lesson learned in linac commissioning here i introduce 3 kinds of beam loss generated by following...
TRANSCRIPT
Lesson learned in Linac Commissioning
Here I introduce 3 kinds of beam loss generated by following issues1. Intra beam stripping (IBSt) in ACS
2. Dark current of an ion source
3. Beam accelerated by transient RFQ RF
T. Maruta KEK/J-PARC
ACS Beam Loss
σx (mm) σy (mm)
• We have observed continuous beam loss in ACS, and residual radiation is higher than our expectation.
• One reason is the property of current transformers.
• We have been investigating the source of beam loss particles for countermeasure.• We measured the contribution of the Intra Beam Stripping (IBSt)
3 times RF frequency jump at SDTL to ACS. longitudinal focusing becomes higher in ACS⇒ ⇒ Beam size at ACS is narrower than SDTL to suffer the equi-partitioning condition.
IBSt is inversely proportional to the beam size.
50 MeVDTL
191 MeVDTL
191 MeVACS
324 MHz 972 MHz
Design beam envelopeEqui-partitioningcondition
Intra Beam Stripping (IBSt)
Beam size in ACS (Simulation)
0.010 W/m
0.020 W/m
0.026 W/m
0.032 W/m
IBSt (Simulation)
We prepared 4 kinds of optics w/ different T ratio; T= 1.3, 1.0 (default), 0.7 and 0.3.
Peak current: 30 mAPulse width : 500 usRepetition : 25 HzBeam duty : 56 %
• The identical optics is applied to DTL – SDTL (T = 1.0).• 3D matching in MEBT2.• Measure the beam loss in ACS and beam profile at the L3BT entrance.
ACS BLM Signal Comp. at T = 0.7, 1.0 and 1.3
SimulationT = 0.7 : 0.020 W/mT = 1.0 : 0.026 W/mT = 1.3 : 0.032 W/m
R (T=0.7/T=1.0) = 0.77
R (T=1.3/T=1.0) = 1.23
The ratios of BLM signal of each T-ratio is well consistent w/ the simulation after ACS08.IBSt could be dominant source of the ACS beam loss.
ACS BLM signal (signal saturation is corrected)
Ratio of ACS BLM signal
Beam Loss by Ion Source Dark CurrentIS RFQ
50 MeV DTL 191 MeV SDTL 400 MeV ACS
DB2
RCS
DB1
Current transformer waveform (w/o chopping)
MacroPulse(100 us)
Current transformer waveform (w/ chopping, duty 100%)
100 us
Beam fromRFQ
Chopper RF
Beam afterchopper
Dark currentMacro pulse
Lost in 3 GeV RCS
• Dark current exists before a macro pulse. Current is about 2 mA (4% of 50 mA).
• The dark current is partially scraped by the chopper, but RF width is not sufficient.
• Un-scraped dark current causes a beam loss in 3-GeV RCS.
60us 50us
1mA 1mA
Beam : 50 mA / 100 us
Chopper
MeasuredCT
Ion Source Dark Current
Beam fromRFQ
Chopper RF
Beam afterchopper
Dark currentMacro pulse
Lost in 3 GeV RCS
60us 50us
Beam fromRFQ
Chopper RF
Beam afterchopper
Dark currentMacro pulse
120us 10us
100 us
1mA
The chopper RF timing is optimized, and then check the current transformer again.
• Extend former RF width to 120 us
• The chopper RF width of a former macro pulse is extended to fully cover the dark current.
• After the timing change, we again measure the CT waveform, and the dark current does not detected.
• The beam loss in RCS is drastically reduced.
L3BT_BLM55
L3BT_BLM57
Chopping Duty 100%
Beam gate0.5V
Beam Loss at Macro Pulse End around BM1Beam after RFQ
Chopper RF(duty 100 %)
ss
10 us
IS RFQ50 MeV
DTL 191 MeV SDTL 400 MeV ACS
DB2
RCS
DB1
Small amount of beam exists after macro-pulse.• This beam cannot be scraped
by chopper. beam property must be ⇒
different from the main part.
Insert carbon plates on beam line to intentionally loss
0.5V
10 us
Timing around Macro Pulse End
Beam @ LEBT
RFQ RF
Beam @ chopperupstream
ssChopper RF(full chop mode)
Beam @chopperdownstream
10 us
Present timing (chopping duty = 100%)
beam at transientRFQ RF
Lost in L3BT scraper
Extinction level of this region looks worse than the beam in beam gate
beam gate
ss
10 us
Proporsed timing (delay the RFQ RF end)
Accelerated by nominal RF
Lost in L3BT scraper
beam gate
After some studies, we found that the loss comes from the beam accelerated by transient RFQ RF
L3BT_BLM55
L3BT_BLM57
Beam Monitor Timing
Chopped (duty 100%), RFQ timing shift : 0 us
L3BT_BLM55
L3BT_BLM57
Beam Monitor Timing
Chopped (duty 100%), RFQ timing shift : 3us
Beam gate Beam gate
No significant beam loss is observed after +3 us shift.
Beam Loss Comp. of Different RFQ RF Timing
Lesson Learned in Linac CommissioningAfter a replacement of linac elements (ex. front-end replacement) and beam power upgrade, new beam loss may appears. We have to pay attention to beam loss distribution in the 1st commissioning.
Time structure of beam loss is a good hint of source.(We normally monitor the integrated BLM signals)
It is difficult to find the beam loss caused by timing in linac single commissioning. Communication with downstream accelerator is important.
Gate Timing Relating to Dark Current
Beam from RFQ
Arcing
Modulation
It is expected that the beam is extracted only when the modulation is on
RFQ RF
800 us
650 us
IonSource
Design(expectation)
Reality
Rise-up of macro pulse is determined by modulation
50 〜 500 us
Dark Current
Small fraction of un-modulated beam is inside the RFQ acceptance, and then accelerated to 400 MeV
Hoffman Stability Chart at εx/εz = 0.7