4.1 CLEARING 

Ingeneral,adozerwillbeusedforclearing.Anexcavatorwillbeusedasrequired.Theroadroutingdoesnotcomewithin30mofawatercoursewiththeexceptionoftheapproachesandcrossingLightningCreek.Banksandriparianareaswillbeclearedwithabrushmowerorchainsaw.Treeswithin10mofLightningCreekwillbeclosecutandstumpsleftinplace.

4.2 HERITAGE RESOURCES PROTECTION 

Theroadroutinghasbeenground‐truthedbyAlexcoofficialsandaknowledgeablecommunitymember.NoheritageresourceswerelocatedwithintheroadROW.Alexco’sHeritageResourcesProtectionPlanforKenoHillSilverDistrictMiningOperationswillbeapplied.

5 ROAD DESIGN AND SPECIFICATIONS 

5.1 HAUL ROAD SPECIFICATIONS 

Allhaulroads,BellekenoHaulroad,LuckyQueenHaulroad,andtheKenoCityBypassroadwillbesubjecttoPart 15.42 and 15.43 of the Yukon Occupational Health and Safety Regulations, which set out minimumdesign criteria for safety considerations. In addition, mine haul road design guidelines developed by theUniversityofAlberta(TannantandRegensburg,2001)andwhichwerereferencedduringthedevelopmentoftheroadplans.

Page 11: KHSD Road Construction Plan-Keno City Bypass Road … · Figure 2 Conceptual Road Design ... This plan is intended to address construction, operation, and maintenance ... The Bypass

  

ROAD CONSTRUCTION PLAN – KENO CITY BYPASS ROADQML‐0009 

Keno Hill Silver District Mining Operations NOVEMBER 2012 

 

KHSD_ROAD_CONSTRUCTION_PLAN‐KENO_CITY_BYPASS_ROAD_NOV2012        8 

 

5.1.1 Haul Road Design Criteria 

CivildesigncriteriaforhaulroadsweredevelopedbyWardropEngineeringInc.basedonapplicablefederalandterritorialcodesandregulations,aswellasindustrystandardsandotherreferencedocuments(AppendixDoftheConstructionSitePlan,Revision1).TheroaddesigncriteriaareshowninTable2.ThedesignvehicleusedasthebasisofdesigncriteriaisshowninTable3.Figure4showsatypicalroadcross‐section.

Table 2 Road Design Criteria 

Haul Road   

Operating Width*  5.881 or 8.822 m 

Design Speed  50 km/hr 

Cross fall  2% 

Maximum Grade  8% 

Surface  200 mm 

Base  300 mm 

Sub‐base  500 mm 

Cut Side Slope  1.5 : 1 

Fill Side Slope  2 : 1 

Subgrade Compaction  >80% 

Granular Compaction  >85% 

* Excludes berms and ditches on both side of haul roads. 1. One way traffic. 2. Two way traffic (passing).

 

Page 12: KHSD Road Construction Plan-Keno City Bypass Road … · Figure 2 Conceptual Road Design ... This plan is intended to address construction, operation, and maintenance ... The Bypass

  

ROAD CONSTRUCTION PLAN – KENO CITY BYPASS ROADQML‐0009 

Keno Hill Silver District Mining Operations NOVEMBER 2012 

 

KHSD_ROAD_CONSTRUCTION_PLAN‐KENO_CITY_BYPASS_ROAD_NOV2012        9 

 

Table 3 Design Vehicle Volvo A30E 

Volvo A30E  Dimension 

Width   2.94 m  

Length   10.3 m  

Height   3.3 m  

Wheel Base   2.216 m 

Tire Pressure   267 kPa 

Weight  Loaded  Empty 

Gross Vehicle Weight  51 060 kg  28 000 kg 

Front Axle  14 990 kg   12 500 kg  

Drive Axle  36 070 kg   15 560 kg  

5.1.2 Haul Road Construction Guidelines  

Generalguidelinesforhaulroadconstructioninclude:

Haulroadsshallbeall‐weatherconstruction;

Safetybermwillbeconstructedonallfills>3.0m;

Heightofsafetybermwillbe1.25m(0.75xthediameteroftireonVolvoA30Earticulatedhaultruck);

Breaksinthesafetybermwillnotexceedthewidthofthebladeoftheequipmentconstructingandmaintainingthebreakstoallowfordrainageandsnowclearance;

Sideslopewillbemaximum2:1ifembankmentisbetween0‐3m;

Sideslopewillbemaximum1.5:1ifembankmentisbetween>3m;

Alternatingvehicularpull‐outswillbeusedateachendofonewaytrafficroadsegments;

Pulloutslengthequals1.5timesthevehiclelength;

Pulloutswidthequals1.5timestheoperatingwidth;and

A clearly marked emergency runaway lane or retardation barrier capable of bringing a runawayvehicletoastopwillbeprovidedandmaintainedbelowwhereroadgradeexceeds5%.

5.1.3 Haul Road Maintenance 

Periodicgradingandresurfacingasdeemednecessarywillbeemployedinordertokeepthehaulroads ingoodrepair.Duringthewinter,haulroadswillbeplowedandsandedtoensurepropertractionismaintained.

Page 13: KHSD Road Construction Plan-Keno City Bypass Road … · Figure 2 Conceptual Road Design ... This plan is intended to address construction, operation, and maintenance ... The Bypass

  

ROAD CONSTRUCTION PLAN – KENO CITY BYPASS ROADQML‐0009 

Keno Hill Silver District Mining Operations NOVEMBER 2012 

 

KHSD_ROAD_CONSTRUCTION_PLAN‐KENO_CITY_BYPASS_ROAD_NOV2012        10 

 

5.1.4 Haul Truck Cleanliness 

Haul truckswill be subject to periodicmaintenance at theDistrictMill site. Thismaintenancewill includewashing,withcaretakenthatallwashwaterberecycledordirectedtothewatertreatmentpond.

5.2 ACCESS TIE‐IN AND STAGING AREAS 

TheKenoCityBypassRoadwillintersectwithWerneckeRoad,SignPostRoad,LightningCreekRoadandtheBellekenoHaulRoad.

ExistingdisturbanceareasalongtheKenoCityBypassRoadtheOnek990PortalPadwillbeusedforstagingconstruction equipment andmaterial (e.g., N‐AMLwaste rock). Fuel will be stored in the designated fuelstorageareawithappropriatecontainmentontheOnek990portalpad.ExplosiveswillbestoredontheOnekhistoricwastedumpsinaccordancewithapplicableregulations.

Nofencingorgatingwillberequired.Thefollowingsectiondescribesaccesscontrolmeasures.

5.3 ACCESS CONTROL  

Therewill be stop signs to stopmine traffic at the intersectionswithWerneckeRoad, SignPostRoadandLightningCreekRoad.Signagewarningofcrossingminetrafficwillbeinstalledinbothdirectionsfromtheintersection, in accordance with regulatory requirements. Appropriate line‐of‐sight distances will bemaintained to ensure crossing trucks and approaching traffic on theWerneckeRoad are able to see eachother. The line‐of‐sight distance requirements of YGHighways & PublicWorks Transport Branch and theHighway Access/Workswithin a Right‐of‐Way permits will be adhered to in order to ensure public andworkersafety.

Signagewarning of crossing/turningmine dump trucks (over the highway dump trucks)will be installedalongSignPostRoad,LightningCreekRoad,BellekenoHaulRoadandWerneckeRoadinaccordancewiththerequirementsanddirectionofYGHighways&PublicWorksTransportBranchofficials.

TheKenoCityBypassRoadisintendedforminepersonneluse.Nogateswillbeused.TheKenoCityBypassRoadwillbearadiocontrolledroadaccessibletominetrafficonly.Signswillbeinstalledattheroadaccesspointsprohibitingpublictrafficfromtravelingonit.Themaximumspeedlimitwillbe40km/h,reducedto20km/hatblindcornersandroadcrossings.

5.3.1 Temporary Access Closure 

Tolimitaccessduringtemporaryclosure,pylonsandsignagewillbeusedtowarnroadusers,andgateswillbeinstalled,asrequired.Thebridgewillnotbedecommissionedduringatemporaryclosure.

Page 14: KHSD Road Construction Plan-Keno City Bypass Road … · Figure 2 Conceptual Road Design ... This plan is intended to address construction, operation, and maintenance ... The Bypass

  

ROAD CONSTRUCTION PLAN – KENO CITY BYPASS ROADQML‐0009 

Keno Hill Silver District Mining Operations NOVEMBER 2012 

 

KHSD_ROAD_CONSTRUCTION_PLAN‐KENO_CITY_BYPASS_ROAD_NOV2012        11 

 

5.3.2 Permanent Access Closure 

Thebridgewill remain inplaceduring the lifeof theproject (~15years).Decommissioningmeasureswillinvolveremovaloftheclearspanbridge,abutmentsandculverts.Theaccessroadswillbedecommissioned,regradedandre‐sloped.Alldisturbedareaswillbescarifiedandre‐vegetated.Thebankswillbestabilizedthroughrevegetationandstrategicplacementoftheexistingriprap.ThesedecommissioningmeasuresareincorporatedintotheReclamationandClosurePlan.

6 BORROW SOURCES 

The Keno City Bypass Road fromWernecke Road to the bank of Lightning Creek at the bridge crossing(~15,000m3ofmaterial),andtheOnek990PortalPad(~4500m3ofmaterial)willbeconstructedwithfillfromthecutsandOnekN‐AML.Ifrequired,borrowmaterialfromthehistoricOnekwastedumpadjacenttotheBypassRoadwillbeusedforinitialdevelopmentuntilsufficientvolumesareavailablefromthedeclinedevelopment.

Bellekeno N‐AML waste rock will be used for constructing the section of access from the bridge to theBellekenoHaulRoad(~4,800m3).

AfterinitialdevelopmentandestablishmentoftheOnekAccessBridge,OnekorBellekenoN‐AMLwasterockmaybeusedformaintenance,upgradesorgeneralconstructionpurposes.

7 GEOCHEMICAL EVALUATION 

TheKenoHill SilverDistrictMiningOperationsWaste RockManagement Plan (WRMP)will be applied toselecting N‐AML material appropriate for construction. Where blasting is required for road construction,material from the blast face will be sampled to ensure it meets the WRMP N‐AML criteria. If it doesn’tadaptivemanagementactionswillbetakentoaddresstherockexposure(e.g.shotcreting).

8 GEOTECHNICAL TESTING 

AKHMengineersgroundtruthedtheroadalignmenttoensuregeotechnicalstabilityoftheroadbed.Someoftheroutingfollowsareasofexistinglineardisturbance(e.g.thehistoricOnekpowerlineROW).Totheextentpossible, routing with sufficient overburden underlain with competent rock was selected. Areas showingsignsofunderlyingpermafrost(stuntedtrees,groundslumping)wereavoidedtotheextentpossible.Inareasofpotentialpermafrost(e.g.portionofKenoCityBypassRoadsouthofLightningCreektotheBellekenoHaulRoad), ground protection measures, such as installation of additional road foundation material, will beapplied.RefertoTable4foradditionalmitigationmeasures.

Page 15: KHSD Road Construction Plan-Keno City Bypass Road … · Figure 2 Conceptual Road Design ... This plan is intended to address construction, operation, and maintenance ... The Bypass

  

ROAD CONSTRUCTION PLAN – KENO CITY BYPASS ROADQML‐0009 

Keno Hill Silver District Mining Operations NOVEMBER 2012 

 

KHSD_ROAD_CONSTRUCTION_PLAN‐KENO_CITY_BYPASS_ROAD_NOV2012        12 

 

9 BEST MANAGEMENT PRACTICES 

Table2outlinestheBestManagementPracticesthatAKHMwillapplytoroadconstruction,maintenanceandclosureactivitiesinordertoprotectenvironmentalconditions.

9.1 ENVIRONMENTAL MONITORING 

In accordancewith clause53ofQZ09‐092, betweenMay andOctober of each year,Alexcowill inspect allunlinedwasterocklocations,whichinthiscaseapplytotheroadbecauseN‐AMLwasterockistobeusedasconstructionmaterial.Asperclause60,wasterockreportingrequirementsincluderecordingintheannualreport:

60.a)anyphysicalinstabilityincludingerosion;

b)upstreampondingofwateranddownstreamseepage;

c)thelocationofpondingandseepage;

d)thevolumeofflow,fieldpHandconductivityofpondingorseepage;

e) visual evidence of sulphide oxidation including snow melt areas or the presence of oxidationproducts;and

f)trendsinpH,andconductivityforanyrecurringseepageorpondinglocation.

TheAdaptiveManagementPlanstipulatesthatseepagefromallstructuresconstructedofN‐AMLwasterockshallbesampledforfieldpHandconductivityandflow.Additionalwaterqualityanalysisistobeconductediftheseepagequantityissufficient.

Todate,noseepshavebeendetectedfromN‐AMLwasterockstructures.

Page 16: KHSD Road Construction Plan-Keno City Bypass Road … · Figure 2 Conceptual Road Design ... This plan is intended to address construction, operation, and maintenance ... The Bypass

 

ROAD CONSTRUCTION PLAN – KENO CITY BYPASS ROADQML‐0009 

Keno Hill Silver District Mining Operations NOVEMBER 2012 

 

KHSD_ROAD_CONSTRUCTION_PLAN‐KENO_CITY_BYPASS_ROAD_NOV2012        13 

 

Table 4 Road Construction Best Management Practices 

Environmental Component  Mitigation 

Runoff,  Sediment  and 

Erosion Control 

 

The road will be graded to allow surface water to drain off the road. Any runoff that drains from the road surface or staging 

areas will be conveyed into permeable roadside ditches and culverts and will likely infiltrate into the subsurface. During large 

storm events  it  is expected that some runoff volume will reach  lightning creek.  It  is expected this volume will not be  large 

enough  to  cause  flooding  issues  downstream  because  the  road  area  represents  a  very  small  percentage  of  the  overall 

watershed area.  

As part of road maintenance, ruts that could be prone to erosion will be filled. 

Vegetation removal will be minimized to the extent possible. 

Water bars will be constructed to promote proper drainage, if required.  

During  bridge  construction/  adjacent  road  development,  temporary  sediment  control,  such  as  silt  fences  or  temporary 

diversion berms, will be installed, monitored and maintained to prevent sediment runoff into the creek.  

If minor rutting is likely to occur, stream bank and bed protection methods (e.g. swamp mats, pads) shall be used provided 

they do not constrict flows or block fish passage. 

Dust Control  Application of water or non petroleum dust suppression agents will be employed  if required to control  fugitive dust  from 

haul  road  surfaces  during  the  summer months.  Run  of mine  ore  from  underground  operations  is  generally wet,  coarse 

grained and free of fines and will not create dust. 

Site Isolation  During bridge construction and adjacent road development, banks and riparian areas will be cleared with a brush mower or 

chainsaw. Trees within 10 m of Lightning Creek will be close cut and stumps left in place.  

Culvert Installation  An overflow culvert will be installed on each side of the bridge crossing within the 1:100 year flood event zone. These are to 

be placed above  the ordinary high water mark and  therefor will not have any effect on  Lightning Creek aquatic  life. The 

banks and riparian area will be cleared with a brush mower or chainsaw within 10 m of the stream bank. Stumps and root 

systems will be  left  in place  to preserve natural  erosion protection. All other  storm water management  culverts will be 

constructed to divert water beneath the roadway between road ditches and will not impact existing stream systems. 

Page 17: KHSD Road Construction Plan-Keno City Bypass Road … · Figure 2 Conceptual Road Design ... This plan is intended to address construction, operation, and maintenance ... The Bypass

DRAWN BY MD

KENO CITY BYPASS ROUTING ANDACCESS MANAGEMENT

NOVEMBER 2012 VERIFIED BY KW

I:\Keno_Area_Mines\ONEK\Maps\2_Permitting\Traffic\Road_Construction_Bypass_Plan_20121114.mxd (Last edited by: jpan;11/14/2012/15:07 PM )

This map is for illustrative purposes only. This is not a legal document. Quartz claim boundaries are current as of March 26,2012. Placer claim boundaries are current as of Feb 26th, 2012. Land Disposition data obtained from Canada Lands SurveySystem, current as of March 2012. Site hydrography and contours derived from 2006 aerial imagery obtained from AeroGeometrics, Calgary Alberta. Aerial photograph obtained from Geodesy Remote Sensing Inc., Calgary Alberta. Imagery acquiredSeptember 13th and 14th 2006.Datum: NAD 83; Projection: UTM Zone 8N

ALEXCO KENO HILL MINING CORP.ONEK AND LUCKY QUEEN

KENO CITYDISTRICTMILL

EXISTINGLUCKY QUEEN

ADIT

TO BELLEKENOMINE

ONEK 990PORTALAND PAD

HISTORICONEK

400 ADIT

DUNCAN CR EEK ROAD

BELLEKENOHAUL ROAD

WERN

ECKE

ROAD

CHRIS

TAL LAKE ROAD

SILVER TRAILHIGH WAY

ChristalLake

E r i c k s o n G u l c h

INSET 1

INSET 2

INSET 3

484000

484000

485000

485000

486000

486000

487000

487000

7087

000

7087

000

7088

000

7088

000

7089

000

7089

000

7090

000

7090

000

7091

000

7091

000²

0 500 1,000250Meters

1:15,000 (when printed on 11 x 17)

FIGURE 1

This drawing has been prepared for the use of Access MiningConsultants Ltd.'s client and may not be used, reproduced or reliedupon by third parties, except as agreed by Access MiningConsultants Ltd. and its client, as required by law or for use ofgovernmental reviewing agencies. Access Mining Consultants Ltd.accepts no responsibility, and denies any liability whatsoever, to anyparty that modifies this drawing without Access Mining ConsultantsLtd.'s express written consent.

Existing Private Road, Haul Road

Proposed Private Road, Haul Road

Existing Public Road, Haul Road

Road Right of Way Watercourse

Waterbody

!"$

Æô 123|

123:

!"$!"$

Æô

Æô

123:WER

NEKE

ROA

D

!"$Æô

INSET 1

INSET 2

123<

!"$Æô

123:

!"$

!"$

ÆôÆô

INSET 3

lhaney
Text Box
FIGURE 1 (REVISED)
Page 18: KHSD Road Construction Plan-Keno City Bypass Road … · Figure 2 Conceptual Road Design ... This plan is intended to address construction, operation, and maintenance ... The Bypass

1,9501,9001,8501,8001,7501,7001,6501,6001,5501,5001,4501,4001,3501,3001,2501,2001,1501,1001,0501,000950900850800750700650600550500450400350300250200150100500

1,0401,0301,0201,010

1,000990980970960950

11010510095908580757065605550454035302520151050

1,000

999

998

997

996

995

994

993

992

991

990

KENO HILLSILVER DISTRICT MINING

OPERATIONS

Profiles derived from 1 meter contour data derivedfrom 2006 aerial imagery obtained from AeroGeometrics, Calgary Alberta.and Site hydrographyand contours derived from 2006 aerial imageryobtained from Aero Geometrics, Calgary Alberta.

NAD 83 UTM Zone 8N

L i g h t n i n g C r e e k

VENTRAISE

DECLINE ANDUNDERGROUNDWORKINGS

ONEK 990PORTALAND PAD

ONEK ACCESSBRIDGEK E N OK E N O

C I T YC I T Y

ONEK HISTORICAL WORKINGS

NOVEMBER 2012KENO

CITYBYPASS

ROAD

L IGHTNINGCREEK

ROAD

BELLEKENOHAUL

ROAD

A'

A

B'

B

0 m

100 m

200 m

300 m

400 m

500 m

600 m

700 m800 m

900 m1000 m

1100 m

1200 m

1300 m1400 m

1500 m

1600 m

1700 m

1800 m1900 m

²

I:\Keno_Area_Mines\ONEK\Maps\1_Overview_Maps\Specific_Topics\Roads\-ProposedRoad_20121119.mxd(Last edited by: mducharme;19/11/2012/15:19 PM )

This drawing has been prepared for the use of Access Mining Consultants Ltd.'s client andmay not be used, reproduced or relied upon by third parties, except as agreed by AccessMining Consultants Ltd. and its client, as required by law or for use of governmentalreviewing agencies. AccessMining Consultants Ltd. accepts no responsibility, and deniesany liability whatsoever, to any party that modifies this drawing without Access MiningConsultants Ltd.'s express written consent.

²

CONCEPTUAL ROAD DESIGN - PROFILE A

A A'

NOT FORCONSTRUCTION

LIGHTNING CREEKBRIDGE

JUNCTION WITHBELLEKENOHAUL ROAD

0 200 400100

Meters

0 200 400 600 800100Meters

Profile A Distance Markers(distance in meters)

Profile A

Profile B

Existing Roads

CONCEPTUAL ROAD DESIGN - PLANCONCEPTUAL ROAD DESIGN OVERVIEW

FIGURE 4CONCEPTUAL ROAD

DESIGN

CONCEPTUAL ROAD DESIGN - PROFILE B

B

B'

ONEK 990PORTAL

ORIGINAL GROUND PROFILE H:V = 3:1

ORIGINAL GROUND PROFILE H:V = 3:1

EL

EV

AT

ION

(IN

ME

TR

ES

)E

LE

VA

TIO

N (

IN M

ET

RE

S)

DISTANCE (IN METRES)

DISTANCE (IN METRES)

lhaney
Text Box
FIGURE 2 (REVISED)
Page 19: KHSD Road Construction Plan-Keno City Bypass Road … · Figure 2 Conceptual Road Design ... This plan is intended to address construction, operation, and maintenance ... The Bypass
lhaney
Text Box
FIGURE 3
Page 20: KHSD Road Construction Plan-Keno City Bypass Road … · Figure 2 Conceptual Road Design ... This plan is intended to address construction, operation, and maintenance ... The Bypass
lhaney
Text Box
FIGURE 4