lec 05
DESCRIPTION
محاضرات د. فاروق القاضيTRANSCRIPT
-
5/22/2018 Lec 05
1/97
For Lectures,
assignments and
PDFsVisit Dr. Farouks Official Page
1
www.facebook.com/dr.farouk.elkadi
-
5/22/2018 Lec 05
2/97
SHEET PILE WALLS
Prepared By:
Prof. Dr. Ing. Farouk El-Kadi
Professor of Geotechincal Engineering
Faculty of Engineering
Ain Shams University
2
Shorouk
Academy
Faculty of Engineering
Civil Engineering Department
Course : Foundation Engineering 2
Fourth Year CivilYear : 2012
-
2013Version : 00
-
5/22/2018 Lec 05
3/97
USE OF SHEET PILING WALLS1. Water front construction
where other types of retainingwalls would requiredewatering of the site
2. Temporary constructionbecause of the high salvagevalue of sheet piles.
3. Construction at locationwhere the upper layer orlayers of subsoil areinadequate for supportingretaining walls.
4. As columns or piles.3
1. .2. . 3.
.4.
-
5/22/2018 Lec 05
4/97
1
. Water front construction
4
Ground surface
Water level
Sheet Pile
Sheet Pile with tie rod
Water level
Ground surface
Sheet Pile
Inclined tie (Pile)
Ground surface
Water level
Sheet Pile
Ground surface
W.L
-
5/22/2018 Lec 05
5/97
1
. Water front construction
5
G.S
G.S
Sheet
Pile
Piles
SheetPile
SheetPile
-
5/22/2018 Lec 05
6/97
1
. Water front construction
6 Bremen
-
5/22/2018 Lec 05
7/97
1. Water front construction
7
-
5/22/2018 Lec 05
8/97
1. Water front construction
8
-
5/22/2018 Lec 05
9/97
1. Water front construction
9
-
5/22/2018 Lec 05
10/97
1. Water front construction
10
(18)
-
5/22/2018 Lec 05
11/97
1. Water front construction
11
58
-
5/22/2018 Lec 05
12/97
1. Water front construction
12
-
5/22/2018 Lec 05
13/97
1. Water front construction
13
-
5/22/2018 Lec 05
14/97
1. Water front construction
14
Coffer DamCable stay bridge
-
5/22/2018 Lec 05
15/97
1. Water front construction
15
-
5/22/2018 Lec 05
16/97
1. Water front construction
16
2
T C i
-
5/22/2018 Lec 05
17/97
2. Temporary Construction
17
Using sheet pile wall as a temporary structure
during subway excavation
-
5/22/2018 Lec 05
18/97
2. Temporary Construction
18
-
5/22/2018 Lec 05
19/97
2. Temporary Construction
19
-
5/22/2018 Lec 05
20/97
3. Weak Soil
20
.
-
5/22/2018 Lec 05
21/97
4. As a column or a pile
21
-
5/22/2018 Lec 05
22/97
S.P.W Failure
22
-
5/22/2018 Lec 05
23/97
S.P.W Failure
23
-
5/22/2018 Lec 05
24/97
Sheet piling are not suitable for the following
cases
1. Very high walls whichrequire
disproportionatelyhigh flexural strengthof the pile section.
2. Inadequate depth ofpenetration due toboulders in the subsoilfor high bedrockwhich prevents pilepenetration.
24
1. .2. .
-
5/22/2018 Lec 05
25/97
25
Problems of driving sheet piles Boulders or obstacles insub soil
-
5/22/2018 Lec 05
26/97
Common types and martial of sheet piles 1. Wood sheet piles.2. Concrete sheet piles.3. Pile used as a sheet pile wall.4. Steel sheet piles.
26
Wood Sheet Piles
-
5/22/2018 Lec 05
27/97
Wood Sheet Piles
27DrivingDirection
DrivingDirection
DrivingDirection
DrivingDirection
Pile Tip
-
5/22/2018 Lec 05
28/97
28
Spiral Stirrups
Space for mortar
Normal steel RFT
Extra RFT for top part
Filling with mortar
Sec. A-B
Sec. C-D
Direction of Driving
Reinforced Concrete Sheet Piles
-
5/22/2018 Lec 05
29/97
Pile Used as a Sheet Piles
29
-
5/22/2018 Lec 05
30/97
Piles Used as a Sheet Piles
30
-
5/22/2018 Lec 05
31/97
Steel Sheet Pile
31
-
5/22/2018 Lec 05
32/97
Common Statical Types and Use of Sheet Piling
A. Statical Types
1. Cantilever sheet piling.
2. Anchored sheet piling. (Free Earth Support, Fixed
Earth Support)
3. Sheet piling with relieving platform.
B. Use of Sheet Piling1. Braced Cuts
2. Cellular Cofferdams
32
2 0
S i l
l l i f h il
-
5/22/2018 Lec 05
33/97
2.0 Statical calculation for sheet pile
walls
The following are the different statical systems for sheetpile wall (Fig.1):
a- Cantilever S.P.W. (Fig. 1a).b- Anchored free S.P.W. (Fig. 1b).
c- Anchored fixed S.P.W. (Fig.1c).
There are different statical systems, such as maltyanchor S.P.W. fixed at the topetc.
We shall explain only the three types explained in (Fig.1) for different types of soil.
33
-
5/22/2018 Lec 05
34/97
34
-
5/22/2018 Lec 05
35/97
35
-
5/22/2018 Lec 05
36/97
36
-
5/22/2018 Lec 05
37/97
37
-
5/22/2018 Lec 05
38/97
2.1 The design procedure comprises the
following:
1. Assemble the general information: Topographical survey.
Elevation of top of wall.
Elevation of ground surface in front of the wall.
Max. water level, mean tide level and low water level.
2. Analyse the subsoil conditions:
Sufficient borings to get full information about soil properties in differentlevels and level of ground water (,,C).
Select the statical type of wall.
Compute earth pressure and surcharge pressure.
Determine the piling penetration.
Determine the bending stress and design the piling. Design the tie rods (for anchored S.P.W).
Design the anchorage (for anchored S.P.W).
Check total stability of sheet piles.
38
-
5/22/2018 Lec 05
39/97
2.1 The design procedure comprises the
following:
3. Lateral pressure acting on sheet piling walls A sheet piling wall may be subjected to some or all of the
following types of lateral pressure.
Earth pressure: active, at rest and passive pressure.
Lateral pressure due to surcharge load. Unbalanced water pressure and seepage pressure.
Mooring pull, ship impact, etc.
Earthquake force, wave pressure, etc.
39
-
5/22/2018 Lec 05
40/97
4. Earth pressure acting on sheet piling wall
Referring to earth pressure theory previously mentioned, Rankineand coulomb methods can only be used under following conditions:
a) Wall is rigid
b) Wall translates or rotates about its bottom. Distribution of earth pressure on a sheet pile wall is statically
indeterminate and a function of the deformation of sheet pile (Fig. 2).
Practically we can use Rankine and Coulomb theories.
For more accurate calculations we can use theories which take into
account the conditions of yield of the wall (Hansen, j. Brinch, 1953). We shall explain one of the new theories which consider the effect of
wall movement on the value of earth pressure
40
2.1 The design procedure comprises the
following:
-
5/22/2018 Lec 05
41/97
41
2.2 Design of cantilever sheet pile wall
-
5/22/2018 Lec 05
42/97
There are different methods and theories for the statically calculation of
sheet pile wall. The main differences between the different methods are:
a-Calculation and distribution of earth pressure.
b-The method and assumptions for statically calculations.
The results needed from statically calculations are:
a- Penetration depth.
b- Max. bending moment.
c- Safe cross section for sheet bile.d- Deformation of sheet pile.
The cantilever sheet pile will be solved with the following methods:
a- Classical method.
i- Conventional.
ii- Simplified method.
b- Graphical method.
c- Blum method.
d- Sub grade reaction method.
42
2.2 Design of cantilever sheet pile wall
-
5/22/2018 Lec 05
43/97
43
2.2.1 Cantilever sheet pile wall (Cohesionless soil Conventional method)
Assumptions:
a. Wall is rigid.
b. Rankine and Coulomb theories for E.P.
p2 =Kp Kad a p3 =h + dKp dKa = = + + ( + )
I. Calculation of penetration depth
Theory:
Penetration depth d = a+b (a = known,
b = unknown)
p2 , p3 = function of b
P2 , P3 = unknown
Required to find a relation between P2 ,
P3 and the unknown b
This can be done by using the equation
0i.e. P1+P3-P2=0 (1)
and dividing the area (O1 EOFA) to two
areas (O1GA, FOEGAF).
-
5/22/2018 Lec 05
44/97
44
2.2.1 Cantilever sheet pile wall (Cohesionless soil Conventional method)
(3A)
(3)
Equation (1) can be written as follows:1+ 3 2 = 0
3 =1
2(2+ 3)2 = 122.
1+ 122+ 3 1
22= 0
=
2 2
1/(
2+
3) (2)
The 2ndequilibrium equation is =
P1b + Z1 12 p2b b
3 + 1
2mp2+ p3 m3= 0
Substituting the value of (m) from equation (2)
P1+ 1 22
6 +(
2+
3)
6 2 2
12+ 3 2
= 0
-
5/22/2018 Lec 05
45/97
45
2.2.1 Cantilever sheet pile wall (Cohesionless soil Conventional method)
This equation can be written in the following form:
b4
+C1b3
-C2b2
-C3b-C4= 0 (4)
Where,
1 = 4( ) , 2 = 81( )C3 =
6P12KP KaZ1+ p4(KP Ka)
2
4 = 114 + 41( )2 4 = + ( )
Solve equation (4) by trial and error to determine b
d=b+a and required depth Dreq.=1.2 1.4d
C il h il ll (C h i l il C i l h d)
-
5/22/2018 Lec 05
46/97
46
2.2.1 Cantilever sheet pile wall (Cohesionless soil Conventional method)
I. Calculation of bending Moment
Steps to calculate bending moment:
1. The depth is known.
2. Draw the net earth pressure.
3. Divide the net earth pressure into strips (Fig.3). The area of every stripe will
act as a concentrated load in the C.G of the strip.
4. Calculate the moment at any section.
5. To calculate the max. bending moment, find the point of zero shear.
I. Design of section of sheet pile wall
From the value of max. bending and all stress of steel used choose the
section needed from the tables of standard section (example Table 1).
Rust effect must be taken into consideration (see table 2).
-
5/22/2018 Lec 05
47/97
47fig(3)
-
5/22/2018 Lec 05
48/97
48
-
5/22/2018 Lec 05
49/97
49
*
-
5/22/2018 Lec 05
50/97
50
fig(4)
Divide the moment into different
concentrated elastic loads
Calculate the moment at point 0
The deflection = (Moment of the moment/EI)
Calculation of deflection
( bl 2) ff i h f d i i f l h ili
-
5/22/2018 Lec 05
51/97
51
Harbor bulkheads
(in./yr)
Beach bulkheads
(in./yr)
Groins and jetties
(in./yr)
Geographical location
South (south of welmington, N.C.) 0.0062 0.017 0.018
North (north of Pt. Pleasant, N.J.) 0.0023 0.0075 0.011
Zone relative to tidal planes
8 ft above mean high water 0.020
5 ft to 8 ft above mean high water 0.0049 0.022 0.010
2 ft to 5 ft above mean high water 0.0081
Mean high water 0.0027 0.0074 0.0055
Mean tide level 0.0024 0.004 0.024
Mean low water 0.0035 0.002 0.028
Mean low water to ground line Average of 4 values = 0.0036
Below ground line Average of 4 values = 0.0016
Exposure to salt spray
Heavy spray 0.0083 0.016 0.016
Moderate spray 0.0041 (beach bulkheads, groins, and jetties are
considered to be subjected to heavy spray)Light spray or none 0.0024
Paint protection
None 0.0045 0.018 0.020
At least painted once 0.0027 0.011 0.010
(Table 2) Factors affecting the rate of deterioration of steel sheet piling
-
5/22/2018 Lec 05
52/97
52
2.2.2 Cantilever sheet pile wall
(Cohesionless soil
simplified
method)
For equilibrium =
1
3 PP D0
Pa
3 H + Do = 0
PP =1
2KPDo
2 , Pa =1
2KA( H + Do )
2
3 ( + )
3 = 0
03 3 + = 0 (I)
From equ. (I) we can get the value of Do
Domust be increased by 20% to get theoretical value and by another 20% for
factor of safety.
This will give a safety factor of 1.5 to 2.0 approximately.
method
)
-
5/22/2018 Lec 05
53/97
method)
53
Blum solved the problem as a statically
problem.
The unknown is the penetration depth
"t" (i.e. x).
The principals for solving the problem
are the same as the simplified method.
0 =
P(L+x a =rx
3
6
3 =6
+ P P. a.
= .
3 =6
21 +
6
3.
3 = mII1 + nII
Where,
=6
2.P
0
=6
3 .
0
.
method
)
-
5/22/2018 Lec 05
54/97
method)
54
The values of mII, nII can be calculated.
Equation (2) can be solved by trial anderror or using the Nomogram given by
Blum for case NO. 2 to get value (Fig. 8). Calculate . Calculate t = u + 1.2 x.
Calculate xm, which is the location of zero
shear i.e. location of max. bending.
x 2P
Calculate the max. bending.
M P x a x
6
-
5/22/2018 Lec 05
55/97
55
Graphical Solution for Cantilever Sheet Pile Wall
-
5/22/2018 Lec 05
56/97
Graphical Solution for Cantilever Sheet Pile Wall
Steps :
1) Assume penetration depth.
2) Draw the net earth pressure on both sides.
3) Divide the net earth pressure and find the resultant foreach division.
4) Draw the force polygon.
5) Calculate the force (C) and bending moment.
56
-
5/22/2018 Lec 05
57/97
57
Charts for calculation ofpenetration depth andbending moment for
cantilever sheet pile insand soil
for some cases onlyI, II, III, IV
-
5/22/2018 Lec 05
58/97
58
-
5/22/2018 Lec 05
59/97
59
Approximate Depth for Penetration of Sheet Pile in
-
5/22/2018 Lec 05
60/97
Approximate Depth for Penetration of Sheet Pile in
Sand
Soil Depth of penetration *
Dense 0.75h
Firm 1.0h
Loose 1.5h
Very loose 2.0h
60
* h = high of piling above the dredge line.
Statical Calculations forCantilever Sheet Pile
-
5/22/2018 Lec 05
61/97
61
Cantilever Sheet PileWall in Cohesive Soil
Statical Calculations forCantilever Sheet Pile
-
5/22/2018 Lec 05
62/97
62
Cantilever Sheet PileWall in Cohesive Soil
(Cont.)
Cantilever S.P.W penetrating Clay
-
5/22/2018 Lec 05
63/97
63
Cantilever S.P.W penetrating Clay
2.2.4
Computer programs to calculate the
-
5/22/2018 Lec 05
64/97
2.2.4 Computer programs to calculate the
required items for design a sheet pile wall
64
.
..:
a. Using sub grad reaction theory (Fig.9).
b. Using finite element method with different soil models.
.Inertiadredge line
2.2.4
Computer programs to calculate the required items for design a sheet pile wall
-
5/22/2018 Lec 05
65/97
65
(Fig. 9) According to CUR 166
Determine the required depth of penetration
f th til h t il ll h i
-
5/22/2018 Lec 05
66/97
66
Ka= tan2(45-30/2) = 0.333,
KP = tan2(45+30/2) = 3.000
P 0.333 16 5.0 26.6kN/m
a .. 0.62m
P 26 .65 26.600.62
=66.5+8.2 = 74.7 kN Taking moments about O1and
dividing by P1.
for the cantilever sheet pile wall shown in
Fig. the soil is cohesionless soil, No ground
water.
Using conventional method
+
-
5/22/2018 Lec 05
67/97
67
Z..+... 2.08m p K Kb 16 2.667 b 42.7b
16 5 0.62 3.0 16 0.62 0.333 or p 266.5 42.7b From Eq.
m pb2Pp p
..
.+.
From Eq.
6
6 0 Or
74.7 2.08 42.7
6 266.585.46 42.7
149.4266.585.4
0 Or
448.2 2.08 42.742.7 149.4
266.585.4 0 Solving by trial and error, b = 4.4m
Alt ti th d f b
-
5/22/2018 Lec 05
68/97
68
Alternative method for b
Using Eq. b Cb Cb Cb C 0 Where
16 5 3.0 16 0.62 2.667162.667
.. 6.24
.
. 14.0 + . ..+.. 109.07 +
. ..+..
148.24 Therefore, 6.24 14.0
109.07 148.24 0 Solving by trial and error, b = 4.40 m
Therefore, d = b + a = 4.40 + 0.62 =
5.02
D = 1.30d=6.50m
-
5/22/2018 Lec 05
69/97
69
Using Simplified method
Taking moment about point A
+ 0
Substituting the values of P1 , P2
. + 0
3 3 0 Ka= 0.333 , Kp=3 , h=5.0 m 2.667d3-5d2-25d-41.67=0
Solving by trial and error d=4.70m
D=1,4d=6.58 m
B
C
P1
P2
h= 5m
d
-
5/22/2018 Lec 05
70/97
70
Using Blum method
h=5L=5.62
Xm = location forpoint of zero shear
u=0.62
Load (ton)
P1 0.0675
P2 0.2
P3 0.3325
P4 0.4675
P5 0.6
P6 0.7325
P7 0.8675
P8 1
P9 1.1325
P10 1.2675
P11 0.8
P12 0.033
Sum 7.5005
C
Distribution of net earth pressure
=7.5005 t
t
-
5/22/2018 Lec 05
71/97
71
Using Blum method
m1 n . P . .
1.6 3 0.33 4.26 . . 7.5 0.334 . . 26.55 0.21 From Blum Chart
=0.7
X = .L = 0.72 x 5.62 = 4.04 t = u +1.2 X = 0.62 +(1.2x4.04) 5.46m
Using F.S = 20%
Tact. = 5.46 x 1.2 = 6.55m
Calculation for point of zeroshear
x = .
. 1.87 M P x a = . a
0.9428.
=5.62 x 7.5 + 26.55 +
0.9428x0.484x20.539
=42.1-26.55+9.37 = 24.97 t.m
-
5/22/2018 Lec 05
72/97
72
arm Area moment
0 25 0 0025 0 000625
-
5/22/2018 Lec 05
73/97
73
To calculate deflection at point 0, M= 25m.t,Zsp calculated 1786 cm, Esteel=2100000
kg/cm2, Selected section Larssen AZ19, I
(cm4)=36980,
Deflection (cm)=8.589042455
0.25 0.0025 0.000625
0.75 0.025 0.01875
1.25 0.0975 0.121875
1.75 0.2525 0.441875
2.25 0.525 1.18125
2.75 0.9453 2.599575
3.25 1.5544 5.05183.75 2.375 8.90625
4.25 3.4475 14.65188
4.75 4.8025 22.81188
5.25 6.45 33.8625
5.75 8.2725 47.56688
6.25 10.0275 62. 67188
6.75 11.45 77.2875
7.25 12.2725 88. 97563
7. 75 12.2275 94. 76313
8.25 11.0475 91. 14188
8.75 8.4675 74.09063
9.25 4.2225 39.05813
9. 555 0.1888 1.803984
Sum 667.0079
By
Dr.
Amr
Radwan
Software Series
-
5/22/2018 Lec 05
74/97
74
By
Dr.
Amr
Radwan
Software Series
-
5/22/2018 Lec 05
75/97
75
Finite element Solution
-
5/22/2018 Lec 05
76/97
76
2.3
Design of Anchored sheet piles (Classical solution)
-
5/22/2018 Lec 05
77/97
g p
77
Statically there are two types of anchored
sheet piles:a. Anchored free sheet pile.
b. Anchored fixed sheet pile.
soil
-
5/22/2018 Lec 05
78/97
78
x 0 (I) T P
2 P
1 0 1T= Tensile force in anchorCalculation of depth (a)
Kh a Ka 0 a (2)12 MM = 0 (II)
1 + 1 2 + + 23 = 0 (3a)
Substituting the value of P2
14 + 1 2 + +2
3 = 0 (3b)
This equation can be written as under
b3 + 1.5b2g + a 3P1f(KPKa ) = 0 (4)
Where, f = a + h e Z1 , g = h eSolve equation (4) to find "b"
d= b+a , DPra.= 1.2 1.4 d
T = P1P2
Find the point of zero shears to calculate the max. bending.
2.3.2
Fixed earth support method for penetration in to sandy soil
-
5/22/2018 Lec 05
79/97
79
Calculation of location of point of inflexion
(i):
According to Blum (1931), there are a
relation between (i/h) and (Fig.2).
2.3.2
Fixed earth support method for penetration in to sandy soil
-
5/22/2018 Lec 05
80/97
80
With these assumptions, the problem is
statically determinate.
Method of statically calculation:
(Equivalent beam method)(Fig. 3)
Assume that the S.P. is a simply supported at
point "M" and fixed at the lower end K.
Then we can divide the beam in two parts:
a. Upper beam "BI".
b. Lower beam "IK".
2.3.2
Fixed earth support method for penetration in to sandy soil
-
5/22/2018 Lec 05
81/97
81
Steps for calculation
a. Design of top beam (B-I) (Fig. 4a):
(a)Upper Beam "BI"(1)Determine the pressure P1 at the dredge level.(2)Estimate the angle of shearing resistanceof the soil.(3)Determine the distance "i" of the point of inflexion from (Fig.2).(4)Determine the distance "a" of the point of zero pressure from the
equation,
a = P1
(KPKa ) (1)
(5)Determine the pressure Poat the point of inflexion from the relation,Po =
P1
a(a i) (2)
(6)Determine the reaction "RI" for the beam "IB" by taking momentsabout the point "M" of anchor forces acting on "IB" (Fig. 4a).
2.3.2
Fixed earth support method for penetration in to sandy soil
-
5/22/2018 Lec 05
82/97
82
Steps for calculation
b. Design of lower beam "I-K"
(a)Lower Beam "IK"(1)Determine the pressure "P2" from the relation
P2 = KP Ka(d a) (3)
Alternatively, P2 =Po
(ai) (d a)
(2)Determine the distance (d-a) by taking moment of the forces onthe beam "IK" about "K" (Fig. 4b) the reaction "RI" on the lower
beam is equal and opposite to that on the upper beam.
(3)Calculate "d" from Eq. (3) and hence find D = 1.2d.(10) Determine the tension "T" in anchor by considering the
equilibrium of beam "IB". Thus
T = P1- RI (4)
Where P1 = total force due to pressure on "IB".
support
-
5/22/2018 Lec 05
83/97
support
83
Sheet pile wall is flexible. For anchored sheet pile in granular soils, the most significant factors are
(Rowe, 1952, Terzaghi, 1954).1- The relative density of soil.2- Relative flexibility of the sheet pile which is expressed in terms of
flexibility number.P =
H4
EI (English unit)
P = 1.1 106H 4
EI (metric unit)
H = total height of the sheet pile (m).
EI = modules of elasticity and moment of inertia for sheet pile 2 , (4/
support
-
5/22/2018 Lec 05
84/97
support
84
For anchored sheet pile in cohesive soil, the most significant factors are(Rowe 1957, 1958):1-The stability number.
=
1 +
= 1.25
Ca = adhesion between soil and sheet pile.
2-Flexibility number.
P =H4
EI= 1.1 106 H4
EI
HH
3- Relative height of piling .
N.B
P = H
4
EI (English unit)
P = 1.1 106 H
4
EI
(Metric unit) (See charts Fig "1")
Charts
for the reduction
-
5/22/2018 Lec 05
85/97
of bending moment for
anchored free earth
support sheet pile wall
85
2.4
Design of anchored sheet piles (Blum
method)
-
5/22/2018 Lec 05
86/97
2.4 Design of anchored sheet piles (Blum method)
86
Assumptions:
Rankine and Coulomb theories are valid.
Assuming fixation for sheet pile at the
location of C.
Treated the problem as statically
indeterminate problem.
The unknowns are the force in tie A and
the penetration depth "x".
The following are the steps for design.
2.4
Design of anchored sheet
-
5/22/2018 Lec 05
87/97
piles (Blum method)
87
Steps for design
Divide the forces as given in (Fig. 2).
Calculate the bending moment as a
function of the load.
Calculate the deflection at location of "A".
Steps of design
-
5/22/2018 Lec 05
88/97
88
Deflection due to force" A" (Fig. 2a)
EJf A. x
3From M O about point C
A x P x a P x a x
6 0
1 A 1 xP x a P x a x6
2 EJ f x
3 P x a P x ax6
3 EJ f Pa . x2 x
3
P6 2 x 3a x
Due to loads (Fig. 2c)
-
5/22/2018 Lec 05
89/97
89
4 EJf P. x a
2 a23 x a
P62 x 3a x aDue to passive pressure (Fig. 2d)
5 EJf x
6 x dx 1204x 5x
deflection at A = 0f 0
P62 x 2a x P62 x 2a x
x18 x
P
6 2 x
3a
x
P62 x
3a x
a
1204x
5x
6 . 6
36012 15 20 2
608 2520
-
5/22/2018 Lec 05
90/97
90
Put,
6 x . IWe get the following equation with the unknown
7 0,8 2,5 2,0
1 6 6.
Or in simple form
8 0,8 2,5 2,0 1 Where
6 .
6 .
9 6
+.
10
6
The mI,nI values are function of earth
pressure above the point of zero load and
-
5/22/2018 Lec 05
91/97
91
can be calculated.
The equation (8) can be solved
mathematically or using the monogram
to get . Calculate .
t = u + 1.2 x
Calculate the tension in tie A
+ 1
+
6
Calculate the max. moment at point of
zero shear
M
=Q.a
2.4.1
Design of anchors
-
5/22/2018 Lec 05
92/97
92
There are different
types of anchor (Fig
2.4/1):
Anchor plates and
beams (deadmen).
Brace piles.
Large existingstructure.
location of anchor plate (Fig.
-
5/22/2018 Lec 05
93/97
2.4/2)
93
The method for determination of safelocation of anchor plate is given in (fig.
2.4/2).
2.4.3
Block stability for anchor free sheet pile
(
)
-
5/22/2018 Lec 05
94/97
(Cohesionless soil)
94
The bloke stability must be calculated to
check the factor of safety for the tie force
(Fig. 2.4.3/1).
= The resultant of active earthpressure from point F' till H'(water pressure not to be
taken into consideration).
d = Calculated depth for
anchored free sheet pile.
= Factor of safety for the forcein tie 1.5As = Tension in tie from the
calculation of block stability.
Ac = Tension in tie from the
calculation of sheet pile.
N.B: If < 1.5, the length of tiemust be increased 45 /2
2.4.4
Typical steel work details
-
5/22/2018 Lec 05
95/97
95
-
5/22/2018 Lec 05
96/97
96
-
5/22/2018 Lec 05
97/97