nov. 9-11, 2004, las vegas, usa8th oecd/nea information exchange meeting on p&t1 r&d...
TRANSCRIPT
Nov. 9-11, 2004, Las Vegas, USA 8th OECD/NEA Information Exchange Meeting on P&T 1
R&D ACTIVITIES ON ACCELERATOR-DRIVEN TRANSMUTATION SYSTEM IN JAERI
Hiroyuki Oigawa, Kazufumi Tsujimoto,Kenji Kikuchi, Yuji Kurata, Toshinobu Sasa, Makoto Umeno, Shigeru Saito, Kenji Nishihara, Motoharu Mizumoto, Hideki Takano, and Nobuo Ouchi
Nov. 9-11, 2004, Las Vegas, USA 8th OECD/NEA Information Exchange Meeting on P&T 2
Contents
Design Study of ADS
R&D on Accelerator
R&D on Pb-Bi (LBE) Spallation Target and Coolant
R&D on Subcritical Reactor Physics
Transmutation Experimental Facility (TEF) in J-PARC Project Transmutation Physics Experimental Facility (TEF-P) ADS Target Test Facility (TEF-T)
Part of this work was funded by the Ministry of Education, Culture, Sports, Science and Technology (MEXT) as one of the R&D programs for innovative nuclear systems.
Nov. 9-11, 2004, Las Vegas, USA 8th OECD/NEA Information Exchange Meeting on P&T 3
JAERI’s Reference ADS
Primary pumpSteam generator
Proton beam
Inner barrelBeam duct
Beam windowReactor vesselCore barrel
Guard vessel
Core support structure
13.5m
11.8m
• Proton beam : 1.5GeV• Spallation target : Pb-Bi• Coolant : Pb-Bi
• Max. keff = 0.97
• Thermal output : 800MWt• MA initial inventory : 2.5t• Fuel composition :
(MA +Pu)Nitride + ZrN
Initial loading:
Zone-1: Pu/HM=30.0%
Zone-2: Pu/HM=48.5%• Transmutation rate :
10%MA / Year• 600EFPD, 1 batch
• Proton beam : 1.5GeV• Spallation target : Pb-Bi• Coolant : Pb-Bi
• Max. keff = 0.97
• Thermal output : 800MWt• MA initial inventory : 2.5t• Fuel composition :
(MA +Pu)Nitride + ZrN
Initial loading:
Zone-1: Pu/HM=30.0%
Zone-2: Pu/HM=48.5%• Transmutation rate :
10%MA / Year• 600EFPD, 1 batch
Nov. 9-11, 2004, Las Vegas, USA 8th OECD/NEA Information Exchange Meeting on P&T 4
Outline of the R&D Activities
3-year Program: Funded by MEXT for 2002-2004. Including SC-LINAC, LBE, and Reactor Design for Future Plant.
J-PARC: Phase-1 Accelerator is being constructed. TEF is in Phase-2 (after completion of Phase-1)
3-year Program3-year ProgramR&D for Future ADS without Proton Beam
J-PARCJ-PARCExperimental Program
using Proton Beam
Experimental ADS and Commercial Plant
Feasibility Assessment International
CollaborationCollaboration
in Japan
Nov. 9-11, 2004, Las Vegas, USA 8th OECD/NEA Information Exchange Meeting on P&T 5
Development of Superconducting LINACDevelopment of Superconducting LINAC
Development of Pb-Bi Target/CoolantDevelopment of Pb-Bi Target/Coolant
Development of Subcritical ReactorDevelopment of Subcritical Reactor
High Energy Accelerator Research Organization (KEK)
Mitsubishi Heavy Industries Ltd.
Mitsui Engineering and Shipbuilding Co. Ltd.
Mitsubishi Electric Corporation
Tohoku University
Japan Nuclear Cycle Development Institute (JNC)
Hokkaido University
Tokyo Institute of Technology
Nagoya University
Kyoto University Research Reactor Institute
Collaboration in Japan
Nov. 9-11, 2004, Las Vegas, USA 8th OECD/NEA Information Exchange Meeting on P&T 6
Design Study : Neutronics
0.94
0.95
0.96
0.97
0.98
0.99
1.00
0
5
10
15
20
0 1000 2000 3000 4000 5000 6000
Effe
ctiv
e m
ultip
licat
ion
fact
or :
kef
fB
eam current (m
A)
Operation time (EFPD)
Beam current
keff
Keff: 0.97 – 0.94 Maximum beam : 1.5 GeV x 18 mA = 27 MW
In this study, 30MW is adopted, though 20MW will be sufficient in the equilibrium cycle.
Keff: 0.97 – 0.94 Maximum beam : 1.5 GeV x 18 mA = 27 MW
In this study, 30MW is adopted, though 20MW will be sufficient in the equilibrium cycle.
Nov. 9-11, 2004, Las Vegas, USA 8th OECD/NEA Information Exchange Meeting on P&T 7
Design Study : Thermal-hydraulics(1) Spallation Target and Core Coolant
(2700)
1890
3390
1000
6450
1030
1390
9050
5250
1800
2000
ビーム導入管
ビーム保護管
内 筒
13700
(285)
4610φ
(2700)
1890
3390
1000
6450
1030
1390
9050
5250
1800
2000
ビーム導入管
ビーム保護管
内 筒
13700
(285)
4610φ
Core barrelCore regionReflector
Support structure
Coolant flow
Beam windowBeam ductProton beam
Target region
Beam duct support
Partition wallFlow control nozzle
Partition wall
Flow control nozzle
Optimization of design parameters:
Inlet temp. : 300 ºC
Beam duct : 45cm
Partition wall
Flow control nozzle
Optimization of design parameters:
Inlet temp. : 300 ºC
Beam duct : 45cm
30 MW proton beam with 1.5 GeV causes heat deposition of 15.7MW.
30 MW proton beam with 1.5 GeV causes heat deposition of 15.7MW.
Nov. 9-11, 2004, Las Vegas, USA 8th OECD/NEA Information Exchange Meeting on P&T 8
Design Study : Thermal-hydraulics (2) Analytical Results for Beam Window
(unit: Kelvin)
450oC
470oC
490oCOuter surfacetemperature
of beam window
(unit: m/s)
1.8m/s
0.2m/s
2.0m/s
• Maximum temperature of outer surface : 490 ºC • Flow control nozzle cools the bottom of the beam window effectively.
• Maximum temperature of outer surface : 490 ºC • Flow control nozzle cools the bottom of the beam window effectively.
Flow speed Temperature
Nov. 9-11, 2004, Las Vegas, USA 8th OECD/NEA Information Exchange Meeting on P&T 9
R&D on Accelerator : SC-LINAC
972 MHz Cryomodule
9-cell , (=0.725)He vessel : Ti (2K)Maximum surface electric field > 30 MV/m
Installed Cryomodule
Superconducting Cavity
Vacuum vessel
Liquid He vessel
Superconducting cavity (9-cell)
RF power coupler
4m
1.2m
Nov. 9-11, 2004, Las Vegas, USA 8th OECD/NEA Information Exchange Meeting on P&T 10
R&D on Accelerator : J-PARC(1) Site Plan
Transmutation Experimental Facility
3 GeV SynchrotronMaterial and LifeScience Facility
Nuclear Physics Facility
50 GeV Synchrotron(1500mL)
Neutrino Facility
500m
LINAC (350mL) Phase-1: 400 MeV Phase-2: 600 MeV
J-PARC : Japan Proton Accelerator Research Complex
Construction of Phase-1 : 2001-2007 (except for some parts)
Transmutation Experimental Facility and 600 MeV LINAC are in Phase-2.
Nov. 9-11, 2004, Las Vegas, USA 8th OECD/NEA Information Exchange Meeting on P&T 11
R&D on Accelerator : J-PARC(2) Status of Construction
11February, 2004
Feb. 2004
Nov. 9-11, 2004, Las Vegas, USA 8th OECD/NEA Information Exchange Meeting on P&T 12
Sep. 2003April 2004Sep, 2004
R&D on Accelerator : J-PARC(3) LINAC Building
Nov. 9-11, 2004, Las Vegas, USA 8th OECD/NEA Information Exchange Meeting on P&T 13
R&D on Accelerator : J-PARC(4) LINAC Beam Test
Beam test is under way at KEK/Tsukuba up to 20 MeV, 30mA.
It will be moved to JAERI/Tokai 2005.
Drift Tube LINAC( < 60 MeV)
RFQ ( < 3 MeV)
Nov. 9-11, 2004, Las Vegas, USA 8th OECD/NEA Information Exchange Meeting on P&T 14
R&D on LBE : Corrosion(1) Static Test
Ferrite : Corrosion film depends on the Cr content.
5%Si –added steel exhibited fine corrosion resistance.
JPCA
Si-added steel
Co
rro
sio
n D
epth
(m
)
0
20
40
60
80
100
0 5 10 15 20
FerriteAusteniteSi-added
Cr(wt%)
550 ºC, 3000 hr.Oxygen - saturated
20m
20m
Nov. 9-11, 2004, Las Vegas, USA 8th OECD/NEA Information Exchange Meeting on P&T 15
R&D on LBE : Corrosion(2) Loop Test
F82H (martensitic) and JPCA (austenitic) are being tested as candidate materials for beam window.
F82H (martensitic) and JPCA (austenitic) are being tested as candidate materials for beam window.
Expansion Tank
EM Pump
Test Section
Drain Tank
Air Cooler
JAERI Pb-Bi Loop-1 (JLBL-1) Flow rate : 5L/min. Temperature : 450ºC
MES Pb-Bi Loop Flow rate : 5L/min. Temperature : 500ºC
3000 hr. continuous operations were successfully completed.Test tubes were analyzed.
3000 hr. continuous operations were successfully completed.Test tubes were analyzed.
Nov. 9-11, 2004, Las Vegas, USA 8th OECD/NEA Information Exchange Meeting on P&T 16
R&D on LBE : Thermal-hydraulics at Beam Window
Heat transfer characteristics are being measured by changing flow rate (100-500 L/min.) and inlet temperature (330-430ºC) parametrically.
Heat transfer characteristics are being measured by changing flow rate (100-500 L/min.) and inlet temperature (330-430ºC) parametrically.
Block diagram
LBE Loop for Beam Window
LBE at Overflow Section
Circulation Pump
Flow Meter
Perforated Plate
Test VesselM
Fl
Heater
Nov. 9-11, 2004, Las Vegas, USA 8th OECD/NEA Information Exchange Meeting on P&T 17
R&D on LBE : Behavior of Radioactive Impurity
Production rate of Polonium (Po) in Pb-Bi was measured by irradiating Pb-Bi in JMTR. No large discrepancy was observed between the calculation and the measurement.
Evaporation rates of Tellurium (Te) from Pb-Bi were measured as a function of temperature to verify the experimental method.
Using the irradiated Pb-Bi, evaporation rates of Po is being measured.
Production rate of Polonium (Po) in Pb-Bi was measured by irradiating Pb-Bi in JMTR. No large discrepancy was observed between the calculation and the measurement.
Evaporation rates of Tellurium (Te) from Pb-Bi were measured as a function of temperature to verify the experimental method.
Using the irradiated Pb-Bi, evaporation rates of Po is being measured.
HeaterHeater
Ar gas
Sampling
Irradiated Pb-Bi
Po
HeaterTranspiration method
Pb-Bi irradiation capsule
Nov. 9-11, 2004, Las Vegas, USA 8th OECD/NEA Information Exchange Meeting on P&T 18
R&D on Subcritical Reactor Physics :
Uncertainty of reactor physics parameters are estimated by the sensitivity of nuclear data calculated by SAGEP code and the error files evaluated for JENDL-3.3. Preliminary analysis showed that the capture reaction of Am-241 has significant effect on k-eff.
Uncertainty of reactor physics parameters are estimated by the sensitivity of nuclear data calculated by SAGEP code and the error files evaluated for JENDL-3.3. Preliminary analysis showed that the capture reaction of Am-241 has significant effect on k-eff.
Fission CaptureNp-237 0.21% 0.25%Pu-239 0.25% 0.07%Pu-240 0.02% 0.03%Pu-241 0.04% 0.02%Am-241 0.14% 0.57%Am-243 0.07% 0.23%
Total 0.76%
Estimated uncertainty on k-eff of BOC of initial cycle
-0.1 0.0 0.1 0.2 0.3 0.4 0.5
Np-237Pu-238Pu-239Pu-240Pu-241Am-241
Am-242mAm-243Cm-244
ZrN-15
FePbBi
Sensitivity Coefficient
C FC
C
C
F
FF
F
F
F
F
C
C
C
C
C
E
E
E
II
I
C
Capture (C)Fission (F)Elastic scattering (E)Inelastic scattering (I)
Isotopes
I
(a) Beginning of 1st. cycle
-0.1 0.0 0.1 0.2 0.3 0.4 0.5
Np-237Pu-238Pu-239Pu-240Pu-241Am-241
Am-242mAm-243Cm-244
ZrN-15
FePbBi
Sensitivity Coefficient
C FC
C
C
F
FF
F
F
F
F
C
C
C
C
C
E
E
E
II
I
C
Capture (C)Fission (F)Elastic scattering (E)Inelastic scattering (I)
Isotopes
I
(a) Beginning of 1st. cycleSensitivity of Nuclear Data to k-eff at the beginning of initial cycle
Nov. 9-11, 2004, Las Vegas, USA 8th OECD/NEA Information Exchange Meeting on P&T 19
ADS Target Test Facility : TEF-T
ADS Target Test Facility : TEF-T
Critical Assembly
Pb-Bi TargetShield
200kW
10W
Laser Charge Exchange
Transmutation Physics Experimental Facility : TEF-P
Transmutation Physics Experimental Facility : TEF-P
Transmutation Experimental Facility (TEF)
Nov. 9-11, 2004, Las Vegas, USA 8th OECD/NEA Information Exchange Meeting on P&T 20
Proton beam
Fixed half assembly
Movable half assembly
Fuel loading machineMovable shield
Core
Safety/control rod drive mechanism
Max. power : ~ 500W, Max beam : ~10 W (~1012n/s)Experiments in critical state can also be performed.
Transmutation Physics Experimental Facility (TEF-P) :
Nov. 9-11, 2004, Las Vegas, USA 8th OECD/NEA Information Exchange Meeting on P&T 21
Liquid Target is contained in sealed-tube
Primary circuit devices are completely isolated
Safe and quick replacement is possible.
Material database can be established by changing irradiation conditions such as temperature, flow rates, beam intensity, oxygen concentration, etc.
Liquid Target is contained in sealed-tube
Primary circuit devices are completely isolated
Safe and quick replacement is possible.
Material database can be established by changing irradiation conditions such as temperature, flow rates, beam intensity, oxygen concentration, etc.
Irradiation samples
Protons
Target room
EM pump
EM flowmeter
Heat exchanger
He
Pb-Bi
ADS Target Test Facility (TEF-T):Double-annular Type Pb-Bi Target
Nov. 9-11, 2004, Las Vegas, USA 8th OECD/NEA Information Exchange Meeting on P&T 22
Check and Review (C&R) by Atomic Energy Commission will be necessary to start TEF.
Safety review is necessary for TEF-P before the construction and the manufacturing because it is a nuclear reactor facility.
R&Ds for TEF:TEF-P: Instrumentation, Laser charge exchangeTEF-T: Pb-Bi technology, Material irradiation effect
Fiscal Year2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
Milestone
J-PA
RC
LINAC
TEF
180MeV 400MeV
600MeV
▼Establishment of New Organization
C&R C&R▼Licensing of TEF-P
Construction Commissioning
Safety reviewTEF-P
TEF-TR&D, Design
Expected Schedule of TEF (Preliminary)
Nov. 9-11, 2004, Las Vegas, USA 8th OECD/NEA Information Exchange Meeting on P&T 23
Summary
Wide range of R&D activities on ADS for transmutation are in progress. Design Study of ADS (Neutronics, Thermal-hydraulics, Structure) Accelerator (SC-LINAC, J-PARC Project) Pb-Bi (LBE) (Corrosion, Thermal-hydraulics of Beam Window, Po) Subcritical Reactor Physics
Transmutation Experimental Facility (TEF) in J-PARC Project Transmutation Physics Experimental Facility (TEF-P) ADS Target Test Facility (TEF-T)
To initiate TEF project, supports from foreign colleagues are greatly appreciated.