oxyfuel and chemical looping and lessons learned from demos
TRANSCRIPT
1
Oxy, Chemical Looping , and Lessons from
Capture Demonstrations
Robert Hilton Robert Hilton Energy, Inc. June 14, 2016
Why Oxy-Combustion? Typical CoE for Generation
from Low Carbon Technologies
ü With other CCS & other low carbon generation
• Environmentally-friendly: ü Near Zero Emissions
ü No new chemicals introduced to plant
ü High CO2 capture rates (>90%) ü No constraints anticipated for large commercial units up to 1000 MWe, high efficiency with ultra-supercritical steam cycles
• Cost competitive: ü With other CCS & other low carbon generation
• Environmentally-friendly: ü Near Zero Emissions ü No new chemicals introduced to plant ü High CO2 capture rates (>90%)
Typical CoE for Post & Oxy CCS Technologies
Source : GE analysis – 2013 – New PC power plants with CCS including transport and storage . NEurope
3
Large Pilot Plants
Demonstration
Full-Scale
2008
2018/2019
Oxy-Combustion Roadmap--Combustion Technology
Lab Scale
1990s
<3 MWth
15- 30 MWth
150- 400 MWe
600-1100 MWe
Reference Design Studies
Modeling & Tool Dev.
2012
4
First oxy pilot plant with complete train for CO2 separation and capture
• GE supplied the Boiler, ESP and other components of the flue gas path
• Technology Partnership with Vattenfall to advance of the Oxyfuel technology
Operation started September 2008 • Very successful – operated extensively
and reliably
• Tests with two lignites (low/high sulfur)
• Test phases with GE Burners (Design A+B) finished
• Detailed performance data and operational experience
30 MWth Oxy-Combustion Pilot Plant at Vattenfall’s Schwarze Pumpe station, Germany
GE Oxy-boiler
GE Oxy-burner
5
15 MWth Oxyfuel Pilot Plant GE Labs, Windsor, CT, USA
Comprehensive Program: • 5 Years (Sept. 2008 – April 2014) • ~21.5 MUSD
Large Pilot Completed: • Evaluated the impacts of different oxy
process options and boiler design parameters • Detailed perfromance data (combustion, heat
transfer, pollutant emissions, deposition, corrosion …)
• Coals tested (Low S Bit (WV), High S Bit (IL), Sub-bit (WY), Lignite (ND, DE)
• Evaluated, improved, and validated engineering and computational tools
Scale-Up Completed: • Development of design guidelines • Large-scale Reference Designs • Demonstration Design • Ready for large demonstration
Oxy-Combustion Pilot with AQCS & GPU – Alstom, Windsor, CT, USA
NDIC
6
Oxy-PC Pilot Testing - Optimized Integration with Boiler, AQCS, FGC, and GPU
ESP at Schwarze Pumpe Oxy Pilot
NID™Dry Flue Gas Desulfurization
Wet Flue Gas Desulfurization
Flue Gas Condenser
Mobile Pilot Gas Processing Unit
7
Oxy-firing Integrated Approach Reference concept with integration
Design Basis • Oxy-Combustion Power Plant 900 MW
Steam Cycle: 600°C / 620°C / 275 bar • Bituminous Coal • Direct cooling (power plant, ASU, GPU) • 90% CO2 Capture - Specification for Storage • Base load operating regime • Flexibility in oxy-mode down to 40%
Estimated Plant Performance Net Eff. (LHV) Net Output
Conventional Air-Fired Plant (No Capture) 46.2% 836 MW Oxy Capture Plant - Not Integrated 34.0% 618 MW Oxy Capture Plant - Integrated 37.1% 673 MW
9
OXY- Two Major Commercial Scale Projects
• FutureGen 2.0 • Retrofit of existing plant- 160 MW
• State Of Illinois
• White Rose • New 462 MW plant
• United Kingdom
• Both full Projects through to sequestration
10
WhiteRoseSite
Alstom Drax
ProjectPromoters
National Grid
Oxy-combus+onPowerPlant&CO2Capture
CO2Transporta+on&Storage
BOC
Loca+on:DraxPowerSta+on,Selby,NorthYorkshire,UK
Drax will no longer be an equity partner but will supply existing infrastructure and operations
Summary: • Largest Oxy-Combustion CCS project worldwide: c.a. 450 MWe (gross)
• New ultra-supercritical coal-fired power plant with full stream treatment
• Biomass co-firing : zero - or near zero - CO2 emissions
• CO2 Transport and offshore Storage network by National Grid
• 90% CO2 capture-rate
White Rose OPP Demonstration Project
13
• Heat integration serves two purposes:
− Cooling for ASU compressor intercoolers
− Transferring this heat to the water steam cycle
• Several option studied pre-FEED and during FEED
• After the condensate pumps the flow is divided in two:
~70% to the LP heaters ~30% to the ASU
exchangers • heated from ~30°C
to 130°C • Turbine extraction steam
flow is reduced • Selected option recovers
up to 40 MW thermal
White Rose OPP Demonstration Project USC OPP & Heat Integration with ASU
14
White Rose OPP Demonstration Project Oxy Boiler Design Features
Specifications • 448 MWe gross • Ultra-Supercritical, sliding pressure
with spiral wall evaporator • USC – 265/52 bar, 600/620°C • Direct pulverized coal firing, Tilting-
tangential firing system
Design Fuel • Range of Bituminous Coals • Locally sources biomass
Operation • Dual 100% Air / 100% Oxy • Cycling load operation • Min. Load 25%
15
Full-Chain CCS Project
GOOLE
YORK
HULL
SELBY
MARKET WEIGHTO
N
DRIFFIELD
BRIDLINGTON
CO2 Store: 5/42
Offshore Platform
CO2 Pipeline
Oxy-Power Plant
Not to scale
Where Are We Now?
• Both projects are ended without any construction • Both worked through FEED Studies • Permits were substantially in place • FutureGen failed to reach Financing Close and
full contract commitments • White Rose had Financing lined up and contracts
set • Both governments withdrew support for different
reasons 17
Lessons Learned
• “It ain’t over till it is over” • Technology risk is always key to secure financing • Ownership of the project must ultimately take the
risk • First of a kind projects need governmental
support- full and permanent commitment • Schedules must accommodate uncertainty,
permitting, and public participation
18
A Comparison of Projects
• Moving Forward Projects • Parrish, Kemper, and Sask
• Owners have assumed the risk and are the principal beneficiaries
• Projects Stopped • FutureGen, White Rose, TECP, HECA, Leucadia
• Developers and /or Consortiums
• All ended for either failure to accommodate risk/wrap guarantees or schedule delivery or political commitment
19
State of the Technology
• Two Major Efforts • GE
• Completed two 3 MW pilots
• Calcium based in Windsor Connecticut
• Metal Based at Chalmers University in Germany
• Ohio State and B&W • Pilot at OSU
• 1 MW at the NCCC
22