menkon tugas rab.docx
TRANSCRIPT
![Page 1: MENKON TUGAS RAB.docx](https://reader036.vdocuments.pub/reader036/viewer/2022082411/5695d4461a28ab9b02a0e0cf/html5/thumbnails/1.jpg)
TUGAS MENEJEMEN KONSTRUKSI
RAB DAN PENJADWALAN
Ati Muliawati 41213010075
Ayyash Syifa Aradia 41213010076
Yeni Lidiawati 41213010083
Zahra Zulfa Firdausy 41213010074
PRODI TEKNIK ARSITEKTURFAKULTAS TEKNIK
UNIVERSITAS MERCU BUANA
![Page 2: MENKON TUGAS RAB.docx](https://reader036.vdocuments.pub/reader036/viewer/2022082411/5695d4461a28ab9b02a0e0cf/html5/thumbnails/2.jpg)
TUGAS MANAJEMEN KONSTRUKSI
DAFTAR ISI
1. Data Bangunan
2. Gambar Rencana .............................................................................................................
3. Rencana Anggaran Satuan Pekerjaan...........................................................................
4. Data Perhitungan Volume Pekerjaan
5. Perhitungan Rencana Anggaran Biaya
6. Dafar Pustaka
![Page 3: MENKON TUGAS RAB.docx](https://reader036.vdocuments.pub/reader036/viewer/2022082411/5695d4461a28ab9b02a0e0cf/html5/thumbnails/3.jpg)
TUGAS MANAJEMEN KONSTRUKSI
DATA BANGUNAN
Nama Proyek : Rumah Tinggal
Wilayah : Jakarta
Alamat : Jln. Gading Indah 5 Blok NF II No. 36 Kelapa Gading Jakarta Utara
Jumlah Lantai : 2 Lantai
Luas Bangunan :
Luas Lahan :
![Page 4: MENKON TUGAS RAB.docx](https://reader036.vdocuments.pub/reader036/viewer/2022082411/5695d4461a28ab9b02a0e0cf/html5/thumbnails/4.jpg)
TUGAS MANAJEMEN KONSTRUKSI
GAMBAR RENCANA
Gambar Denah
Gambar Tampak
Gambar Potongan
Sketsa
![Page 5: MENKON TUGAS RAB.docx](https://reader036.vdocuments.pub/reader036/viewer/2022082411/5695d4461a28ab9b02a0e0cf/html5/thumbnails/5.jpg)
TUGAS MANAJEMEN KONSTRUKSI
RENCANA ANGGARAN SATUAN PEKERJAAN
DAFTAR HARGA SATUAN PEKERJAAN (HSP)TAHUN ANGGARAN 2015
PROVINSI WILAYAH :KABUPATENNO. URAIAN PEKERJAAN SATUAN HARGA SATUAN
(RP.)
ANALISA BIAYA KONSTRUKSI PEKERJAAN PERSIAPAN1 PENGUKURAN KEMBALI DAN PEMASANGAN 1 M'
BOUWPLANKM' RP. 945.000
2 PEMBONGKARAN BANGUNAN LAMA DAN PERBERSIHAN 1 M² LAPANGAN
M² RP. 3.000.000
ANALISA BIAYA KONSTRUKSI PEKERJAAN TANAH1 MENGGALI 1 M³ TANAH BIASA SEDALAM 1 METER M³ RP. 56.5002 PENGURUGAN KEMBALI 1 M³ GALIAN TANAH M² RP. 87.5003 PENGURUGAN 1 M³ DENGAN PASIR URUG M³ RP 250.0004 PENGURUGAN 1 M³ SIRTU PADAT M³ RP. 200.000
ANALISA BIAYA KONSTRUKSI PEKERJAAN PONDASI1 PEMASANGAN 1 M³ PONDASI BATU BELAH 1Sp : 3Pp M³ RP. 750.0002 PEMASANGAN 1 M³ PONDASI BATU BELAH 1Sp : 4Pp M³ RP. 700.0003 PEMASANGAN 1 M³ PONDASI BATU BELAH 1Sp : 5Pp M³ RP. 670.0004 PEMASANGAN 1 M³ PONDASI BATU BELAH 1Sp : 6Pp M³ RP. 660.0005 PEMASANGAN 1 M³ PONDASI BATU BELAH 1Sp : 8Pp M³ RP. 630.0006 PEMASANGAN 1 M³ BATU KOSONG (AANSTAMPING) M³ RP. 330.000
ANALISA BIAYA KONSTRUKSI PEKERJAAN BETON1 MEMBUAT 1 M³ PONDASI BETON BERTULANG (150 Kg
BESI + BEKISTING ) M³ RP. 3.800.000
2 MEMBUAT 1 M³ SLOOF BETON BERTULANG (200 Kg BESI + BEKISTING )
M³ RP. 3.500.000
3 MEMBUAT 1 M³ KOLOM BETON BERTULANG (300 Kg BESI + BEKISTING )
M³ RP 3.750.000
4 MEMBUAT 1 M³ BALOK BETON BERTULANG (200 Kg BESI + BEKISTING )
M³ RP 3.750.000
5 MEMBUAT 1 M³ KOLOM BETON BERTULANG (150 Kg BESI + BEKISTING )
M³ RP 3.750.000
6 MEMBUAT 1 M³ DINDING BETON BERTULANG (150 Kg BESI + BEKISTING )
M³ RP 3.750.000
7 MEMBUAT 1 M³ DINDING BETON BERTULANG (200 Kg BESI + BEKISTING )
M³ RP. 4.000.000
8 MEMBUAT 1 M' KOLOM PRAKTIS BETON BERTULANG (11 x 11) Cm
M' RP 2.750.000
![Page 6: MENKON TUGAS RAB.docx](https://reader036.vdocuments.pub/reader036/viewer/2022082411/5695d4461a28ab9b02a0e0cf/html5/thumbnails/6.jpg)
TUGAS MANAJEMEN KONSTRUKSI
9 MEMBUAT 1 M' RING BALOK BETON BERTULANG (10 x 15) Cm
M' RP 3.500.000
ANALISA BIAYA KONSTRUKSI PEKERJAAN DINDING1 PEMASANGAN 1 M² DINDING BATA MERAH UKURAN
(5X11X22) cm TEBAL 1 BATU, M² RP 125.000
2 CAMPURAN SPESI 1 SP : 2 PP
ANALISA KONSTRUKSI PEKERJAAN PLESTERAN1 PEMASANGAN 1 M² PLESTERAN 1 SP : 1 PP, TEBAL 15
mm M² RP 25.000
2 PEMASANGAN 1 M² PLESTERAN 1 SP : 2 PP, TEBAL 15 mm
M² RP 22.500
3 PEMASANGAN 1 M² ACIAN M² RP. 20.0004 PEMASANGAN 1 M² WATER PROOFING COATING M² RP. 90.0005 PEMASANGAN 1 M² PLESTERAN + ACIAN PAKAI
DRYMIX PM 200 + PM 200 M² RP. 100.000
ANALISA MEKANIKAL ELEKTRIKAL1 PEMASANGAN 1 BUAH STOP KONTAK STANDAR Bh Rp. 27.5002 PEMASANGAN 1 BUAH SAKLAR TUNGGAL Bh Rp. 27.5003 PEMASANGAN 1 BUAH SAKLAR GANDA Bh Rp. 27.5004 PEMASANGAN 1 BUAH LAMPU TL 1x40 WATT LENGKAP
BOX Bh Rp. 75.000
5 PEMASANGAN 1 BUAH LAMPU TL 1x20 WATT LENGKAP BOX
Bh Rp. 75.000
ANALISA KONSTRUKSI PEKERJAAN PENGECATAN1 PENGECATAN 1 M² TEMBOK BARU (1 LPS PLAMIR , 1
LPS CAT DASAR, 2 LAPIS CAT PENUTUP) M² Rp. 22.500
DI BUAT TANGGALCATATANBobot Isi Pasir = 1.400 kg/m3Bobot Isi Kerikil = 1.350 kg/m3Bobot Isi Batu Granit = 2.800 kg/m3 (Sumber : Ir. Sunggono KH.Buku Teknik Sipil. Penerbit Nova. 1995. Bandung.)Bobot Isi Semen Portland 1 Zak = 50 Kg.
![Page 7: MENKON TUGAS RAB.docx](https://reader036.vdocuments.pub/reader036/viewer/2022082411/5695d4461a28ab9b02a0e0cf/html5/thumbnails/7.jpg)
TUGAS MANAJEMEN KONSTRUKSI
DATA PERHITUNGAN VOLUME PEKERJAAN
I. PEKERJAAN PERSIAPAN
1 Pekerjaan Pembersihan Lokasi Site
Panjang X Lebar
12 11 132
132 M2
2 Pek. Pasang Bouwplank
Panjang X Unit
12 12 144
144 M'
3 Luas Bangunan (IMB)
Panjang X Lebar X Unit
12 11 1 132
132 M2
II. PEKERJAAN GALIAN TANAH & URUGAN PASIR
1 Pekerjaan Galian Tanah Pondasi Foot Plate
Panjang X Lebar X Dalam
8 0,7 0,6 37,44
37,44 M3
2 Pekerjaan Galian Septictank dan Tandon Air
Panjang X Lebar X Dalam
6
6 M3
3 Pekerjaan Galian Got, Saluran Depan
Panjang X Lebar X Tebal
6
6 M3
4 Pekerjaan Galian Saluran Air Hujan
Panjang
42
![Page 8: MENKON TUGAS RAB.docx](https://reader036.vdocuments.pub/reader036/viewer/2022082411/5695d4461a28ab9b02a0e0cf/html5/thumbnails/8.jpg)
TUGAS MANAJEMEN KONSTRUKSI
42 M'
5 Pekerjaan Tanah Urugan + Puing Bangunan
Panjang X Lebar
90
90 M3
6 Pekerjaan Pasir Urugan Bawah Lantai & Pondasi
Panjang X Lebar X Tebal
12,6
12,60 M3
III. PEKERJAAN PONDASI & STRUKTUR DASAR
1 Pekerjaan Pondasi Rollag Bata
Panjang X Lebar X Tebal
79 M3
2 Pekerjaan Pondasi Foot Plate Beton Bertulang
Panjang X Penampang Pondasi X Tinggi
3,25 M3
IV
.
PEKERJAAN BETON
1 Pekerjaan Sloof Beton Uk. 15x20 cm
Tinggi X Panjang X Lebar X Unit
0,53
0,53 M3
2 Pekerjaan Sloof Beton Uk. 20x30 cm
Tinggi X Panjang X Lebar X Unit
4,05
4,05 M3
3 Pekerjaan Kolom Praktis Uk. 15x15 cm
Tinggi X Panjang X Lebar X Unit
1,02
1,02 M3
4 Pekerjaan Kolom Utama Uk. 15x40 cm
![Page 9: MENKON TUGAS RAB.docx](https://reader036.vdocuments.pub/reader036/viewer/2022082411/5695d4461a28ab9b02a0e0cf/html5/thumbnails/9.jpg)
TUGAS MANAJEMEN KONSTRUKSI
Tinggi X Panjang X Lebar X Unit
4,29
4,29 M3
5 Pekerjaan Ring Balk 15x20 cm
Tinggi X Panjang X Lebar X Unit
2
2 M3
6 Pekerjaan Balok Beton Uk. 20x50 cm
Tinggi X Panjang X Lebar X Unit
7,05
7,05 M3
7 Pekerjaan Balok Anak Uk. 20x30 cm
Tinggi X Panjang X Lebar X Unit
3,52
3,52 M3
8 Pekerjaan Balok Sofi-sofi Uk. 15x20 cm
Tinggi X Panjang X Lebar X Unit
0,56
0,56 M3
9 Pekerjaan Dak Beton t. 12 cm
Tinggi X Panjang X Lebar X Unit
8,46
8,46 M3
V. PEKERJAAN DINDING1. Pekerjaan Pemasangan dinding bata
Panjang X Lebar X Unit1 439,5
439,5 M3
VI. PEKERJAAN ATAP
1 Pekerjaan Balok listplank 3 x 12 cm dan Nok Genteng Kan Murni
Panjang X Lebar
18
18 M2
2 Pekerjaan Genteng Kan Murni Hitam tanpa Alumunium Voil
![Page 10: MENKON TUGAS RAB.docx](https://reader036.vdocuments.pub/reader036/viewer/2022082411/5695d4461a28ab9b02a0e0cf/html5/thumbnails/10.jpg)
TUGAS MANAJEMEN KONSTRUKSI
Panjang X Lebar
116
116 M2
3 Pekerjaan Rangka Atap Baja Ringan
Panjang X Lebar
116
116 M2
VII. PEKERJAAN LANTAI
1 Urugan pasir bawah lantai t=10 cm
Panjang X Lebar X Unit
1 132
132 M2
2 Pekerjaan Lantai kerja t = 5 cm
Panjang X Lebar X Unit
1 132
132 M2
3 PekerjaanBeton Rabat t=10cm + Wiremesh M8
Panjang X Lebar X Unit
1 132
132 M2
VIII. PEKERJAAN FINISHING & PENGECATAN
1 Pekerjaan Pengecatan dinding
Panjang X Lebar X Unit
721
721 M2
2 Pekerjaan plester beton rabat
Panjang X Lebar X Unit
1 132
132 M2
![Page 11: MENKON TUGAS RAB.docx](https://reader036.vdocuments.pub/reader036/viewer/2022082411/5695d4461a28ab9b02a0e0cf/html5/thumbnails/11.jpg)
TUGAS MANAJEMEN KONSTRUKSI
PERHITUNGAN RENCANA ANGGARAN BIAYA
I. PEKERJAAN PERSIAPAN
1.1 Akomodasi & Transportasi : 8 Bln x Rp 625.000,- = Rp. 5.000.000,-
1.2 Keamanan Lingkungan : 8 Bln x Rp 250.000,- = Rp. 2.000.000,-
1.3 Bongkar Bangunan Lama : 1 LS x Rp 3.000.000,- = Rp. 3.000.000,-
1.4 Listrik Kerja & Air Kerja : 8 Bln x Rp 250.000,- = Rp. 2.000.000,-
1.5 Papan Bowplank &
Benangan
: 42 M' x Rp 22.500,- = Rp. 945.000,-
Total Keseluruhan Rp. 12. 945.000,-
II. PEKERJAAN GALIAN TANAH & URUGAN
2.1 Galian Tanah Pondasi Foot
Plate
: 37,44 M3 x RP
56.500,-
= Rp. 2.115.360,-
2.2 Galian Septictank dan
Tandon Air
: 6,00 M3 x RP 56.500,- = Rp. 339.600,-
2.3 Galian Got, Saluran Depan : 6 M3 x RP 22.500,- = Rp. 135.000,-
2.4 Galian Saluran Air Hujan : 42 M' x RP 22.500,- = Rp. 945.000,-
2.5 Tanah Urugan + Puing
Bangunan ± 100 cm
: 90 M3 x RP 87.500,- = Rp. 7.875.000,-
2.6 Pasir Urugan Bawah Lantai
& Pondasi
: 12,60 M3 x RP
250.000,-
= Rp. 3.150.000,-
Total Keseluruhan Rp. 14.559.960,-
III. PEKERJAAN PONDASI BATU KALI
3.1 Pondasi Batu Kali - -
3.2 Pondasi Rollag Bata : 79 M' x RP 125.000,- = Rp. 9.875.000,-
3.3 Pondasi Foot Plate Beton
Bertulang
: 3,25 M3 x RP
3.500.000,-
= Rp. 11.375.000,-
Total Keseluruhan Rp. 21.250.000,-
![Page 12: MENKON TUGAS RAB.docx](https://reader036.vdocuments.pub/reader036/viewer/2022082411/5695d4461a28ab9b02a0e0cf/html5/thumbnails/12.jpg)
TUGAS MANAJEMEN KONSTRUKSI
IV. PEKERJAAN BETON BERTULANG
4.1 Sloof Beton Uk. 15x20 cm : 0,53 M3 x RP
2.750.000,-
= Rp. 1.475.000,-
4.2 Sloof Beton Uk. 20x30 cm : 4,05 M3 x RP
3.500.000,-
= Rp. 14.175.000,-
4.3 Kolom Praktis Uk. 15x15
cm
: 1,02 M3 x RP
2.750.000,-
= Rp. 2.805.000,-
4.4 Kolom Utama Uk. 15x40
cm
: 4,29 M3 x RP
3.750.000,-
= Rp. 16.087.500,-
4.5 Ring Balk 15x20 cm : 2,00 M3 x RP
3.500.000,-
= Rp. 7.000.000,-
4.6 Balok Beton Uk. 20x50 cm : 7,05 M3 x RP
3.750.000,-
= Rp. 26.437.500,-
4.7 Balok Anak Uk. 20x30 cm : 3,52 M3 x RP
3.750.000,-
= Rp. 13.200.000,-
4.8 Balok Sofi-sofi Uk. 15x20
cm
: 0,59 M3 x RP
3.750.000,-
= Rp. 2.212.000,-
4.9 Dak Beton t. 12 cm : 8,46 M3 x RP
3.750.000,-
= Rp. 31.725.000,-
Total Keseluruhan Rp. 115.099.500,-
V. PEKERJAAN DINDING BATA & ACIAN
5.1 Dinding Bata Heubel : 439,50 M2 x RP
115.000,-
= Rp. 50.542.000,-
5.2 Dinding Bata, Pagar Depan : 6,00 M2 x RP
125.000,-
= Rp. 750.000,-
5.3 Dinding Bata Heubel untuk
Sofi-sofi
: 21,0 M2 x RP
125.000,-
= Rp. 2.625.000,-
5.4 Plesteran & Acian : 879 M2 x RP 22.500,- = Rp. 19.777.500,-
Total Keseluruhan Rp. 73.695.000,-
![Page 13: MENKON TUGAS RAB.docx](https://reader036.vdocuments.pub/reader036/viewer/2022082411/5695d4461a28ab9b02a0e0cf/html5/thumbnails/13.jpg)
TUGAS MANAJEMEN KONSTRUKSI
VI. PEKERJAAN KUSEN PINTU & JENDELA
6.1 Kusen Pintu Alumunium
Silver 2"x5"
: 11,0 BH x RP
375.000,-
= Rp. 4.125.000,-
6.2 Kusen Jendela Alumunium
Silver 2"x5"
: 8,0 BH x RP 475.000,- = Rp. 3.800.000,-
6.3 Daun Pintu Panel Kayu
Kamper
: 3,0 BH x RP 750.000,- = Rp. 2.250.000,-
6.4 Daun Pintu Triplex 9mm
Lapis HVL
: 8 BH x RP 475.000,- = Rp. 3.800.000,-
6.5 Daun Pintu Kaca Rangka
Alumunium
- -
6.6 Daun Jendela Rangka
Alumunium
: 15 BH x RP 350.000,- = Rp. 5.250.000,-
6.7 Jendela Ventilasi: Kaca, Uk.
30x40 cm
: 12 BH x RP 250.000,- = Rp. 3.000.000,-
6.8 Kawat Nyamuk, Lobang
Angin Uk. 20x30 cm
: 26 BH x RP 27.500,- = Rp. 715.000,-
Total Keseluruhan Rp. 22.940.000,-
VII. PEKERJAAN ATAP & PENUTUP ATAP
7.1 Nok Genteng Kan Murni :18 M1 x Rp. 75.500,- = Rp. 1.359.000,-
7.2 Genteng Kan Murni Hitam
tanpa Alumunium Voil
:116 M2 x Rp. 175.000 = Rp. 20.300.000,-
7.3 List Plang Uk. 3x12 cm
GRC L= 30 cm
:18 M1 x Rp. 27.500 = Rp. 495.000,-
7.4 Talang Atap, Miring, Papan
& Seng
:9 M1 x Rp. 47.500 = Rp. 427.500,-
7.5 Rangka Atap Baja Ringan :116 M2 x Rp. 125.000 = Rp. 14.500.000,-
7.6 Nok & Gording Baja Cnp.
150.653,2
- -
Total Keseluruhan Rp. 37.081.500,-
VIII. PEKERJAAN PLAFOND
8.1 Plafond Gypsum 9mm Jaya :132 M2 x Rp. 85.000,- = Rp. 11.220.000,-
![Page 14: MENKON TUGAS RAB.docx](https://reader036.vdocuments.pub/reader036/viewer/2022082411/5695d4461a28ab9b02a0e0cf/html5/thumbnails/14.jpg)
TUGAS MANAJEMEN KONSTRUKSI
Board
8.2 Rangka Plafond Hollow
Galvanize
:132 m2 x Rp. 65.000,- = Rp. 8.580.000,-
8.3 Drop Ceiling :32 M1 x Rp. 42.500,- = Rp. 1.360.000,-
8.4 List Plafond Gypsum Uk.
10x10 cm
:188,75 M1 x Rp.
12.500,-
= Rp. 2.359.000,-
Total Keseluruhan Rp. 23. 519.375,-
IX. PEKERJAAN INSTALASI LISTRIK
9.1 Titik Lampu Down Light
Ex. Osram
:28 BH x Rp. 75.000,- = Rp. 2.100.000,-
9.2 Lampu T.S Pd. Drop Ceiling - -
9.3 Lampu Teras termasuk
Timer Otom
- -
9.4 Lampu Taman Ex. Taiwan - -
9.5 Saklar Tunggal, Broco
Standart
:8 BH x Rp. 27.500,- = Rp. 220.000,-
9.6 Saklar Seri, Broco Standart :4 BH x Rp. 27.500,- = Rp. 110.000,-
9.7 Stop Kontak, Broco :11 BH x Rp. 27.500,- = Rp. 302.000,-
9.8 Stop Kontak Ac, Water
Heater
:4 BH x Rp. 42.500,- = Rp. 170.000,-
9.9 Instalasi Cable Eterna :150 M1 x Rp. 22.500,- = Rp. 3.375.000,-
9.10 Pipa Pembungkus Cable,
Clipsal
:150 M1 x Rp. 17.500,- = Rp. 2.625.000,-
9.11 Mcb. Merin. Gerin 2A & 5A :4 BH x Rp. 32.500,- = Rp. 130.000,-
9.12 Ongkos Pasang Exausvan :2 BH x Rp. 75.000,- = Rp. 150.000,-
Total Keseluruhan Rp. 9.182.000,-
X. DEK. INTSTALASI AIR & SANITASI
10.1 Pipa Sedot ke Sumur PV - -
![Page 15: MENKON TUGAS RAB.docx](https://reader036.vdocuments.pub/reader036/viewer/2022082411/5695d4461a28ab9b02a0e0cf/html5/thumbnails/15.jpg)
TUGAS MANAJEMEN KONSTRUKSI
Ø1,5" & Ø 1" Wavin
10.2 Pompa Air, Semi Getpump :1 BH x Rp. 175.000,- = Rp. 175.000,-
10.3 Tangki Air, Kap. 1.000 L
Penguin
:1 BH x Rp 1.250.000,- = Rp. 1.250.000,-
10.4 Pipa Air Bersih Distribusi Ø
1,5" Wavin
:84 M1 x Rp. 47.500,- = Rp. 3.990.000,-
10.5 Pipa Air Isi ke Tangki Ø
1,5" Wavin
:8 M1 x Rp. 47.500,- = Rp. 380.000,-
10.6 Pipa Air Kran Ø 1/2" Wavin :24,50 M1 x Rp.
22.500,-
= Rp. 551.250,-
10.7 Pipa Air Panas Ø 1/2"
Tembaga
:13 M1 x Rp. 27.500,- = Rp. 357.500,-
10.8 Pipa Air Hujan Ø 4" Wavin :44 M1 x Rp. 67.500,- = Rp. 2.970.000,-
10.9 Pipa Air Kotor Tinja Ø 4"
Wavin
:18,50 M1 x Rp.
67.500,-
= Rp. 1.248.750,-
10.10 Ongkos Pasang Closet :2 BH x Rp. 100.000,- = Rp. 200.000,-
10.11 Ongkos Pasang Westafel :2 BH x Rp. 75.000,- = Rp. 150.000,-
10.12 Ongkos Pasang Aksesoris :6 BH x Rp. 25.000,- = Rp. 150.000,-
10.13 Ongkos Pasang Kran Air :9 BH x Rp. 20.000,- = Rp. 180.000,-
10.14 Ongkos Pasang Water
Heater
:1 BH x Rp. 75.000,- = Rp. 75.000,-
10.15 Radar Otomatis :1 BH x Rp. 75.000,- = Rp. 75.000,-
Total Keseluruhan Rp. 11.752.500,-
XI. PEKERJAAN LANTAI DAN DINDING KERAMIK
![Page 16: MENKON TUGAS RAB.docx](https://reader036.vdocuments.pub/reader036/viewer/2022082411/5695d4461a28ab9b02a0e0cf/html5/thumbnails/16.jpg)
TUGAS MANAJEMEN KONSTRUKSI
11.1 Lantai Keramik Romance
40x40cm
:66 M2 x Rp. 175.000,- = Rp. 11.550.000,-
11.2 Lantai Keramik Romance
60x60cm
:66 M2 x Rp. 225.000,- = Rp. 14.850.000.-
11.3 Lantai Keramik Kia
25x25cm
:6 M2 x Rp. 125.000,- = Rp 750.000,-
11.4 Dinding Keramik Kia
25x40cm
:83,75 M2 x Rp.
125.000,-
= Rp. 10.468.000,-
11.5 Lantai Beton Tumbuk
t.10cm
- -
11.6 Lantai Keramik, Motif Batu
Singkat
:20 M2 x Rp. 175.000,- = Rp. 3.500.000,-
11.7 Dind. Keramik Motif Batu,
Tampak Depan
:10,50 M2 x Rp.
225.000,-
= Rp. 2.362.500,-
11.8 Punt Lantai t=10cm
Romance
:132 M2 x Rp. 22.500,- = Rp. 2.970.000,-
11.9 Keramik Dinding, Motif
Batu Pagar Depan
:9 M2 x Rp. 175.000,- = Rp. 1.575.000,-
11.10 Batu Sisir, Untuk Pilar
Pagar Depan
- -
Total Keseluruhan Rp. 48.026.250,-
XII. PEKERJAAN CAT FINISHING
12.1 Cat Dinding,
Mowilex/Setara
:721 M2 x Rp. 22.500,- = Rp. 16.222.500,-
12.2 Cat Plafond, Moxilex/Setara :132 M2 x Rp. 22.500,- = Rp. 2.970.000,-
12.3 Cat Melamik Daun Pintu
Depan
:2 BH x Rp. 450.000,- = Rp. 900.000,-
12.4 Cat Melamik Daun Jendela
Depan
- -
12.5 Cat Dind. Luarr Water Seal,
Mowilex
:157 M2 x Rp. 28.500,- = Rp. 4.474.500,-
![Page 17: MENKON TUGAS RAB.docx](https://reader036.vdocuments.pub/reader036/viewer/2022082411/5695d4461a28ab9b02a0e0cf/html5/thumbnails/17.jpg)
TUGAS MANAJEMEN KONSTRUKSI
12.6 Cat Minyak List Plang GRC :21 M2 x Rp. 17.500,- = Rp. 367.500,-
12.7 Cat Minyak Pagar Besi
(Pintu Pagar)
:12 M2 x Rp. 28.500,- = Rp. 342.000,-
Total Keseluruhan Rp. 25.276.500,-
XIII. PEKERJAAN LAIN-LAIN
13.1 Septictang 100x200xt
150cm tutup Baton, Dind.
Bata Heubel
:1 BH x Rp. 2.500.000,- = Rp. 2.500.000,-
13.2 Tandon Air Beton,
100x200xt 200cm
:1 BH x Rp. 3.500.000,- = Rp. 3.500.000,-
13.3 Meja Dapur Beton Finish
Keramik
:5,50 MI x Rp. 400.000,- = Rp. 2.200.000,-
13.4 Jembatan Beton, Got Depan
t.15cm
- -
13.5 Pintu Besi, 100x200cm :1 BH x Rp. 750.000,- = Rp. 750.000,-
13.6 Pintu Pagar Besi
uk:200x300cm
:6 M2 x Rp. 350.000,- = Rp. 2.100.000,-
13.7 Pagar Tembok Depan :6 M2 x Rp. 450.000,- = Rp. 2.700.000,-
13.8 Canopy 500x3,50cm (car
port) atap solar tuf
:17,50 M2 x Rp.
450.000,-
= Rp. 7.875.000,-
13.9 Pengurusan Gambar dan
Izin IMB
:Ls M2 x Rp.
35.000.000,-
= Rp. 35.000.000,-
Total Keseluruhan Rp. 56.625.000,-
XIV PEKERJAAN
PEMBERSIHAN
14.1 Pembersihan Keseluruhan :90 M2 x Rp. 10.000,- = Rp. 900.000,-
14.2 Buang Puing Luar Lokasi : - LS x Rp. 1.500.000,- = Rp. 1.500.000,-
Total Keseluruhan Rp. 2.400.000,-
Jumlah I s/d XIV Rp. 474.352.585,-
Jasa Pelaksana 10% Rp. 47.435.285,5,-
Jumlah Keseluruhan Rp. 521.787.843,5,-
![Page 18: MENKON TUGAS RAB.docx](https://reader036.vdocuments.pub/reader036/viewer/2022082411/5695d4461a28ab9b02a0e0cf/html5/thumbnails/18.jpg)
TUGAS MANAJEMEN KONSTRUKSI
Pembulatan Rp. 521.000.000,-
Terbilang ( Lima Ratus Dua Puluh Satu Juta Rupiah )
SYARAT PEMBAYARAN
1. Uang Muka Ke 1 25% Saat SPK Disetujui (blm termasuk IMB)
2. Pembayaran Ke 2 25% Saat Progress Kerja 55%
3. Pembayaran Ke 3 25% Saat Progress Kerja 80%
4. Pembayaran Ke 4 23% Saat Progress Kerja 100%
5. Retensi 2% Selama 60 hari sejak serah terima
WAKTU PELAKSANAAN
180 hari kerja s/d 240 hari kerja
![Page 19: MENKON TUGAS RAB.docx](https://reader036.vdocuments.pub/reader036/viewer/2022082411/5695d4461a28ab9b02a0e0cf/html5/thumbnails/19.jpg)
TUGAS MANAJEMEN KONSTRUKSI
DAFAR PUSTAKA
1. Proyek Rumah Tinggal Kelapa Gading Jakarta Utara, Gambar Rencana dan RAB
Rumah Tinggal
2. Harga Satuan Bangunan Tahun 2015