SWET GANGA HYDROPOWER & CONSTRUCTION LIMITED Sankha Park, Dhumbarahi, G.P.O.Box 19737, Kathmandu Nepal Site Office: Sirise, Ramechhap
SANIMA HYDRO AND ENGINEERING (P.) LIMITED.
Shankha Park, Dhumbarahi, Kathmandu M.C, Ward no.: 04, Nepal
G. P.O. Box. 19737, Kathmandu, Nepal
Tel: (977-1) 4372828/ 4373030/ 4015788, Fax: (977-1) 4015799
Email: [email protected], Web: www.sanimaengineering.com
LOWER LIKHU HYDROPOWER PROJECT (28.1MW)
MONTHLY PROGRESS REPORT # 17
SEPTEMBER, 2019
SWET GANGA HYDROPOWER & CONSTRUCTION LIMITED Sankha Park, Dhumbarahi, G.P.O.Box 19737, Kathmandu Nepal Site Office: Sirise, Ramechhap
SANIMA HYDRO AND ENGINEERING (P.) LIMITED.
Shankha Park, Dhumbarahi, Kathmandu M.C, Ward no.: 04, Nepal
G. P.O. Box. 19737, Kathmandu, Nepal
Tel: (977-1) 4372828/ 4373030/ 4015788, Fax: (977-1) 4015799
Email: [email protected], Web: www.sanimaengineering.com
LOWER LIKHU HYDROPOWER PROJECT (28.1 MW)
MONTHLY PROGRESS REPORT # 17
SEPTEMBER, 2019
Rev: _________________________________________________________________
Prepared By:
Signature Date
Aashish Dhakal
Checked By:
Sudip Chapagain
Approved By:
Bhojraj Paudel
Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September 2019
i Sanima Hydro and Engineering Pvt. Ltd.
Table of Contents 1. PROJECT OVERVIEW AND INSTITUTIONAL ARRANGEMENT ............................... 1
2. KEY DATES .................................................................................................................. 1
3. CONTRACT PACKAGES AND IMPLEMENTATION ................................................... 2
4. FINANCING .................................................................................................................. 2
5. RESOURCES AT SITE ................................................................................................. 2
6. CIVIL CONSTRUCTION WORK PROGRESS .............................................................. 6
6. 1 HEADWORKS ...................................................................................................................... 6
6.2 TUNNEL ................................................................................................................................ 9
6.2.1.HRT INLET PORTAL ......................................................................................................... 9
6.2.2.SETI OUTLET PORTAL ................................................................................................... 10
6.2.3. SETI INLET PORTAL ...................................................................................................... 11
6.2.4. POKU OUTLET PORTAL ................................................................................................ 12
6.2.5. POKU INLET PORTAL .................................................................................................... 13
6.2.6. HRT OUTLET PORTAL .................................................................................................. 14
6.3. SURGE SHAFT AND CONNECTING TUNNEL ................................................................ 16
6.4. PENSTOCK ........................................................................................................................ 16
6.5. POWERHOUSE ................................................................................................................. 18
6.6. TAILRACE .......................................................................................................................... 18
7. HYDRO-MECHANICAL WORKS PROGRESS .......................................................... 19
8. ELECTRICAL WORKS ............................................................................................... 21
9. POWERHOUSE CAMP .............................................................................................. 21
10. SOCIAL AND PUBLIC .............................................................................................. 23
11. ENVIRONMENT, HEALTH AND SAFETY ............................................................... 24
12. EQUIPMENT BREAKDOWN .................................................................................... 25
13. VISITORS OF THE MONTH ..................................................................................... 25
14. PHOTOS ................................................................................................................... 27
15. PROGRESS CHART ................................................................................................ 31
Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September 2019
ii Sanima Hydro and Engineering Pvt. Ltd.
List of Figures
Figure 1: Construction activities in intake and undersluice .............................................................. 7
Figure 2: Divide wall panel 1 and 2 .................................................................................................. 7
Figure 3: Hard stone lining at undersluice apron ............................................................................. 8
Figure 4: Settling basin and Sediment Flushing area ...................................................................... 8
Figure 5: Tunnel from Face-01 (Main inlet portal) ............................................................................ 9
Figure 6: Tunnel from Face-02 (Seti Outlet portal) ........................................................................ 10
Figure 7: Tunnel from Face-03 (Seti inlet portal) ........................................................................... 11
Figure 8: Tunnel from Face-04 (Poku outlet portal) ....................................................................... 12
Figure 9: Tunnel from Face-05 (Poku inlet portal) ......................................................................... 13
Figure 10: Tunnel from Face-06 (Main outlet portal)...................................................................... 14
Figure 11: Surge shaft from top ..................................................................................................... 16
Figure 12: Slope protection at penstock alignment ........................................................................ 17
Figure 13: Rebar laying for concrete casing around irrigation pipe across penstock alignment .... 17
Figure 14: View of tailrace culvert panel 03 before concreting ...................................................... 18
Figure 15: Tailrace culvert panel 3 ................................................................................................. 19
Figure 16: Rolled MS pipes at HM yard ......................................................................................... 20
Figure 17: Installation of gravel flushing bellmouth ........................................................................ 20
Figure 18: Over and under Voltage protection scheme ................................................................. 21
Figure 19: Powerhouse staff quarter (Type: Block F) .................................................................... 22
Figure 20: View of Powerhouse Camp .......................................................................................... 22
Figure 21: Billiards House at Powerhouse Camp .......................................................................... 23
Figure 22: Restrictive signage at tunnel face ................................................................................. 24
Figure 23: Emergency assembly point at Seti ............................................................................... 25
Figure 24: LLHP and SHEPL team with Geological consultant Mr. Subash Sunuwar ................... 26
Figure 25: LLHP team with members from COWI and DIF ............................................................ 26
Figure 26: Installation of gravel flushing pipe (Left) and Outlet of gravel flushing (Right) .............. 27
Figure 27: Calibration of aggregate for concreting at site (left) and newly unloaded rebar (right) . 27
Figure 28: Masonry at settling basin (left) gravel flushing stop-log installation (right) .................... 27
Figure 29: Hard stone cutting at Headworks (left) and storage (right) ........................................... 28
Figure 30: Headworks construction ............................................................................................... 28
Figure 31: Crusher at Headworks (left) and material stock (right) ................................................. 28
Figure 32: Irrigation canal across Penstock alignment (left) and concrete casing (right) ............... 29
Figure 33: Main inlet tunnel (Left) and Safety meeting (Right) ....................................................... 29
Figure 34: Traffic signage at Sirise bazaar .................................................................................... 29
Figure 35: Safety signage at access road (left) and speed limit sign (right)................................... 30
Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September 2019
iii Sanima Hydro and Engineering Pvt. Ltd.
Figure 36: Wire net fence for electrical panel board at Powerhouse (left) and LOTO for safety (right)
....................................................................................................................................................... 30
Figure 37: Fence posts around Powerhouse staff quarter (left) and chain link fencing (right) ....... 30
Figure 38: Tailrace culvert panel 6 to 10 (left) and safety signs at surge shaft area (right) ........... 31
Figure 39: Plate rolling machine at HM yard (Left) and shotcrete at penstock slope area (right) .. 31
List of Tables
Table 1: Human Resource at site from the Employer’s side ............................................................ 2
Table 2: Human Resource at site from Civil Contractor’s side ......................................................... 3
Table 3: Human Resource at site from Hydro-Mechanical Contractor’s side .................................. 3
Table 4: Equipment mobilized by civil contractor ............................................................................. 4
Table 5: Equipment mobilized by Hydro-Mechanical contractor ...................................................... 4
Table 6: Construction material stored by Civil contractor ................................................................. 5
Table 7: Progress summary of Headworks ...................................................................................... 6
Table 8: Overall Tunnel Excavation Progress ................................................................................ 15
Table 9: Detail of concrete quantity at tailrace ............................................................................... 18
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
1 Sanima Hydro and Engineering Pvt. Ltd.
1. PROJECT OVERVIEW AND INSTITUTIONAL ARRANGEMENT
Lower Likhu Hydropower Project (LLHP) is a run-of-river (RoR) hydropower project which utilizes Gross Head 118 m and Design Discharge of 29.75 m3/s resulting in to an installed capacity of 28.1 MW. The entire project area (Headworks to Powerhouse) is located in LikhuTamakoshi Rural Municipality (Saipu-2 and Bijulikot-4) of Ramechhap, Province no.3 of Nepal. Geographically, the project lies between Longitudes 86°15’38” E to 86°13’17” E and Latitudes 27°25’56” N to 27°22’47”N. Geologically, the project area belongs to the Lesser Himalayas.
The project’s headworks area is accessible via two different road routes. One from Kathmandu-Dhulikhel-Charikot-Nayapul-Dhobi-Sirise (170 km) and another from Kathmandu-Dhulikhel-Khurkot-Manthali-Dhobi-Sirise (227 km). Manthali Bazar is the nearest city which is about 45 km from the proposed headworks area.
Construction Management:
a) The Employer/Owner Swet Ganga Hydropower & Construction Ltd. (SGHCL)
b) The Engineer/ Consultant Sanima Hydro and Engineering PVT. Ltd. (SHEPL)
c) The Contractor High Himalaya Hydro-Bavari Construction J.V.
(Civil Construction Works)
d) The Contractor Machhapuchhre Metal & Machinery Works (P.)Ltd. (3MW) (Hydro-mechanical
Works) e) The Contractor Asia Pacific Power-Tech Co. Ltd., China
(Electro-mechanical Works)
f) The Contractor Tender Evaluation completed
(Transmission-line Works)
2. KEY DATES
Description Date
Grid connection agreement 12th Chaitra 2072 (25thMarch 2016)
Generation License issued by Department Electricity Development (DoED), Ministry of Energy (MoEn), Government of Nepal (GoN)
2nd Baisakh 2073 (14thApril 2016)
The license period of the project is from
28th Chaitra 2072 to 27thChaitra 2107 B. S.
Power Purchase Agreement (PPA) with Nepal Electricity Authority (NEA)
14th Poush 2073 (29thDec 2016)
Letter of Acceptance for civil works 7thFebruary 2018
Financial Closure 22nd February 2018
Contract of main Civil works 5thChaitra 2074 (19thMarch 2018)
Contract of Hydro-mechanical 9thPoush 2075 (24thDec 2018)
RCOD 1stDecember 2021
Electro-Mechanical Contract Award 18th Bhadra 2076 (4th September 2019)
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
2 Sanima Hydro and Engineering Pvt. Ltd.
3. CONTRACT PACKAGES AND IMPLEMENTATION
a) Main civil construction works Contract Package 1
b) Hydro-mechanical and Penstock Contract Package 2
c) Equipment (electromechanical) Contract Package 3
d) Power evacuation Transmission Contract Package 4
e) Pre-construction works, camp, facilities, social environment Direct by the Em-ployer
4. FINANCING
a) Equity Promoters 25% of the total Project Cost
b) Debt Consortium of Banks 75% of the total Project Cost (Lead Bank-Laxmi Bank Ltd, Member Banks: Kumari Bank Ltd., Hy-droelectricity Investment and Development Company Ltd. Century Commercial Bank Ltd., and Prabhu Bank Ltd.)
5. RESOURCES AT SITE
From Employer’s side:
Table 1: Human Resource at site from the Employer’s side
Description Number Description Number
Acting Resident Engineer 1 Social and Environment officer 2
Assistant Manager (Environment) 1 Social Mobilizer 3
Safety Officer 1 Survey Helper 1
Geologist 3 Office Assistant 2
Civil Engineer 5 Driver 3
Electrical Engineer 1 Supervisor 8
Geomatics Engineer 1 Cook 2
Admin/Account 3
Sub-Engineer(Overseer) 3
Surveyor 1
Assistant Sub Engineer(Sub Overseer) 1 Total: 42
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
3 Sanima Hydro and Engineering Pvt. Ltd.
From Civil Contractor’s side:
Table 2: Human Resource at site from Civil Contractor’s side
Description Number
Project Manager 1
Construction Manager 1
Tunnel Manager 1
Plant Manager 1
Engineer 14
Geologist 3
Overseer/Sub-overseer 10
Surveyor 4
Supervisor/Foreman 5
Lab Technician 3
Skilled Worker 12
Unskilled labours (Including crusher) 40
Operator/Driver 37
Helpers 10
Mechanical/Electrical staff 48
Office/store/Purchase 31
Security guards 20
Office Assistant 1
Cook 9
Peon (ktm) 3
Other Workers
Powerhouse rock crusher 41
Headworks and rock crusher 184
HRT inlet portal 18
Poku area 43
HRT outlet and surge shaft 31
Seti portals 33
Total 604
From Hydro-Mechanical Contractor’s side:
Table 3: Human Resource at site from Hydro-Mechanical Contractor’s side
Description Number
Engineer 1
Supervisor 2
Foreman 1
Welder 5
Electrician 1
Fitter 5
Helper 7
Store in-charge 1
Hydra Operator 1
Total 24
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
4 Sanima Hydro and Engineering Pvt. Ltd.
Equipment mobilized by Civil Contractor at site
Table 4: Equipment mobilized by civil contractor
Equipment mobilized by Hydro-Mechanical Contractor at site
Table 5: Equipment mobilized by Hydro-Mechanical contractor
S.N Equipment Number
1 Hydraulic Crane 1
2 Rolling machine 1
3 Pug machine 1
4 Tractor 1
S.N Equipment Name Number S.N Equipment Name Num-ber
1 Generator 62.5KVA 2 26 Pusher leg 43
2 Generator 30KVA 1 27 Blaster (Exploder) 6
3 Generator 125KVA 2 28 Siren 6
4 Generator 25 KVA 1 29 Core Cutting machine 2
5 Generator 160 KVA 3 30 Hand drilling machine 3
6 Generator 250 KVA 3 31 Air compressor 9
7 Air Receiver tank 6 32 Vibrators 1
8 Ohm meter 6 33 Water pump 10” 2
9 Excavator 7 34 Water pump 12” 1
10 Dum Truck 9 35 Water Pump (1HP) 9
11 Transportation Truck 1 36 Grinding machine(4”) 6
12 Backhoe Loader (JCB) 3 37 Grinding machine(7”) 1
13 Wheeled loader 5 38 Welding machine(single/3-phase)
9
14 Tractor 10 39 Ply cutter machine (8”/7”) 1
15 Light vehicle 6 40 Prism with tripod set 5
16 Motor bike 7 41 Leveling staff (5m) 4
17 Concrete mixer(including lab) 10 42 Total station (Topcon GM-105) with tripod set
3
18 Grouting pump 6 43 Auto level with tripod set 3
19 Concrete pump 2 44 Shot Crete machine PZ5 6
20 Jackhammer 48 45 Compressive strength test machine
1
21 Blower fan set 6 43 Lubricator 43
22 Pull out test machine 1 47 Diesel Tank 16000Ltr 3
23 Shotcrete Robot (Jacon) 1 48 Muck loader on wheel base 2
24 Shotcrete Robot (Cifa) 1 49 Transit mixer 4
25 Concrete Batching Plant 1
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
5 Sanima Hydro and Engineering Pvt. Ltd.
Construction materials stored by Civil Contractor at site:
Table 6: Construction material stored by Civil contractor
Materials Unit Balance Qty
Diesel Litres 4,868.92
Rebar (25mm) Kg 10,912.5
Rebar (20mm) Kg 32,959.13
Rebar (16mm) Kg 6,473.19
Rebar (12mm) Kg 28,299.5
Rebar (10mm) Kg 0
Cement Bags 1,125
Micro silica Kg 1,099
Steel Fiber Kg 0
Accelerator liquid Kg 2,280
Pneumatic Oil Litres 1,014
Plasticizer Kg 66.94
Rock bolt 20mm*2m Nos. 0
Rock bolt 20mm*3m Nos. 0
Rock bolt 25mm*4m Nos. 307
Steel rib Set 7
Sank rod 5’ Nos. 4
Sank rod 6’ Nos. 11
Sank rod 8’ Nos. 58
Sank rod 10’ Nos. 14
Sank rod 12’ Nos. 7
Sank rod 15’ Nos. 15
Wire mesh 100*100*4mm Roll 8
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
6 Sanima Hydro and Engineering Pvt. Ltd.
6. CIVIL CONSTRUCTION WORK PROGRESS
6. 1 HEADWORKS
Total 7 number of upstream floodwall panels and 13 number of downstream floodwall
panels have been completed. Final lift concreting is remaining in upstream floodwall
panel 2 and 5 (2m height) and downstream floodwall panel 1 and 2 (1m height).
Construction of undersluice has been completed up to level of 738.8m.
Construction of divide wall panel 1 and 2 has been completed.
Construction of divide wall panel 3 has been completed up to level of 735m.
Backfilling behind the floodwalls has been going on.
Hard stone lining in upstream apron panel 1 and 2 of undersluice has been going on.
Concreting at panel no 1 of gravel flushing has been completed.
Concreting at base of intake has been completed up to the level of 735.00 m.
The base slab of Sediment flushing panel no 10 has been completed.
Excavation for settling basin has been ongoing. Construction of stone masonry wall has
been started from riverside.
Construction of upstream cutoff wall 1 and downstream cutoff wall 1 and 2: Panel 1 and
2 completed.
Construction of stilling basin panel no. 1 and 2 completed.
Construction of weir panel no.1 upto level 734m completed.
Construction of Apron panel no. 1 and 2 completed.
Construction of Gravel flushing panel no.1 completed.
Table 7: Progress summary of Headworks
S.N Description Units Till
August, 2019
August,2019 September,2019 Total
Quantity
1. C15 concrete m3 274.789 82.171 3.5 278.289
2. C25 concrete m3 7179.24 1066.8 305.69 7484.93
3. Re-bar ton 550 86 17.237 567.237
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
7 Sanima Hydro and Engineering Pvt. Ltd.
Figure 1: Construction activities in intake and undersluice
Figure 2: Divide wall panel 1 and 2
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
8 Sanima Hydro and Engineering Pvt. Ltd.
Figure 3: Hard stone lining at undersluice apron
Figure 4: Settling basin and Sediment Flushing area
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
9 Sanima Hydro and Engineering Pvt. Ltd.
6.2 TUNNEL
6.2.1.HRT INLET PORTAL
The total excavated length from Face 1 (Main inlet portal) is 257.80 m. The geology of the tunnel comprises of thinly foliated, dark grey to bluish grey colour, slightly weathered to fresh, undulated phyllite with partings and subordinates of quartzite and Meta-sandstones. Clay coatings are present along discontinuities. The class of rock is support type V.
Figure 5: Tunnel from Face-01 (Main inlet portal)
Progress Analysis of Main Inlet Tunnel
0
10
20
30
40
50
60
Pro
gre
ss in m
ete
r
Progress in month
Main inlet (Face 1)Monthly progress (m)
Target
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
10 Sanima Hydro and Engineering Pvt. Ltd.
6.2.2.SETI OUTLET PORTAL
The total excavation from Face 2 (Seti outlet portal) is 409.00m. The geology of the tunnel comprises of thinly foliated, grey to greyish black colour, slightly weathered to fresh phyllite with partings of quartzite and Meta-sandstones. Lenses of quartzite are present, and clay coatings along discontinu-ities. The class of rock is support type V.
Figure 6: Tunnel from Face-02 (Seti Outlet portal)
Progress Analysis of Seti Outlet Tunnel
0
10
20
30
40
50
60
70
Pro
gre
ss in p
erc
enta
ge
Progress in month
Seti outlet (Face 2)Monthly progress (m)
Target
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
11 Sanima Hydro and Engineering Pvt. Ltd.
6.2.3. SETI INLET PORTAL
The total excavation from Face 3 (Seti Inlet Portal) is 546.00 m. The geology of the tunnel comprises of thinly to thickly foliated phyllite with inter-beds of thick bedded light to yellowish grey quartzite and grey to bluish grey, Meta-sandstone. The rock is fresh to moderately weathered with clay coatings along discontinuities. The class of rock is support type III.
Figure 7: Tunnel from Face-03 (Seti inlet portal)
Progress Analysis of Seti Inlet Tunnel
0
10
20
30
40
50
60
70
80
90
100
Pro
gre
ss in m
ete
r
Progress in month
Seti inlet (Face 3)
Monthly progress (m)
Target
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
12 Sanima Hydro and Engineering Pvt. Ltd.
6.2.4. POKU OUTLET PORTAL
The total excavation from Face 4 (Poku Outlet Portal) is 428.80m. The geology of the tunnel com-prises interbeds of thickly foliated medium grain Metasandstone with thinly foliated bluish grey phyl-lite. The rock is fresh to slightly weathered, bluish grey colour with clay coatings along discontinuities. The class of rock is support type III.
Figure 8: Tunnel from Face-04 (Poku outlet portal)
Progress Analysis of Poku Outlet Tunnel
0
10
20
30
40
50
60
70
80
90
100
Pro
gre
ss in m
ete
r
Progress in month
Poku outlet (Face 4)
Monthly progress (m)
Target
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
13 Sanima Hydro and Engineering Pvt. Ltd.
6.2.5. POKU INLET PORTAL
Total excavation from Face 5 (Poku inlet Portal) is 550.80m. The general geology of the tunnel com-prises of thickly to thinly foliated, fresh to slightly weathered light grey meta-sandstone with partings and interbeds of phyllite with clay coating along discontinuities. The class of rock is support type III.
Figure 9: Tunnel from Face-05 (Poku inlet portal)
Progress Analysis of Poku Inlet Tunnel
0
20
40
60
80
100
120
Pro
gre
ss in m
ete
r
Progress in month
Poku inlet (Face 5)Monthly progress (m)
Target
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
14 Sanima Hydro and Engineering Pvt. Ltd.
6.2.6. HRT OUTLET PORTAL
Total excavation from Face 6 (Main outlet portal) is 476.80m. The general geology of the tunnel comprises of thin to thick foliations of greenish grey Meta-sandstone with partings and inter-beddings of greenish grey phyllite, and clay coatings along discontinuities. The class of rock is support type V.
Figure 10: Tunnel from Face-06 (Main outlet portal)
Progress Analysis of Main Outlet Tunnel
0
10
20
30
40
50
60
70
80
Pro
gre
ss in m
ete
r
Progress in month
Poku outlet (Face 6)
Monthly progress (m)
Target
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
15 Sanima Hydro and Engineering Pvt. Ltd.
Table 8: Overall Tunnel Excavation Progress
Face Length of tunnel (m)
Progress (m) Total (%)
Remarks Till Au-gust,2019 August,2019 September,2019 Total
Inlet portal 911.50 222.70 34.4 35.10 257.80 28.283
Seti outlet 911.50 385.60 53.9 23.40 409.00 44.871
Seti inlet 609.50 497.60 89.7 48.40 546.00 89.582
Poku outlet 609.50 377.20 67.9 51.60 428.80 70.353
Poku inlet 878.00 494.90 97.3 55.90 550.80 62.733
Outlet por-tal 877.00 426.10 59.8 50.70 476.80 54.367
Total 4797.000 2404.100 403 265.10 2669.20 55.643
0.00
100.00
200.00
300.00
400.00
500.00
600.00
700.00
800.00
900.00
1000.00
Inlet portal Seti outlet Seti inlet Poku outlet Poku inlet Outlet portal
Length of tunnel(m)
Progress(m)
Tun
ne
l Le
ngt
hin
m
ete
r
Progress Detail of Tunnel
Faces
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
16 Sanima Hydro and Engineering Pvt. Ltd.
6.3. SURGE SHAFT AND CONNECTING TUNNEL
Full diameter excavation of surge shaft was started on June 2019. Protection of hill slope has been
completed with 75mm thick plain shotcrete with wire mesh. The excavation of connecting tunnel has
been completed up to 0+035.0m chainage, in which the outer diameter of the surge shaft is
encountered at 0+024.3m. Gantry has been installed at the surge shaft for further excavation and
mucking purpose.
6.4. PENSTOCK
The excavation for penstock has been going on below the access road as the first stage of
excavation. The excavation for Anchor block VB-02 has been completed and the penstock
alignment below the anchor block up to the existing irrigation canal has been completed. 5mm
thick fiber reinforced shotcrete has been installed at this portion for slope protection. The per-
manent diversion of the irrigation canal has been completed with installation of MS pipes with
concrete casing.
Figure 11: Surge shaft with gantry
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
17 Sanima Hydro and Engineering Pvt. Ltd.
Figure 12: Slope protection at penstock alignment
Figure 13: Rebar laying for concrete casing around irrigation pipe across penstock alignment
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
18 Sanima Hydro and Engineering Pvt. Ltd.
6.5. POWERHOUSE
Top soil removal has been completed at the Powerhouse excavation area.
6.6. TAILRACE
Construction of tailrace culvert panel 4, 7, 8, 9 and 10 has been complete.
Construction of panel 3 and 6 is completed up to 1.3m from base.
Table 9: Detail of concrete quantity at tailrace
Figure 14: View of tailrace culvert panel 03 before concreting
Description
Concrete(m3) Rebar(ton) Remarks
Till August September Total
Till August September Total
Tailrace culvert panel no. 3,4,6,7,8, 9 and 10
488.5 301.5 790 56 34 90
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
19 Sanima Hydro and Engineering Pvt. Ltd.
Figure 15: Tailrace culvert panel 3
7. HYDRO-MECHANICAL WORKS PROGRESS
Top seal beam of undersluice stop-log have been installed at both bays and installation of
side seal beam has been completed up to 6m height at both bays.
The top seal beam of radial gate has been installed and installation of side seal beam has
been completed up to 6m height at both bays.
Installation of gravel flushing pipe has been completed to 48.5% (42.015m out of 86.64).
Installation of gravel flushing transition has commenced.
About 65% of steel lining has been completed in undersluice wall.
Irrigation canal pipe at penstock alignment (39 m length) has been installed and handed
over.
Undersluice stop-log frame has been erected.
Steel lining at undersluice has been completed at both bays.
Steel lining has been completed at intake front wall.
Settling basin flushing outlet gate has been erected at four bays up to top seal beam.
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
20 Sanima Hydro and Engineering Pvt. Ltd.
Figure 16: Rolled MS pipes at HM yard
Figure 17: Installation of gravel flushing bellmouth
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
21 Sanima Hydro and Engineering Pvt. Ltd.
8. CONSTRUCTION POWER WORKS
Over voltage and under voltage protection scheme has been installed at the distribution
transformer of Headworks.
6/8 MVA transformer has been procured by NEA for installation at Manthali sub-station.
Maintenance of 33 kV transmission line (Line stringing, bush cutting) from Manthali sub-
station to proposed Sangutar sub-station has been ongoing in coordination with NEA.
1:6 c/s (Cement/Sand) Stone masonry foundation drawing has been issued for construc-
tion for installation of transformers at Seti, Poku and Powerhouse area.
Figure 18: Over and under voltage protection scheme
9. POWERHOUSE CAMP
Gabion works below Block A have been completed.
Construction of Powerhouse camp block F has been completed with finishing works re-
maining.
The main gate pillars have been constructed and fence posts have been installed around
the camp area.
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
22 Sanima Hydro and Engineering Pvt. Ltd.
Figure 19: Powerhouse staff quarter (Type: Block F)
Figure 20: View of Powerhouse Camp
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
23 Sanima Hydro and Engineering Pvt. Ltd.
Figure 21: Recreational house at powerhouse camp
10. SOCIAL AND PUBLIC
Several parts of the road at Ratmata bazaar were repaired by the means of drain cutting,
muck filling and grading.
The road to the school at Ratmata has been upgraded with stone masonry steps.
Several coordination meetings have been conducted with the respective community for
support and feedback.
Drinking water supply pipes have been provided to the residents of Poku area.
Land procurement has been made near the confluence of Pokali and Likhu River.
Compensation has been provided for eroded cultivation area at left bank of Likhu River
upstream of Headworks.
The public road at Poku area has been made serviceable by using excavator and backhoe
loader during several times.
Maintenance has been done at several locations of the irrigation canal at Ratmata, Seti
and Poku.
Stone masonry wall has been constructed at the boundary of Arunodaya School for erosion
control.
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
24 Sanima Hydro and Engineering Pvt. Ltd.
11. ENVIRONMENT, HEALTH AND SAFETY
Safety meeting was organized in Contractor’s office on 14th September and safety issues
were discussed.
Safety orientation was provided to the workers of main inlet tunnel on 15th September.
Weekly safety meeting was held with 3H-BC JV at contractors meeting hall on 21st Sep-
tember.
Tunnel safety training was provided to tunnel workers by COWI representative Mr. Szymon
Kowalczuk at 3H-BC JV meeting hall on 24th September.
Safety signage were displayed at Surge shaft area on 22nd September.
Electrical panel board at Powerhouse was secured with wire net fence on 9th September.
Sign boards for emergency assembly point were displayed on 21st September.
Traffic sign boards were displayed at required portions of the access road on 21st Septem-
ber.
Traffic sign boards were displayed at Sirise Bazaar on 20th September.
Figure 22: Restrictive signage at tunnel face
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
25 Sanima Hydro and Engineering Pvt. Ltd.
Figure 23: Emergency assembly point at Seti
12. EQUIPMENT BREAKDOWN
Propeller shaft of backhoe loader (JCB) of seti was broken down from September 10 and
it was repaired on September 12.
The wheel loader (DOOSAN SD200) of Seti was in breakdown condition due to severe
damage in engine parts from 5th September. It was repaired on 8th September and mobi-
lised again.
13. VISITORS OF THE MONTH
Senior geology consultant Mr. Subash Sunuwar visited site on 11th September.
A group of trainers from COWI and DIF visited the site on 23rd September for providing
training to the tunnel crew.
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
26 Sanima Hydro and Engineering Pvt. Ltd.
Figure 24: LLHP and SHEPL team with Geology consultant Mr. Subash Sunuwar
Figure 25: LLHP team with members from COWI and DIF
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
27 Sanima Hydro and Engineering Pvt. Ltd.
14. PHOTOS
Figure 26: Installation of gravel flushing pipe (Left) and Outlet of gravel flushing (Right)
Figure 28: Masonry at settling basin (left) gravel flushing stop-log installation (right)
Figure 27: Calibration of aggregate for concreting at site (left) and newly unloaded rebar (right)
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
28 Sanima Hydro and Engineering Pvt. Ltd.
Figure 29: Hard stone cutting at Headworks (left) and storage (right)
Figure 30: Headworks construction
Figure 31: Crusher at Headworks (left) and material stock (right)
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
29 Sanima Hydro and Engineering Pvt. Ltd.
Figure 32: Irrigation canal across Penstock alignment (left) and concrete casing (right)
Figure 33: Main inlet tunnel (Left) and Safety meeting (Right)
Figure 34: Traffic signage at Sirise bazaar
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
30 Sanima Hydro and Engineering Pvt. Ltd.
Figure 35: Safety signage at access road (left) and speed limit sign (right)
Figure 36: Wire net fence for electrical panel board at Powerhouse (left) and LOTO for safety (right)
Figure 37: Fence posts around Powerhouse staff quarter (left) and chain link fencing (right)
Swet Ganga Hydropower & Construction Limited Lower Likhu Hydropower Project (28.1 MW) Monthly Progress Report, September, 2019
31 Sanima Hydro and Engineering Pvt. Ltd.
Figure 38: Tailrace culvert panel 6 to 10 (left) and safety signs at surge shaft area (right)
Figure 39: Plate rolling machine at HM yard (Left) and shotcrete at penstock slope area (right)
15. PROGRESS CHART
32.0%
13.0%1.0% 1.0%
PER
CEN
TAG
E O
F W
OR
K
OVERALL PROGRESS OF PROJECT
Percentage of work