mivan tech
TRANSCRIPT
![Page 1: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/1.jpg)
Mivan Technology TEJAS C.PATIL
![Page 2: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/2.jpg)
Introduction
• It is the information about Advance Technologies In Building Construction.• The construction industry is rapidly changing.
With-changing times, new processes and the materials are being used.• A lot of research and development is carried out
in the construction industry throughout the globe• Time, economy and utility of space have become
the important aspects of the construction industry.
![Page 3: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/3.jpg)
MIVAN(Aluminum Formwork)
• FORMWORK :-
Formwork is the temporary moulds or shutters in which concrete is placed, so that it will have desired shape or outline when hardened. This temporary casing is known as Formwork or Shuttering.
.
![Page 4: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/4.jpg)
History of MIVAN
Mivan is an aluminum formwork system developed by a European construction company. In 1990, the Mivan Company Ltd. from Malaysia started manufacturing these formwork systems. Today, more than 30,000sqm of formwork from Mivan Co. Ltd. is used across the world. There are a number of buildings in Mumbai that are being constructed with the help of the Mivan system, that has proven economical as well as satisfactory for the overall Indian construction environment. Mivan technology is suitable for constructing large number of houses in a short span of time using room size forms to construct walls and slabs in one continuous pour on concrete. In this system of formwork construction, cast–in–situ concrete wall and floor slabs cast monolithic provides the structural system in one continuous pour. On the removal of the formwork mold a high quality concrete finish is produced to accurate tolerances and verticality. The high tolerance of the finish means that, no further plastering is required.
![Page 5: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/5.jpg)
Uses of Mivan Formwork
• 3S – System of Construction – Speed, Strength, Safety.
• Column and beam construction are eliminated.
• Walls and slabs are cast in one operation.
• Specially designed, easy to handle light weight pre-engineered aluminum forms.
• Fitting and erecting the portion of shuttering.
• Carrying out concreting of the walls and slabs together.
![Page 6: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/6.jpg)
Advantages of Mivan formwork over conventional construction
• More seismic resistance: - The box type construction provides more seismic resistance to the structure.
• Increased durability: - The durability of a complete concrete structure is more than conventional brick bat masonry.
• Lesser number of joints thereby reducing the leakages and enhancing the durability.
• Higher carpet area- Due to shear walls the walls are thin thus increasing area.
• Integral and smooth finishing of wall and slab- Smooth finish of aluminum can be seen vividly on walls.
![Page 7: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/7.jpg)
• Uniform quality of construction – Uniform grade of concrete is used.
• Negligible maintenance – Strong built up of concrete needs no maintenance.
• Faster completion – Unsurpassed construction speed can be achieved due to light weight of forms.
• Lesser manual labour- Less labour is required for carrying formworks.
• Simplified foundation design due to consistent load distribution.
• The natural density of concrete wall result in better sound transmission coefficient.
![Page 8: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/8.jpg)
Limitations Of Mivan• Because of small sizes finishing lines are seen on the concrete surfaces. • Concealed services become difficult due to small
thickness of components. • It requires uniform planning as well as uniform
elevations to be cost effective. • Modifications are not possible as all members are
caste in RCC. • The formwork requires number of spacer, wall ties
etc. which are create problems such as seepage, leakages during monsoon.• Due to box-type construction shrinkage cracks are
likely to appear.• Heat of Hydration is high due to shear walls.
![Page 9: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/9.jpg)
METHOD AND SYSTEM OF CONSTRUCTION BY MIVAN
FORMWORK
INTRODUCTION• MIVAN is the brand name from Mivan Far East,
Malaysia. It is Aluminum alloy Form work The Aluminum formwork system for concreting is probably the most versatile modern construction system. Unlike other systems it is equally suited to both high and low rise construction specifically designed to allow the rapid construction of multiple unit projects at optimum productivity.
![Page 10: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/10.jpg)
![Page 11: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/11.jpg)
WALL PANEL: The Wall Panel forms the face of the wall from the top of the Rocker to the underside
of the Top Panel.
![Page 12: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/12.jpg)
ROCKER: The Rocker forms the wall face at the bottom of the wall panels and helps to facilitate striking.
![Page 13: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/13.jpg)
KICKER: The kicker forms the wall Face at the top of the Top Panels. It is anchored to the
concrete and acts as a ledge for the Wall panels on the next floor to sit on.
![Page 14: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/14.jpg)
BEAM SOFFIT BULKHEAD: The Beam Soffit Bulkhead is used to form the soffit of the beam. It is
used for beams less than 300mm.
![Page 15: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/15.jpg)
DECK COMPONENT: The deck panel rests between pairs of mid-beams and provides a horizontal surface for casting the slabs and provides a horizontal surface for casting the slabs.
![Page 16: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/16.jpg)
INTERNAL SOFFIT CORNER: The Internal Soffit Corner forms the vertical corner between walls and / or beam faces and horizontal internal
corners between wall / beam face and soffit of slabs.
![Page 17: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/17.jpg)
INTERNAL CORNER:
The Internal Corner connects 2 pieces of
vertical formwork together of their
internal intersection.
![Page 18: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/18.jpg)
PROP LENGTH: The prop length is manufactured to a specific length for
each project. It transmits load to the
previous slab.
![Page 19: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/19.jpg)
PANEL PULLER: It is required for removing panels after concreting of wall.
![Page 20: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/20.jpg)
TIE PULLER: It is required for removing wall Ties after de shuttering of panels.
![Page 21: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/21.jpg)
BEAM – BAR: These are used in pairs to fix the Mid
Beam and End Beams to the deck prop. The beam_ Bar is removed when the slab is cast to allow quick striking of the deck form work.
![Page 22: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/22.jpg)
CASE STUDY• Project Name - Amanora Park Town.• Location - Hadapsar,Pune.• Size Of Project - 78,000 m2.• Project Cost - Rs. 650 million.• Client - City Development Corp.• Consultant - P & T, J & W Consultant.• Cycle - 11 days per floor.• Storey - 22 Storey.• System Of Formwork- 6000 sq.mt.• Year Of Completion - On Going.
![Page 23: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/23.jpg)
![Page 24: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/24.jpg)
![Page 25: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/25.jpg)
![Page 26: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/26.jpg)
![Page 27: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/27.jpg)
![Page 28: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/28.jpg)
![Page 29: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/29.jpg)
![Page 30: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/30.jpg)
![Page 31: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/31.jpg)
![Page 32: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/32.jpg)
![Page 33: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/33.jpg)
![Page 34: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/34.jpg)
CONCLUSION The task of housing due to the rising population of the country is
becoming increasingly monumental. In terms of technical capabilities to face this challenge, the potential is enormous; it only needs to be judiciously exploited. Traditionally, construction firms all over the world have been slow to adopt the innovation and changes. Contractors are a conservative lot. It is the need of time to analyze the depth of the problem and find effective solutions. Our aim is to serves as a cost effective and efficient tool to solve the problems of the mega housing project all over the world. Our aim is to maximize the use of modern construction techniques and equipments on its entire project. We have tried to cover each and every aspect related to conventional and aluminum form construction. We thus infer that aluminum form construction is able to provide high quality construction at unbelievable speed and at reasonable cost. This technology has great potential for application in India to provide affordable housing to its rising population. Thus it can be concluded that quality and speed must be given due consideration with regards to economy. Good quality construction will never deter to projects speed nor will it be uneconomical. In fact time consuming repairs and modification due to poor quality work generally delay the job and cause additional financial impact on the project. Some experts feel that housing alternatives with low maintenance requirements may be preferred even if at the slightly may preferred even if at the higher initial cost.
![Page 35: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/35.jpg)
FUTURE SCOPES
This thesis work is restricted to only Mivan formwork and not other type of aluminum formworks. The future researchers can continue by working over other type of formworks construction by analyzing activities like brickwork, plastering, painting and many more. Furthermore interviews of different people from construction industry can be taken based on questionnaire prepared and analysis can be done.
![Page 36: Mivan tech](https://reader035.vdocuments.pub/reader035/viewer/2022062218/5879482d1a28abb1418b4613/html5/thumbnails/36.jpg)
Thank You…