parth belani
TRANSCRIPT
-
8/17/2019 Parth Belani
1/83
SUMMER INTERNSHIP REPORT ON
DETAILED PROCEDURE
AND
FINANCIAL MODELING
FOR DEVELOPMENT OF A GREEN FIELD WIND POWER
PROJECT
UNDER THE GUIDANCE OF
Mrs Sreelata Nilesh, Senior Fellow, CAMPS, NPTI
&
Mr Rajat Roy, Dy. Manager, Ecoren Energy India Pvt Ltd
At
Ecoren Energy India Pvt Ltd
Submitted by
PARTH BELANI
ROLL NO: 1120812204
MBA (POWER MANAGEMENT)
(Under the Ministry of Power, Govt. of India)
Affiliated to
MAHARSHI DAYANAND UNIVERSITY, ROTHAK
AUGUST 2012
-
8/17/2019 Parth Belani
2/83
ii
TRAINING COMPLETION CERTIFICATE
-
8/17/2019 Parth Belani
3/83
iii
DECLARATION
I, Parth Belani, Roll no. 1120812204, student of MBA (Power Management) at National
Power Training Institute, Faridabad, hereby declare that the summer training report
programme of the National Power Training Institute, Faridabad hereby declare that the
Summer Training Report entitled –
“DETAILED PROCEDURE AND FINANCIAL MODELING FOR DEVELOPMENT OF A
GREEN FIELD WIND POWER PROJECT”
Is an original work and the same has not been submitted to any other Institute for the award
of any other degree.
A Seminar presentation of the Training Report was made on ……………….. and the
suggestions as approved by the faculty were duly incorporated.
Presentation In charge Signature of the
Candidate (Faculty)
Countersigned
Director/Principal of the Institute
-
8/17/2019 Parth Belani
4/83
iv
ACKNOWLEDGEMENT
I express my sincere thanks to Mr Rajat Roy (Business Development Manager), Ecoren
Energy India Private Limited for giving me a great opportunity to work in such an esteem
organization. I am solemnly thankful to Mr Rakesh Patel (Business Analyst), Ecoren Energy
India Private Limited for his guidance and support. I am also thankful to the entire staff of,
Ecoren Energy India Private Limited for sharing their knowledge and assistance.
I feel deep sense of gratitude towards Mr J.S.S. RAO, Principal Director, CAMPS (NPTI),
Mr S. K. Chaudhary, Principal Director, CAMPS, Mrs Indu Maheshwari, Dy. Director,
NPTI and Mrs Manju Mam, Dy. Director, NPTI, Dr Rohit Verma, Dy. Director, NPTI for
arranging my internship at Ecoren Energy India Private Limited. I also take this opportunity
to express my sincere thanks to Mrs Sreelata Nilesh (Senior Fellow), NPTI for being my
internal project guide and providing valuable inputs in the completion of this project.
.
-
8/17/2019 Parth Belani
5/83
v
EXECUTIVE SUMMARY
In April 2012 Indian power sector reached a tremendous milestone of achieving 2,00,000
MW of total installed power capacity. Commencing with a meagre installed capacity of about1360 MW in 1947, the year the country attained independence, India’s power sector grew
substantially over the last six and a half decades, and the installed capacity at the end of June
2012 stands at 2,05,340 MW. However contribution of renewable power is 24,833 MW,
which is only 12.1% of the total installed capacity. Further, the Government of India desires
to significantly improve the country's annual per capita consumption. The government has
not been successful in its efforts to achieve per capita consumption of 1000 units and to
ensure a minimum lifeline consumption of 1 unit per household per day as a merit good by
the year 2012. In order to achieve this scale of supply and ensure sufficient electricity to all at
reasonable rates, it is necessary to explore all possible options of generating and supplying
electricity.
Renewable energy sources can make important contributions to sustainable development.
Currently, their exploitation in commercial markets is low, mainly because of high cost and
technological constraints. Most renewable energy technologies are still at an early stage of
development. However wind power, compared to other renewable energy sources, has lower
costs and improved technology. Development of wind power projects, therefore, is a key to
India’s future economic growth looking at the benefits of wind energy and the energy deficit
the country is facing today. Nevertheless, investors’ lack of interest in wind energy sector is
conspicuous because of lack of procedural understanding of development of wind power
projects.
The need for defining an effective and comprehensive wind power project implementation
methodology for India is imperative. Not only there are growing uncertainties about the
critical as well as sub critical activities of wind power projects implementation, but the
information associated with them is meagre and highly dispersed in nature and is not easily
available. Insufficient information may lead to misleading decisions by project developers
and investor’s. Many wind power project investments are not implemented, not because of
financial, technical, commercial, managerial or regulatory aspects, but merely because of
procedural complexities and inadequate guidelines about them.
-
8/17/2019 Parth Belani
6/83
vi
Therefore this study is intended to explicate a generalized methodology for wind power
project implementation. This methodology will act as a source of knowledge for wind energy
power project implementation to the stakeholders of the Indian power sector.
This report includes all the major steps that are required to take for putting in place a wind
power project. It starts with project and financial planning procedure followed by factors that
need to be taken into consideration for selecting a state of preference. The project then guides
about feasibility study, wind resource assessment, site survey, micro-siting, land acquisition,
financial planning & strategy, and power sale options. The project also includes financial
modelling that can help the investor in his decision of whether to accept or reject the project.
-
8/17/2019 Parth Belani
7/83
vii
LIST OF ABBREVIATIONS
CDM Clean Development Mechanism
CPV Concentrated Photo Voltaic
CEA Central Electricity Authority
CERC Central Electricity Regulatory Commission
CUF Capacity Utilization Factor
IEGC Indian Electricity Grid Code
KWh Kilo Watt Hour
MNRE Ministry of New and Renewable Energy
MoP Ministry of Power
MW Megawatt
NLDC National Load Despatch Centre
NOC No Objection Certificate
O&M Operation & Maintenance
PLF Plant Load Factor
PPA Power Purchase Agreement
RE Renewable Energy
REC Renewable Energy Certificate
RET Renewable Energy Technology
RPO Renewable Purchase Obligation
SERC State Electricity Regulatory Commission
SHP Small Hydro Plant
SLDC State Load Despatch Centre
SNA State Nodal Agency
-
8/17/2019 Parth Belani
8/83
viii
LIST OF TABLES
Table 1 : State wise Wind Power Till 2020 .......................................................................... 17
Table 2 : State Feed-in-Tariffs ............................................................................................. 18
Table 3 : Sharing of CDM Benefits in Different States ........................................................ 23
Table 4 : Reactive Energy Charges ...................................................................................... 23
Table 5 : State wise Banking Regulations ............................................................................ 24
Table 6 : State wise Transmission and Wheeling Charges ................................................... 25
Table 7 : REC Floor and Forbearance Prices of REC ........................................................... 44
-
8/17/2019 Parth Belani
9/83
ix
LIST OF FIGURES
Figure 1 : Financial Planning Process .................................................................................. 15
Figure 2 : Wind Power Potential and Installed Capacity ...................................................... 16
Figure 3 : State wise Achievable wind Potential Till 2020 ................................................... 17
Figure 4 : Feed-in-Tariff...................................................................................................... 18
Figure 5: Feasibility Study .................................................................................................. 27
Figure 6 : CDM Timeframe ................................................................................................. 40
Figure 7 : CDM Project Cycle ............................................................................................. 41
Figure 8 : REC Procedure.................................................................................................... 44
Figure 9 : REC Mechanism ................................................................................................. 45
Figure 10 : Hurdles in Financial Closure ............................................................................. 51
Figure 11 : Power Sale Options ........................................................................................... 53
Figure 12 : Parameters of Financial Modelling .................................................................... 59
Figure 13 : Cost Estimate per Project Phase ........................................................................ 60
Figure 14 : Project Cash-flow and Key Indicators................................................................ 62
Figure 15 : Types of Risk in Various Phases of Project........................................................ 63
http://d/university%20final%20report/MAIN%20REPORT.docx%23_Toc334424803http://d/university%20final%20report/MAIN%20REPORT.docx%23_Toc334424803
-
8/17/2019 Parth Belani
10/83
x
Table of Contents
TRAINING COMPLETION CERTIFICATE ................................................................................................ ii
DECLARATION .................................................................................................................................. iii
ACKNOWLEDGEMENT ...................................................................................................................... iv
EXECUTIVE SUMMARY ....................................................................................................................... v
LIST OF ABBREVIATIONS ...................................................................................................................vii
LIST OF TABLES ................................................................................................................................ viii
LIST OF FIGURES ................................................................................................................................ix
Table of Contents .............................................................................................................................. x
CHAPTER 1: INTRODUCTION .............................................................................................................. 1
1.1 About the project..................................................................................................................... 11.2 Problem Statement .................................................................................................................. 2
1.3 Scope of Project ....................................................................................................................... 2
1.4 Objective of the project ........................................................................................................... 2
1.5 Methodology ........................................................................................................................... 2
1.6 About the organisation ............................................................................................................ 3
1.6.1 Critical Assessment of the Organization............................................................................. 4
CHAPTER 2: LITERATURE REVIEW AND POLICY FRAMEWORK ............................................................. 5
2.1 Literature Review ..................................................................................................................... 5
2.2 Policy Framework .................................................................................................................. 10
2.2.1 National Electricity Policy, 2005 ...................................................................................... 10
2.2.2 National Tariff Policy, 2006.............................................................................................. 10
2.2.3 Rural Electrification Policy, 2006 ..................................................................................... 11
CHAPTER 3: WPP DEVELOPMENT PROCEDURE ................................................................................ 12
3.1 Introduction - Wind Power Project development procedure .................................................. 12
3.2 Project and Financial Planning................................................................................................ 13
3.2.1 Project Planning .............................................................................................................. 13
3.2.2 Financial Planning ........................................................................................................... 13
3.3 Selection of State of preference ............................................................................................. 16
3.3.1 Wind Power Potential and Installed Capacity .................................................................. 16
3.3.2 Feed-in-Tariffs ................................................................................................................. 17
3.3.3 Special incentives and facilities by State Governments .................................................... 18
3.3.4 Simplicity of procedures followed in the State ................................................................. 20
3.3.5 Evacuation Infrastructure ................................................................................................ 21
-
8/17/2019 Parth Belani
11/83
xi
3.3.6 Grid availability ............................................................................................................... 22
3.3.7 Regularity in the receipt of payment ............................................................................... 22
3.3.8 Sharing of CDM Benefits.................................................................................................. 22
3.3.9 Reactive Energy Charges ................................................................................................. 23
3.3.10 Banking ......................................................................................................................... 24
3.3.11 Transmission and wheeling charges............................................................................... 25
3.4 Site Identification ................................................................................................................... 25
3.5 Feasibility Study ..................................................................................................................... 26
3.5.1 Generalized activities for feasibility study of Wind Power Projects: ................................. 27
3.6 Mast Installation, Data Collection and Data Verification ......................................................... 31
3.6.1 Permission for Mast Installation and Subsequent Capacity Allocation ............................ 31
3.6.2 Installation of Wind Mast ................................................................................................ 33
3.6.3 Data collection ................................................................................................................ 33
3.6.4 Validation of Data through CWET .................................................................................... 34
3.7 Site Survey ............................................................................................................................. 34
3.7.1 Soil / Ground Conditions ................................................................................................. 34
3.7.2 Soil Erosion ..................................................................................................................... 34
3.7.3 Accessibility .................................................................................................................... 35
3.7.4 Closeness to Grid ............................................................................................................ 35
3.8 Wind Farm Layout.................................................................................................................. 36
3.8.1 Inter-turbine separation .................................................................................................. 36
3.8.2 Changes in elevation of area ........................................................................................... 37
3.8.3 Other factors ................................................................................................................... 37
3.8.4 Layout using software ..................................................................................................... 37
3.9 Land acquisition ..................................................................................................................... 37
3.10 Clean Development Mechanism ........................................................................................... 403.10.1 CDM project cycle ........................................................................................................ 41
3.11 Renewable Energy Certificates ............................................................................................. 43
3.11.1 Types of REC ................................................................................................................. 44
3.11.2 The operational framework for REC mechanism ............................................................ 44
3.12 Detailed Project Report ........................................................................................................ 47
3.12.1 Contents to be covered in a DPR ................................................................................... 48
3.13 Financing Strategy and Financial Closure .............................................................................. 49
3.13.1 Financing strategy ......................................................................................................... 49
-
8/17/2019 Parth Belani
12/83
xii
3.13.2 Financial Closure ........................................................................................................... 50
3.14 Power Sale options .............................................................................................................. 53
3.15 Physical implementation of the Project ................................................................................ 54
3.15.1 Engineering ................................................................................................................... 54
3.15.2 Procurement ................................................................................................................. 55
3.15.3 Construction ................................................................................................................. 55
3.15.4 Testing and Commissioning ........................................................................................... 57
3.15.5 Operation and Maintenance ......................................................................................... 58
CHAPTER 4: FINANCIAL MODELLING ................................................................................................ 59
4.1 Cost estimates ....................................................................................................................... 59
4.2 Development of a project model ........................................................................................... 60
4.3 Analysis of financial indicators ............................................................................................... 61
4.4 Sensitivity Analysis ................................................................................................................. 62
4.5 Risk analysis ........................................................................................................................... 63
4.5.1 Assessing risk .................................................................................................................. 63
4.5.2 Managing Risk ................................................................................................................. 64
CHAPTER 5: SUMMARY.................................................................................................................... 65
5.1 Conclusion ............................................................................................................................. 65
5.2 Recommendations ................................................................................................................. 67
Bibliography .................................................................................................................................... 69
ANNEXURES .................................................................................................................................... 71
-
8/17/2019 Parth Belani
13/83
1
CHAPTER 1: INTRODUCTION
1.1 About the project
In April 2012 Indian power sector crossed a remarkable milestone of crossing 200000 MW of
total installed capacity. On 30th June 2012, the country’s total installed power capacity stood
at an enormous figure of 205340.26 MW, out of which total renewable energy was 24832.68
MW. The share of Wind energy in Renewable energy produced in India is very high at 70%.
Still, India’s goal of ‘energy security’ is far from achieved. India has peak demand power
shortage of 12% and the cost of Fossil fuel is increasing day by day. Also, in National Action
Plan for Climate Change (NAPCC), India has committed to increase its renewable energy
share to 15% by 2020. Development of renewable energy, therefore, is necessary if Indian
economy is to achieve sustainable growth at fast pace in the future.
Nevertheless, increasing the share to renewable energy in India’s energy mix is a difficult
task, renewable energy being far more expensive compared to the conventional energy.
Wind power is less expensive compared to all other potential sources of renewable energy
like solar power. Also, India has huge unexplored wind power potential. The estimated Indianwind energy potential has been assumed by the Ministry of New and Renewable Energy in a
study conducted in the late 90's to be 45000 MW. A more recent study by C-WET, India's
wind energy potential is estimated to be more than 1,00,000 MW at a hub height of 80
metres. Therefore utilising wind potential seems to a one of the most credible way to achieve
India’s energy security.
The development of a wind power project is a complex task because of technical, managerial
and regulatory hurdles. Apart from that, different procedures are followed in different states
for various activities, which play its part in increasing the complexity. Hence this sector is not
attracting large investments. This Report, therefore, is an attempt to guide the investors to
understand the complex procedure of wind power development.
-
8/17/2019 Parth Belani
14/83
2
1.2 Problem Statement
Development of wind power project, which is a necessary task for achieving India’s energy
security, is a complex task. Different tariffs, policies and procedures followed in various
Indian states add to this complexity. Apart from this, benefits like Accelerated Depreciation
(AD) and Generation Based Incentives (GBI) are abandoned. Hence the wind power sector,
compared to conventional energy sources, is less attractive to investors. Therefore there is a
need of a document that can guide the investors to understand the procedure of a WPP
development. This report is an attempt in this direction.
1.3 Scope of Project
This project is an attempt to be guideline to the cumbersome procedure of setting up a wind
power project. It deals with all the technical, economic and regulatory issues related to WPP
development. The differences in policies/procedures followed in different states in the
permission of wind resource assessment, land acquisition, feed-in-tariffs etc. are also covered
in this report so that it can be useful to understand the diversities in various states with regard
to wind power. This report also covers financial modelling of a wind power project which can
be a guideline for checking financial viability of a WPP.
1.4 Objective of the project
Wind power development is a riskier investment compared to the investments in conventional
sources of energy. In India, diversities in policies/procedures in different states make it even
more risky and hence unattractive. The objective of the project is to guide the investors in
understanding the procedure of development of wind power project. The intension is to
persuade investments in the wind power sector by making the understanding of WPP
development procedure simpler. By making the WPP development attractive by developing
more understandable, the project is intended to contribute in India’s pursuit of energy
security.
1.5 Methodology
The project has been prepared by gathering the dispersed information about various
proceedings of wind power project development. The regulations of State Electricity
-
8/17/2019 Parth Belani
15/83
3
Regulatory Commissions (SERCs) of states with major wind energy potential have been
studied. These states include Andhra Pradesh, Karnataka, Gujarat, Rajasthan, Madhya
Pradesh, and Maharashtra. The guidelines published by various State Nodal Agencies (SNAs)
for procedures like land acquisition and capacity allocation have been gathered and
understood deeply for making this project useful. Experience of the Business Development
team of Ecoren Energy India Private Limited has added value to this project. All the
information gathered as mentioned above was then studied and put in proper sequence to
understand the flow of the development procedure. Technical books have been studied to add
major important technical issues and their solutions that need to be included in the project.
1.6 About the organisationLaunched in September, 2010, ECOREN ENERGY has been set up by a group of private
investors with the help of number of prominent Indian banks, and insurance companies.
Ecoren Energy India Private Limited is a renewable Independent Power Producer (IPP)
focused on development, owning and operating wind power projects across India. The
company is currently focusing on the states of Andhra Pradesh, Karnataka, Maharashtra,
Rajasthan, Madhya Pradesh and Gujarat for development of wind power projects. Ecoren is
led by visionary management with the objective of creating green and sustainable business
models and promoting renewable energy. Ecoren’s Vision is to demonstrate responsible
leadership in mainstreaming renewable sector in the energy space by innovation, cost-
effectiveness and profitable growth. Ecoren’s team comprised of talented and experience
individuals across the domains of Project management & execution, Regulatory, Technical,
Finance, Business Development and Wind Resource Assessment.
-
8/17/2019 Parth Belani
16/83
4
The ECOREN Factor
Ecoren is distinctive in how it balances stakeholder value, with social responsibility to make
the world a better place and to do so profitably. The organisation keeps this philosophy in the
core of its values, and wants to achieve this with a sense of pride, ownership and long-term
commitment in all of its projects from start to finish.
1.6.1 Critical Assessment of the Organization
Strengths
Core Team of expert professionals.
Excellent work Culture
Knowledge management
Intellectual capital
Reporting performance
Technical expertise
Weaknesses
Relatively new organization
Small Workforce
Opportunities
Global shift towards Renewable energy
Liberalising Government perspective towards RE generators
Young and talented workforce of India
More stress on renewable energy
Threats
High degree of openness may lead to information leakage
Capture of efficient windy sites by older and bigger players in the wind power sector
-
8/17/2019 Parth Belani
17/83
5
CHAPTER 2: LITERATURE REVIEW AND POLICY
FRAMEWORK
2.1 Literature Review
Literature has been prepared by authors all around the world explaining whole procedure
wind power project development or a part of the mighty procedure. The papers/journals
reviewed before preparation of this report, and a brief about them is explained here.
“Siting and output prediction for wind energy project planning”, a paper presented by B.H.
Bailey (AWS Sci., Albany, NY) at Power Engineering Society Winter Meeting, focuses on
outlay of wind farms. This paper summarizes and illustrates the steps involved when siting
and planning the design and performance of wind power plants. The topics covered are: site
screening techniques and parameters; wind resource mapping as a siting tool; the role and
design of wind measurement campaigns; optimizing wind plant turbine layout using
advanced modelling tools; predicting a site's long-term wind resource and annual wind plant
production; and due diligence reporting to obtain project financing.
A paper titled “Research of wind power project risk assessment based on Hierarchy-grey
Analytic Method” appeared in an international conference “Mechatronic science, Electric
Engineering and Computer (MEC), 2011”. The paper was presented by Younggui (Sch. of
Bus. Adm., North China Electrical. Power Univ., Baoding, China) et al on August 2011. This
report explains that Global environmental problems have become increasingly prominent.
Wind power as a clean and renewable energy, becomes various countries gradually in the pet
who seeks in the energy alternative process. Wind power in the global range has developed
rapidly, but it should realize that wind power project is also a risk in the process of
development cannot be avoided. This article needle wind power projects characteristic,Hierarchy-grey Analytic Method is proposed based on the wind project risk assessment
methods. Through carries on the empirical analysis to some wind electricity project to draw
the conclusion. Then carries on the wind electricity project for the enterprise the risk
management to provide the basis.
On April 2008, at Electric Utility Deregulation and Restructuring and Power Technologies,
2008, Author N.R. Ullah (Chalmers University, Goteborg) et al presented a paper titled
“Detailed modelling for large scale wind power installations - a real projec t case study”. This
-
8/17/2019 Parth Belani
18/83
6
paper reports on the modelling issues performed related to a feasibility study to investigate
the possibilities to connect the 640 MW off-shore wind power farm, planned for Krieger's
Flak 30 km south of Trelleborg (Sweden), to the E.ON 130 kV sub transmission system. The
aim of the entire study is to answer the question if such a connection is possible, and under
what conditions; it is not meant as a design project. Following a general connection design
discussion, the study comprises three major parts, fault current calculations, load flow
calculations, and dynamic simulations. Concerning the modelling aspects, much effort has
been put on details and scalability for the dynamic simulations.
In June 2010, at Energy Market (EEM), 2010, 7th International Conference on the European
a paper titled “Economic evaluation of wind generation projects in electricity markets” was
Mr Pereira A.J.C., Inst. Super. de Eng. de Coimbra, Inst. Politec. De Coimbra, Coimbra,
Portugal. In this paper the author explained the electricity markets. He evaluated economic
evaluation of WPPs in electricity markets. He explains that investments in new generation,
especially in renewables, grew up in several countries contributing to change the generation
mix. Among these new technologies, wind power became an important source in the sense
that the share in installed capacity is large in countries as Germany, Denmark, Spain and
Portugal namely considering the prices paid to the generated power. These subsidizing
schemes are in several cases responsible for a large amount of the final end user costsmeaning that in the future new ways of integrating this power in the grid have to be adopted.
This means that for investors it is important to evaluate from an economic point of view the
interest of new wind power projects admitting changes in current tariff schemes. For
regulatory agencies it is also important to investigate the impact of changes in current
schemes. This paper details an approach to characterize this type of investments in terms of
the Net Present Value, NPV, and the Internal Return Rate, IRR, so that more sounded
investment and policy decisions are adopted.
In August 2010, in the conference of Emergency Management and Management Sciences
(ICEMMS), Author Chongming Liu (North China Electrical Power University, Beijing,
China) et al presented a paper titled “Risk analysis and assessment of wind power project”. In
this report he explains that Wind power is a kind of renewable clean energy source, which
has a very important significance for energy conservation and social efficiency. But now,
wind power development has not yet formed a complete system, and there are different kinds
of risks exist in wind power project development process. This paper conduct a detailed study
for this, analyses the risk factors including natural disaster risks, technology risks, economic
http://ieeexplore.ieee.org/xpl/mostRecentIssue.jsp?punumber=5551851http://ieeexplore.ieee.org/xpl/mostRecentIssue.jsp?punumber=5551851
-
8/17/2019 Parth Belani
19/83
7
risks, and policy risks in four aspects, then construct a fuzzy comprehensive evaluation
model, and use the model in a wind power project on risk assessment, which verifies the
feasibility and effectiveness of the evaluation model.
Author J.I. Munoz et al presented a paper at PowerTech in Bucharest, in June 2009 which
was titled “Risk assessment of wind power generation project investments based on real
options”. This paper presents a decision-making tool for investment in a wind energy plant
using a real options approach. In the first part of the work, the volatilities of market prices
and wind regimes are obtained from geometric Brownian motion with mean reversion (GBM-
MR) and Weibull models, respectively. From these and other values, such as investment and
maintenance costs, the net present value (NPV) curve (made up of different values of NPV in
different periods) of the investment is calculated, as well as its average volatility. In the
second part, a real options valuation method is applied to calculate the value of the option to
invest. The volatility of the NPV curve reflecting different periods is inserted into a trinomial
investment option valuation tree. In this way, it's possible to calculate the probabilities of
investing right now, deferring the investment, or not investing at all. This powerful decision
tool allows wind energy investors to decide whether to invest in many different scenarios.
Several realistic case studies are presented to illustrate the decision-making method.
In September 2011, Consolidated Energy Consultants Limited (CECL) prepared a report
titled “Assessment of investment climate for wind power development in India” for Indian
Renewable Energy Development Agency (IREDA). This document explained indicated seven
key states in India where wind power potential is considerable. CECL explained Government
policy/guidelines, regulations by respective SERCs, guidelines from respective SNAs and
wind resource assessment in all key states. The report also included perception of investors
and financing/profitability. Based on these above mentioned factors, the ranking is given to
states. In the end, the report indicates constraints and barriers which are impediments in the
path of investments in wind power projects in India.
Author Salehi-Dobakhshari (Electrical Engineering department, Sharif University of
Technology, Tehran, Iran) et al presented a paper titled “Integration of large-scale wind farm
projects including system reliability analysis” at Renewable power generation, IET on
January 2011. His study intends to develop a comprehensive procedure for evaluating
locational value of a wind farm project incorporating reduction in transmission system losses,
load delivery point interruption cost and operating cost of generating units. The energy
-
8/17/2019 Parth Belani
20/83
8
extracted from the wind farm in normal operation condition is considered to replace the
energy from fossil-fuelled conventional units. In addition, composite system reliability
analysis in the presence of wind power is carried out to evaluate total costs associated with
curtailed energy at different load points as well as generation of generating units in
contingency conditions. System reliability analysis related to large-scale wind farms, along
with operating cost and transmission losses analysis, can assist policy makers to prioritise
wind farm projects based on the total benefits of wind power including reliability benefits and
savings in fossil-fuelled energy sources.
Author Guangjie Wang (Sch. of Manage., Wuhan Univ. of Technol., Wuhan), at Wireless
Communications, Networking and Mobile Computing, 2008, presented a paper titled
“Technical-Economic Analysis of Wind Energy Projects in China” in Oct 2008. In this paper
he explains that the renewable energy consumption has been increased rapidly with high
economic growth in China. As one of the most promising renewable energy resource, wind
energy has become a major part of the plans for sustainable development. The technical-
economic analysis of the project reveals that the revenue from certified emission reductions
(CERs) of clean development mechanism (CDM) project can increase the profitability of the
project but it doesn't play a decisive role. The sensitivity analysis of single parameter shows
that investment, electricity price and production are the key parameters influencing theeffectiveness of projects. The status of wind energy projects in China is elaborated and the
four approaches of developing wind energy projects are proposed.
Author Martinez-Cesena (Electrical Energy & Power Syst. Group, Univ. of Manchester,
Manchester, UK) et al presented a paper titled “Wind Power Projects Planning Considering
Real Options for the Wind Resource Assessment” on January 2012. The paper explains that
Investments in wind power projects (WPPs) have increased in the last few years. This trend is
partially due to the availability of support schemes, which increase the economic
attractiveness of WPPs. Alternatively, the value of WPPs can be enhanced by improving
available techniques used for their planning and design. After reviewing WPP literature, it
was concluded that available tools for the planning and design of WPP could be improved by
addressing the uncertainty of the wind resource assessment (WRA), and this source of
uncertainty could be used to enhance the value of WPPs with real options (ROs) theory. ROs
theory is known for its potential to increase the expected worth of projects by exploiting the
value of flexibility within the projects' investment decisions and designs. Nevertheless, ROs
literature has to be extended to properly address the design of WPPs. Based on the gaps in
-
8/17/2019 Parth Belani
21/83
9
ROs theory and WPPs planning, this paper proposes a methodology that relies on ROs theory
to incorporate WRA uncertainty in the planning and design process of WPPs. The
methodology is illustrated with a small case study and its potential to increase the value of
WPPs under different conditions is analysed for a wide range of case studies. The results
illustrate the circumstances and assumptions that can improve and weaken the effectiveness
of the methodology. It is concluded that the application of the proposed ROs methodology
results in increased value for WPPs in most scenarios.
-
8/17/2019 Parth Belani
22/83
10
2.2 Policy Framework
2.2.1 National Electricity Policy, 2005
Clause 5.2.20: Non – Conventional Energy Sources
This clause talks about harnessing fully feasible potential of non – conventional energy
resources mainly small hydro, wind and bio-mass to create additional power generation. It
also talks that suitable promotional measures will be taken to encourage private sector
participation.
Clause 5.12: Cogeneration and Non-Conventional Energy Sources
5.12.1
This clause highlights the fact that there is an urgent need to promote generation of electricity
based on Non-conventional sources of energy as they are environment friendly. For this
purpose, efforts are to be made to reduce the capital cost of projects. Cost of energy can also
be reduced by promoting competition within such projects. At the same time, adequate
promotional measures would also have to be taken for development of technologies and a
sustained growth of these sources.
5.12.2
This clause restates what is mentioned In Electricity Act 2003 under section 86(1) (e) and
basically talks about to promote co-generation and generation of electricity from renewablesources the state commissions are required to fix a percentage of renewable energy out of
total consumption of electricity in the area of distribution licensee.
Clause 5.6: Technology Development and R&D
This clause highlights the fact that special efforts are needed for research, development,
demonstration and commercialization of non-conventional energy systems. Such systems
would need to meet international standards, specifications and performance parameters.
2.2.2 National Tariff Policy, 2006
Clause 6.4: Non-conventional sources of energy generation including Co-generation:
a) In continuation to provisions of section 86(1) (e) of Electricity Act 2003, The clause
states that the procurement by distribution companies shall be done at preferential
tariffs determined by the Appropriate Commission as it will take some time before non-
conventional technologies can compete with conventional sources in terms of cost of
electricity.
-
8/17/2019 Parth Belani
23/83
11
b) Procurement by Distribution Licensees for future requirements shall be done, as far as
possible, through competitive bidding process under Section 63 of the Electricity Act
within suppliers offering energy from same type of non-conventional sources.
c) The Central Commission should lay down guidelines for pricing non-firm power,
especially from non – conventional sources, to be followed in cases where such
procurement is not through competitive bidding.
d) In the Amendment in Tariff Policy the Ministry of Power has directed the State
Electricity Regulators to fix a percentage of energy purchase from solar power under
the RPOs. The solar power purchase obligation for States may start with 0.25% in
Phase I (by 2013) and go up to 3% by 2022 This will be complemented by solar
specific Renewable Energy Certificate (REC) mechanism to allow solar power
generation companies to sell certificates to the utilities to meet their solar power
purchase obligations.
2.2.3 Rural Electrification Policy, 2006
Clause 1.3:
This clause states that non-conventional energy sources such as solar, wind, biomass, small
hydro, geo-thermal; tidal etc. along with conventional sources can be appropriately and
optimally utilized to make available reliable supply of electricity to each and every
household.
Clause 3: Approach to Rural electrification:
3.3 Decentralized distributed generation facilities together with local distribution network
may be based either on conventional or non-conventional methods of electricity generation
whichever is more suitable and economical. Non-conventional sources of energy could be
utilized even where grid connectivity exists provided it is found to be cost effective.
Clause 8: Policy Provisions for Permitting Stand Alone Systems for Rural Areas
8.9 This clause highlights the fact that State Governments will have to create Institutions for
back-up services and technical support to systems based on non-conventional sources of
energy. Such services would be provided on cost basis so as to make the arrangements
sustainable.
-
8/17/2019 Parth Belani
24/83
12
CHAPTER 3: WPP DEVELOPMENT PROCEDURE
3.1 Introduction - Wind Power Project development
procedure
The detailed procedure for setting up a wind power project is explained here. It consists of
following steps.
1. Project and Financial planning
2.
Selection of state of preference
3. Site identification
4.
Feasibility study5. Wind mast installation, data collection and data verification
6. site survey
7.
wind farm layout
8. Land acquisition
9. CDM related procedures
10. REC related procedures
11. DPR preparation
12.
Financial strategy and financial closure
13. Decision regarding power sale options
14. Physical implementation of the project
The above mentioned tasks are the sub procedures of the wind power project development.
They are explained here in this chapter.
-
8/17/2019 Parth Belani
25/83
13
3.2 Project and Financial Planning
3.2.1 Project Planning
The key to a successful project is in the planning. Project planning is done to increase the
likelihood that a project will be implemented efficiently, effectively and successfully. It
involves working out what one wants to do and how is one going to do it. Creating a project
plan is the first thing one should do when undertaking any kind of project.
In case of wind power projects, the overall project plan may be comprised of several points:
Business goal
Project scopes
Financial structure
Policy guidelines
Central govt. policy: MNRE
State govt. policy: SNA
List of constraints & assumption
Professional assistance
Technical planning
Permitting planning
Energy market analysis (who will buy the power)
Regulatory compliance
Legal aspects
Ease & cost of maintenance
Meeting the expectation & goals of stakeholders
Long term outlook & expansion opportunities
Gantt chart preparation
Schedule flexibility
3.2.2 Financial Planning
It includes three major decisions:
Decide how much you need (budgeting decisions)
Decide when you will need it (cash flow)
Decide where it will come from (financial planning)
-
8/17/2019 Parth Belani
26/83
14
Wind power projects, like all renewable energy projects, have a strong financial component
which determines profitability or other goals, which incentives are used and how, who takes
risks and earns rewards, how the development budget is controlled, and what has to be done
to qualify for the intended financing.
Financial planning for WPP, like other RE power projects, comprises of following
parameters:
1) General project information
a.
Rated capacity
b. PLF or CUF
c.
Inflation
d. Start year
e. Project lifetime
2)
Revenues - cash inflows
a. Ancillary products or benefits (like CDM, RECs etc.)
b.
Cost recovery- Depreciation
c. Cost recovery- tax credits
d.
Grants & incentivese. Power purchase agreement or other sales agreement
3) Costs - cash outflow
a. Equipment cost including installation & site preparation
b. Balance of system(BOS) costs including all non-equipment Capital costs- such as
interconnection & civil works
c. Developer soft costs, such as developer planning, environmental studies licensing
& permitting & negotiation of PPA
d. loan interest
e. Recurrent costs, such as equipment replacement
f. Operation & maintenance
g. Site owner rent or royalties
h. Property tax
i.
Project insurance
j. Income tax on revenue
-
8/17/2019 Parth Belani
27/83
15
4) Financing costs – debt & equity
a.
Loan debt
b. Debt percentage (the percentage of capital costs being covered by a loan)
c. Loan interest rate & term
d.
Equity
e. Equity financing fees
f.
Initial working capital
g. Debt financing fees
h. Discount rate
i. Scenario analysis
Figure 1 : Financial Planning Process
-
8/17/2019 Parth Belani
28/83
16
3.3 Selection of State of preference
The selection of the state of preference is the next task after the planning procedure has been
completed. Following major factors are taken into consideration for selection of a state.
Developers give different weightages to these factors depending upon their own strengths and
weaknesses.
3.3.1 Wind Power Potential and Installed Capacity
Wind availability is the first major factor taken into consideration by the developer to select
the state for developing a wind power project. Out of the total wind power potential, the
unutilised part is what attracts the developer for setting up the WPP. The total wind energy
potential in India has been estimated at 49130 MW out of which more than 14000 MW has
been utilised by various developers. The state wise wind power potential and installed
capacities as on 31.12.2011 are shown below in the table.
Figure 2 : Wind Power Potential and Installed Capacity
(Source: MNRE & Directory Indian Windpower 2011)
Andhra Pradesh, Gujarat and Karnataka seem to be the most lucrative states as far as the
potential and installed capacity of the wind power is concerned, since these states have large
portion of their wind resource unutilised. Maharashtra and Rajasthan too have huge untapped
potential. In Tamil Nadu, On the other hand, almost all the windy sites have been already
occupied. Still, with advancement in the technology it is becoming viable to set up WPPs in
the less windy sites. State wise achievable wind potential till 2020 is given below.
5394
10609
8591
790 920
5439 5005 5374
7008
213
2641 1852
35 330
2560 1830
6613
40
20004000
6000
8000
10000
12000
Estimated Potential (MW) Installed capacity as on 31.12.2011 (MW)
-
8/17/2019 Parth Belani
29/83
17
Table 1 : State wise Wind Power Till 2020
State Incremental (MW) Re-powering (MW)
Andhra Pradesh 7000-8000
Gujarat 6000-7000
Karnataka 5000 1000
Madhya Pradesh 3000-3500
Maharashtra 6000-7000
Rajasthan 4000-5000
Tamil Nadu 7000-8000 1500
Orissa 500
Chhattisgarh 500
Jharkhand 500
Total 39000-43000 2500
Figure 3 : State wise Achievable wind Potential Till 2020
[Source: CRIS analysis based on registered projects and pipeline of developers in various
states]
3.3.2 Feed-in-Tariffs
A feed-in tariff (FiT), also known as feed-in law, advanced renewable tariff or preferential
tariff is another important factor that affects the developers’ decision of selecting a state for
setting up of WPPs. FiT is a policy mechanism designed to encourage the adoption of
renewable energy sources and to help accelerate the transition toward grid parity for such
projects. The Feed-in-Tariffs declared by the SERCs of the key states are shown below.
-
8/17/2019 Parth Belani
30/83
18
Table 2 : State Feed-in-Tariffs
States Tariff rate (Rs/Unit)Tariff Period
(Years)
Gujarat 3.56 25
Maharashtra
Wind zone – I 5.67
13Wind zone – II 4.93
Wind zone – III 4.2
Wind zone – IV 3.78
RajasthanJaisalmer, Jodhpur and Balmer 4.46
20Other districts 4.69
Madhya
Pradesh4.35 25
Karnataka 3.7 10
Tamil Nadu 3.39 20
Andhra Pradesh 3.5 10
Figure 4 : Feed-in-Tariff
3.3.3 Special incentives and facilities by State GovernmentsSome state governments have declared special incentive or facilities to attract the wind / RE
developers which are explained here. The developers should study these incentives before
arriving to a decision of finalising the state of preference.
Government of Karnataka:
(From Karnataka Renewable Energy Policy 2009-14)
Green Energy Fund: Green Energy Fund shall be established to facilitate financing for
RE projects.
Consent from Departments & Statutory Clearances: KREDL shall obtain consent &
statutory clearances from concerned state departments for sites developed by them. In
case of private land KREDL shall assist the developers in this regard.
Allotment Committee: A committee under Chairmanship of Additional Chief
Secretary/Principle Secretary, Energy Department will consider allotment of capacity to
entrepreneurs.
-
8/17/2019 Parth Belani
31/83
19
Settlements: Transactions shall be settled on monthly basis. Interest at the rate of State
Bank of India short term prime lending rate shall be payable for delayed payment beyond
a month.
Exemption from Demand Cut: Exemption of demand cut to the extent of 50% ofinstalled capacity assigned for captive use purpose, will be allowed.
Financial Incentives: Entry tax & other incentives shall be available to RE generation in
accordance with Industrial Policy 2009-10.
Letter of Credit: Facility of LOC shall be provided by the ESCOMS to developer and its
cost will be reimbursed to ESCOMs from Green Energy Fund.
Award Scheme: RE projects successfully commissioned during the original agreement
period will be awarded with a certificate with appreciation by the Govt. and a cash
incentive from Green Energy Fund.
Government of Madhya Pradesh:
(Notification No.6591-F18-10-XIII-93 dated 17.10.2006 as amended vide order No. F18-10-
XIII-93 dated 12.05.2008)
Green Energy Fund: will be created for facilitation of power generation through non-
conventional energy sources.
Exemption from Open Access Charges: Nonconventional Energy based power
generation shall be exempted from Open Access charges.
Projects will be eligible for all benefits available to new industries under the Industrial
Promotion Policy 2004.
However one discouraging factor for WPP owners included in the state wind policy is that
the 3rd party purchaser of wind energy will be allowed the facility of reduction in contract
demand.
Government of Maharashtra:
(From NCE Policy 2008)
Evacuation Arrangement: To be constructed with the approval of Transco/Discom by
the developer at his cost. 50% of the approved expenditure to be reimbursed out of Green
Energy Fund.
-
8/17/2019 Parth Belani
32/83
20
Approach Road: To be constructed by MEDA out of Green Energy Fund. Repairs or
strengthening of existing roads to be done by developer at his cost.
Encouragement to Co-operative Sector: 11% of total share capital of the project shall
be paid from Green Energy Fund for projects set up by co-operative institutions. Letter of Credit: The DISCOM shall provide the facility of LOC to the developer & the
cost involved to be reimbursed to the DISCOM out of Green Energy Fund.
Octroi / Entry Tax: Taxes actually paid shall be reimbursed by MEDA out of Green
Energy Fund.
Eligibility for Sanction
It is obligatory to sell 50% of electricity to the Distribution Company under a long
term agreement at the rate determined by MERC. Remaining 50% shall be sold within
the State.
Benefits under the policy shall be available to only such projects for which
infrastructure approval is accorded by the Govt.
Government of Rajasthan:
(From NCE Policy dated 25.10.2004 as amended vide letters dated 10.03.05, 16.07.05,
24.02.06, 30.11.06, 19.01.07 & 27.03.2008)
Merit Order Despatch Not applicable to Wind Power Project
Exemption from Electricity Duty: Energy sold to a 3rd party will be exempted from
payment of ED @50% for a period of 7 years from COD.
Relocation of project: Re-location of project, if justified shall be permitted without any
additional charge.
3.3.4 Simplicity of procedures followed in the State
Proactive and simplified procedure ensures smooth and timely completion of the project. The
index for attitude of the State agency gets reflected in quantum of capacity addition. Higher
capacity additions obviously indicate that investor faces least problems. Though this factor is
of primary consideration to the developer yet it is also relevant to IPP owners particularly
after completion of the project and routine O&M.
-
8/17/2019 Parth Belani
33/83
21
The procedures required to be followed in different states at various stages (mast installation,
land acquisition, issue and redemption of REC etc.) of development of a WPP is explained in
the relevant topics of this report.
3.3.5 Evacuation Infrastructure
The evacuation infrastructure development for wind power project is very costly and time
consuming since the WPPs are generally in the remote sites where the grid connectivity is
usually not readily available. Whether this infrastructure has to be developed by the grid
utility or by the developer is a major factor for developer in his decision of selecting a state
for WPP development. Various states have different policies for the evacuation infrastructure
development which are explained here.
Andhra Pradesh: Cost to be borne by the developer.
Gujarat: Voltage level for evacuation shall be 66 kV and above. Govt. Policy (Amendment-
1) 2007 dated 07.01.2009 provides that owner will bear the entire cost up to 100 km; beyond
this limit GETCO will construct at its cost. Approved capital cost includes 38 lakhs per MW
towards cost of transmission line from project site to grid sub-station.
Karnataka and Madhya Pradesh: Cost to be borne by the developer. The capital costs
specified by the respective SERCs are inclusive of the power evacuation infrastructure.
Maharashtra: Cost to be borne by the developer. Capital Cost of Project/MW is inclusive of
cost of power evacuation infrastructure up to interconnection point. Capital cost is linked to
price indexation formula.
Rajasthan: A sum of Rs.2.00 Lakhs per MW is payable to RVPN as connectivity charges.
RVPN to develop evacuation system from Pooling Sub-station to Grid Substation. If
evacuation system is constructed by developer beyond pooling substation, Commission may
determine transmission tariff on case to case basis.
Tamil Nadu: To be borne by the Licensee if entire energy is sold to the Distribution
Licensee. For captive consumption and third party sale, cost will have to be borne by the
Developer but the work will be executed by the Licensee.
-
8/17/2019 Parth Belani
34/83
22
3.3.6 Grid availability
This is a major problem primarily faced by WPP developers. Obtaining sanction and/or
commissioning of the project gets adversely affected due to non-availability of evacuation
facility. None of the states have so far made medium and long term plan to meet the demandof Wind Power Sector. The short term solution as offered by them is proving to be in-
adequate because of higher growth rate now being observed. Even after commissioning of the
project, particularly in Tamil Nadu, the wind farm feeders are occasionally switched off
during high generation period which badly affects the investors. Therefore the WPPs must
consider the Grid availability conditions in the state in their decision of selecting a state for
WPP. Grid availability conditions are comparatively better in Andhra Pradesh, Gujarat and
Rajasthan.
3.3.7 Regularity in the receipt of payment
This is an important factor that IPP owners and Bankers would consider to ensure financial
viability of the project. The financial health of almost all State utilities is in bad shape.
Comparative ranking of the states carried out by Consolidated Energy Consultants Limited
(CECL) based on the general experience of IPP owners regarding timely receipt of payment
shows that Rajasthan, Gujarat and Karnataka are better compared to other states as far as
regularity in payment from the DISCOMs is concerned.
3.3.8 Sharing of CDM Benefits
The Clean Development Mechanism (CDM) is a project-based mechanism that allows public
or private entities to invest in greenhouse gas (GHG) mitigating activities in developing
countries and earn abatement credits, which can then be applied against their own GHG
emissions or sold in the open market. For wind power producers, CDM benefits may become
a source of revenue which can improve their project IRR by 1-1.5% and can make the project
financially viable. CERC and different SERCs have declared sharing of the CDM benefits
differently between the DISCOMs and the Developers. The WPP developers should examine
the sharing of CDM benefits and its impact on the revenue in various states before arriving to
a conclusion of finalising the state of preference.
-
8/17/2019 Parth Belani
35/83
23
The regulations regarding sharing of CDM benefits between the developers and the
distribution licensees in different states are explained in the following table.
Table 3 : Sharing of CDM Benefits in Different States
State Sharing of CDM benefits
CERC
regulation, 2009
100% to developers in the 1st year, reducing 10% every year till the
sharing becomes 50:50 between developer and beneficiary.
Gujarat As per CERC regulation
Maharashtra As per CERC regulation
Rajasthan75% to developer, 25% to Distribution licensee. Share of the licensee
shall be fully passed on to consumers.
M.P. As per CERC regulation
Karnataka As per CERC regulation
Tamil Nadu 100% 1st year, reducing 10% yearly up to 50:50
A.P. 90% to developer and 10% to beneficiaries.
3.3.9 Reactive Energy Charges
Table 4 : Reactive Energy Charges
State Reactive Energy Charges
GujaratUpto 10% reactive power consumption - 10 paisa/Kvarh
Above 10% reactive power consumption - 25paisa/kvarh above 10%
Maharashtra 25 paisa/Kvarh with 5% escalation per year
Rajasthan 5.75 paisa/Kvarh escalating 25 paise per year
M.P. 27 paisa /Kvarh
Tamil Nadu 25 paise/Kvarh upto 10% and double beyond
A.P. 10 paise/Kvarh upto10% and 25 paise above10
Reactive power consumption of wind turbine generators is high, especially during Start-up.
Sometimes the reactive power consumption during start up is equivalent to the kW power
rating of the turbine. This reactive power has traditionally always been imported from the
grid. Although Wind turbine generators now-a-days are commonly fitted with reactive
compensation systems of various ratings, there is requirement of reactive power consumptionfrom the grid during start-ups and for voltage control. Hence, the reactive power charges
-
8/17/2019 Parth Belani
36/83
24
applicable in the various states should be considered by the developer. The Reactive Energy
charges in in various states are indicated in the following table.
3.3.10 Banking
Power banking is like cash banking whereby wind power producers feed in the electricity
generated by their wind mills to the state grid and then draw that power for captive use within
the period specified by the Appropriate Commission. Despite the development of latest
technology in the wind energy sector it is still not possible to declare the exact wind power
generation. Hence, to help the wind power generators and attract investment, some states
have come up with the provision of banking of wind power. The banking charges are
applicable as decided by the Appropriate Commission. In Banking, only the transactions of
energy take place; there is no transaction of currency. Banking regulations in key states are
explained in the following table.
Table 5 : State wise Banking Regulations
State Banking Regulations
Gujarat Only for captive use. Allowed for one month.
Maharashtra
Allowed for a year (only for captive). Surplus energy is limited to 10% of
injected to grid up to 31st march and purchased by state at lowest Tod slab
rate of HT.
Rajasthan
Allowed only for 6 months from April to September and October to March.
Banking is not permitted from December to February. Surplus energy is
paid at 60% of large industrial tariff.
M.P.
Permitted for a period of a financial year at 2% charge. Consumption of
banked energy is subject to approval of Discom. Surplus energy at the end
of banking period to be procured by the Discom as per the decision of the
MPERC.
Karnataka
Permitted for 12 months at 2@ charge. Energy banked beyond the
prescribed time will be utilised and paid for by the Karnataka Power
Transmission Co. Ltd/Distribution Licensee concerned at tariff applicable as
per KERC norms.
Tamil Nadu Allowed for 1 year at 5% banking charge.
A.P. Not allowed. Surplus power is paid at 75% of lowest bid tariff.
-
8/17/2019 Parth Belani
37/83
25
3.3.11 Transmission and wheeling charges
Transmission and Wheeling charges, specified by SERCs of the key states, as a percentage of
the total energy transmitted are given in the following table. The losses assumed for
computation of the transmission and wheeling charges should also be taken intoconsideration.
Table 6 : State wise Transmission and Wheeling Charges
State Transmission and wheeling charges
Gujarat
1) For 66KV and above - charges and losses are those applicable to open
access consumers
2)
For below 66KV - charges are those applicable to open access consumers;
considering
i)
For more than one WEGs - Losses at 10% and shared in the ratio of
4:6 between transmission and distribution
ii) For one WEG - losses at 7% and shared in the ratio of 4:3 between
transmission and distribution.
Maharashtra
Transmission losses 4.85% and wheeling losses 0 to 9% according to the
voltage level.
Transmission charges - Rs 126.86/KW/month (long term), Rs 31.72/KW/month
(short term).
Wheeling charges - Rs 0 to 245/kw/month according to voltage level.
Rajasthan
Transmission loss - from 4.4 to 8% at different voltage levels
Transmission charges - Rs 76/kw/month
Wheeling charges 5.5 paise/kwh
M.P. 2% of the energy injected
Karnataka 5% and Rs. 1.15/kwh for third party sale
Tamil Nadu 5% of energy injected
A.P. 5% of energy injected
3.4 Site Identification
After finalising the state to develop a WPP the next task is to select the best possible sites forinstallation of WPP. Following factors should be taken into consideration for selection of site.
-
8/17/2019 Parth Belani
38/83
26
There must be evidence of significant wind speed. Wind power density should be
greater than or equal to 200 watt/m2.
Locations like hills, ridges, plateaus, mountains etc. are preferred as these sites have
more wind speeds compared to their surrounding locations. The available area should be taken into consideration. Generally 15-25 acre/MW of
land is required, but this may vary depending upon the micro-siting.
Wind direction and wind shear – The sites with constant speeds and directions are
more effective for wind power production and hence has plants at such sites have
higher PLFs.
Land cover pattern should be studies as it affects wind speeds at various heights.
Accessibility – The heavy transportation vehicles should be able to reach to thelocation of the proposed WPP at reasonable cost of road construction and
transportation.
Land ownership (Private/revenue/forest) also is an important factor to be considered.
Additional forest/environment clearances are required for occupying a forest land. On
the other hand, the developer may face problems like non-convicibility of owners in
occupation of private land.
Prior commitments of the land – The developer needs ensure that the proposed land is
not already committed to any other WPP developer.
Sites approved by C-WET must be given preference as the technical and regulatory
work to occupy such sites reduces compared to other sites.
There must be reasonable access to electrical transmission.
The terrain must be favourable to construction.
Apart from these several other factors need to be taken into consideration like - Cost
of land, rehabilitation issues, scope for future expansion, labour and skills availability,
minimum impact on labours etc.
3.5 Feasibility Study
Feasibility study is a preliminary study that is done to determine a project‘s viability through
identifying potential return on investment as well as any fatal flow in the project if any. The
results of the study are used to determine whether to proceed with the project or not. It
provides a structured method that focuses on problems, identifies objectives, evaluates
-
8/17/2019 Parth Belani
39/83
27
alternatives, and aids in the selection of the best solution. It also describes current market
situations, explores outcomes, and assesses the range of costs and benefits associated with the
recommended action. In short, the technical and commercial viability of the project is
checked in the feasibility study. After studying the outcomes of the feasibility study the
owner choses whether to proceed further with the project or not.
Feasibility Tasks:
Site inspection
Wind resource review
Investigation of interconnection opportunities
Selection of suitable process and technology
Capacity fixation on the basis of project
Capital cost study Profitability analysis
Fatal flaws review
Grant research and application development
Investigation of site access
3.5.1 Generalized activities for feasibility study of Wind Power Projects:
A. Wind Resource Assessment
The first consideration in choosing a site is the wind availability. It is the most important
factor affecting the viability of the project. To determine whether to have a project or not, it is
necessary to conduct a resource assessment. Professional resource assessment is necessary to
raise debt financing, necessary approvals/ clearances before proceeding further. In some
cases, technology providers may be able to help in identifying options, the best location or
technology to be used.
Feasibility
Study
Commercial
Viability
Technical
Viability
Figure 5: Feasibility Study
-
8/17/2019 Parth Belani
40/83
28
B. Technology selection
Various wind energy technologies are available for generating power. However each
technology has its own merits & demerits. Therefore the project viability depends on the
selection of appropriate technology.
Various technological choices have to be made for the following:
Size and capacity of the turbines
Hub height
Rated and cut-in wind speeds
Vertical or Horizontal axes
Active and passive yaw
Type of rotor controls Airfoil nomenclature
Tip-speed ratio
Pitch control and stall control
Rotor diameter
Rotor solidity
Betz limit
Number of blades Blade composition
Type of generator
Type of hub
Type of towers
Type of drive trains
C.
Preliminary design Preliminary design includes engineering the project‘s details, including equipments locations,
wiring, control systems, roads and foundations. The design of the scheme should be
completed at a level adequate for costing and a bill of quantities to be determined. Hence, the
design should be adequate for tendering purposes, and would include general arrangement
and layout drawings. Prominent aspects of the works can be categorized into:
Civil works
Generating equipment
Grid inter-connection design
-
8/17/2019 Parth Belani
41/83
29
Optimum system capacity
Size & layout of structures & equipment
If possible, the designers will therefore need to work closely with the machinery suppliers, so
that specific equipment parameters can be considered as the basis of the design.
D. Grid connectivity
Check for an appropriate connection point near site
Conversations with those who have an understanding of the system in the area where you
propose to connect your project and contact local utility or Discom. It provides following
information:
i.
Understanding the transmission & distribution systemii.
Power line capacity
iii. Substation capacity
iv. Existing protection scheme of power system
v. Conductor size
vi.
Cost estimates for transmission upgrades
Next step is to approach transmission utility , with an application, which includes the
following:i. Feasibility study
ii. System impact study
iii.
Facility study
iv.
Interconnection agreement
The final step is executing the agreements and constructing the additional infrastructure
needed to get your energy on the grid.
E. Environmental impact Assessment
An environmental impact assessment (EIA) is an assessment of the possible impact — positive
or negative — that a proposed project may have on the environment, together consisting of the
natural, social and economic aspects. The purpose of the assessment is to ensure that decision
makers consider the ensuing environmental impacts when deciding whether to proceed with a
project. The Ministry of Environment and Forests of India have been in a great effort in
Environmental Impact Assessment in India. The main laws in nation are Water Act (1974),
The Indian Wildlife (Protection) Act (1972), The Air (Prevention and Control of Pollution)
-
8/17/2019 Parth Belani
42/83
30
Act (1981) and The Environment (Protection) Act (1986). The responsible body for this is
Central Pollution Control Board (CPCB). Wind-power generation has very low emissions on
a life cycle basis, but has a number of environmental effects that may limit its potential. The
following is required before the project implementation.
Land use analysis- Helps in assessing the changes in land use pattern for setting up wind
energy stations
Air pollution
Impact on flora & fauna
Visual impact assessment
Noise impact assessment
Hydrological assessment
Impact on communication signal
On-site contamination & hazardous material issue
Waste water management practices
Depletion of water resources
Economic effects on local economy (e.g. creation of jobs)
Mitigating measures- ways in which any adverse environmental impact may be
minimized
F. Social impact assessment
Social impact assessment includes the processes of analysing, monitoring and managing the
intended and unintended social consequences, both positive and negative, of planned
interventions (policies, programs, plans, projects) and any social change processes invoked
by those interventions. Its primary purpose is to bring about a more sustainable and equitable
biophysical and human environment. SIA is often carried out as part of, or in addition to,
Environmental Impact Assessment, but it has not yet been as widely adopted as EIA in
formal planning systems, often playing a minor role in combined environmental and social
assessments. The Social Impact Assessment is analysed taking into account the effects of the
RE power project implementation on the population around the site region under various
aspects such as:
Displacement of Habitat due to project implementation
-
8/17/2019 Parth Belani
43/83
31
Proximity to populated area
Worker health & safety issues
Local population deprived of use of their domestic fuel (Biomass)
Improved Power Availability situation for the local population Adequate Direct & Indirect employment opportunities to Rural Local population
G. Economic viability
The purpose of an economic analysis is to demonstrate that the proposed project achieves
optimum utilization of resources and is of sufficient economic merit to justify an investment
in it. The analysis is therefore first made in the planning stage of the project, before any
financial arrangements are discussed or entered into. The financing agencies will generally
wish to see and approve the results of the analysis prior to making a commitment on
financing the whole or part of the project. Economic analysis is always comparative. Sound
economic evaluation of the proposed project during pre-feasibility and feasibility analysis is a
fundamental requirement, particularly when the project requires a bank‘s assistance and
financial commitment. The economic viability of the project is tested by financial modelling,
which is explained in Chapter 4 of this report.
3.6 Mast Installation, Data Collection and Data
Verification
3.6.1 Permission for Mast Installation and Subsequent Capacity
Allocation
After finalising the site for the mast installation, the developer of a Wind Power Project has
to take permission for installation of mast. A Land Option Agreement gives the developer the
first right to develop the land for a wind farm. It should precedent the erection of masts to
ensure that the data remains with the owner of the mast. It generally includes the following
The right of first refusal to develop the land for renewable
Details of the wind resource measurement agreement
Detail of data use if no turbine is installed.
Different procedures are followed in different states for obtaining the permission for mast
installation. First of all, the developer has to contact the State Nodal Agency for the
permission for installation of a mast. The SNA issues the permit if the land is either private
-
8/17/2019 Parth Belani
44/83
32
or revenue land. If the site for mast installation falls into forest land, the permission from
forest department is also required. The procedure that needs to be followed in different states
is explained below.
Andhra Pradesh, Rajasthan and Orissa
If the site is within the radius specified by the corresponding SNA (25 Km in Orissa)
from the CWET mast, land is directly allotted on the Capacity Allotment basis, i.e.in
terms of MW as per asked by the developer.
Otherwise, application for land allotment for Wind Resource Assessment has to be
submitted by the developer to the SNA. The area within the radius specified by the SNA
(AP and Orissa - 5 km, Rajasthan – 10 Km) from the proposed mast location will be
blocked for 2 years for wind resource assessment.
An application in the forest department is required for land allocation if mast location is
in forest land. A fee of 1 lac per mast has to be paid to the forest department. This is
applicable in all the states.
Only the owner’s consent is required if the proposed mast location is in the private land.
Approval for capacity allocation is sought from the SNA after the wind resource
assessment is done.
Karnataka and Madhya Pradesh
In Karnataka and Madhya Pradesh, site for the mast installation is indicated and applied
for permission to SNA. The SNA gives permission directly on capacity allotment basis.
Maharashtra:
No permission is required from MEDA for mast installation. Permission from forest
department is needed if the proposed mast location is in the forest land (fees of Rs 1
lakh/mast).
The data collected is then registered with CWET. CWET examines and approves the
data.
MEDA, based on approval from CWET, certifies that the area within 10 Km radius from
the mast is windy.
An application, along with the MEDA certificate has to be submitted in forest
department for land diversion.
-
8/17/2019 Parth Belani
45/83
33
MEDA allots the land on Capacity Allocation basis.
Gujarat:
Mast installation is to be done directly after the purchase of the land and no permission isrequired from GEDA. CWET and GEDA are only need to be informed about installation
of mast.
Approval from forest department is required if the proposed location for mast installation
is in the forest land for which the fees are Rs 1 Lakh/mast.
3.6.2 Installation of Wind Mast
Wind Mast installation is started after the permission has been received from the SNA/forest
department.
Experienced teams, skilled at installing wind monitoring met masts and equipment to the
highest standards are required for the Wind Mast Installation. Generally, consultants who
have core competency in the mast installation are hired. The consultants also provide wind
monitoring product for the specific application and install instrumentation.
3.6.3 Data collection
MNRE published guidelines for wind data measurement on 20.06.2008. The
following basic parameters are needed to be collected with the installed masts, for
minimum 12 months.
Wind speed (measure by anemometer)
Wind direction (measure by wind vane)
Wind shear - Increase in wind speed at greater height above ground
Wind speed distribution
Temperature (measure by temperature sensor)
Vertical wind speed (optional)
Change in temperature with height (optional)
Barometric pressure (optional)
Roughness of terrain (obstacles presence like nearby trees, buildings etc.)
-
8/17/2019 Parth Belani
46/83
34
Wind power can be measure by:
WPD (W/m2) = ½*air density*rotor swept area*(wind speed) 3
3.6.4 Validation of Data through CWET
The data collected though the mast has to be verified through CWET. The CWET Verifies
the method and procedure of wind monitoring including installation details, sensors
calibrations and data collection by the company at the station and prepares report
accordingly. The cost is to be paid by the developer. The Developer also has to arrange site
visits for the CWET scientists for verification of ground realities if the CWET asks for the
same.
3.7 Site Survey
After the data has been approved by the CWET, team of the developer makes a visit to the
site to conduct a site survey. Primary feasibility of the site for a wind farm development is
checked at this stage.
3.7.1 Soil / Ground Conditions
Wind turbine generators require very solid foundations to secure that large structure in high
wind conditions.