Kupu Taurangi Hauora o Aotearoa
Ringing the changes
Beth Loe
August 2011
Kupu Taurangi Hauora o Aotearoa
Change register – why?
Year 2011 – National Medication Chart
Year 2016 – 20 or more medication charts
Kupu Taurangi Hauora o Aotearoa
Kupu Taurangi Hauora o Aotearoa
Post implementation change register
• Identification of issues that do not relate to NMC e.g.
prescribing and administration practice
• Identification of specific features that do not function
as intended in practice
Future change register
• Changes in clinical practice
• Law changes
Kupu Taurangi Hauora o Aotearoa
Kupu Taurangi Hauora o Aotearoa
Engaging clinicians
(paper based or electronic system)
• Advertise
• Annual blitz
• Put it on meeting agendas
Kupu Taurangi Hauora o Aotearoa
Local process
• Have a locally agreed form (paper or electronic)
DHB staff to complete
Date:
Organisation: Ward / unit:
Author: Contact details:
Brief description of proposed change:
Kupu Taurangi Hauora o Aotearoa
Local Committee
• Needs to be multidisciplinary
• Could be: NMC project team
Medicines Advisory Committee
Medication Safety Committee
Kupu Taurangi Hauora o Aotearoa
Stage 1
Complete NMC proposal for change formEach DHB collates suggested changes and classifies all proposed changes to the NMC using the
following process
Question 1.
Is there local evidence
of an issue with the
NMC design
that compromises
patient safety?
Question 2.
Does local evidence
suggest that the
proposed change will
improve patient
safety?
DHB NMC designated
committee rejects
proposal for change
Question 3.
Does the proposed
change comply with
the medication
charting standards?
Go to
question 2
Change approved by
DHB NMC designated
committee
Go to Stage 2DHB NMC designated
committee can still approve
change and proposal
go to Stage 2
Yes
Yes
Yes No
No
No
Kupu Taurangi Hauora o Aotearoa
Why have a local decision
• Additional information can be added to a change request
if necessary
• Respond Yes or No to change request knowing local
situation
• Provides guidance to national design sub-committee on
change requests
Kupu Taurangi Hauora o Aotearoa
Stage 2Submit proposal for change to the national NMC
design committee
Stage 3
Reporting decisions to stakeholders
Submit NMC change form
The DHB NMC
designated
committee will:
The national NMC
design committee,
with its governance
endorsement will:
Inform stakeholders
of proposal for
change status i.e.
accepted / rejected
locally / nationally,
including rationale
Facilitate DHB-wide
change management
process to implement
revised NMC
Inform DHB NMC
designated
committees of
national decisions,
including rationale
Revise NMC with
national printer and
advise DHB NMC
designated
committee when
available
Provide recommendation
to approve or further
investigate
Provide evidence and
rationale
Kupu Taurangi Hauora o Aotearoa
Electronic
Change
Register (ECR)
Kupu Taurangi Hauora o Aotearoa
Electronic Change Register (ECR)
• Details to be sent to DHB NMC project leads
next week
• Log in will be for an individual in each DHB
Kupu Taurangi Hauora o Aotearoa
Help File
Kupu Taurangi Hauora o Aotearoa
Help Files
• Process for local committee review
• Information for submitters for the electronic
change register
Kupu Taurangi Hauora o Aotearoa
National Design Subcommittee
• Has reported to SQM Group but will report to
new Expert Clinical and Technical Advisory
Group
• Multidisciplinary with nurses, doctors and
pharmacists
Kupu Taurangi Hauora o Aotearoa
First Design Review
• Work starting now
• Completion expected between February/April 2012