PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
2/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada
PREFACE
The Project Procurement Management (PPM) Template is intended as guidance for procurement
managers and the teams involved in complex project procurements. It should be considered tobe a work in process that will be refined as feedback becomes available from users.
In order to make this document widely available, it is being posted on the PWGSC web site athttp://www.ames-mpsl.com
Some hardcopies also are being distributed for the convenience of many interested professionals.However, distribution is not controlled. Therefore, hardcopy updates cannot be provided toholders of the document. Rather, you are requested to check the web site to obtain the latestrevision which will be indicated by the revision number and date on the cover page.
Your comments are solicited. The collective knowledge and experience of the many peopleinvolved in complex procurement can be of great value in improving the content of theTemplate. Please forward your comments by E-mail to [email protected].
The author acknowledges the importance to this work of several documents cited herein:
SOSB Business Process Renewal Blueprint, Final Report, October 2, 1998;
Canadian Government Procurement Guide, Computer Sciences Corporation; 1997.
Draft DND Acquisition Reform Guide, Directorate of Business Change Management,March 31, 1998;
Systems Engineering Management
, Computer Sciences Corporation, October, 1998.
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
3/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada i
TABLE OF CONTENTS
Section Title Page
1. FOCUS OF THE PPM TEMPLATE............................................................................1
2. FORCES FOR CHANGE .............................................................................................2
3. THE PPM TEMPLATE AND DESKTOP TOOL.......................................................6
4. INTEGRATED PROCUREMENT TEAMS................................................................7
5. PROJECT PROCUREMENT MANAGEMENT FRAMEWORK..........................10
5.1 Phase 1 - Project and Procurement Planning (P&PP) ...................................10
5.1.1 Validate Requirements ...........................................................................12
5.1.1.1 Analyze (Review Clients) Requirement..................................... 135.1.1.2 Define Procurement Concept...................................................... 15
5.2 Phase 2 - Solicitation Planning........................................................................19
5.2.1 Define Procurement Requirements .........................................................215.2.1.1 Define Business and Technical Requirements............................. 235.2.1.2 Define Project Management Strategy.......................................... 255.2.1.3 Define Scope of Contract(s)........................................................ 345.2.1.4 Define Reporting Strategy...........................................................355.2.1.5 Define Approval Strategy ........................................................... 365.2.1.6 Define the Change Management Strategy....................................36
5.2.2 Define Procurement Strategy..................................................................36
5.2.2.1 Validate Sources of Supply......................................................... 385.2.2.2 Define Procurement Methodology (Tools & Techniques) ........... 395.2.2.3 Define Bid Evaluation Criteria and Basis of Source Selection ..... 395.2.2.4 Prepare Bid Solicitation Document ............................................. 405.2.2.5 Obtain Management Approval of the Procurement Strategy........ 44
5.3 Phase 3 - Solicitation and Source Selection (S&SS)........................................455.3.1 Execute Procurement Strategy................................................................47
5.3.1.1 Solicit Bids.................................................................................485.3.1.2 Receive Bids...............................................................................485.3.1.3 Evaluate Bids..............................................................................495.3.1.4 Select Contractor ........................................................................ 50
5.3.1.5 Negotiate Contract...................................................................... 515.3.1.6 Prepare Contract ......................................................................... 525.3.1.7 Obtain Contract Approval ........................................................... 525.3.1.8 Award Contract .......................................................................... 53
5.4 Phase 4 - Contract Management .....................................................................545.4.1 Manage Contract .................................................................................... 56
5.4.1.1 Manage Technical, Systems and Quality Performance ................ 57
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
4/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada ii
5.4.1.2 Manage Cost/Schedule and Delivery Performance ...................... 585.4.1.3 Manage Government Furnished Resources (GFR) Performance.. 595.4.1.4 Administer Contract ................................................................... 59
5.5 Phase 5 - Contract Closeout ............................................................................595.5.1 Contract Closeout...................................................................................615.5.1.1 Physical Disengagement ............................................................. 625.5.1.2 Administrative Disengagement ................................................... 62
Figures
Figure Title Page
Figure 1 Procurement Types ......................................................................................................2
Figure 2 Social, Industrial and Economic Objectives..................................................................3Figure 3 Desktop Tool Main View ..........................................................................................7Figure 4 Integrated Procurement Team.......................................................................................8Figure 5 Complex Procurement Effort Profile ............................................................................9Figure 6 Project and Procurement Planning Process.................................................................13Figure 7 Integrated Procurement Team Concept.......................................................................15Figure 8 Market Research Service............................................................................................16Figure 9 Procurement Management Plan..................................................................................19Figure 10 Solicitation Planning Process Part I.......................................................................21Figure 11 Options Analysis......................................................................................................22Figure 12 Business Case Analysis............................................................................................24
Figure 13 SEI Continuous Risk Management Model................................................................26Figure 14 Dealing with Risk.....................................................................................................28Figure 15 Risk Mitigation Through Contract Management.......................................................29Figure 16 Choosing From a Plethora of Standards....................................................................31Figure 17 Determining Contract Scope ....................................................................................35Figure 18 Solicitation Planning Process Part II......................................................................37Figure 19 Alternative Procurement Strategies...........................................................................38Figure 20 Requirements Management Leading to Product Acceptance.....................................41Figure 21 Communicating in the Contracting Process ..............................................................42Figure 22 Typical Structure of an RFP .....................................................................................43Figure 23 Selection of the Winning Proposal............................................................................44
Figure 24 Solicitation and Source Selection Process.................................................................47Figure 25 Proposal Evaluation .................................................................................................50Figure 26 Contract Management Process .................................................................................56Figure 27 Contract Management ..............................................................................................57Figure 28 Delivery and Acceptance..........................................................................................58Figure 29 Contract Closeout Process........................................................................................61Figure 30 Contract Closeout.....................................................................................................61
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
5/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada iii
Tables
Table Title Page
Table 1 PPM in the Project and Procurement Planning Phase...................................................11Table 2 PPM in the Solicitation Planning Phase .......................................................................20Table 3 PPM in the Solicitation and Source Selection Phase ....................................................46Table 4 PPM in the Contract Management Phase .....................................................................55Table 5 PPM in the Contract Closeout Phase............................................................................60
Annexes
Annex Title
A MPSL ServicesB Project Procurement Management (PPM) TemplateC PPM Work Breakdown StructureD The Relationship Between The Complex Procurement Functions and Core Competency
AreasE Life Cycle Wall ChartsF Sample Activity Templates
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
6/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada iv
ACRONYMS
ABE Automated Buying Environment
ACRO Advisory Committee on Repair
AIT Agreement on Internal Trade
AMESS Aerospace, Marine and Electronics Systems Sector
ASD Alternative Service Delivery
BDP Benefits Driven Procurement
BPR Business Process Renewal
BRU Bid Receiving Unit
CBP Core Best Practice
CCC Canadian Commercial Corporation
CFP Canadian Forces Publication
C/SPMS Cost/Schedule Performance Management Standard
CDRL Contract Data Requirements Lists
CEIL Contract End Items List
CIS Customer Information Service
CITT Canadian International Trade Tribunal
CMF Contract Management FrameworkCMIS Configuration Management Information System
COTS Commercial-Off-The-Shelf
CPAA Contract Planning and Advance Approval
CPP Common Purpose Procurement
CSC Computer Sciences Corporation
DID Data Item Description
DMS Document Management System
DND Department of National Defence
DoD Department of Defense (US)
EPA Effective Project Approval
FAA Financial Administration Act
FTE Full Time Equivalent
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
7/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada v
GBO Government Business Opportunities
GCRs Government Contract Regulations
GETSGovernment Electronic Tendering System
GFR Government Furnished Resources
IM/IT Information Management/Information Technology
IP Internet Protocol
IPPD Integrated Process and Product Development
IPS Informatics Professional Services
IPT Integrated Procurement Team
IT Information Technology
LOI Letter Of Interest
LSAR Logistics Support Analysis Record
MA&S Material Acquisition and Support
MCP Major Crown Project
MOU Memorandum Of Understanding
MPSL Major Project Service Line
MRP Manufacturing Resource Planning
NAFTA North American Free Trade Agreement
NDI Non-Developmental Item
NSN NATO Stock Number
OBS Organization Breakdown Structure
P&A Price and Availability
P&PP Project and Procurement Planning
PFC Pre-Facilitated Contract
PIP Project Implementation Plan
PMBOK Project Management Body Of Knowledge
PMI Project Management Institute
PMO Project Management Office
PMP Procurement Management Plan
PNs Part Numbers
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
8/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada vi
PO&M Personnel, Operations and Maintenance
PPA Preliminary Project Approval
PPMProject Procurement Management
PPMS Project Performance Management Standard
PPRA Project Profile and Risk Assessment
PRC Procurement Review Committee
PWGSC Public Works and Government Services Canada
RCI Request for Contractor Information
RFP Request For Proposal
ROM Rough Order of Magnitude
SAR Search and Rescue
SEI Software Engineering Institute
SI System Integration
SOA Special Operating Agency
SOI Solicitation Of Interest
SOO Statement of Operational Objectives
SOP Solution Oriented Procurement
SOR Statement of Operational Requirements
SOSB Supply Operations Service Branch
SOW Statement of Work
SPAC Senior Project Advisory Committee
SRB Senior Review Board
SS(ID) Synopsis Sheet (Identification)
S&SS Solicitation and Source Selection
TB Treasury Board
TPP Total Package Procurement
TQM Total Quality Management
UGD Unique Government Development
WBS Work Breakdown Structure
WTO-AGP World Trade Organization-Agreement on Government Procurement
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
9/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 1
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
1. FOCUS OF THE PPM TEMPLATE
Among a broad range of common services, Public Works and Government Services Canada(PWGSC) provides procurement services to federal government departments and agencies. Ofthe $8 Billion annual expenditure on goods and services, roughly half of this expenditure is inthe area of complex procurement that is characterized by significant technical and business risk.
Project Procurement Management (PPM) is the effective integration of project management
principles and practices in the procurement process. PPM is the PWGSC discipline applied tomajor acquisition and support projects.
The PPM Template presented in this document is based on work processes and the businessenvironment of the Aerospace, Marine and Electronics Systems Sector (AMESS), andspecifically, the Major Project Service Line (MPSL) that manages the government's mostcomplex and sensitive project undertakings, characterized by capital expenditures above $50Million (CAN), with significant risk and project management implications.
Within PWGSC there is a well-known distinction between standard and complex procurement.The former is transaction based, characterized by the purchase of commercial goods and servicesusing automated techniques and customer direct-order supply arrangements, such as standingoffers. Individual transactions are relatively low dollar value and thousands of contractualdocuments are issued1. The focus is on Part Numbers (PNs), NATO Stock Numbered (NSN)items and Commercial-Off-The-Shelf (COTS) procurement. In comparison, complexprocurements are higher dollar value, more complex, often involving development, integration,business process change, or outsourcing. Complex procurement typically results in fewercontractual transactions, and far more effort in project and procurement planning, sourceselection, and contract management.
Figure 1 illustrates both standard and complex procurement types. On the far left of the figure,Client Delegatedprocurement activity is performed locally by the client departments within theirdelegated authority. Catalogued item procurement refers to the simplest type of procurementperformed by Supply Operations Services Branch (SOSB), where technical compliance, priceand availability are the main selection criteria. Simplified procurement is one step up on thecomplexity scale because there may be a simple Statement of Work (SOW) or technicalspecification, or there may be additional selection criteria2.
1 Taken from the SOSB BPR Requirement, 14 September 19982 Taken from the SOSB BPR Requirement, 14 September 1998
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
10/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 2
DEGREE OF COMPLEXITYLOW HIGHDELEGATED PROCUREMENT
AUTHORITY
PWGSCEnablers -
Standing
Offers,
Catalogues
LocalPurchase
Orders
SOSB
Facilitated
COMPLEX PROCUREMENT
SOSB
Contracted
SOSB
Contracted
STANDARD PROCUREMENT
Goods &
Services Requests
Client DelegatedProcurement Process
ManufacturersPart Numbers,
NATO Stock Numbers,
Commercial-Off-The-Shelf
Low Risk andComplexity
Simple Spec/SOW
Quick Competitions,
Electronic Business
Via Internet
Catalogued Item
ProcurementProcess
Review Policies Reduce Open Bidding
Times Pre-Qualify Vendors
Use of E-Business
Simplified
ProcurementProcess
Higher Risk,Complex SOW,
Pre-Facilitated Contracts,
Capital Equipment,
Major System Procurement
Integrated
Procurement Team,
Contract Management
Framework based on Risk,
Contract Administration
and Resources onContractors Site
Integrated
Procurement
Team
Figure 1 Procurement Types3
There is only one category of complex procurement shown in Figure 1; however in reality thereare many gradations of complexity. What distinguishes complex procurement is the need forteamwork between SOSB, the client department and industry through an integrated procurementprocess to ensure a successful project. This teamwork involves more extensive and earlierteaming with the client, and consultation with industry in order to better define the procurementrequirements and position the solicitation process.
2. FORCES FOR CHANGE
In Canada complex procurement is an instrument of public policy. The social, industrial andeconomic objectives of federal government procurement projects are identified in Figure 2. Thegovernment Treasury Board has emphasized that all procurement must be guided by principlesof value for money, fairness, openness, and transparency. In large, sensitive procurements the
interests of regional and industrial policy and priorities come into play through a network ofadvocacy organizations.
3 Taken from SOSB BPR Report, dated 14 September 1998
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
11/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 3
SOCIAL, INDUSTRIAL AND ECONOMIC OBJECTIVES
Within the constraints of trade agreements, contribute to a favorable balance of
payments, by ensuring that sufficient expenditures occur in Canada to offsetproject expenditures in other countries
Develop the nations industrial base by taking advantage of opportunities
presented by major projects to expand Canadian industrial capability in terms of
technological opportunities, managerial capability, and production capacity
Improve Canadian competitiveness in world markets by stimulating Canadian
exports and promoting replacement of imports
Provide employment, especially in economically disadvantaged regions of the
country
Consistent with government obligations under Comprehensive Land Claims
Agreements, take into account the current capacity and increased ability over
time of aboriginal firms, within settlement areas, to compete for and tosuccessfully complete government contracts.
Figure 2 Social, Industrial and Economic Objectives
Within the last several years, national legislation, international trade agreements and aboriginalland settlement agreements have been added to the procurement context. The North AmericanFree Trade Agreement (NAFTA), the World Trade Organization Agreement on GovernmentProcurement (WTO-AGP), and the Agreement on Internal Trade (AIT) govern much of federalgovernment procurement. The Canadian International Trade Tribunal (CITT) is a quasi-judicialbody that investigates complaints by potential suppliers. When the CITT investigates a
complaint, it makes a determination and recommendations, for example, re-evaluation, re-tendering or providing compensation. The recommendations of the tribunal are generallyimplemented by the government organization in question.
The federal government has been downsizing in recent years. In the Supply Operations ServiceBranch (SOSB), program reviews and employee departure programs have reduced the workforceby about 30%. During this period the procurement environment has become more complex.Both internal and external audits and challenge processes are signalling that some corecompetencies are suffering due to a lack of experienced personnel.
As a result of these environmental changes, there is a need to provide guidance and tools for
complex procurement. The purpose of the Template is to assist procurement managers andtheir teams in perf orming work more eff ectively. Also, it will assist MPSL in identifyingcompetencies, and in related training and professional development initiatives. The template isalso intended to provide an orientation and reference for new employees, customers and otherstakeholders, and to support:
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
12/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 4
A more disciplined, repeatable, and measurable process;
PPM competencies;
Training requirements; The capability and approach to benchmark the process; and
The capability to evaluate the process, products (i.e. RFP, Contract) and the peopleworking in complex procurements.
I t is not intended that the Template be used to generate policy for complex procur ement.
The PPM Template focuses on the procurement services of Major Project Service Line (MPSL)organization, although the processes are generic enough to be applicable branch-wide in complexprocurement. Annex A describes the range of MPSL procurement, project and program services
that are available to client departments. Some of the driving forces behind the template are: In conducting complex procurement, sophisticated strategies and models are used to
incorporate a range of business, technical, and program/project management practiceswhich require high skill levels;
The effects of downsizing, outsourcing, and business renewal in PWGSC, clientdepartments and industry means that it is no longer practical to rely exclusively onmentoring to maintain and pass on knowledge; and
There is a growing trend toward "projectising" work, even in program serviceenvironments, supported by knowledge repositories, accessible through Internet Protocol(IP) based technologies.
The PPM Template approach reflects several major initiatives currently impacting PWGSCprocurement operations. The first of these,La Releve is a public sector-wide initiative sponsoredby the Clerk of the Privy Council that seeks to modernize service delivery and re-position thehuman resources to meet present and future needs. The overall PWGSC initiatives supportingLa Releve are to:
Review the procurement process, mechanisms, and technology;
Improve the working environment, increase efficiency, reduce costs, and enhance humanresource skills;
Identify needed productivity improvements; and
Define the impact on PWGSC of the reengineering of PWGSCs largest single customer,the Department of National Defence (DND) and recommend responses that are alsosuitable for other client departments.
Another high profile PWGSC initiative is Benefits Driven Procurement (BDP). BDP is a set ofprocurement principles and processes that recognizes the sources and consequences of risk in
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
13/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 5
complex project procurements, and promotes intervention at appropriate times. It has evolvedfrom experience in Information Technology and System Integration procurements. Under BDP,the contractor is brought in early, before the requirements are fully defined. The contractor
works closely with the customer in defining and implementing an appropriate solution. BDPseeks:
A reduction in procurement process time and cost to government and industry;
Long term business relationships between customers and contractors,
Continuous risk management;
Business-case management, and
The use of best practices.
The PPM Template incorporates BDP processes that have been identified for information
technology and systems integration projects.
In September 1998 the SOSB business process renewal study phase was completed. The keymessage in the Report is the need to:
Respond to the Shift
in Business
- from transaction to knowledge-based procurement.
Foster a Results
Oriented Culture
- methods for meeting productivity demands and governmentprocurement objectives will require employees to assume greaterresponsibility and accountability in meeting client needs and
managing contractual risks.
Prepare for
Electronic Business
- select Information Management/Information Technology (IM/IT)tools that ensure a lead role in the selection and management of E-Business tools.
Create a Learning
Organization
- provide the necessary resources to sustain the change effort,communicate best practices, lead communications, and support alearning organization culture.
The Template also considers acquisitionprocess change underway in DND, for example:
Equipment
Management Teams
- organizational alignment by system being procured or supported;
New relationships
with industry
- such as long term business relationships, for example in partnering,support and bundling of procurements using Pre-FacilitatedContracts (PFC);
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
14/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 6
Alternative Service
Delivery (ASD)
- provision of non-core services by the most appropriate means.After evaluation of alternatives, a government agency or industrywill be chosen to provide the service whichever is the most cost
effective.
Strong preference for
teaming
- that integrates procurement and project management capabilityoutside functional stovepipes.
The new procurement methods, such as BDP, PFC and ASD are addressed later in the Template.However, it should be noted here that such methods demand a very knowledgeable PWGSCContract Authority able to devote considerable time to individual complex procurements,supported by project management and contract process expertise.
3. THE PPM TEMPLATE AND DESKTOP TOOL
PWGSC and customer procurement personnel do not have a comprehensive, easy-to-useguidance document to assist them in doing their work. This need led to the development of thePPM Template and its presentation on a desktop computer tool.
The idea of the desktop originated in the US Department of Defense (DoD). A Canadian versionis being created by the Department of National Defence (DND) as part of its Acquisition Reforminitiative. The MPSL desktop will be linked in the area of common processes to that of DND, inorder to ensure compatibility, and to maximize the synergy of guidance tools being used by thetwo departments.
The PPM Template has two immediate customers. First, the MPSL has a requirement for theTemplate (and the related training gap and needs assessment) as a deliverable for the BranchBusiness Plan. Second, the branch-wide business renewal process defined a requirement for aContract Management Framework (CMF) in response to various audits, effectiveness studies andfocus group feedback. Detailed activity level templates are being prepared to provide guidancein preparing project and procurement documents, and for different PPM processes, for example,contract management.
The Template will be linked through the MPSL web page4 with information on policy, guidance,training and innovative procurement practices, including a library with search and query
capability.
The Template will also be made available as part of a desktop tool, and in Work BreakdownStructure (Annex C) and wall chart (Annex E) formats. In addition to the template or processview, the desktop tool will contain several other views that allow users to find related
4 MPSL web page: http://www.ames-mpsl.com
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
15/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 7
information or ask questions and provide input to the desktop repository. The main view of thedesktop tool is shown in Figure 3.
DESKTOP
MAIN VIEW
PROCESSES
TOOLS
TRAINING
WHATS NEW
LIBRARY
SEARCH
QUERY
People
Processes Tools
EDUCATION AND TRAINING
STRUCTURED BUSINESS PRACTICES
PROJECT PROCUREMENT
MANAGEMENT
Figure 3 Desktop Tool Main View
The desktop tool enables direct support of all those performing procurement activities who needguidance, templates, computer tools, etc. Updates are immediately available to all users, withoutthe previous cost and time delay associated with distribution of paper. Also, feedback can bereadily obtained electronically, enabling lessons learned for example, to be provided when theyoccur rather than months or years later.
4. INTEGRATED PROCUREMENT TEAMS
One of the acquisition reforms in the US, UK and Australia is the introduction of integratedproduct and process teams. Benchmarking studies have concluded that using such teams is aCore Best Practice (CBP) for organizations that manage project business.5 Multi-disciplinaryproject teams improve the effectiveness of project decisions and work delivery. Many customerand contractor organizations have replaced functional stovepipes with teams and integratedprocesses that support this concept. The U.S. Department of Defense (DoD) acquisition projects
use teaming arrangements that involve government and industry in the development ofequipment, software, and business systems.
The IPT is a natural evolution of the industry concept of concurrent engineering that replaces thelengthy, sequential processes of design-production-logistics engineering with a much shorter and
5 Project Management Institute (PMI) Benchmarking Research Report, Page 22.
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
16/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 8
more effective and integrated process. The IPT is characterized by physical co-location ofintegrated teams, concurrent design, production and logistics engineering; parallel, incrementalproduct and data releases; electronic data replacing paper, GroupWare and collaborative work
tools; and overall, integrated product teams and management structure
6
. The IPT may alsoinclude joint contractor and customer decision making through alliances or long-term businessrelationships.
In Canada, federal organizations take on very little system design and development. Mostdevelopment effort involves modification of existing products to suit customer needs. In DNDprojects, the IPT has been adapted to the modest scope associated with "development effort", andthe customer does not share design authority responsibility with the contractor. However, theIPT approach has a significant impact on the contractor. With the IPT approach, contractorsneed not write many of the documents now used to describe how it conducts project business.These business practices should be evident to the government team members who participate in
the project along side the contractors personnel. Depending on the contract provisions, projectbusiness processes can be influenced by all team members.
In the Template, the phrase Integrated Procurement Team (IPT) has been used to describe theteam concept. (DND uses the term: Integrated Project Team.) One of the most importantrecommendations from PWGSC and DND business process renewal is the early formation of theIPT. Larger projects often have specialists in functional areas, such as systems engineering andintegrated logistics support. Some teams will have a member from Industry Canada who willaddress Industrial, Regional and Aboriginal Benefits. A few projects will also have a small teamco-located with the contractor. The concept of an IPT is illustrated in Figure 4. Significanteffort needs to be devoted to training procurement personnel in the reform concepts that arebeing implemented, for example the roles of IPT members in relation to departmental mandates.
OperationsTechnicalFinance
Contracting
CLIENT DEPARTMENT
CONTRACTOR
PWGSC
OTHER
DEPARTMENTS
r Use of information technology
r Shared access to computer tools and databases
Figure 4 Integrated Procurement Team
6 Taken from the Canadian Government Procurement Guide, B.F. Hough, CSC.
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
17/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 9
"During interviews conducted as part of the PWGSC and DND business process a common
theme was the importance of adequate staffing to manage the procurement. Obtaining qualified
people, ensuring adequate training, avoiding excessive staff turnover, and benefiting from priorproject management experience were all concerns. Human resources deficiencies can adverselyaffect the ability of a project office to progress in a timely and efficient manner.7"
This research suggested that SOSB and client departments no longer have the necessaryexperienced personnel to manage complex procurements. To partially offset this problem, manyproject offices have obtained expertise and assistance by contracting for support. Examples are:
Establishing a cadre of contractor support staff called a Project Management SupportOffice - to provide specialized engineering, logistics and project management support;
Hiring experts in specialized topics where such highly skilled resources are not available
within the Branch; and Hiring consultants to perform or assist with time consuming tasks, such as drafting the
Statement of Work and specifications8.
These concerns are being addressed by MPSL in the competency/gap/training and recruitmentprocess, and in DND through implementation of the Project Management Occupational Analysisand related improvements in training.
Figure 5 illustrates the project procurement life cycle, and the five (5) the PPM phases. IPTmembers work together throughout the project to achieve the procurement objectives.
Objectives &
Constraints
Defined
Solution
Defined
Requirements
Defined
Product
Accepted
Delivery &
Installation
CompleteLogistics
Support
Fielded
Statement of
Requirements
PerformanceSpecification
Detailed
Specifications
TIME
ACQUISITION
MILESTONES
Maintenance
Plan Test &
Evaluation
Reports
Support
Planned
Product
Qualified
Product Baseline
KE Y
DOCUMENTS
EFFORT
INDUSTRY
GOVT
PHASE 1 PHASE 2 PHASE 3 PHASE 4 PHASE 5
Figure 5 Complex Procurement Effort Profile
7 DND and PWGSC interviews conducted in 1998.8 Taken from DND Acquisition Reform Guide, Team Leader G. Reinhardus, Author B.F. Hough.
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
18/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 10
5. PROJECT PROCUREMENT MANAGEMENT FRAMEWORK
The approach taken in defining the Project Procurement Management (PPM) business process
was a topdown, hierarchical method comprising the following elements:
Governance and
Accountability
Framework
- a review of government, central agency and departmental mission andbusiness planning documents to verify that PPM is an initiativeconsistent with the current vision for the Branch.
PPM Concepts - were developed to link PPM activities with goals, competencies andresponsibilities.
PPM Process
Template
- were defined to relate the objective of each activity to the process and itsoutput/outcome.
PPM Activity
Templates
- are being prepared in order to provide detailed guidance for each PPMprocess. These templates will contain how to information that will becontributed and maintained by subject matter experts.
The PPM processes identified in the Template are shown in a Work Breakdown Structure (WBS)in Annex C. Sample Activity Templates are contained in Annex F.
5.1 Phase 1 - Project and Procurement Planning (P&PP)
The Guide to the Project Management Body Of Knowledge (PMBOK) defines the procurementplanning process as "determining what to buy and when"
9. The process includes identifying
project needs that can be best met by procuring products or services outside the projectorganization.
The concepts presented in Table 1 are aimed at giving a high-level view of PPM in relation to theproject phase goals, responsibilities, and needed competencies. PPM is also linked to inputs,tools and techniques, and outputs of the project phase.
9 PMBOK, Procurement Page 132.
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
19/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 11
Table 1 PPM in the Project and Procurement Planning Phase
COMPETENCY AREA GOALS10 RESPONSIBILITY
IPT = Input D = Decision
Financial Management Confirm project priority and affordability D = Strategic, financial and userorganizations
Project/TechnicalManagement
Determine or confirm project feasibility IPTD = Project Leader/Manager/Director
Capability Assessment Assess project organization capability D = Project Leader/Manager
Risk Management Assess the project risks IPTD = Project Manager
Procurement Management Determine allocation and IPTmembership
IPTD = Project Manager
Procurement Management Determine the overall procurementapproach
IPTD = Project Manager
INPUTS TOOLS & TECHNIQUES OUTPUTS
Program approval to proceedwith planning
System or commoditydesignation
Concept/Development phase outputs
Project and Procurement businesscapital plans and resource forecasts
Planning for P&PP phase anddefinition of project performanceobjectives
File allocated within Branch, and IPTdefined
Business Requirements and Case Business Case Template Life Cycle Costing Model
Statement of Operational
Requirements (SOR)
SOR Template and preliminary
SOW/SPEC
Project Scope Statement and Work
Breakdown Structure (WBS)
COTS, SOP, UGD11 content
Results of Capability & RiskAssessment
Capability and risk impacts Mitigation plans and action
Project constraints andassumptions
Expert judgement Refine/integrate with risk planning
Options analysis, trade-offstudies
Surveys, Market/Product Research,Letter of Interest
Potential Sources of Supply andCapability Assessment
National objectives inprocurement
Industry Canada review Procurement Review Committee12
Record of Decision
Other planning outputs Preliminary WBS, cost, schedule,quality, cash flow, risk management
planning, phasing, gates, ramps
Procurement Management Plan (PMP)- draft
10 The idea of linking PPM processes to goals and inputs-outputs is taken from the BDP Guide (Godcharles, Goulet and Fournier) and thePMBOK.11 Commercial-Off-The Shelf, Solution Oriented Procurement, Unique Government Development these are Treasury Board Secretariat defined
procurement strategies12 For major Crown projects, the Senior Project Advisory Committee; for R&O, the Advisory Committee on Repair and Overhaul
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
20/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 12
5.1.1 Validate Requirements
Validate Requirements starts with review and analysis, from a procurement perspective, of the
outputs of the client departments project identification phase. Based on the review of the draftrequirement documents, the procurement responsibilities, including planning and control aredetermined, and the Integrated Procurement Team (IPT) membership is determined.
The process is defined in the Supply Manual Memorandum Of Understanding (MOU) ofProcurement Activities as: the definition of operational needs13. It starts with problemidentification and is completed with the start of the Development Phase when a number ofoptions to satisfy the requirement are examined. Validate Requirements is the first point ofcontact between an SOSB account manager and customer requirements and/or project officestaff. This contact may occur prior to or during the identification/concept phase when the projectobjectives and requirements are being defined. The typical program management activities in
the identification phase are:
Description of the operational deficiency;
Identification of potential solutions in broad terms;
Rough Order of Magnitude (ROM) cost estimate;
Creation of Project Charter;
First Statement of Operational Requirements (SOR) or Business Requirements; and
Identification of cash phasing in the capital planning process.
In DND, the Identification Phase culminates in a Program Decision Document, the SynopsisSheet (Identification) or SS(ID). The purpose of the SS(ID) is to obtain:
Agreement on the deficiency or need;
Agreement on the proposed options to be examined;
Funding for the Development Phase; and
Planning approval for the anticipated capital cost.14
The PPM Process in the Project and Procurement Planning Phase is shown in Figure 6. Eachprocess is then described below.
13 DND/PWGSC Responsibility Matrix, Page 3.14 CFP 125, Chapter 7, Page 46. Note: This is not capital project cost approval.
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
21/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 13
PHASE 1 PROJECT AND PROCUREMENT PLANNING15
VALIDATE REQUIREMENTS
Analyze (Review Clients) Requirement
Define Performance Objectives
Determine Allocation and Teaming
Identify and Form Integrated Procurement Team (IPT)
Define Procurement Concept
Identify Sources of Supply
Identify and Define Procurement Concept
Refine Performance Objectives
Prepare Procurement Management Plan (PMP)
Figure 6 Project and Procurement Planning Process
5.1.1.1 Analyze (Review Clients) Requirement
Objective: To understand the problem, deficiency, or opportunity; tounderstand the views of the sponsor and stakeholders; to ascertain the state ofrequirement documents; and to determine the project management required
for the procurement.
Process: Contact the project sponsor and stakeholders. Review thepreliminary requirement documents and background project documentationsuch as the deficiency description, ROM estimates, Project Charter, WorkBreakdown Structure (WBS), and Risk Assessment to determine procurementimplications and obtain inputs for the Procurement Management Plan (PMP).
Output: Customer contact is made, project and requirement documents arereviewed and analyzed, and procurement implications are determined ThePMP is started for the project, with inputs from key documents and contactpoints.
Define Performance Objectives
Objective: To assist the client department in defining the top-levelacquisition objectives of the project.
15 The PPM process is shown without numbering. Annex C contains a numbered of WBS view of PPM.
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
22/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 14
Process: Review requirements documents, such as draft Statement ofOperational Requirements (SOR) and the options analysis that identifyalternative ways to satisfy the required capability of the project. Since the
identified options are the basis for Development Phase trade-off decisions, theearlier that all credible solution alternatives are considered, the more quicklythe procurement can proceed. Since project performance objectives typicallyrelate directly to procurement objectives (expressed later as contractperformance requirements), it is essential that there is procurement input tothe customer at this point in the project.
Output: Project objectives expressed in the requirement documents and inthe Project Charter are clarified.
Determine Allocation and Teaming
Objective: To determine which SOSB organization and personnel shouldteam with the client department organizations to conduct the projectprocurement.
Process: The procurement file is allocated based on considerations such assystem or commodity designation, product and project managementcomplexity, and the need for planning, control and risk management expertisein support of the procurement. Teaming within and between sectors also isidentified where procurements cross organization boundaries.
Output: File allocation, SOSB and sector teaming is identified and recordedin the PMP. The Contracting Authority office and individual file holder is
identified as the single point of contact with customer requirements staff andthe Project Manager. Teaming within and between sectors is established. Thesource of particular expertise, for example planning and control, is identified.
Identify and Form Integrated Procurement Team (IPT)
Objective: To identify and assign the IPT members that will be responsibleto execute the end-to-end procurement process, including the transition fromcapital acquisition to operations and support procurement.
Process: The IPT is formed at the call of the Project Manager, and inconjunction with other product or process teams supporting the projectobjectives. The IPT is composed of core members (technical specialist,logistics/financial specialist, operations specialist (user representative),contracting specialist and many supporting specialists that provide, forexample, legal, cost, risk, policy, trade agreements, and security advice.Figure 7 illustrates operation of the IPT.
The IPT operates under the direction of the Project Leader from the clientdepartment. Under the Project Manager, the core team accomplishes the
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
23/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 15
many tasks in the procurement process. The specialists provide inputs asneeded. Interaction with industry is via procurement instruments, such as theRequest For Proposals and resulting contract. The selected contractor is
responsible for satisfying the specified requirement by developing/providingthe needed new or enhanced operational capability.
Output: IPT membership and responsibilities are established and recorded inthe PMP.
REQUIREMENT PROCUREMENT PROCESSOPERATION
CAPABILITY
CORE TEAM
Project
Management
Operations Technical
Contracting
Finance
PROJECTLEADERS
DIRECTION
INTERACTIONWITH
INDUSTRY
SPECIALIST SUPPORT
Policy Advise
Risk Assessment
Quality Standards
Expertise
Test and Evaluation
Capability
Configuration Management
Support
Documentation Support
Supply System
Expertise
Security Advice
Legal Advice
Cost Accounting
Figure 7 Integrated Procurement Team Concept
5.1.1.2 Define Procurement Concept
Using the output of Validate Requirements, this process identifies potential sources of supply,links project and procurement objectives, and starts the formal procurement planning process.
Identify Sources of Supply
Objective: Using requirement documents, suppliers are assessed to verify theavailability of products that meet the requirements; their ability to modifyproducts to meet user requirements; and their willingness to propose solutionsthat maximize Commercial Off-The-Shelf (COTS) product and servicecontent.
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
24/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 16
Process: Researching sources of supply can involve interaction with users,contacting companies for information, and getting source and productinformation from other users (e.g. allies) or mining the wealth of information
on the internet.
16
In addition to these methods, technical journals, unsolicitedproposals, Price and Availability (P&A), catalogues and conferences, surveys,and plant visits are techniques to identify potential sources. Information onthe historical performance of these sources can also be useful, even at thisstage of planning. This Process should stimulate industry interest in theproject, and focus on their capability to adapt existing (COTS) solutions to theproject requirements. PWGSC provides a valuable service to clientdepartments in assisting with Market Research as suggested by Figure 8.
Output: The potential sources of supply, and the procurement assessment ofthe COTS alternatives identified for the project are recorded in the PMP.
MARKET RESEARCH SERVICE
Before buying goods and services, get to know the market.
Availability of products to meet the requirement as is;
Ability of suppliers to modify their products to meetthe users requirement; and
Flexibility of users to modify their requirements to
allow the purchase of commercial-off-the-shelf goods
and services.
SOURCES OF SUPPLY
USERS ALLIES INTERNET JOURNALS COMPANIES . . .
Figure 8 Market Research Service
Identify and Define Procurement Concept
Objective: To identify and conduct preliminary analysis of considerationsthat will impact the procurement strategy.
Process: The procurement concept includes an examination of topics such as:
Identifying opportunities for using Benefits Driven Procurement(BDP). In this phase the Project Team is:
Preparing a Business Case
16 DND Acquisition Reform Guide, Team Leader G. Reinhardus; Author B.F. Hough.
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
25/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 17
Determining if information technology solutions for the needexist
Performing an evaluation of the departments project
management and software process management capability Preparing project scope and risk assessment
Assess applicability of the BDP approach and seeking projectapproval
In addition to BDP considerations, the procurement concept involvesconsideration of:
Canadian vs. off-shore industrial capability, that may requireassessment of major policy and trade legislation issues
Need for Government Furnished Resources (GFR)
Technology transfer, patents, licensing and royalty issues
The overall procurement timeline and process; major projectand contract milestones
Preliminary identification of procurement effort/resource level
Target cost and cash flow
Identification of appropriate authorities (technical, design,system, inspection, quality assurance)
Need for and coordination of interdepartmental or internationalagreements
Identification of relevant standards and templates for technicaland project management disciplines
Project Management needs and capability
Risks and mitigation strategies17
With the introduction of trade agreements like NAFTA, WTO-AGPand AIT, the non-competitive approach to the procurement process iscalled limited tendering. It is a deviation from the competitive processincluding the ability to contact a sole or single supplier or a number ofsuppliers individually. The conditions under which limited tenderingmay be used are very specific, and the Supply Manual, paragraph5.030 should be consulted for the details. In all cases the client mustprovide the rationale for exceptions to competitive procurement beforea procurement strategy that uses limited tendering can be followed.
The appropriate procurement approach for the project depends upon manyfactors, such as the nature of the project, the time and resources that you haveand the market place availability of a solution.
The points of involvement and resulting effort profiles vary, depending uponthe procurement concept selected. For example, under BDP, industry is
17 Canadian Government Procurement Guide, B.F. Hough, CSC.
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
26/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 18
brought in when the project objectives are clear, but requirements have not yetbeen specified. The requirements definition work is largely transferred toindustry. Under Commercial-Off-The-Shelf procurement, product
development effort and risk is avoided. However, the specific (logistics)support requirements must still be planned. With Total Package Procurement,life cycle product support is provided by industry, and maintenance planningis simplified18.
Feedback on the Procurement Concept should be sought within the IPT(s) andfrom potential sources of supply.
Output: A preliminary review and analysis of factors contributing to theprocurement concept is recorded in the PMP. In many cases, this analysis willraise questions that may not be answered until later in the procurementprocess, or conditions may change, requiring further review of how thesefactors will influence the procurement.
Refine Performance Objectives
Objective: To review and refine the procurement objectives using feedbackfrom within the IPT and from potential sources of supply.
Process: Using the outputs of early dialogue with industry, requirements andbusiness planning documents, the procurement concept, and the project lifecycle methodology, review and refine the procurement performanceobjectives.
Output: Using project, requirements, and procurement planning and industry
feedback (e.g. homepage, industry days, plant visits, company presentations),update the performance objectives and requirement documents. This resultsin revisions to requirements definition documents, such as Statement ofOperational Requirements, Statement of Objectives, Business Requirementsand any preliminary specifications.
Prepare Procurement Management Plan (PMP)
Objective: To integrate the planning effort of the IPT in a single procurementplan that will be used for overall management, coordination andcommunication of procurement activity, and as the basis for the contractapproval strategy.
Process: Using information gathered in the activities to date, prepare a draftof the PMP and review it within the IPT. The PMP evolves over the life ofthe procurement as it adds content on project, contract management andcontract administration activities. An outline of the PMP is presented in
18 DND Acquisition Reform Guide, Team Leader- G. Reinhardus; Aughor B.F. Hough.
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
27/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 19
Figure 9. The PMP is both a plan and a record of the key activities anddecisions during the life of the project procurement.
Output: The draft PMP is prepared.
1. Description
Requirement
Budget and Financial Code
Need Date
2. Policy Issues
Authorization Reference
Risks (Time, Cost, Performance)
Protection of the Crown
Contract Administration
3. Sourcing
Procurement Method
Trade Agreements
Competitive vs Sole Source
Multi-Sourcing
4. Evaluation Criteria
Best Price, Best Value, Best
Technical
Socioeconomic Considerations
5. Procurement Milestones
RFP Issued
Bids Closed
Contract Award
Deliveries Commence
Contract Complete
6. Additional Comments
Any additional information that
the Approval Authority shouldbe aware of.
7. Revisions To The Plan
Approved By:
Figure 9 Procurement Management Plan
5.2 Phase 2 - Solicitation Planning
The PMBOK defines solicitation planning as "documenting the project requirements andidentifying potential sources of supply"19. The process includes preparing all the documents thatwill be necessary in the solicitation and source selection phase. These concepts are presented inTable 2.
19 PMBOK, Procurement, Page 137.
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
28/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 20
Table 2 PPM in the Solicitation Planning Phase
COMPETENCY AREA GOALSRESPONSIBILITY
IPT = Input D = DecisionMultidisciplinary Define Procurement Requirements in Bid
Solicitation DocumentsIPTD = Project Manager
Project/Procurement/TechnicalManagement
Determine contract scope (WBS), forexample bundling, PFC, BDP, ASDopportunities
Determine applicability of trade agreements
IPTD = Project Manager
D Procurement Manager20
Multidisciplinary Define Contract Management andAdministration strategies
IPTD = Procurement Manager
Technical/Procurement/Cost &Pricing Management
Define evaluation methodology and basis ofselecting the winning bid
IPTD = Project Manager
Procurement Management Obtain advance approval for procurementstrategy
IPTD = Procurement Manager
INPUTS TOOLS & TECHNIQUES OUTPUTS
Scope Documents: WBS,SOW, SPEC, Plans, cash flow
Document templates Requirements documentsconsistent with procurementstrategy and best practices
Draft Contract documents:T&Cs, SOW, SPEC, Plans,DIDs/CDRL, Master Schedule,WBS
Contract documents: T&Cs,SOW, SPEC, Plans,DIDs/CDRL, Master Schedule,WBS
Evaluation Methodology andBasis of Selection
Document templates Evaluation Plan- Methodologies,criteria (attributes, weighting,thresholds) and basis ofselection. Evaluation teamresources.
Potential Sources of Supply Guidance documents: Communication withindustry- Industry Days, feedback on draftsolicitation documents, site visits and
presentations
Suppliers aware of pendingprocurement, knowledgeableabout requirements in relation tocapabilities
Risk Mitigation Plans andResults
Procurement risk assessment, risk tools Update mitigation plans
Life Cycle Costing andpreliminary Estimates
Expert judgement, estimating techniques Independent estimates
20 In this context Procurement Manger is the PWGSC lead IPT position. Finance and logistics represents the DND procurement position.
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
29/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 21
Solicitation planning processes are grouped under:
Define Procurement Requirements; and
Define Procurement Strategy.
Part I, the PPM Process in the Solicitation Planning Process, is shown in Figure 10. Eachprocess is then described below.
PHASE 2 SOLICITATION PLANNING (PART I)
DEFINE PROCUREMENT REQUIREMENTS
Define Business and Technical Requirements
Define Project Management Strategy
Define Risk Management Strategy
Define Contract Management StrategyDefine Delivery and Acceptance StrategyDefine Quality Assurance Strategy
Define Financial Management StrategyDefine Government Furnished Resources (GFR) Strategy
Define Bid Solicitation Strategy
Define Contract Administration Strategy
Define Scope of Contract(s)
Define Reporting Strategy
Define Approval Strategy
Define Change Management Strategy
Figure 10 Solicitation Planning Process Part I
5.2.1 Define Procurement Requirements
This group of processes involves developing procurement strategies and preparing thesolicitation documents and resulting contract(s). The emphasis is on defining strategies, withinthe IPT, for project and risk management, contract management and administration.
These strategies are defined during the project Development Phase when the selected options arebeing studied in detail. The process provides the Rough Order of Magnitude (ROM) costs(capital and personnel, operating and maintenance costs). It also identifies the benefits, risks and
opportunities of each option with a view to finding the best option to further define in detail, ifnecessary, during a Definition Phase. Options analysis is conducted in an iterative fashion,starting with an assessment of the various ways of meeting the need. For example, anoperational capability (e.g. sovereignty patrol) could be carried out in many different ways.Figure 11 illustrates options analysis and provides basic advice. In the development phase, onewould examine the options selected during the identification phase, before selecting long range
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
30/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 22
patrol aircraft, and then define the particular aircraft that will best meet the operationalrequirement.
Define operational need
Identify options
Analyse each option
Select preferred option
Note: Stay at high level. Leave
implementation details to
industry.
Example:
0 50 100 150 200 250
6
5
4
3
2
1
0
TotalSystemC
ostPerPoundof
PayloadonStation
Aircraft Payload Weight (Thousands lbs.)
Antisubmarine Warfare Patrol Aircraft Operations
Source: Cost Considerations in Systems Analysis, G.H. Fisher, Rand, 1971
Conventional Jet Aircraft
Small Long-Endurance
Aircraft
Large Long-EnduranceAircraft
Figure 11 Options Analysis
Key program management activities in the Development Phase are:
Options analysis/feasibility studies to examine the capability levels that would beprovided by the options;
Cost estimates of both acquisition and life cycle support;
Assessment of industry capability in terms of technology, personnel and priorities;
Socio-economic21 and market studies;
Price and availability studies;
Refinement of the SOR;
Project Profile and Risk Assessment (PPRA)22 for large projects;
Shift of project leadership from sponsoring organization to the implementingorganization; and
Substantive estimate of the Definition Phase cost.23
21 Typically these are Industry Canada assessments of the project potential to generate Industrial Regional Benefits22 This is an assessment used by the Treasury Board Secretariat to determine how the project should be managed23 CFP 125, Chapter 7, Project Approval, a substantive estimate is one that is sufficiently accurate to support entering into contract
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
31/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 23
5.2.1.1 Define Business and Technical Requirements
Objective: To define, in terms suitable for contracting, the operationalrequirement or business case, and the technical description of the operational
need, including applicable portions of specifications and standards.
Process: The definition of technical requirements is an iterative process thatstarts with operations/user personnel describing their needs in a Statement ofOperational Requirements (SOR) or in a Business Requirements document. AStatement of Operational Objectives (SOO) may also be used to define theprimary performance, operational and support system objectives of theproject. This permits earlier contractor participation in defining performancespecifications. In general, requirement documents should state performanceor functional objectives rather than require design solutions.24
In this phase, the SOR or Business Requirements should be refined with user,
stakeholder, and potential supplier input. Potential suppliers will need keyoperations, system and support information to assist in providing input on theSOR or Business Requirements, and or to help in preparing or validatingspecifications. 25
Many departments now require business case methodology to obtain approvalfor any capital major expenditure. Preparation of the Business Case, inconjunction with the business requirements document is commonplace inInformation Technology projects. Figure 12 describes a business caseanalysis approach that can be used to establish and maintain a businessrequirements baseline for the project.
24 Canadian Government Procurement Guide, B.F. Hough, CSC.25 Canadian Government Procurement Guide, B.F. Hough, CSC.
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
32/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 24
BASELINE CURRENTPARAMETERS
IDENTIFYALTERNATIVES
FORMULATEASSUMPTIONS
2.
3.
4.
DETERMINEBENEFITS OF EACH
ALTERNATIVE
DETERMINECOSTS OF EACHALTERNATIVE
6.5.
COMPAREALTERNATIVES
PERFORMRISK ANALYSIS
MAKE
DECISION
IDENTIFYRISKS
8.7.
9.
10.
MAINTAINBUSINESS CASE
11.
DEFINEOBJECTIVES
1.
Figure 12 Business Case Analysis
The process of preparing a business case involves:
Define
Objectives
- Define the required capability.
BaselineCurrent
Parameters
- Record the life cycle costs and benefits/shortcomings of the existing situation to provide abaseline against which to measure future costs andbenefits.
Identify
Alternatives
- Identify viable alternatives. (This step is iterative main alternatives are addressed first, then sub-alternatives.) Collect, organize, evaluate andsummarize necessary data.
Formulate
Assumptions
- Identify important assumptions up front. (These
become evident as the business case is developed.)
Determine
Costs
- Identify and estimate life cycle costs for eachalternative. Perform crosscheck analysis to validateimportant data.
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
33/123
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
34/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 26
important to ensure adequate resources are available to the IPT to supportcontract management, for example, in the area of earned value management.
Output: The IPT defines and records in the PMP the project, risk and
contract management strategies that will be used in the contracting process.
Define Risk Management Strategy
Risk management is recognized by client departments as an important aspect of theacquisition process. A risk assessment is required as part of the project approval process.
Bidders are often required to identify significant risks and risk mitigation methods in their
proposals. Project implementation often involves preparation and implementation of a risk
management plan.27
Objective: To apply continuous risk management in the project procurement.
Process: Figure 13 illustrates the principles behind the Software Engineering
Institute (SEI) Continuous Risk Management model which has beenspecifically developed to apply to complex procurement projects, particularlyprojects involving significant design, development, and integration effort.These projects often involve risk to cost/schedule/performance objectives.Process, methods and tools that encourage communication and teamwork arepart of the full SEI model.
Source: SEI Continuous Risk Management Guidebook
COMMUNICATE
CON
TROL
IDEN
TIFY
ANALYZE
PLANCONTINGENCIES
TRA
CK
Figure 13 SEI Continuous Risk Management Model28
27 DND Acquisition Reform Guide, Team Leader G. Reinhardus; Author B.F. Hough.28 Continuous Risk Management Guide. Carnegie Melon University, Software Engineering Institute. Page 267.
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
35/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 27
The steps in the SEI Continuous Risk Management Model are:
Identify Risks- Search for and capture risks before they become
problems. Capture statement of risk and context.
Analyze Risk
Data
- Transform risk data into decision-makinginformation. Determine what is important and setpriorities. Evaluate impact, probability, andtimeframe; and, classify and prioritize risks.
Plan
Contingencies
- Translate risk information into decisions andmitigation plans and implementation.
Track Risks
and Responses
- Monitor risk indicators and mitigation plans/actions.
Acquire, compile and report data on risk mitigation.
Control
Mitigation
- Correct for deviations from the mitigation plans.Corrective actions impact process and product.Change plans as needed. Analyze tracking data andmake decisions.
Communicate - Provide information and feedback on current andemerging risks. This is the key function that linksand drives the others. Steps are iterative, and eachstep is a vehicle for the communication of risk.
Given that much of the project risk occurs within the procurement process, itis important that risk management is a continuous process. Figure 14indicates the some methods that can be used to identify and manage risks, anda short discussion of techniques follows the figure.
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
36/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 28
EXPERIENCE-BASED RISK MANAGEMENT
RISK IDENTIFICATION RISK ANALYSIS
Brainstorming
Structured Walk-Throughs
Problem Reporting
RISK TRACKING AND CONTROL CONTINGENCY PLANNING
Estimated Impact On:
Technical
Schedule
Cost
Socio-Economic Benefits Other
Technical Margins and Fallbacks
Slack in Schedule Contingency in Budget
Flexibility in Economic Benefits Risk Mitigation Planning
Risk Matrix in Bid
Risk Management Plan Risk Tracking Process
COMMUNICATION
Figure 14 Dealing with Risk29
Brainstorming is effective during early project planning. Whatproblems were experienced with similar projects? Are all stakeholderson side? Is the schedule overly optimistic? Is the state of the art being
exceeded?
Once a project plan has been developed, a structured walk-through ofproject information the work breakdown structure, critical pathmethod schedule, product breakdown structure, etc. can be used toidentify potential problem areas.
During project implementation, a problem reporting process should beestablished. Typically the government project manager and industrycounterpart can designate issues as risks to be entered into a problemtracking database. Each identified risk is assigned to someone, getwell plans are formulated and the risk is tracked to resolution.30
The project plan should include contingencies to allow for technical problems,work slippage, cost over-runs, and difficulties in accomplishing economicbenefits goals.
29 Systems Engineering Management, B.F. Hough, CSC.30DND Acquisition Reform Guide
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
37/123
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
38/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 30
Define Delivery and Acceptance Strategy
Objective: To develop and record the strategy for continuous monitoring,
including feedback and corrective action, of activities associated with deliveryand acceptance.
Process: The strategy should address all mechanisms that will be used tomonitor delivery and perform acceptance, for example:
Establishing credible product/service delivery and in-service dates
Preparing acceptance criteria for deliverables
Monitoring of contractor progress reports; master, support, and special
schedules; earned value data; and the effectiveness of related projectmanagement processes including change control;
Packaging, Handling, Support, Transportation (PHST) (e.g. hazardous
materials) planning; and
Expediting and follow-up on delivery status and delays, andunsatisfactory performance until final delivery.31
Output: Strategy prepared by the IPT and recorded in the PMP of allmechanisms that will be used to monitor delivery performance and performacceptance.
Define Quality Assurance Strategy
Objective: To develop and record the Quality Assurance Strategy that will be
used to monitor contractor performance. Process: Quality Assurance processes include the ISO 9,000, 10,000 and
14,000 series standards and guidelines, proprietary approaches (e.g. Deming,Juran, Crosby) and non-proprietary approaches such as Total QualityManagement (TQM) and Continuous Improvement.
Quality Assurance is typically a technical specialist function, and a subjectmatter expert should form part of the IPT and should lead the effort to definethis strategy. The strategy should address the following elements:
Quality Planning (identification of standards and tailoring);
Quality Assurance (ensuring project/contract activity meets standards);
and Quality Control (monitoring project/contract results for compliance,
and resolving unsatisfactory performance).32
31 BPR Team #1 Report.32 PMBOK. Quality Assurance.
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
39/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 31
With the cancellation by the US DoD of its military standards and the growinguse of international and commercial standards, it is becoming more difficult todefine quality and process related requirements. There are many competing
standards to choose from. Just staying informed about what standards exist,which are widely accepted, and what is the latest version, is a real challenge.Also, selection of any given set of standards may have unintended effects oncompanies ability to bid. This new challenge, highlighted in Figure 16,applies to quality assurance, engineering and logistics, and projectmanagement disciplines.
Output. Strategy prepared by the IPT and recorded in the PMP for QualityPlanning, Assurance and Control.
CHOOSING FROM A PLETHORA OF STANDARDS
- A NEW CHALLENGE IN PROCUREMENTINTERNATIONAL STANDARDS
INTERNATIONAL ASSOCIATION
AND INSTITUTIONS STANDARDS
PROPRIETARY
GUIDANCE
ISO 9,000 Series ISO 10,000 Series
ISO 14,000 Series
SEI - Capability Maturity Model
SEI - Continuous Risk Management
EIA - Configuration Management SAE - Failure Modes, Effects and
Criticality Analysis
IEEE - Systems Engineering
SOLE - Supportability
Deming
Juran
Crosby etc.
NON-PROPRIETARY
GUIDANCE Total Quality
Management
Continuous
Improvement
Figure 16 Choosing From a Plethora of Standards
Define Financial Management Strategy Objective: To develop and record the Financial Management Strategy that
will be used to monitor contractor performance.
Process: The strategy should address all mechanisms that will be used tomonitor delivery performance, for example:
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
40/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 32
Verify the time, cost elements and other factors charged to thecontract;
Ensure that contract billings are in accordance with contract
provisions; Ensure that the work is performed; that products and services have
been delivered, or (in the case of progress payments) that work inprogress is reasonable and payment is in accordance with contractprovisions;
Correlate progress and earned value status and projections with actualand planned billings;
Monitor time recording system and cost accounting system;
Monitor contractor financial and cost/schedule performance; and
Verify financial input to contract closeout.
Output: Strategy prepared by the IPT and recorded in the PMP formanagement of cash flow, funds, budget, payment, cost, price and ratedetermination, and performance management.
Define Government Furnished Resources (GFR) Strategy
Objective: To develop and document the GFR Strategy that will be used tomonitor contractor performance.
Process: GFR should be provided on an exception basis only whencontractors cannot provide the appropriate resources. Coordination of theprovision of GFR may impose significant administrative effort on the IPT.
The timeliness and quality of GFR delivery brings with it contract risk and theneed to track the availability of incoming/outgoing resources in order to avoidconsequential delays and cost growth. The strategy should address allmechanisms that will be used to manage the GFR, for example:
GFR requirements in the form of information, materials, testequipment, system assets and personnel;
Agreements in the form of loans or other formal agreements; and
Tracking mechanisms to coordinate resource movements, repairs,upgrades, and corrective action at operational units/supply locationsand contractor facilities.
Terms and Conditions that specify rights and obligations with regardto GFR.
Output: Strategy prepared by the IPT and recorded in the PMP for GFRmanagement.
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
41/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 33
Define Bid Solicitation Strategy
Objective: To develop and record the Bid Solicitation Strategy that will beused to solicit bids, evaluate proposals, select the winning contractor, and
negotiate an acceptable contract package.
Process: The strategy should address all mechanisms that will be used tomanage the bid solicitation, for example:
The main elements of the Solicitation Document (Certifications,Terms and Conditions, Statement of Work, Evaluation Criteria, Basisof Selection, Attached Documents);
The evaluation elements (e.g. Technical Proposal, Presentation andInterviews, Historical Performance and Risk Assessment, CostEvaluation);
The basis of selection (e.g. best price, best value, best technical)
The evaluation methodology (e.g. criteria, attributes, weighting,thresholds);
The evaluation plan (detailed process and scoring formats that thevaluation team uses);
Evaluation team (core members, subject matter experts, challengecommittee);
Debriefing unsuccessful bidders; and
Negotiation strategy and process.
Output: Strategy prepared by the IPT and recorded in the PMP for bid
solicitation.
Define Contract Administration Strategy
Objective: To develop and document the Contract Administration Strategythat will be used to administer the contract.
Process: The strategy should address all mechanisms that will be used toadminister the contract. Whereas contract management is concerned withperformance monitoring, contract administration deals with the day-to-dayadministration of the contract: verification and payment of claims/invoices;filing and data management; loan administration; and contract reporting.
Preparing for administration includes: Review of the procurement file to identify anticipated contract
provisions and preparation of a list of administrative functions;
Allocating contract administrative functions to various team members;
Providing notice and instructions to those involved in administration;
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
42/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 34
After contract award, ensuring the contractor is notified of personnel,roles and delegated authority, and having contractor counterpartsnamed with their authorities; and
Considering past performance and issues that have occurred with thecontractor in performing contract administration.33
It is important that all team members know their administrative roles. Some
redundancy may be desirable in key areas. However, duplication between IPTmembers should be avoided.
Output: Identification of contract management and administration functionsto be performed, and the resources necessary to perform them, prepared by theIPT and recorded in the PMP.
5.2.1.3 Define Scope of Contract(s)
Objective: To develop and record the strategy for Pre-Facilitated Contracting(PFC), designation as a Benefits Driven Procurement, Alternative ServiceDelivery, Total Package Procurement, or other scope alternatives.
Process: Dramatically different contract scopes are now available to choosefrom. Opportunities to bundle and establish pre-facilitated contracts are nowbeing examined across systems and commodity classes on an ongoing basis.However, new opportunities will occur as acquisitions move into a supportmode, and personnel are encouraged to exploit these opportunities in order tomove from repetitive transactions into higher value contracting activity.
Figure 17 presents four different contract scopes. Each of these approaches
involves establishing a long term relationship with the contractor. EarlyPWGSC participation in planning is essential.
Output: Strategy prepared by IPT for Pre-Facilitated Contracts (PFC),Benefits Driven Procurement (BDP) application of Total PackageProcurement (TPP), Alternative Service Delivery, or some other approach,recorded in the PMP.
33 BPR Team #1 Report.
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
43/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 35
CONTRACT SCOPE - CONSIDERATIONS
ALTERNATIVE SERVICE DELIVERY
Non-core services are competed between
industry and in-house provider
Costs are reduced for both retained and
contracted-out services
Logistics support is greatly simplified
BENEFITS DRIVEN PROCUREMENT
Contractor selection is based on
capability and track record
Contractor is brought in early before
requirements are fully defined
Government prepares statement ofobjectives in lieu of SOW/Specification
PRE-FACILITATED CONTRACTS
Related goods and services are bundled
Number of contracting transactions are
greatly reduced
Based on long term relationships with
competent supplier
TOTAL PACKAGE PROCUREMENT
Contract is for system and life cycle support
Basis of source selection is life cycle cost
Contractor guarantees reliability and bears cost
of excessive repairs/overhauls
Figure 17 Determining Contract Scope
5.2.1.4 Define Reporting Strategy
Objective: To develop and document the Reporting Strategy that will be usedto administer the contract.
Process: To define the format and content of contract management andadministration reports that will be required of the contractor. Care should betaken to minimize the reporting burden by tailoring required reports to thescope and complexity of the anticipated contract. Government and industryresources for oversight are limited, and it is important that reporting (indeedall contract data requirements), are reviewed before being specified in thecontract. Templates of Data Item Descriptions (DIDs) and Contract DataRequirements Lists (CDRLs) are often available from previous contracts,however each data item should be challenged as to its need and costeffectiveness.
Output: Strategy prepared by IPT and recorded in the PMP for contract andproject reporting.
-
7/28/2019 Modelo de Gesto de Projeto de Aquisio
44/123
PROJECT PROCUREMENT MANAGEMENT TEMPLATE
Public Works and Government Services Canada 36
5.2.1.5 Define Approval Strategy
Objective: To define and document the Approval Strategy.
Process: To define and document the approval strategy applicable to theprocurement. Unless appropriate approval lead time is planned for, theprocess can impose delays on the overall procurement time-line pushing outcontract award and contractor delivery dates. BPR has recommendedincreased delegation, and a simplified approval and reporting system,however, these recommendations apply to complex procurements withindepartmental approval limits. Many complex procurements will requireTreasury Board Approval because of the size and sensitivity of publicexpenditure involved.
Output: Strategy prepared by IPT and recorded in the PMP for procurementstrategy approval, and contract approval and signing authorities.
5.2.1.6 Define the Change Management Strategy
Objective: To define and document the change management strategy thatwill be u