metode konstruksi (2015)
TRANSCRIPT
![Page 1: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/1.jpg)
METODE
KONSTRUKSI (2015) PROGRAM S1 NON
REGULER
DIKERJAKAN OLEH:
M.
DOSEN PENGAMPU : IR. ARY SETIAWAN, S.T., M.Sc., Ph.D.
JEREMY IWADA S G. I1114047
KURNIAWAN DILIARISTIANTO I1114048
LANARIA PANGESTU I1114049
ZUHDI FADHLI I1114052
![Page 2: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/2.jpg)
PENGERJAAN
PEKERJAAN
RIPPING/CLEARING
DATA LAHAN
PEKERJAAN
PEMUATAN
PEKERJAAN
PENGANGKUTAN
PEKERJAAN
PEMADATAN
1
5
4
3
2
REKAPITULASI
6
![Page 3: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/3.jpg)
DATA LAHAN YANG DIKERJAKAN
Nama Pekerjaan : Lahan Parkir Jurusan
Tek.Sipil, Univ. Sebelelas
Maret, Surakarta.
Lokasi : Surakarta, Jawa
Tengah.
Panjang : 35 m
Lebar : 15 m
Tebal tanah : 1,7 m
Elevasi lahan : + 93 m
![Page 4: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/4.jpg)
Sketsa lahan
DENAH
POT. A-A
Note : Dalam satuan meter
![Page 5: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/5.jpg)
KONDISI AKSES - JALAN
![Page 6: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/6.jpg)
KONDISI
LAHAN
HOME
![Page 7: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/7.jpg)
1.Pekerjaan ripping/clearing
METODE
ALAT YANG DIGUNAKAN
ESTIMASI/ PERHITUNGAN
PRODUKSI ALAT, DURASI DAN
BIAYA
PENJELASAN
![Page 8: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/8.jpg)
PENJELASAN RIPPING Yaitu pemotongan bagian atas permukaan
tanah agar bersih dari rumput maupun tanah yang
kurang baik.
METODE
![Page 9: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/9.jpg)
Alat yang dipergunakan
Wheel Bulldozer
Caterpillar D8U
Akses dan Medan :
Lingkungan universitas
Lebar jalan ± 3m
jarak gusur rerata
60 m
![Page 10: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/10.jpg)
ESTIMASI/PERHITUNGAN
A. PRODUKSI ALAT (CARA GRAFIK) No. Uraian Crawler Wheel
1. Operator: a. baik sekali
b. sedang c. buruk
1.0
0.75 0.60
1.0
0.75 0.60
2. Bahan: a. stock pile
b. sulit dipotong
dengan tilt silinder tanpa tilt silinder
dengan kabel kendali
c. keras dipotong/digusur (kering/non-
kohesif) d. batu hasil ledakan
1.20
0.80
0.70
0.60
0.80 0.60-0.80
1.20
0.75 -
-
0.80 -
3. Dengan metode slot dozing 1.20 1.20 4. Dengan metode berdampingan (side by side
dozing)
1.15-1.25 1.15-1.25
5. Penglihatan pada waktu operasi berdebu, kabut, gelap dan hujan
0.80
0.70
6. Efiseiensi kerja: a. 50 menit/jam b. 40 menit/jam
0.84 0.67
0.84 0.67
7. Direct drive trans. (fixed time 0.01 menit) 0.80 -
8. Bulldozer: a. A blade
b. C blade
c. D5 (sempit)
d. U blade e. Bowl blade
0.50-0.75
0.50-0.75
0.90
1.20 1.30
-
0.50-0.75
-
1.20 1.30
FAKTOR KOREKSI
![Page 11: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/11.jpg)
FAKTOR % KEMIRINGAN : -
2%
FAKTOR KOREKSI
KEMIRINGAN LAHAN : 1.2
![Page 12: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/12.jpg)
Dari grafik
produksi alat
didapat produksi
ideal = 410
m3/jam (LM)
![Page 13: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/13.jpg)
koreksi berat tanah :
Jadi produksi nyata = 410 * 0.80 * 1.2 * 1.20 * 0.75 *
0.84 * 0.856
= 254,713 m3/jam (LM)
Vol. tanah ripping :
Panjang : 35 m
Lebar : 15 m
Tebal tanah max ripping: 0,3 m
Vol. tanah : 157,5 m3 (BM) = 157,5*1,25=
196,875 m3 (LM)
![Page 14: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/14.jpg)
B. DURASI DURASI : VOL.TERSEDIA/ PRODUKSI ALAT
: 196,875 m3 (LM)/ 254,713 m3/jam (LM)
: ± 47 MENIT ~ 1 JAM
C. BIAYA (SEWA)
BIAYA SEWA : DURASI * BIAYA SEWA PER JAM
: 1 * RP 200.000 (ALL IN)
: RP 200.000,-
HOME
![Page 15: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/15.jpg)
PEKERJAAN
PEMUATAN ALAT YANG
DIGUNAKAN
ESTIMASI/ PERHITUNGAN
PRODUKSI ALAT, DURASI
DAN BIAYA
PENJELASAN
METODE
![Page 16: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/16.jpg)
PENJELASAN Yaitu usaha memuat hasil CLEARING/STRIPPING ke
dalam alat pengangkut.
METODE
![Page 17: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/17.jpg)
Alat yang dipergunakan
WHEEL LOADER
(BACKHOE) KOMATSU
PC 220-1
![Page 18: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/18.jpg)
ESTIMASI/PERHITUNGAN
A. PRODUKSI ALAT (CARA TEORITIS)
BC yang digunakan = 0,9
![Page 19: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/19.jpg)
Bucket factor
tanah
lempung
digunakan 0,8
![Page 20: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/20.jpg)
![Page 21: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/21.jpg)
B. DURASI DURASI : VOL.TERSEDIA/ PRODUKSI ALAT
: 196,875 m3 (LM)/ 75,35 m3/jam (LM)
: ± 2 JAM 37 MENIT = 2,61 JAM
C. BIAYA (SEWA) (SUMBER : INTERNET) BIAYA SEWA : DURASI * BIAYA SEWA PER JAM
: 2,61 * RP 200.000
: RP 522.000,-
HOME
![Page 22: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/22.jpg)
PEKERJAAN PENGANGKUTAN
ALAT YANG
DIGUNAKAN
ESTIMASI/ PERHITUNGAN
PRODUKSI ALAT, DURASI
DAN BIAYA
PENJELASAN
![Page 23: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/23.jpg)
Yaitu usaha memindahkan hasil CLEARING/STRIPPING
ke lokasi pembuangan/pemanfaatan (DUMPING).
PENJELASAN
Alat yang dipergunakan
Dump Truck Kapasitas bak
4 m3
(untuk faktor keamanan
diisi 3,5 m3)
![Page 24: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/24.jpg)
ESTIMASI/PERHITUNGAN
A. PRODUKSI ALAT (CARA TEORITIS)
Kapasitas buket loader = 1m3
Waktu pemuatan = 2,79 menit ( 3,5 m3 hingga
bak terisi)
Fixed time = 3 menit Cycle time per rit = 0,8 menit (2,79/3,5)
![Page 25: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/25.jpg)
Mencari nilai Vessel
C : Kapasitas Vessel
Kapasitas buket loader (KB) = 1m3
BF = 0,85
C = 3,5 m3
N = 3,5/(1 * 0,85) = 4,12 ~ 4 kali
(penggunaan 1 dumptruck)
• Mencari nilai Dumptruck Cycle Time
![Page 26: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/26.jpg)
CT = (4*0,8)+1,44+0,82+1,2+0,3
= 6,96 ~ 7 menit
• Mencari nilai Faktor Koreksi Total
![Page 27: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/27.jpg)
PRODUKSI : (3,5*60*0,5)/7 = 15 m3/jam (LM) MENGGUNAKAN 1
BUAH DUMPTRUCK
B. DURASI DURASI : VOL.TERSEDIA/ PRODUKSI ALAT
: 196,875 m3 (LM)/ 15 m3/jam (LM)
: ± 13JAM 7,5 MENIT = 13,125 JAM
C. BIAYA (SEWA) (SUMBER : INTERNET) BIAYA SEWA : DURASI * BIAYA SEWA PER JAM
: 13,125 * RP 200.000
: RP 2.625.000,-
HOME
![Page 28: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/28.jpg)
PEKERJAAN PEMADATAN
ALAT YANG
DIGUNAKAN
ESTIMASI/ PERHITUNGAN
PRODUKSI ALAT, DURASI
DAN BIAYA
PENJELASAN
METODE
![Page 29: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/29.jpg)
Yaitu usaha untuk memadatkan tanah agar
didapatkan daya dukung tanah yang disyaratkan.
PENJELASAN
METODE
![Page 30: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/30.jpg)
ALAT YANG DIGUNAKAN
Penggilas roda tiga
(three sheet roller)
berat 8 ton
lebar efektif compactor
60 cm,
kecepatan operasi 2
km/jam
![Page 31: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/31.jpg)
ESTIMASI/PERHITUNGAN
A. PRODUKSI ALAT (CARA TEORITIS)
LUAS LAHAN : 475 m2
Jumlah pass = 10 kali
/lapis/jam2m 9010
0.75*2000*0.60F
Vol. = F* ketebalan per lapis (0,1 m)
= 90 * 0,1 = 9 m3 / jam
![Page 32: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/32.jpg)
B. DURASI
C. BIAYA (SEWA) (SUMBER : INTERNET)
HOME
DURASI : Luas TERSEDIA/ 1PRODUKSI ALAT
: 196,875 m3/ jam : 9 m3/jam (CM)
: ± 22 JAM
: ± 3 hari (8 jam kerja/hari)
BIAYA SEWA : DURASI * BIAYA SEWA PER JAM
: 22 * RP 200.000
: RP 4.400.000,-
![Page 33: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/33.jpg)
REKAPITULASI
NO PEKERJAAN ALAT DURASI BIAYA
PER JAM BIAYA
1 RIPPING/
CLEARING
BULLDOZER Caterpillar
D8U ± 1 JAM RP 200.000,- RP 200.000,-
2 PEMUATAN (LOADING)
WHEEL LOADER
(BACKHOE) KOMATSU PC
220-1
± 2 JAM 37 MENIT
RP 200.000 RP 522.000,-
3 PENGANGKUTAN
(DUMPING)
Dump Truck
Kapasitas bak 4 m3
± 13JAM 7,5 MENIT
RP 200.000,- RP 2.625.000,-
4 PEMADATAN
(COMPACTING)
Penggilas roda tiga
(three sheet roller)
± 22 JAM RP 200.000,- RP 4.400.000,-
END
![Page 34: Metode konstruksi (2015)](https://reader034.vdocuments.pub/reader034/viewer/2022050723/55ca6ff1bb61eb8a268b4583/html5/thumbnails/34.jpg)
SELESAI