oleh ir. sumihar simamora, cessibima.pu.go.id/pluginfile.php/53272/mod_resource/content/1... ·...
TRANSCRIPT
![Page 1: Oleh Ir. Sumihar Simamora, CESsibima.pu.go.id/pluginfile.php/53272/mod_resource/content/1... · konstruksi, dan life cycle cost. 2.a. Area kerja/penerapan VE ... Berapa biaya yg timbul(What](https://reader031.vdocuments.pub/reader031/viewer/2022022804/5c8f289809d3f2ec738c389a/html5/thumbnails/1.jpg)
Oleh
Ir. Sumihar Simamora, CES
![Page 2: Oleh Ir. Sumihar Simamora, CESsibima.pu.go.id/pluginfile.php/53272/mod_resource/content/1... · konstruksi, dan life cycle cost. 2.a. Area kerja/penerapan VE ... Berapa biaya yg timbul(What](https://reader031.vdocuments.pub/reader031/viewer/2022022804/5c8f289809d3f2ec738c389a/html5/thumbnails/2.jpg)
A. Pendahuluan Dasar Hukum :
Peraturan Menteri Pekerjaan Umum Nomor 45/PRT/M/2007 tentang Pedoman Teknis Pembangunan Bangunan Gedung Negara.
Halaman 74 : Dalam penyusunan VECP, pelaksana konstruksi secara in house, bagi yang memiliki tenaga ahli VE, atau bekerjasama dengan pemberi jasa keahlian VE, harus menggunakan metodologi yang sesuai dengan standar pelaksanaan studi VE yang lazim berlaku.
![Page 3: Oleh Ir. Sumihar Simamora, CESsibima.pu.go.id/pluginfile.php/53272/mod_resource/content/1... · konstruksi, dan life cycle cost. 2.a. Area kerja/penerapan VE ... Berapa biaya yg timbul(What](https://reader031.vdocuments.pub/reader031/viewer/2022022804/5c8f289809d3f2ec738c389a/html5/thumbnails/3.jpg)
A. Pendahuluan
dalam hal terjadi penghematan karena penggunaan VECP dalam rangka pemberian alternatif penawaran tersebut, pengaturan biaya hasil penghematan (H) adalah sebagai berikut : 60% dari H meningkatkan mutu dan/atau
menambah kegiatan pekerjaan konstruksi fisik 25% dari H tambahan biaya pemborong + VE 10% dari H tambahan biaya Konsultan
perencana 5% dari H tambahan konsultan MK
![Page 4: Oleh Ir. Sumihar Simamora, CESsibima.pu.go.id/pluginfile.php/53272/mod_resource/content/1... · konstruksi, dan life cycle cost. 2.a. Area kerja/penerapan VE ... Berapa biaya yg timbul(What](https://reader031.vdocuments.pub/reader031/viewer/2022022804/5c8f289809d3f2ec738c389a/html5/thumbnails/4.jpg)
KEMANFAATAN VALUE ENGINEERING
Menurunkan Biaya operasi (Lowering operation cost) Menurunkan Biaya pemeliharaan (Lowering maintenance cost) Memperbaiki Kualitas Pengelolaan (Improve quality
management) Meningkatkan efisiensi sumber daya (Improve resource
efficiency) Menyederhanakan prosedur (Simplify procedure) Meminimalkan paper work (Minimise paper work) Menurunkan biaya tenaga kerja (Lowering staffing cost) Mengoptimalkan skema pengembangan(Optimise scheme
expenditure) Meningkatkan kepuasan pelanggan (Satisfy customer) Mengembangkan penghargaan terhadap attitude (Develop value
attitude)
![Page 5: Oleh Ir. Sumihar Simamora, CESsibima.pu.go.id/pluginfile.php/53272/mod_resource/content/1... · konstruksi, dan life cycle cost. 2.a. Area kerja/penerapan VE ... Berapa biaya yg timbul(What](https://reader031.vdocuments.pub/reader031/viewer/2022022804/5c8f289809d3f2ec738c389a/html5/thumbnails/5.jpg)
2. Apa itu VE Value Engineering (VE, or Value Analysis) : Suatu
kajian teknis :
Mencari hubungan terbaik antara Cost, Reliability dan Kinerja
Dilaksanakan multi disiplin tim
Menggunakan rekayasa teknik untuk menghemat biaya yang tidak perlu
Menganalisa proyek dari sudut FUNGSI /COST
Menyiapkan usulan yang bisa memperbaiki kinerja, konstruksi, dan life cycle cost.
![Page 6: Oleh Ir. Sumihar Simamora, CESsibima.pu.go.id/pluginfile.php/53272/mod_resource/content/1... · konstruksi, dan life cycle cost. 2.a. Area kerja/penerapan VE ... Berapa biaya yg timbul(What](https://reader031.vdocuments.pub/reader031/viewer/2022022804/5c8f289809d3f2ec738c389a/html5/thumbnails/6.jpg)
2.a. Area kerja/penerapan VE
Disain Test Pabrikasi Konstruksi Operasi Pemeliharaan Data Piranti lunak Prosedur, spesifikasi dan praktek
savi
ng
waktu disain build O&M
![Page 7: Oleh Ir. Sumihar Simamora, CESsibima.pu.go.id/pluginfile.php/53272/mod_resource/content/1... · konstruksi, dan life cycle cost. 2.a. Area kerja/penerapan VE ... Berapa biaya yg timbul(What](https://reader031.vdocuments.pub/reader031/viewer/2022022804/5c8f289809d3f2ec738c389a/html5/thumbnails/7.jpg)
3. VE itu di domain Ekonomi
(ada 7 domain Value : ekonomi,politik, sosial, estetik, etika/moral, agama, dan judicial). VE hanya kita bahas dari ekonomi bukan yg lain.
Jika di domain ekonomi, maka :
COST VALUE Nilai produksi Ongkos produksi suatu komponen
EXCHANGE VALUE Nilai pertukaran Ongkos tukar suatu komponen
ESTEEM VALUE Nilai estim Nilai kemewahan suatu komponen
USE VALUE Nilai kegunaan Nilai kemanfaatan suatu komponen
![Page 8: Oleh Ir. Sumihar Simamora, CESsibima.pu.go.id/pluginfile.php/53272/mod_resource/content/1... · konstruksi, dan life cycle cost. 2.a. Area kerja/penerapan VE ... Berapa biaya yg timbul(What](https://reader031.vdocuments.pub/reader031/viewer/2022022804/5c8f289809d3f2ec738c389a/html5/thumbnails/8.jpg)
DALAM PEMBUATAN PRODUCT, PROCESS, SERVICE DAN SYSTEM
MINIMUM COST
MAXIMUM VALUE
1. PERFFORMANCE 2. QUALITY 3. RELIABILITY / MAINTAINABILITY 4. SAFETY
MEMPERTAHANKAN :
![Page 9: Oleh Ir. Sumihar Simamora, CESsibima.pu.go.id/pluginfile.php/53272/mod_resource/content/1... · konstruksi, dan life cycle cost. 2.a. Area kerja/penerapan VE ... Berapa biaya yg timbul(What](https://reader031.vdocuments.pub/reader031/viewer/2022022804/5c8f289809d3f2ec738c389a/html5/thumbnails/9.jpg)
B. Metodologi penyelenggaraan VE
V E melaksanakan empat pilar
FOCUS ON FUNCTION
STEP BY STEP APPROACH
EMPHASIS ON CREATIVITY
MULTI-DISCPLINARY TEAM APPROACH
![Page 10: Oleh Ir. Sumihar Simamora, CESsibima.pu.go.id/pluginfile.php/53272/mod_resource/content/1... · konstruksi, dan life cycle cost. 2.a. Area kerja/penerapan VE ... Berapa biaya yg timbul(What](https://reader031.vdocuments.pub/reader031/viewer/2022022804/5c8f289809d3f2ec738c389a/html5/thumbnails/10.jpg)
B1. FOCUS ON FUNCTION What is the Function of a hammer?
Hanya untuk memaku paku ditambah fungsinya: Mencabut paku
PONDASImemikul seluruh beban dan menyalurkannya ke tanah
Apa Fungsi pondasi?
Bentuk Pondasi: • Pondasi dangkal • Pondasi dalam
![Page 11: Oleh Ir. Sumihar Simamora, CESsibima.pu.go.id/pluginfile.php/53272/mod_resource/content/1... · konstruksi, dan life cycle cost. 2.a. Area kerja/penerapan VE ... Berapa biaya yg timbul(What](https://reader031.vdocuments.pub/reader031/viewer/2022022804/5c8f289809d3f2ec738c389a/html5/thumbnails/11.jpg)
B2. STEP BY STEP APPROACH
1. Tahap orientasi (Orientation phase)
2. Tahap informasi (Information phase)
3. Tahap fungsi (Function phase)
4. Tahap kreativitas (Creativity phase)
5. Tahap evaluasi (Evaluation phase)
6. Tahap rekomendasi (Recommendation phase)
7. Tahap implementasi (Implementation phase)
8. Tahap Audit (Audit phase)
![Page 12: Oleh Ir. Sumihar Simamora, CESsibima.pu.go.id/pluginfile.php/53272/mod_resource/content/1... · konstruksi, dan life cycle cost. 2.a. Area kerja/penerapan VE ... Berapa biaya yg timbul(What](https://reader031.vdocuments.pub/reader031/viewer/2022022804/5c8f289809d3f2ec738c389a/html5/thumbnails/12.jpg)
1. ORIENTATION PHASE
VE AWARENESS perlu kesadaran bahwa sumber daya terbatas bahan
lokal
PROJECT SELECTION Unnecessary Cost dan poor valuepeluang
menggunakan bahan dan metode lain
TEAM SELECTION Multi disiplin
Mencari proyek yg memberi peluang untuk di VE
Perlu tahu informasi harga satuan : • Bangunan gedung • Per satuanpekerjaan
![Page 13: Oleh Ir. Sumihar Simamora, CESsibima.pu.go.id/pluginfile.php/53272/mod_resource/content/1... · konstruksi, dan life cycle cost. 2.a. Area kerja/penerapan VE ... Berapa biaya yg timbul(What](https://reader031.vdocuments.pub/reader031/viewer/2022022804/5c8f289809d3f2ec738c389a/html5/thumbnails/13.jpg)
TECHNICAL DATAkumpulkan data teknis SPECIFICATIONSpelajari peluang perbaikan spek DRAWINGSkumpulkan gambar MATERIAL & PROCESSING COSTpelajari harga bahan
dan pembuatan bahan PROCESS SEQUENCE FLOW CHARTpelajari prosedur
pembuatan SCRAP OR WASTAGES REJECTIONS VENDOR DETAILS COMPLAINTS RECEIVED MANAGEMENT REQUIREMENTS
2. INFORMATION PHASE
![Page 14: Oleh Ir. Sumihar Simamora, CESsibima.pu.go.id/pluginfile.php/53272/mod_resource/content/1... · konstruksi, dan life cycle cost. 2.a. Area kerja/penerapan VE ... Berapa biaya yg timbul(What](https://reader031.vdocuments.pub/reader031/viewer/2022022804/5c8f289809d3f2ec738c389a/html5/thumbnails/14.jpg)
3. FUNCTION PHASE
Contoh : Apa Fungsi sebuah Palu ?
Apa itu palu (What is IT ?) Apa tugas palu (What does it DO ?) Apa fungsi palu (What are the FUNCTIONS?) Berapa biaya yg timbul(What does it COST ?) Apa ada yg dapat melakukan tugas /fungsi itu
(What else will do this JOB) dan berapa biaya nya (What does It COST)
![Page 15: Oleh Ir. Sumihar Simamora, CESsibima.pu.go.id/pluginfile.php/53272/mod_resource/content/1... · konstruksi, dan life cycle cost. 2.a. Area kerja/penerapan VE ... Berapa biaya yg timbul(What](https://reader031.vdocuments.pub/reader031/viewer/2022022804/5c8f289809d3f2ec738c389a/html5/thumbnails/15.jpg)
4. CREATIVE PHASE
Secara kreatif mencari alternatif-alternatif untuk menghasilkan
FUNGSI tanpa melibatkan pertimbangan.
(FIND ALTERNATIVES OF ACHIEVING THE FUNCTION
WITHOUT ANY JUDGEMENT)
5. EVALUATION PHASE Libatkan pertimbangan dalam pengambilan alternatif terbaik
(APPLY JUDGEMENT FOR RIGHT ALTERNATIVE)
BY • PAIRED COMPARISON MATRIX • DECISION MATRIX
![Page 16: Oleh Ir. Sumihar Simamora, CESsibima.pu.go.id/pluginfile.php/53272/mod_resource/content/1... · konstruksi, dan life cycle cost. 2.a. Area kerja/penerapan VE ... Berapa biaya yg timbul(What](https://reader031.vdocuments.pub/reader031/viewer/2022022804/5c8f289809d3f2ec738c389a/html5/thumbnails/16.jpg)
6. RECOMMENDATION PHASE
Sajikan hasil studi VE kepada pemilik proyek
7. IMPLEMENTATION PHASE
8. AUDIT PHASE
Pantau PELAKSANAAN HASIL VE
AUDIT LAH HASIL VE TERHADAP PELAKSANAAN VE
![Page 17: Oleh Ir. Sumihar Simamora, CESsibima.pu.go.id/pluginfile.php/53272/mod_resource/content/1... · konstruksi, dan life cycle cost. 2.a. Area kerja/penerapan VE ... Berapa biaya yg timbul(What](https://reader031.vdocuments.pub/reader031/viewer/2022022804/5c8f289809d3f2ec738c389a/html5/thumbnails/17.jpg)
B3. EMPHASIS ON CREATIVITY
What can we ADD to an object TO IMPROVE IT ? What can we SUBTRACT TO IMPROVE IT ? Can we RE-ARRANGE TO IMPROVE IT ? Can we MAGNIFY THE OBJECT ? What is THE OPPOSITE OF THE OBJECT ? Does the object have OTHER USES ? Can we REDUCE THE SIZE ? What are the ALTERNATIVE WAYS ?
![Page 18: Oleh Ir. Sumihar Simamora, CESsibima.pu.go.id/pluginfile.php/53272/mod_resource/content/1... · konstruksi, dan life cycle cost. 2.a. Area kerja/penerapan VE ... Berapa biaya yg timbul(What](https://reader031.vdocuments.pub/reader031/viewer/2022022804/5c8f289809d3f2ec738c389a/html5/thumbnails/18.jpg)
B4. MULTI-DISCPLINARY TEAM APPROACH
Production Maintenance Engineering Service Purchase Finance Any other
![Page 19: Oleh Ir. Sumihar Simamora, CESsibima.pu.go.id/pluginfile.php/53272/mod_resource/content/1... · konstruksi, dan life cycle cost. 2.a. Area kerja/penerapan VE ... Berapa biaya yg timbul(What](https://reader031.vdocuments.pub/reader031/viewer/2022022804/5c8f289809d3f2ec738c389a/html5/thumbnails/19.jpg)
A SACRIFICE OF QUALITY
A CRASH COST REDUCTION METHOD
A ONE TIME GIMMICK
A MONOPOLY OF ONE
A CRITICISM OF EXISTING DESIGN,
PROCESS, METHOD OR SYSTEM
ROUTINE ACTIVITIES
![Page 20: Oleh Ir. Sumihar Simamora, CESsibima.pu.go.id/pluginfile.php/53272/mod_resource/content/1... · konstruksi, dan life cycle cost. 2.a. Area kerja/penerapan VE ... Berapa biaya yg timbul(What](https://reader031.vdocuments.pub/reader031/viewer/2022022804/5c8f289809d3f2ec738c389a/html5/thumbnails/20.jpg)
Bentuk-bentuk yang umum: Review bahankesulitan bahan bangunan Review disain pondasiperbaikan pondasi kesulitan alat pancang
Review bekistingpenggunaan bekisting : U shapebalok Pelat betonpelat lantai Baja bondexbekisting pelat Bekisting convensionalbekisting sewa Bangun Kantor konvensionalsewa
Review Strukturpre stress Review metode kerjaKonvensional/pre fab/top
down/up and down
![Page 21: Oleh Ir. Sumihar Simamora, CESsibima.pu.go.id/pluginfile.php/53272/mod_resource/content/1... · konstruksi, dan life cycle cost. 2.a. Area kerja/penerapan VE ... Berapa biaya yg timbul(What](https://reader031.vdocuments.pub/reader031/viewer/2022022804/5c8f289809d3f2ec738c389a/html5/thumbnails/21.jpg)
Thank you See you for next session