lecture on 21-3-15 - altafrehman · 1 ce-319 (3 credit hours) geotechnical and foundation...
TRANSCRIPT
1
CE-319 (3 Credit Hours)
Geotechnical and Foundation Engineering
Foundation Settlements-immediate
settlement
Instructor:
Dr Irshad Ahmad
Lecture on 21-3-15
Department of Civil Engineering
University of Engineering and Technology, Peshawar
2
Foundation Settlement- Introduction
Some Typical Loads on Building Foundations
Number and Depth of boring
Immediate settlement calculations using Theory of Elasticity
SPT Procedure
SPT corrections
SPT correlations
Immediate settlement using SPT
Contents
5
Some Typical Loads on Building Foundations
Settlements are cause by
change in stress in the soil mass
Change in stress occurs because
Of building loads
8
Depth of boring
For Square footing:
10% qo at 2B
For Strip footing
10% qo at 6.5B
For circular footing
10% qo at 2 Dia
9
Immediate Settlement
We will find immediate settlement through
THEORY OF ELASTICITY
USING STANDARD PENETRATION TEST RESULTS
13
Example
Method-1: Taking weighted average of Es
Method-2: Method of superposition
Both methods are discussed in class
14
Example-Using Weighted Average of Es
Es (average) = (42.53 + 60 8)/11=55 Mpa,
H=11m, B=B/2=33.5/2=16.75,
H/ B=11/16.75=0.66 (use 0.7)
L/B = (39.5/2)/(33.5/2)= 1.18
Assume, =0.33, I=0.12 (after interpolation)
H=qoB(1-2)/Es m I
= 134 16.75 (1-0.332)/(55 1000) 4 0.12
= 0.0175m = 17.5 mm
15
Example- Method of Superposition
Methodology: Calculate Hi
(1) Consider the 3m Sand layer with Es overlying
sand stone.
(2) Consider whole 11m layer as Clay with Es=60
MPa overlying Sand stone.
(3) Consider upper 3m layer as Clay with Es=60
Mpa overlaying Sandstone.
16
Es = 42.5Mpa,
H=3m,B=B/2=16.75,
H/ B=3/16.75=0.18, L/B= 1.18
I=0.0316
H=qoB(1-2)/Es m I
134 16.75 (1-0.332)/(42.5 4
0.0316
= 5.96 mm
Es = 60 Mpa,
H=11m,B=B/2=16.75,
H/B=3/16.75=0.18, L/B= 1.18
I=0.12
H=qoB(1-2)/Es m I
134 16.75 (1-0.332)/(60 4
0.0316
= 16 mm
Es = 60 Mpa,
H=3m, B=B/2=16.75,
H/B=3/16.75=0.18, L/B= 1.18
I=0.0316
H=qoB(1-2)/Es m I
134 16.75 (1-0.332)/(60 4
0.0316
= 4.2 mm
H= 5.96 + 16 - 4.2 = 17.7 mm
17
Standard Penetration Test (ASTM D-1586)
Practicing Engineers use the SPT widely in estimating the bearing
capacity of soils and to assess the in-situ relative density of a sand
deposit.
The test is performed using a split spoon barrel sampler 50mm
external diameter, 35mm internal diameter and about 650mm in length
and connected to the end of boring rods.
After boring has been advanced to the desired sampling elevation and
excessive cutting has been removed, attach the split spoon sampler to
the sampling rods and lover into borehole.
Drive the sample with blows from 140lb (63.5 kg) hammer falling
freely through a height of 760mm (30 inch).
The sampler is advanced under the impact of the hammer into three
successive (6 inch) increments. (i.e. total 18 inch).
18
Standard Penetration Test (ASTM D-1586)
Count the number of blows in each 6 inch increment until one of the
following occurs
A total of 50 blows have been applied during any of the three 6
inch increments.
A total of 100 blows have been applied
There is no observed advance of the sampler during the
application of 10 successive blows of the hammer.
The sampler is advanced the complete 18 inch without the
limiting blow counts occurring as describe in 1,2 and 3.
The 1st 6 inch is considered to be a seating drive. The sum of the
number of blows required for the 2nd and 3rd 6-inch penetration is
termed the standard penetration resistance or the N-value.
33
Problem (Bowel P-266)
Fill up the below table using equation for the widths given and prepare
a graph
36
Example (Bowels P-543)
Find allowable BC qa to ensure
FOS=3 against Shear failure
Si <= 50 m
Solution:
(1) Shear Criteria:
qu = c Nc sc + D Nq + ½ B N s
BC factors: For ⱷ = 0, Nc = 5.14, Nq = 1 and
N = 0
Shape factors: sc=1.3, and s=0.8
qu (net)= qu(gross) - D =
(1505.14 1.3 + 18.7 1.5 1) - 18.7 1.5
= 1000 kPa
qsafe = qu/FOS = 334 kN/m2
37
Example (Bowels P-543)
Es1= 1000 cu = 1000(300/2)=150 000 kPa
Es2= 500(N55+15)= 500[18(70/55)+15]=18950 kPa
Es2= 500(N55+15)= 500[22(70/55)+15]=22 000 kPa
Es2= 500(N55+15)= 500[40(70/55)+15]=32 900 kPa
(2) Settlement Criteria
Es(average)= 3.4(150000)+3.3(18950)+7(22000)
+13.8(32900)]/27.5 = 42 930 kPa
H from base of the mat to rock = (4.9-
1.5)+3.3+7+13.8 = 27.5m,
Estimate the mat will be on the order of 14m,
giving
B=B/2=14/2=7, H/ B=27.5/74, L/B = 1
For =0.33, I=0.42 (after interpolation)
H=qoB(1-2)/Es m I
0.05 = qo 7 (1-0.332)/(42930) 4 0.42
qo= 204 kPa
Allowable Bearing Capacity:
qa=200 kPa, settlement controls:
As the design proceeds and B is found to be
substantially different from 14m, it may be
necessary to revise qa.