parth belani

Upload: satna-claus

Post on 06-Jul-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/17/2019 Parth Belani

    1/83

    SUMMER INTERNSHIP REPORT ON

    DETAILED PROCEDURE

     AND

    FINANCIAL MODELING

    FOR DEVELOPMENT OF A GREEN FIELD WIND POWER

    PROJECT 

    UNDER THE GUIDANCE OF

    Mrs Sreelata Nilesh, Senior Fellow, CAMPS, NPTI 

    Mr Rajat Roy, Dy. Manager, Ecoren Energy India Pvt Ltd

    At 

    Ecoren Energy India Pvt Ltd

    Submitted by

    PARTH BELANI 

    ROLL NO: 1120812204 

    MBA (POWER MANAGEMENT)

    (Under the Ministry of Power, Govt. of India)

    Affiliated to 

    MAHARSHI DAYANAND UNIVERSITY, ROTHAK

    AUGUST 2012

  • 8/17/2019 Parth Belani

    2/83

    ii

    TRAINING COMPLETION CERTIFICATE

  • 8/17/2019 Parth Belani

    3/83

    iii

    DECLARATION

    I, Parth Belani, Roll no. 1120812204, student of MBA (Power Management) at National

    Power Training Institute, Faridabad, hereby declare that the summer training report

     programme of the National Power Training Institute, Faridabad hereby declare that the

    Summer Training Report entitled –  

    “DETAILED PROCEDURE AND FINANCIAL MODELING FOR DEVELOPMENT OF A

    GREEN FIELD WIND POWER PROJECT” 

    Is an original work and the same has not been submitted to any other Institute for the award

    of any other degree.

    A Seminar presentation of the Training Report was made on ……………….. and the

    suggestions as approved by the faculty were duly incorporated.

    Presentation In charge Signature of the

    Candidate (Faculty)

    Countersigned

    Director/Principal of the Institute 

  • 8/17/2019 Parth Belani

    4/83

    iv

    ACKNOWLEDGEMENT

    I express my sincere thanks to Mr Rajat Roy (Business Development Manager), Ecoren

    Energy India Private Limited for giving me a great opportunity to work in such an esteem

    organization. I am solemnly thankful to Mr Rakesh Patel (Business Analyst), Ecoren Energy

    India Private Limited for his guidance and support. I am also thankful to the entire staff of,

    Ecoren Energy India Private Limited for sharing their knowledge and assistance.

    I feel deep sense of gratitude towards Mr J.S.S. RAO, Principal Director, CAMPS (NPTI),

    Mr S. K. Chaudhary, Principal Director, CAMPS, Mrs Indu Maheshwari, Dy. Director,

     NPTI and Mrs Manju Mam, Dy. Director, NPTI, Dr Rohit Verma, Dy. Director, NPTI for

    arranging my internship at Ecoren Energy India Private Limited. I also take this opportunity

    to express my sincere thanks to Mrs Sreelata Nilesh (Senior Fellow), NPTI for being my

    internal project guide and providing valuable inputs in the completion of this project.

    .

  • 8/17/2019 Parth Belani

    5/83

    v

    EXECUTIVE SUMMARY

    In April 2012 Indian power sector reached a tremendous milestone of achieving 2,00,000

    MW of total installed power capacity. Commencing with a meagre installed capacity of about1360 MW in 1947, the year the country attained independence, India’s power sector grew

    substantially over the last six and a half decades, and the installed capacity at the end of June

    2012 stands at 2,05,340 MW. However contribution of renewable power is 24,833 MW,

    which is only 12.1% of the total installed capacity. Further, the Government of India desires

    to significantly improve the country's annual per capita consumption. The government has

    not been successful in its efforts to achieve per capita consumption of 1000 units and to

    ensure a minimum lifeline consumption of 1 unit per household per day as a merit good by

    the year 2012. In order to achieve this scale of supply and ensure sufficient electricity to all at

    reasonable rates, it is necessary to explore all possible options of generating and supplying

    electricity.

    Renewable energy sources can make important contributions to sustainable development.

    Currently, their exploitation in commercial markets is low, mainly because of high cost and

    technological constraints. Most renewable energy technologies are still at an early stage of

    development. However wind power, compared to other renewable energy sources, has lower

    costs and improved technology. Development of wind power projects, therefore, is a key to

    India’s future economic growth looking at the benefits of wind energy and the energy deficit

    the country is facing today.  Nevertheless, investors’ lack of interest in wind energy sector is

    conspicuous because of lack of procedural understanding of development of wind power

     projects.

    The need for defining an effective and comprehensive wind power project implementation

    methodology for India is imperative. Not only there are growing uncertainties about the

    critical as well as sub critical activities of wind power projects implementation, but the

    information associated with them is meagre and highly dispersed in nature and is not easily

    available. Insufficient information may lead to misleading decisions by project developers

    and investor’s. Many wind power project investments are not implemented, not because of

    financial, technical, commercial, managerial or regulatory aspects, but merely because of

     procedural complexities and inadequate guidelines about them.

  • 8/17/2019 Parth Belani

    6/83

    vi

    Therefore this study is intended to explicate a generalized methodology for wind power

     project implementation. This methodology will act as a source of knowledge for wind energy

     power project implementation to the stakeholders of the Indian power sector. 

    This report includes all the major steps that are required to take for putting in place a wind

     power project. It starts with project and financial planning procedure followed by factors that

    need to be taken into consideration for selecting a state of preference. The project then guides

    about feasibility study, wind resource assessment, site survey, micro-siting, land acquisition,

    financial planning & strategy, and power sale options. The project also includes financial

    modelling that can help the investor in his decision of whether to accept or reject the project. 

  • 8/17/2019 Parth Belani

    7/83

    vii

    LIST OF ABBREVIATIONS

    CDM Clean Development Mechanism

    CPV Concentrated Photo Voltaic

    CEA Central Electricity Authority

    CERC Central Electricity Regulatory Commission

    CUF Capacity Utilization Factor

    IEGC Indian Electricity Grid Code

    KWh Kilo Watt Hour

    MNRE Ministry of New and Renewable Energy

    MoP Ministry of Power

    MW Megawatt

     NLDC National Load Despatch Centre

     NOC No Objection Certificate

    O&M Operation & Maintenance

    PLF Plant Load Factor

    PPA Power Purchase Agreement

    RE Renewable Energy

    REC Renewable Energy Certificate

    RET Renewable Energy Technology

    RPO Renewable Purchase Obligation

    SERC State Electricity Regulatory Commission

    SHP Small Hydro Plant

    SLDC State Load Despatch Centre

    SNA State Nodal Agency

  • 8/17/2019 Parth Belani

    8/83

    viii

    LIST OF TABLES

    Table 1 : State wise Wind Power Till 2020 .......................................................................... 17

    Table 2 : State Feed-in-Tariffs ............................................................................................. 18

    Table 3 : Sharing of CDM Benefits in Different States ........................................................ 23

    Table 4 : Reactive Energy Charges ...................................................................................... 23

    Table 5 : State wise Banking Regulations ............................................................................ 24

    Table 6 : State wise Transmission and Wheeling Charges ................................................... 25

    Table 7 : REC Floor and Forbearance Prices of REC ........................................................... 44 

  • 8/17/2019 Parth Belani

    9/83

    ix

    LIST OF FIGURES

    Figure 1 : Financial Planning Process .................................................................................. 15

    Figure 2 : Wind Power Potential and Installed Capacity ...................................................... 16

    Figure 3 : State wise Achievable wind Potential Till 2020 ................................................... 17

    Figure 4 : Feed-in-Tariff...................................................................................................... 18

    Figure 5: Feasibility Study .................................................................................................. 27

    Figure 6 : CDM Timeframe ................................................................................................. 40

    Figure 7 : CDM Project Cycle ............................................................................................. 41

    Figure 8 : REC Procedure.................................................................................................... 44

    Figure 9 : REC Mechanism ................................................................................................. 45

    Figure 10 : Hurdles in Financial Closure ............................................................................. 51

    Figure 11 : Power Sale Options ........................................................................................... 53

    Figure 12 : Parameters of Financial Modelling .................................................................... 59

    Figure 13 : Cost Estimate per Project Phase ........................................................................ 60

    Figure 14 : Project Cash-flow and Key Indicators................................................................ 62

    Figure 15 : Types of Risk in Various Phases of Project........................................................ 63 

    http://d/university%20final%20report/MAIN%20REPORT.docx%23_Toc334424803http://d/university%20final%20report/MAIN%20REPORT.docx%23_Toc334424803

  • 8/17/2019 Parth Belani

    10/83

    x

    Table of Contents

    TRAINING COMPLETION CERTIFICATE ................................................................................................ ii

    DECLARATION .................................................................................................................................. iii

    ACKNOWLEDGEMENT ...................................................................................................................... iv

    EXECUTIVE SUMMARY ....................................................................................................................... v

    LIST OF ABBREVIATIONS ...................................................................................................................vii

    LIST OF TABLES ................................................................................................................................ viii

    LIST OF FIGURES ................................................................................................................................ix

    Table of Contents .............................................................................................................................. x

    CHAPTER 1: INTRODUCTION .............................................................................................................. 1

    1.1 About the project..................................................................................................................... 11.2 Problem Statement .................................................................................................................. 2

    1.3 Scope of Project ....................................................................................................................... 2

    1.4 Objective of the project ........................................................................................................... 2

    1.5 Methodology ........................................................................................................................... 2

    1.6 About the organisation ............................................................................................................ 3

    1.6.1 Critical Assessment of the Organization............................................................................. 4

    CHAPTER 2: LITERATURE REVIEW AND POLICY FRAMEWORK ............................................................. 5

    2.1 Literature Review ..................................................................................................................... 5

    2.2 Policy Framework .................................................................................................................. 10

    2.2.1 National Electricity Policy, 2005 ...................................................................................... 10

    2.2.2 National Tariff Policy, 2006.............................................................................................. 10

    2.2.3 Rural Electrification Policy, 2006 ..................................................................................... 11

    CHAPTER 3: WPP DEVELOPMENT PROCEDURE ................................................................................ 12

    3.1 Introduction - Wind Power Project development procedure .................................................. 12

    3.2 Project and Financial Planning................................................................................................ 13

    3.2.1 Project Planning .............................................................................................................. 13

    3.2.2 Financial Planning ........................................................................................................... 13

    3.3 Selection of State of preference ............................................................................................. 16

    3.3.1 Wind Power Potential and Installed Capacity .................................................................. 16

    3.3.2 Feed-in-Tariffs ................................................................................................................. 17

    3.3.3 Special incentives and facilities by State Governments .................................................... 18

    3.3.4 Simplicity of procedures followed in the State ................................................................. 20

    3.3.5 Evacuation Infrastructure ................................................................................................ 21

  • 8/17/2019 Parth Belani

    11/83

    xi

    3.3.6 Grid availability ............................................................................................................... 22

    3.3.7 Regularity in the receipt of payment ............................................................................... 22

    3.3.8 Sharing of CDM Benefits.................................................................................................. 22

    3.3.9 Reactive Energy Charges ................................................................................................. 23

    3.3.10 Banking ......................................................................................................................... 24

    3.3.11 Transmission and wheeling charges............................................................................... 25

    3.4 Site Identification ................................................................................................................... 25

    3.5 Feasibility Study ..................................................................................................................... 26

    3.5.1 Generalized activities for feasibility study of Wind Power Projects: ................................. 27

    3.6 Mast Installation, Data Collection and Data Verification ......................................................... 31

    3.6.1 Permission for Mast Installation and Subsequent Capacity Allocation ............................ 31

    3.6.2 Installation of Wind Mast ................................................................................................ 33

    3.6.3 Data collection ................................................................................................................ 33

    3.6.4 Validation of Data through CWET .................................................................................... 34

    3.7 Site Survey ............................................................................................................................. 34

    3.7.1 Soil / Ground Conditions ................................................................................................. 34

    3.7.2 Soil Erosion ..................................................................................................................... 34

    3.7.3 Accessibility .................................................................................................................... 35

    3.7.4 Closeness to Grid ............................................................................................................ 35

    3.8 Wind Farm Layout.................................................................................................................. 36

    3.8.1 Inter-turbine separation .................................................................................................. 36

    3.8.2 Changes in elevation of area ........................................................................................... 37

    3.8.3 Other factors ................................................................................................................... 37

    3.8.4 Layout using software ..................................................................................................... 37

    3.9 Land acquisition ..................................................................................................................... 37

    3.10 Clean Development Mechanism ........................................................................................... 403.10.1 CDM project cycle ........................................................................................................ 41

    3.11 Renewable Energy Certificates ............................................................................................. 43

    3.11.1 Types of REC ................................................................................................................. 44

    3.11.2 The operational framework for REC mechanism ............................................................ 44

    3.12 Detailed Project Report ........................................................................................................ 47

    3.12.1 Contents to be covered in a DPR ................................................................................... 48

    3.13 Financing Strategy and Financial Closure .............................................................................. 49

    3.13.1 Financing strategy ......................................................................................................... 49

  • 8/17/2019 Parth Belani

    12/83

    xii

    3.13.2 Financial Closure ........................................................................................................... 50

    3.14 Power Sale options .............................................................................................................. 53

    3.15 Physical implementation of the Project ................................................................................ 54

    3.15.1 Engineering ................................................................................................................... 54

    3.15.2 Procurement ................................................................................................................. 55

    3.15.3 Construction ................................................................................................................. 55

    3.15.4 Testing and Commissioning ........................................................................................... 57

    3.15.5 Operation and Maintenance ......................................................................................... 58

    CHAPTER 4: FINANCIAL MODELLING ................................................................................................ 59

    4.1 Cost estimates ....................................................................................................................... 59

    4.2 Development of a project model ........................................................................................... 60

    4.3 Analysis of financial indicators ............................................................................................... 61

    4.4 Sensitivity Analysis ................................................................................................................. 62

    4.5 Risk analysis ........................................................................................................................... 63

    4.5.1 Assessing risk .................................................................................................................. 63

    4.5.2 Managing Risk ................................................................................................................. 64

    CHAPTER 5: SUMMARY.................................................................................................................... 65

    5.1 Conclusion ............................................................................................................................. 65

    5.2 Recommendations ................................................................................................................. 67

    Bibliography .................................................................................................................................... 69

    ANNEXURES .................................................................................................................................... 71

  • 8/17/2019 Parth Belani

    13/83

    1

    CHAPTER 1: INTRODUCTION

    1.1 About the project

    In April 2012 Indian power sector crossed a remarkable milestone of crossing 200000 MW of

    total installed capacity. On 30th June 2012, the country’s total installed power capacity stood

    at an enormous figure of 205340.26 MW, out of which total renewable energy was 24832.68

    MW. The share of Wind energy in Renewable energy produced in India is very high at 70%.

    Still, India’s goal of ‘energy security’ is far from achieved.   India has peak demand power

    shortage of 12% and the cost of Fossil fuel is increasing day by day. Also, in National Action

    Plan for Climate Change (NAPCC), India has committed to increase its renewable energy

    share to 15% by 2020. Development of renewable energy, therefore, is necessary if Indian

    economy is to achieve sustainable growth at fast pace in the future.

     Nevertheless, increasing the share to renewable energy in India’s energy mix is a difficult

    task, renewable energy being far more expensive compared to the conventional energy.

    Wind power is less expensive compared to all other potential sources of renewable energy

    like solar power. Also, India has huge unexplored wind power potential. The estimated Indianwind energy potential has been assumed by the Ministry of New and Renewable Energy in a

    study conducted in the late 90's to be 45000 MW. A more recent study by C-WET, India's

    wind energy potential is estimated to be more than 1,00,000 MW at a hub height of 80

    metres. Therefore utilising wind potential seems to a one of the most credible way to achieve

    India’s energy security. 

    The development of a wind power project is a complex task because of technical, managerial

    and regulatory hurdles. Apart from that, different procedures are followed in different states

    for various activities, which play its part in increasing the complexity. Hence this sector is not

    attracting large investments. This Report, therefore, is an attempt to guide the investors to

    understand the complex procedure of wind power development.

  • 8/17/2019 Parth Belani

    14/83

    2

    1.2 Problem Statement

    Development of wind power project, which is a necessary task for achieving India’s energy

    security, is a complex task. Different tariffs, policies and procedures followed in various

    Indian states add to this complexity. Apart from this, benefits like Accelerated Depreciation

    (AD) and Generation Based Incentives (GBI) are abandoned. Hence the wind power sector,

    compared to conventional energy sources, is less attractive to investors. Therefore there is a

    need of a document that can guide the investors to understand the procedure of a WPP

    development. This report is an attempt in this direction.

    1.3 Scope of Project

    This project is an attempt to be guideline to the cumbersome procedure of setting up a wind

     power project. It deals with all the technical, economic and regulatory issues related to WPP

    development. The differences in policies/procedures followed in different states in the

     permission of wind resource assessment, land acquisition, feed-in-tariffs etc. are also covered

    in this report so that it can be useful to understand the diversities in various states with regard

    to wind power. This report also covers financial modelling of a wind power project which can

     be a guideline for checking financial viability of a WPP.

    1.4 Objective of the project

    Wind power development is a riskier investment compared to the investments in conventional

    sources of energy. In India, diversities in policies/procedures in different states make it even

    more risky and hence unattractive. The objective of the project is to guide the investors in

    understanding the procedure of development of wind power project. The intension is to

     persuade investments in the wind power sector by making the understanding of WPP

    development procedure simpler. By making the WPP development attractive by developing

    more understandable, the project is intended to contribute in India’s pursuit of energy

    security.

    1.5 Methodology

    The project has been prepared by gathering the dispersed information about various

     proceedings of wind power project development. The regulations of State Electricity

  • 8/17/2019 Parth Belani

    15/83

    3

    Regulatory Commissions (SERCs) of states with major wind energy potential have been

    studied. These states include Andhra Pradesh, Karnataka, Gujarat, Rajasthan, Madhya

    Pradesh, and Maharashtra. The guidelines published by various State Nodal Agencies (SNAs)

    for procedures like land acquisition and capacity allocation have been gathered and

    understood deeply for making this project useful. Experience of the Business Development

    team of Ecoren Energy India Private Limited has added value to this project. All the

    information gathered as mentioned above was then studied and put in proper sequence to

    understand the flow of the development procedure. Technical books have been studied to add

    major important technical issues and their solutions that need to be included in the project.

    1.6 About the organisationLaunched in September, 2010, ECOREN ENERGY has been set up by a group of private

    investors with the help of number of prominent Indian banks, and insurance companies.

    Ecoren Energy India Private Limited is a renewable Independent Power Producer (IPP)

    focused on development, owning and operating wind power projects across India. The

    company is currently focusing on the states of Andhra Pradesh, Karnataka, Maharashtra,

    Rajasthan, Madhya Pradesh and Gujarat for development of wind power projects. Ecoren is

    led by visionary management with the objective of creating green and sustainable business

    models and promoting renewable energy. Ecoren’s Vision is to demonstrate responsible

    leadership in mainstreaming renewable sector in the energy space by innovation, cost-

    effectiveness and profitable growth. Ecoren’s team comprised of talented and experience

    individuals across the domains of Project management & execution, Regulatory, Technical,

    Finance, Business Development and Wind Resource Assessment.

  • 8/17/2019 Parth Belani

    16/83

    4

    The ECOREN Factor

    Ecoren is distinctive in how it balances stakeholder value, with social responsibility to make

    the world a better place and to do so profitably. The organisation keeps this philosophy in the

    core of its values, and wants to achieve this with a sense of pride, ownership and long-term

    commitment in all of its projects from start to finish.

    1.6.1 Critical Assessment of the Organization

    Strengths

      Core Team of expert professionals.

      Excellent work Culture

      Knowledge management

      Intellectual capital

      Reporting performance

      Technical expertise

    Weaknesses

      Relatively new organization

      Small Workforce

    Opportunities

      Global shift towards Renewable energy

      Liberalising Government perspective towards RE generators

      Young and talented workforce of India

      More stress on renewable energy

    Threats 

      High degree of openness may lead to information leakage

      Capture of efficient windy sites by older and bigger players in the wind power sector

  • 8/17/2019 Parth Belani

    17/83

    5

    CHAPTER 2: LITERATURE REVIEW AND POLICY

    FRAMEWORK

    2.1 Literature Review

    Literature has been prepared by authors all around the world explaining whole procedure

    wind power project development or a part of the mighty procedure. The papers/journals

    reviewed before preparation of this report, and a brief about them is explained here.

    “Siting and output prediction for wind energy project planning”, a paper presented by B.H.

    Bailey (AWS Sci., Albany, NY) at Power Engineering Society Winter Meeting, focuses on

    outlay of wind farms. This paper summarizes and illustrates the steps involved when siting

    and planning the design and performance of wind power plants. The topics covered are: site

    screening techniques and parameters; wind resource mapping as a siting tool; the role and

    design of wind measurement campaigns; optimizing wind plant turbine layout using

    advanced modelling tools; predicting a site's long-term wind resource and annual wind plant

     production; and due diligence reporting to obtain project financing.

    A paper titled “Research of wind power project risk assessment based on Hierarchy-grey

    Analytic Method” appeared in an international conference “Mechatronic science, Electric

    Engineering and Computer (MEC), 2011”. The paper was presented by Younggui (Sch. of

    Bus. Adm., North China Electrical. Power Univ., Baoding, China) et al on August 2011. This

    report explains that Global environmental problems have become increasingly prominent.

    Wind power as a clean and renewable energy, becomes various countries gradually in the pet

    who seeks in the energy alternative process. Wind power in the global range has developed

    rapidly, but it should realize that wind power project is also a risk in the process of

    development cannot be avoided. This article needle wind power projects characteristic,Hierarchy-grey Analytic Method is proposed based on the wind project risk assessment

    methods. Through carries on the empirical analysis to some wind electricity project to draw

    the conclusion. Then carries on the wind electricity project for the enterprise the risk

    management to provide the basis.

    On April 2008, at Electric Utility Deregulation and Restructuring and Power Technologies,

    2008, Author N.R. Ullah (Chalmers University, Goteborg) et al presented a paper titled

    “Detailed modelling for large scale wind power installations - a real projec t case study”. This

  • 8/17/2019 Parth Belani

    18/83

    6

     paper reports on the modelling issues performed related to a feasibility study to investigate

    the possibilities to connect the 640 MW off-shore wind power farm, planned for Krieger's

    Flak 30 km south of Trelleborg (Sweden), to the E.ON 130 kV sub transmission system. The

    aim of the entire study is to answer the question if such a connection is possible, and under

    what conditions; it is not meant as a design project. Following a general connection design

    discussion, the study comprises three major parts, fault current calculations, load flow

    calculations, and dynamic simulations. Concerning the modelling aspects, much effort has

     been put on details and scalability for the dynamic simulations.

    In June 2010, at Energy Market (EEM), 2010, 7th International Conference on the European

    a  paper titled “Economic evaluation of wind generation projects in electricity markets” was

    Mr Pereira A.J.C., Inst. Super. de Eng. de Coimbra, Inst. Politec. De Coimbra, Coimbra,

    Portugal. In this paper the author explained the electricity markets. He evaluated economic

    evaluation of WPPs in electricity markets. He explains that investments in new generation,

    especially in renewables, grew up in several countries contributing to change the generation

    mix. Among these new technologies, wind power became an important source in the sense

    that the share in installed capacity is large in countries as Germany, Denmark, Spain and

    Portugal namely considering the prices paid to the generated power. These subsidizing

    schemes are in several cases responsible for a large amount of the final end user costsmeaning that in the future new ways of integrating this power in the grid have to be adopted.

    This means that for investors it is important to evaluate from an economic point of view the

    interest of new wind power projects admitting changes in current tariff schemes. For

    regulatory agencies it is also important to investigate the impact of changes in current

    schemes. This paper details an approach to characterize this type of investments in terms of

    the Net Present Value, NPV, and the Internal Return Rate, IRR, so that more sounded

    investment and policy decisions are adopted.

    In August 2010, in the conference of Emergency Management and Management Sciences

    (ICEMMS), Author Chongming Liu (North China Electrical Power University, Beijing,

    China) et al presented a paper titled “Risk analysis and assessment of wind power project”. In

    this report he explains that Wind power is a kind of renewable clean energy source, which

    has a very important significance for energy conservation and social efficiency. But now,

    wind power development has not yet formed a complete system, and there are different kinds

    of risks exist in wind power project development process. This paper conduct a detailed study

    for this, analyses the risk factors including natural disaster risks, technology risks, economic

    http://ieeexplore.ieee.org/xpl/mostRecentIssue.jsp?punumber=5551851http://ieeexplore.ieee.org/xpl/mostRecentIssue.jsp?punumber=5551851

  • 8/17/2019 Parth Belani

    19/83

    7

    risks, and policy risks in four aspects, then construct a fuzzy comprehensive evaluation

    model, and use the model in a wind power project on risk assessment, which verifies the

    feasibility and effectiveness of the evaluation model.

    Author J.I. Munoz et al presented a paper at PowerTech in Bucharest, in June 2009 which

    was titled “Risk assessment of wind power generation project investments based on real

    options”. This paper presents a decision-making tool for investment in a wind energy plant

    using a real options approach. In the first part of the work, the volatilities of market prices

    and wind regimes are obtained from geometric Brownian motion with mean reversion (GBM-

    MR) and Weibull models, respectively. From these and other values, such as investment and

    maintenance costs, the net present value (NPV) curve (made up of different values of NPV in

    different periods) of the investment is calculated, as well as its average volatility. In the

    second part, a real options valuation method is applied to calculate the value of the option to

    invest. The volatility of the NPV curve reflecting different periods is inserted into a trinomial

    investment option valuation tree. In this way, it's possible to calculate the probabilities of

    investing right now, deferring the investment, or not investing at all. This powerful decision

    tool allows wind energy investors to decide whether to invest in many different scenarios.

    Several realistic case studies are presented to illustrate the decision-making method.

    In September 2011, Consolidated Energy Consultants Limited (CECL) prepared a report

    titled “Assessment of investment climate for wind power development in India” for Indian

    Renewable Energy Development Agency (IREDA). This document explained indicated seven

    key states in India where wind power potential is considerable. CECL explained Government

     policy/guidelines, regulations by respective SERCs, guidelines from respective SNAs and

    wind resource assessment in all key states. The report also included perception of investors

    and financing/profitability. Based on these above mentioned factors, the ranking is given to

    states. In the end, the report indicates constraints and barriers which are impediments in the

     path of investments in wind power projects in India.

    Author Salehi-Dobakhshari (Electrical Engineering department, Sharif University of

    Technology, Tehran, Iran) et al presented a paper titled “Integration of large-scale wind farm

     projects including system reliability analysis” at Renewable power generation, IET on

    January 2011. His study intends to develop a comprehensive procedure for evaluating

    locational value of a wind farm project incorporating reduction in transmission system losses,

    load delivery point interruption cost and operating cost of generating units. The energy

  • 8/17/2019 Parth Belani

    20/83

    8

    extracted from the wind farm in normal operation condition is considered to replace the

    energy from fossil-fuelled conventional units. In addition, composite system reliability

    analysis in the presence of wind power is carried out to evaluate total costs associated with

    curtailed energy at different load points as well as generation of generating units in

    contingency conditions. System reliability analysis related to large-scale wind farms, along

    with operating cost and transmission losses analysis, can assist policy makers to prioritise

    wind farm projects based on the total benefits of wind power including reliability benefits and

    savings in fossil-fuelled energy sources.

    Author Guangjie Wang (Sch. of Manage., Wuhan Univ. of Technol., Wuhan), at Wireless

    Communications, Networking and Mobile Computing, 2008, presented a paper titled

    “Technical-Economic Analysis of Wind Energy Projects in China” in Oct 2008. In this paper

    he explains that the renewable energy consumption has been increased rapidly with high

    economic growth in China. As one of the most promising renewable energy resource, wind

    energy has become a major part of the plans for sustainable development. The technical-

    economic analysis of the project reveals that the revenue from certified emission reductions

    (CERs) of clean development mechanism (CDM) project can increase the profitability of the

     project but it doesn't play a decisive role. The sensitivity analysis of single parameter shows

    that investment, electricity price and production are the key parameters influencing theeffectiveness of projects. The status of wind energy projects in China is elaborated and the

    four approaches of developing wind energy projects are proposed.

    Author Martinez-Cesena (Electrical Energy & Power Syst. Group, Univ. of Manchester,

    Manchester, UK) et al presented a paper titled “Wind Power Projects Planning Considering

    Real Options for the Wind Resource Assessment” on January 2012. The paper explains that

    Investments in wind power projects (WPPs) have increased in the last few years. This trend is

     partially due to the availability of support schemes, which increase the economic

    attractiveness of WPPs. Alternatively, the value of WPPs can be enhanced by improving

    available techniques used for their planning and design. After reviewing WPP literature, it

    was concluded that available tools for the planning and design of WPP could be improved by

    addressing the uncertainty of the wind resource assessment (WRA), and this source of

    uncertainty could be used to enhance the value of WPPs with real options (ROs) theory. ROs

    theory is known for its potential to increase the expected worth of projects by exploiting the

    value of flexibility within the projects' investment decisions and designs. Nevertheless, ROs

    literature has to be extended to properly address the design of WPPs. Based on the gaps in

  • 8/17/2019 Parth Belani

    21/83

    9

    ROs theory and WPPs planning, this paper proposes a methodology that relies on ROs theory

    to incorporate WRA uncertainty in the planning and design process of WPPs. The

    methodology is illustrated with a small case study and its potential to increase the value of

    WPPs under different conditions is analysed for a wide range of case studies. The results

    illustrate the circumstances and assumptions that can improve and weaken the effectiveness

    of the methodology. It is concluded that the application of the proposed ROs methodology

    results in increased value for WPPs in most scenarios.

  • 8/17/2019 Parth Belani

    22/83

    10

    2.2 Policy Framework

    2.2.1 National Electricity Policy, 2005

    Clause 5.2.20: Non –  Conventional Energy Sources

    This clause talks about harnessing fully feasible potential of non  –   conventional energy

    resources mainly small hydro, wind and bio-mass to create additional power generation. It

    also talks that suitable promotional measures will be taken to encourage private sector

     participation.

    Clause 5.12: Cogeneration and Non-Conventional Energy Sources

    5.12.1

    This clause highlights the fact that there is an urgent need to promote generation of electricity

     based on Non-conventional sources of energy as they are environment friendly. For this

     purpose, efforts are to be made to reduce the capital cost of projects. Cost of energy can also

     be reduced by promoting competition within such projects. At the same time, adequate

     promotional measures would also have to be taken for development of technologies and a

    sustained growth of these sources.

    5.12.2

    This clause restates what is mentioned In Electricity Act 2003 under section 86(1) (e) and

     basically talks about to promote co-generation and generation of electricity from renewablesources the state commissions are required to fix a percentage of renewable energy out of

    total consumption of electricity in the area of distribution licensee.

    Clause 5.6: Technology Development and R&D

    This clause highlights the fact that special efforts are needed for research, development,

    demonstration and commercialization of non-conventional energy systems. Such systems

    would need to meet international standards, specifications and performance parameters.

    2.2.2 National Tariff Policy, 2006

    Clause 6.4: Non-conventional sources of energy generation including Co-generation:

    a)  In continuation to provisions of section 86(1) (e) of Electricity Act 2003, The clause

    states that the procurement by distribution companies shall be done at preferential

    tariffs determined by the Appropriate Commission as it will take some time before non-

    conventional technologies can compete with conventional sources in terms of cost of

    electricity.

  • 8/17/2019 Parth Belani

    23/83

    11

     b)  Procurement by Distribution Licensees for future requirements shall be done, as far as

     possible, through competitive bidding process under Section 63 of the Electricity Act

    within suppliers offering energy from same type of non-conventional sources.

    c)  The Central Commission should lay down guidelines for pricing non-firm power,

    especially from non – conventional sources, to be followed in cases where such

     procurement is not through competitive bidding.

    d)  In the Amendment in Tariff Policy the Ministry of Power has directed the State

    Electricity Regulators to fix a percentage of energy purchase from solar power under

    the RPOs. The solar power purchase obligation for States may start with 0.25% in

    Phase I (by 2013) and go up to 3% by 2022 This will be complemented by solar

    specific Renewable Energy Certificate (REC) mechanism to allow solar power

    generation companies to sell certificates to the utilities to meet their solar power

     purchase obligations.

    2.2.3 Rural Electrification Policy, 2006

    Clause 1.3:

    This clause states that non-conventional energy sources such as solar, wind, biomass, small

    hydro, geo-thermal; tidal etc. along with conventional sources can be appropriately and

    optimally utilized to make available reliable supply of electricity to each and every

    household.

    Clause 3: Approach to Rural electrification:

    3.3 Decentralized distributed generation facilities together with local distribution network

    may be based either on conventional or non-conventional methods of electricity generation

    whichever is more suitable and economical. Non-conventional sources of energy could be

    utilized even where grid connectivity exists provided it is found to be cost effective.

    Clause 8: Policy Provisions for Permitting Stand Alone Systems for Rural Areas

    8.9 This clause highlights the fact that State Governments will have to create Institutions for

     back-up services and technical support to systems based on non-conventional sources of

    energy. Such services would be provided on cost basis so as to make the arrangements

    sustainable.

  • 8/17/2019 Parth Belani

    24/83

    12

    CHAPTER 3: WPP DEVELOPMENT PROCEDURE

    3.1 Introduction - Wind Power Project development

    procedure

    The detailed procedure for setting up a wind power project is explained here. It consists of

    following steps.

    1.  Project and Financial planning

    2. 

    Selection of state of preference

    3.  Site identification

    4. 

    Feasibility study5.  Wind mast installation, data collection and data verification

    6.  site survey

    7. 

    wind farm layout

    8.  Land acquisition

    9.  CDM related procedures

    10. REC related procedures

    11. DPR preparation

    12. 

    Financial strategy and financial closure

    13. Decision regarding power sale options

    14. Physical implementation of the project

    The above mentioned tasks are the sub procedures of the wind power project development.

    They are explained here in this chapter. 

  • 8/17/2019 Parth Belani

    25/83

    13

    3.2 Project and Financial Planning

    3.2.1 Project Planning

    The key to a successful project is in the planning. Project planning is done to increase the

    likelihood that a project will be implemented efficiently, effectively and successfully. It

    involves working out what one wants to do and how is one going to do it. Creating a project

     plan is the first thing one should do when undertaking any kind of project.

    In case of wind power projects, the overall project plan may be comprised of several points:

      Business goal

      Project scopes

      Financial structure

      Policy guidelines

      Central govt. policy: MNRE

      State govt. policy: SNA

      List of constraints & assumption

      Professional assistance

      Technical planning

     

    Permitting planning

      Energy market analysis (who will buy the power)

      Regulatory compliance

      Legal aspects

      Ease & cost of maintenance

      Meeting the expectation & goals of stakeholders

      Long term outlook & expansion opportunities

      Gantt chart preparation

      Schedule flexibility

    3.2.2 Financial Planning

    It includes three major decisions:

      Decide how much you need (budgeting decisions)

     

    Decide when you will need it (cash flow)

      Decide where it will come from (financial planning)

  • 8/17/2019 Parth Belani

    26/83

    14

    Wind power projects, like all renewable energy projects, have a strong financial component

    which determines profitability or other goals, which incentives are used and how, who takes

    risks and earns rewards, how the development budget is controlled, and what has to be done

    to qualify for the intended financing.

    Financial planning for WPP, like other RE power projects, comprises of following

     parameters:

    1)  General project information

    a. 

    Rated capacity

     b.  PLF or CUF

    c. 

    Inflation

    d.  Start year

    e.  Project lifetime

    2) 

    Revenues - cash inflows

    a.  Ancillary products or benefits (like CDM, RECs etc.)

     b. 

    Cost recovery- Depreciation

    c.  Cost recovery- tax credits

    d. 

    Grants & incentivese.  Power purchase agreement or other sales agreement

    3)  Costs - cash outflow

    a.  Equipment cost including installation & site preparation

     b.  Balance of system(BOS) costs including all non-equipment Capital costs- such as

    interconnection & civil works

    c.  Developer soft costs, such as developer planning, environmental studies licensing

    & permitting & negotiation of PPA

    d.  loan interest

    e.  Recurrent costs, such as equipment replacement

    f.  Operation & maintenance

    g.  Site owner rent or royalties

    h.  Property tax

    i. 

    Project insurance

     j.  Income tax on revenue

  • 8/17/2019 Parth Belani

    27/83

    15

    4)  Financing costs –  debt & equity

    a. 

    Loan debt

     b.  Debt percentage (the percentage of capital costs being covered by a loan)

    c.  Loan interest rate & term

    d. 

    Equity

    e.  Equity financing fees

    f. 

    Initial working capital

    g.  Debt financing fees

    h.  Discount rate

    i.  Scenario analysis 

    Figure 1 : Financial Planning Process

  • 8/17/2019 Parth Belani

    28/83

    16

    3.3 Selection of State of preference

    The selection of the state of preference is the next task after the planning procedure has been

    completed. Following major factors are taken into consideration for selection of a state.

    Developers give different weightages to these factors depending upon their own strengths and

    weaknesses. 

    3.3.1 Wind Power Potential and Installed Capacity

    Wind availability is the first major factor taken into consideration by the developer to select

    the state for developing a wind power project. Out of the total wind power potential, the

    unutilised part is what attracts the developer for setting up the WPP. The total wind energy

     potential in India has been estimated at 49130 MW out of which more than 14000 MW has

     been utilised by various developers. The state wise wind power potential and installed

    capacities as on 31.12.2011 are shown below in the table. 

    Figure 2 : Wind Power Potential and Installed Capacity

    (Source: MNRE & Directory Indian Windpower 2011)

    Andhra Pradesh, Gujarat and Karnataka seem to be the most lucrative states as far as the

     potential and installed capacity of the wind power is concerned, since these states have large

     portion of their wind resource unutilised. Maharashtra and Rajasthan too have huge untapped

     potential. In Tamil Nadu, On the other hand, almost all the windy sites have been already

    occupied. Still, with advancement in the technology it is becoming viable to set up WPPs in

    the less windy sites. State wise achievable wind potential till 2020 is given below.

    5394

    10609

    8591

    790 920

    5439 5005 5374

    7008

    213

    2641 1852

    35 330

    2560 1830

    6613

    40

    20004000

    6000

    8000

    10000

    12000

    Estimated Potential (MW) Installed capacity as on 31.12.2011 (MW)

  • 8/17/2019 Parth Belani

    29/83

    17

    Table 1 : State wise Wind Power Till 2020

    State Incremental (MW) Re-powering (MW)

    Andhra Pradesh 7000-8000

    Gujarat 6000-7000

    Karnataka 5000 1000

    Madhya Pradesh 3000-3500

    Maharashtra 6000-7000

    Rajasthan 4000-5000

    Tamil Nadu 7000-8000 1500

    Orissa 500

    Chhattisgarh 500

    Jharkhand 500

    Total 39000-43000 2500

    Figure 3 : State wise Achievable wind Potential Till 2020 

    [Source: CRIS analysis based on registered projects and pipeline of developers in various

    states]

    3.3.2 Feed-in-Tariffs 

    A feed-in tariff (FiT), also known as feed-in law, advanced renewable tariff or preferential

    tariff is another important factor that affects the developers’ decision of selecting a state for

    setting up of WPPs. FiT is a policy mechanism designed to encourage the adoption of

    renewable energy sources and to help accelerate the transition toward grid parity for such

     projects. The Feed-in-Tariffs declared by the SERCs of the key states are shown below.

  • 8/17/2019 Parth Belani

    30/83

    18

    Table 2 : State Feed-in-Tariffs

    States Tariff rate (Rs/Unit)Tariff Period

    (Years)

    Gujarat 3.56 25

    Maharashtra

    Wind zone –  I 5.67

    13Wind zone –  II 4.93

    Wind zone –  III 4.2

    Wind zone –  IV 3.78

    RajasthanJaisalmer, Jodhpur and Balmer 4.46

    20Other districts 4.69

    Madhya

    Pradesh4.35 25

    Karnataka 3.7 10

    Tamil Nadu 3.39 20

    Andhra Pradesh 3.5 10

    Figure 4 : Feed-in-Tariff

    3.3.3 Special incentives and facilities by State GovernmentsSome state governments have declared special incentive or facilities to attract the wind / RE

    developers which are explained here. The developers should study these incentives before

    arriving to a decision of finalising the state of preference.

    Government of Karnataka:

    (From Karnataka Renewable Energy Policy 2009-14)

      Green Energy Fund: Green Energy Fund shall be established to facilitate financing for

    RE projects. 

      Consent from Departments & Statutory Clearances: KREDL shall obtain consent &

    statutory clearances from concerned state departments  for sites developed by them. In

    case of private land KREDL shall assist the developers in this regard. 

      Allotment Committee: A committee under Chairmanship of Additional Chief

    Secretary/Principle Secretary, Energy Department will consider allotment of capacity to  

    entrepreneurs. 

  • 8/17/2019 Parth Belani

    31/83

    19

      Settlements: Transactions shall be settled on monthly basis. Interest at the rate of State

    Bank of India short term prime lending rate shall be payable for delayed payment beyond

    a month. 

     

    Exemption from Demand Cut: Exemption of demand cut to the extent of 50% ofinstalled capacity assigned for captive use purpose, will be allowed. 

      Financial Incentives: Entry tax & other incentives shall be available to RE generation in

    accordance with Industrial Policy 2009-10. 

      Letter of Credit: Facility of LOC shall be provided by the ESCOMS to developer and its

    cost will be reimbursed to ESCOMs from Green Energy Fund.  

      Award Scheme: RE projects successfully commissioned during the original agreement

     period  will be awarded with a certificate with appreciation by the Govt. and a cash

    incentive from Green Energy Fund. 

    Government of Madhya Pradesh:

    (Notification No.6591-F18-10-XIII-93 dated 17.10.2006 as amended vide order No. F18-10-

    XIII-93 dated 12.05.2008)

      Green Energy Fund: will be created for facilitation of power generation through non-

    conventional energy sources.

      Exemption from Open Access Charges:  Nonconventional Energy based power

    generation shall be exempted from Open Access charges.

      Projects will be eligible for all benefits available to new industries under the Industrial

    Promotion Policy 2004.

    However one discouraging factor for WPP owners included in the state wind policy is that

    the 3rd party purchaser of wind energy will be allowed the facility of reduction in contract

    demand. 

    Government of Maharashtra:

    (From NCE Policy 2008) 

      Evacuation Arrangement: To be constructed with the approval of Transco/Discom by

    the developer at his cost. 50% of the approved expenditure to be reimbursed out of Green

    Energy Fund. 

  • 8/17/2019 Parth Belani

    32/83

    20

      Approach Road: To be constructed by MEDA out of Green Energy Fund. Repairs or

    strengthening of existing roads to be done by developer at his cost. 

      Encouragement to Co-operative Sector: 11% of total share capital of the project shall

     be paid from Green Energy Fund for projects set up by co-operative institutions.   Letter of Credit: The DISCOM shall provide the facility of LOC to the developer & the

    cost involved to be reimbursed to the DISCOM out of Green Energy Fund. 

      Octroi / Entry Tax: Taxes actually paid shall be reimbursed by MEDA out of Green

    Energy Fund. 

      Eligibility for Sanction

      It is obligatory to sell 50% of electricity to the Distribution Company under a long

    term agreement at the rate determined by MERC. Remaining 50% shall be sold within

    the State.

      Benefits under the policy shall be available to only such projects for which

    infrastructure approval is accorded by the Govt.

    Government of Rajasthan:

    (From NCE Policy dated 25.10.2004 as amended vide letters dated 10.03.05, 16.07.05,

    24.02.06, 30.11.06, 19.01.07 & 27.03.2008)

      Merit Order Despatch Not applicable to Wind Power Project 

      Exemption from Electricity Duty: Energy sold to a 3rd party will be exempted from

     payment of ED @50% for a  period of 7 years from COD. 

      Relocation of project: Re-location of project, if justified shall be permitted without any

    additional charge.

    3.3.4 Simplicity of procedures followed in the State

    Proactive and simplified procedure ensures smooth and timely completion of the project. The

    index for attitude of the State agency gets reflected in quantum of capacity addition. Higher

    capacity additions obviously indicate that investor faces least problems. Though this factor is

    of primary consideration to the developer yet it is also relevant to IPP owners particularly

    after completion of the project and routine O&M.

  • 8/17/2019 Parth Belani

    33/83

    21

    The procedures required to be followed in different states at various stages (mast installation,

    land acquisition, issue and redemption of REC etc.) of development of a WPP is explained in

    the relevant topics of this report.

    3.3.5 Evacuation Infrastructure

    The evacuation infrastructure development for wind power project is very costly and time

    consuming since the WPPs are generally in the remote sites where the grid connectivity is

    usually not readily available. Whether this infrastructure has to be developed by the grid

    utility or by the developer is a major factor for developer in his decision of selecting a state

    for WPP development. Various states have different policies for the evacuation infrastructure

    development which are explained here.

    Andhra Pradesh: Cost to be borne by the developer. 

    Gujarat: Voltage level for evacuation shall be 66 kV and above. Govt. Policy (Amendment-

    1) 2007 dated 07.01.2009 provides that owner will bear the entire cost up to 100 km; beyond

    this limit GETCO will construct at its cost. Approved capital cost includes 38 lakhs per MW

    towards cost of transmission line from project site to grid sub-station. 

    Karnataka and Madhya Pradesh: Cost to be borne by the developer. The capital costs

    specified by the respective SERCs are inclusive of the power evacuation infrastructure. 

    Maharashtra: Cost to be borne by the developer. Capital Cost of Project/MW is inclusive of

    cost of   power evacuation infrastructure up to interconnection point. Capital cost is linked to

     price indexation formula. 

    Rajasthan: A sum of Rs.2.00 Lakhs per MW is payable to RVPN as connectivity charges.

    RVPN to develop evacuation system from Pooling Sub-station to Grid Substation. If

    evacuation system is constructed by developer beyond pooling substation, Commission may

    determine transmission tariff on case to case basis.

    Tamil Nadu: To be borne by the Licensee if entire energy is sold to the Distribution

    Licensee. For captive consumption and third party sale, cost will have to be borne by the

    Developer but the work will be executed by the Licensee.

  • 8/17/2019 Parth Belani

    34/83

    22

    3.3.6 Grid availability

    This is a major problem primarily faced by WPP developers. Obtaining sanction and/or

    commissioning of the project gets adversely affected due to non-availability of evacuation

    facility. None of the states have so far made medium and long term plan to meet the demandof Wind Power Sector. The short term solution as offered by them is proving to be in-

    adequate because of higher growth rate now being observed. Even after commissioning of the

     project, particularly in Tamil Nadu, the wind farm feeders are occasionally switched off

    during high generation period which badly affects the investors. Therefore the WPPs must

    consider the Grid availability conditions in the state in their decision of selecting a state for

    WPP. Grid availability conditions are comparatively better in Andhra Pradesh, Gujarat and

    Rajasthan.

    3.3.7 Regularity in the receipt of payment

    This is an important factor that IPP owners and Bankers would consider to ensure financial

    viability of the project. The financial health of almost all State utilities is in bad shape.

    Comparative ranking of the states carried out by Consolidated Energy Consultants Limited

    (CECL) based on the general experience of IPP owners regarding timely receipt of payment

    shows that Rajasthan, Gujarat and Karnataka are better compared to other states as far as

    regularity in payment from the DISCOMs is concerned.

    3.3.8 Sharing of CDM Benefits

    The Clean Development Mechanism (CDM) is a project-based mechanism that allows public

    or private entities to invest in greenhouse gas (GHG) mitigating activities in developing

    countries and earn abatement credits, which can then be applied against their own GHG

    emissions or sold in the open market. For wind power producers, CDM benefits may become

    a source of revenue which can improve their project IRR by 1-1.5% and can make the project

    financially viable. CERC and different SERCs have declared sharing of the CDM benefits

    differently between the DISCOMs and the Developers. The WPP developers should examine

    the sharing of CDM benefits and its impact on the revenue in various states before arriving to

    a conclusion of finalising the state of preference.

  • 8/17/2019 Parth Belani

    35/83

    23

    The regulations regarding sharing of CDM benefits between the developers and the

    distribution licensees in different states are explained in the following table.

    Table 3 : Sharing of CDM Benefits in Different States

    State Sharing of CDM benefits

    CERC

    regulation, 2009

    100% to developers in the 1st year, reducing 10% every year till the

    sharing becomes 50:50 between developer and beneficiary.

    Gujarat As per CERC regulation

    Maharashtra As per CERC regulation

    Rajasthan75% to developer, 25% to Distribution licensee. Share of the licensee

    shall be fully passed on to consumers.

    M.P. As per CERC regulation

    Karnataka As per CERC regulation

    Tamil Nadu 100% 1st year, reducing 10% yearly up to 50:50

    A.P. 90% to developer and 10% to beneficiaries.

    3.3.9 Reactive Energy Charges

    Table 4 : Reactive Energy Charges

    State Reactive Energy Charges

    GujaratUpto 10% reactive power consumption - 10 paisa/Kvarh

    Above 10% reactive power consumption - 25paisa/kvarh above 10%

    Maharashtra 25 paisa/Kvarh with 5% escalation per year

    Rajasthan 5.75 paisa/Kvarh escalating 25 paise per year

    M.P. 27 paisa /Kvarh

    Tamil Nadu 25 paise/Kvarh upto 10% and double beyond

    A.P. 10  paise/Kvarh upto10% and 25 paise above10

    Reactive power consumption of wind turbine generators is high, especially during Start-up.

    Sometimes the reactive power consumption during start up is equivalent to the kW power

    rating of the turbine. This reactive power has traditionally always been imported from the

    grid. Although Wind turbine generators now-a-days are commonly fitted with reactive

    compensation systems of various ratings, there is requirement of reactive power consumptionfrom the grid during start-ups and for voltage control. Hence, the reactive power charges

  • 8/17/2019 Parth Belani

    36/83

    24

    applicable in the various states should be considered by the developer. The Reactive Energy

    charges in in various states are indicated in the following table.

    3.3.10 Banking

    Power banking is like cash banking whereby wind power producers feed in the electricity

    generated by their wind mills to the state grid and then draw that power for captive use within

    the period specified by the Appropriate Commission. Despite the development of latest

    technology in the wind energy sector it is still not possible to declare the exact wind power

    generation. Hence, to help the wind power generators and attract investment, some states

    have come up with the provision of banking of wind power. The banking charges are

    applicable as decided by the Appropriate Commission. In Banking, only the transactions of

    energy take place; there is no transaction of currency. Banking regulations in key states are

    explained in the following table. 

    Table 5 : State wise Banking Regulations

    State Banking Regulations

    Gujarat Only for captive use. Allowed for one month.

    Maharashtra

    Allowed for a year (only for captive). Surplus energy is limited to 10% of

    injected to grid up to 31st march and purchased by state at lowest Tod slab

    rate of HT.

    Rajasthan

    Allowed only for 6 months from April to September and October to March.

    Banking is not permitted from December to February. Surplus energy is

     paid at 60% of large industrial tariff.

    M.P.

    Permitted for a period of a financial year at 2% charge. Consumption of

     banked energy is subject to approval of Discom. Surplus energy at the end

    of banking period to be procured by the Discom as per the decision of the

    MPERC.

    Karnataka

    Permitted for 12 months at 2@ charge. Energy banked beyond the

     prescribed time will be utilised and paid for by the Karnataka Power

    Transmission Co. Ltd/Distribution Licensee concerned at tariff applicable as

     per KERC norms.

    Tamil Nadu Allowed for 1 year at 5% banking charge.

    A.P. Not allowed. Surplus power is paid at 75% of lowest bid tariff.

  • 8/17/2019 Parth Belani

    37/83

    25

    3.3.11 Transmission and wheeling charges

    Transmission and Wheeling charges, specified by SERCs of the key states, as a percentage of

    the total energy transmitted are given in the following table. The losses assumed for

    computation of the transmission and wheeling charges should also be taken intoconsideration.

    Table 6 : State wise Transmission and Wheeling Charges

    State Transmission and wheeling charges

    Gujarat

    1)  For 66KV and above - charges and losses are those applicable to open

    access consumers

    2) 

    For below 66KV - charges are those applicable to open access consumers;

    considering

    i) 

    For more than one WEGs - Losses at 10% and shared in the ratio of

    4:6 between transmission and distribution

    ii)  For one WEG - losses at 7% and shared in the ratio of 4:3 between

    transmission and distribution.

    Maharashtra

    Transmission losses 4.85% and wheeling losses 0 to 9% according to the

    voltage level.

    Transmission charges - Rs 126.86/KW/month (long term), Rs 31.72/KW/month

    (short term).

    Wheeling charges - Rs 0 to 245/kw/month according to voltage level.

    Rajasthan

    Transmission loss - from 4.4 to 8% at different voltage levels

    Transmission charges - Rs 76/kw/month

    Wheeling charges 5.5 paise/kwh

    M.P. 2% of the energy injected

    Karnataka 5% and Rs. 1.15/kwh for third party sale

    Tamil Nadu 5% of energy injected

    A.P. 5% of energy injected

    3.4 Site Identification

    After finalising the state to develop a WPP the next task is to select the best possible sites forinstallation of WPP. Following factors should be taken into consideration for selection of site.

  • 8/17/2019 Parth Belani

    38/83

    26

      There must be evidence of significant wind speed. Wind power density should be

    greater than or equal to 200 watt/m2.

      Locations like hills, ridges, plateaus, mountains etc. are preferred as these sites have

    more wind speeds compared to their surrounding locations.  The available area should be taken into consideration. Generally 15-25 acre/MW of

    land is required, but this may vary depending upon the micro-siting.

      Wind direction and wind shear  –   The sites with constant speeds and directions are

    more effective for wind power production and hence has plants at such sites have

    higher PLFs.

      Land cover pattern should be studies as it affects wind speeds at various heights.

     

    Accessibility  –   The heavy transportation vehicles should be able to reach to thelocation of the proposed WPP at reasonable cost of road construction and

    transportation.

      Land ownership (Private/revenue/forest) also is an important factor to be considered.

    Additional forest/environment clearances are required for occupying a forest land. On

    the other hand, the developer may face problems like non-convicibility of owners in

    occupation of private land.

      Prior commitments of the land –  The developer needs ensure that the proposed land is

    not already committed to any other WPP developer.

      Sites approved by C-WET must be given preference as the technical and regulatory

    work to occupy such sites reduces compared to other sites.

      There must be reasonable access to electrical transmission.

      The terrain must be favourable to construction.

      Apart from these several other factors need to be taken into consideration like - Cost

    of land, rehabilitation issues, scope for future expansion, labour and skills availability,

    minimum impact on labours etc.

    3.5 Feasibility Study

    Feasibility study is a preliminary study that is done to determine a project‘s viability through

    identifying potential return on investment as well as any fatal flow in the project if any. The

    results of the study are used to determine whether to proceed with the project or not. It

     provides a structured method that focuses on problems, identifies objectives, evaluates

  • 8/17/2019 Parth Belani

    39/83

    27

    alternatives, and aids in the selection of the best solution. It also describes current market

    situations, explores outcomes, and assesses the range of costs and benefits associated with the

    recommended action. In short, the technical and commercial viability of the project is

    checked in the feasibility study. After studying the outcomes of the feasibility study the

    owner choses whether to proceed further with the project or not.

    Feasibility Tasks:

      Site inspection

      Wind resource review

      Investigation of interconnection opportunities

      Selection of suitable process and technology

      Capacity fixation on the basis of project

     

    Capital cost study  Profitability analysis

      Fatal flaws review

      Grant research and application development

      Investigation of site access

    3.5.1 Generalized activities for feasibility study of Wind Power Projects:

    A.  Wind Resource Assessment 

    The first consideration in choosing a site is the wind availability. It is the most important

    factor affecting the viability of the project. To determine whether to have a project or not, it is

    necessary to conduct a resource assessment. Professional resource assessment is necessary to

    raise debt financing, necessary approvals/ clearances before proceeding further. In some

    cases, technology providers may be able to help in identifying options, the best location or

    technology to be used.

    Feasibility

    Study

    Commercial

    Viability

    Technical

    Viability

    Figure 5: Feasibility Study  

  • 8/17/2019 Parth Belani

    40/83

    28

    B.  Technology selection 

    Various wind energy technologies are available for generating power. However each

    technology has its own merits & demerits. Therefore the project viability depends on the

    selection of appropriate technology.

    Various technological choices have to be made for the following:

      Size and capacity of the turbines

      Hub height

      Rated and cut-in wind speeds

      Vertical or Horizontal axes

      Active and passive yaw

     

    Type of rotor controls  Airfoil nomenclature

      Tip-speed ratio

      Pitch control and stall control

      Rotor diameter

      Rotor solidity

      Betz limit

     

     Number of blades  Blade composition

      Type of generator

      Type of hub

      Type of towers

      Type of drive trains

    C. 

    Preliminary design Preliminary design includes engineering the project‘s details, including equipments locations,

    wiring, control systems, roads and foundations. The design of the scheme should be

    completed at a level adequate for costing and a bill of quantities to be determined. Hence, the

    design should be adequate for tendering purposes, and would include general arrangement

    and layout drawings. Prominent aspects of the works can be categorized into:

      Civil works

     

    Generating equipment

      Grid inter-connection design

  • 8/17/2019 Parth Belani

    41/83

    29

      Optimum system capacity

      Size & layout of structures & equipment

    If possible, the designers will therefore need to work closely with the machinery suppliers, so

    that specific equipment parameters can be considered as the basis of the design.

    D.  Grid connectivity 

      Check for an appropriate connection point near site

      Conversations with those who have an understanding of the system in the area where you

     propose to connect your project and contact local utility or Discom. It provides following

    information:

    i. 

    Understanding the transmission & distribution systemii.

     

    Power line capacity

    iii.  Substation capacity

    iv.  Existing protection scheme of power system

    v.  Conductor size

    vi. 

    Cost estimates for transmission upgrades

       Next step is to approach transmission utility , with an application, which includes the

    following:i.  Feasibility study

    ii.  System impact study

    iii. 

    Facility study

    iv. 

    Interconnection agreement

      The final step is executing the agreements and constructing the additional infrastructure

    needed to get your energy on the grid.

    E.  Environmental impact Assessment

    An environmental impact assessment (EIA) is an assessment of the possible impact —  positive

    or negative — that a proposed project may have on the environment, together consisting of the

    natural, social and economic aspects. The purpose of the assessment is to ensure that decision

    makers consider the ensuing environmental impacts when deciding whether to proceed with a

     project. The Ministry of Environment and Forests of India have been in a great effort in

    Environmental Impact Assessment in India. The main laws in nation are Water Act (1974),

    The Indian Wildlife (Protection) Act (1972), The Air (Prevention and Control of Pollution)

  • 8/17/2019 Parth Belani

    42/83

    30

    Act (1981) and The Environment (Protection) Act (1986). The responsible body for this is

    Central Pollution Control Board (CPCB). Wind-power generation has very low emissions on

    a life cycle basis, but has a number of environmental effects that may limit its potential. The

    following is required before the project implementation.

      Land use analysis- Helps in assessing the changes in land use pattern for setting up wind

    energy stations

      Air pollution

      Impact on flora & fauna

      Visual impact assessment

       Noise impact assessment

      Hydrological assessment

      Impact on communication signal

      On-site contamination & hazardous material issue

      Waste water management practices

      Depletion of water resources

      Economic effects on local economy (e.g. creation of jobs)

      Mitigating measures- ways in which any adverse environmental impact may be

    minimized

    F.  Social impact assessment 

    Social impact assessment includes the processes of analysing, monitoring and managing the

    intended and unintended social consequences, both positive and negative, of planned

    interventions (policies, programs, plans, projects) and any social change processes invoked

     by those interventions. Its primary purpose is to bring about a more sustainable and equitable

     biophysical and human environment. SIA is often carried out as part of, or in addition to,

    Environmental Impact Assessment, but it has not yet been as widely adopted as EIA in

    formal planning systems, often playing a minor role in combined environmental and social

    assessments. The Social Impact Assessment is analysed taking into account the effects of the

    RE power project implementation on the population around the site region under various

    aspects such as:

      Displacement of Habitat due to project implementation

  • 8/17/2019 Parth Belani

    43/83

    31

      Proximity to populated area

      Worker health & safety issues

      Local population deprived of use of their domestic fuel (Biomass)

     

    Improved Power Availability situation for the local population  Adequate Direct & Indirect employment opportunities to Rural Local population

    G.  Economic viability

    The purpose of an economic analysis is to demonstrate that the proposed project achieves

    optimum utilization of resources and is of sufficient economic merit to justify an investment

    in it. The analysis is therefore first made in the planning stage of the project, before any

    financial arrangements are discussed or entered into. The financing agencies will generally

    wish to see and approve the results of the analysis prior to making a commitment on

    financing the whole or part of the project. Economic analysis is always comparative. Sound

    economic evaluation of the proposed project during pre-feasibility and feasibility analysis is a

    fundamental requirement, particularly when the project requires a bank‘s assistance and

    financial commitment. The economic viability of the project is tested by financial modelling,

    which is explained in Chapter 4 of this report.

    3.6 Mast Installation, Data Collection and Data

    Verification  

    3.6.1 Permission for Mast Installation and Subsequent Capacity

    Allocation

    After finalising the site for the mast installation, the developer of a Wind Power Project has

    to take permission for installation of mast. A Land Option Agreement gives the developer the

    first right to develop the land for a wind farm. It should precedent the erection of masts to

    ensure that the data remains with the owner of the mast. It generally includes the following

      The right of first refusal to develop the land for renewable

      Details of the wind resource measurement agreement

      Detail of data use if no turbine is installed.

    Different procedures are followed in different states for obtaining the permission for mast

    installation. First of all, the developer has to contact the State Nodal Agency for the

     permission for installation of a mast. The SNA issues the permit if the land is either private

  • 8/17/2019 Parth Belani

    44/83

    32

    or revenue land. If the site for mast installation falls into forest land, the permission from

    forest department is also required. The procedure that needs to be followed in different states

    is explained below.

    Andhra Pradesh, Rajasthan and Orissa

      If the site is within the radius specified by the corresponding SNA (25 Km in Orissa)

    from the CWET mast, land is directly allotted on the Capacity Allotment basis, i.e.in

    terms of MW as per asked by the developer.

      Otherwise, application for land allotment for Wind Resource Assessment has to be

    submitted by the developer to the SNA. The area within the radius specified by the SNA

    (AP and Orissa - 5 km, Rajasthan  –   10 Km) from the proposed mast location will be

     blocked for 2 years for wind resource assessment.

      An application in the forest department is required for land allocation if mast location is

    in forest land. A fee of 1 lac per mast has to be paid to the forest department. This is

    applicable in all the states.

      Only the owner’s consent is required if the proposed mast location is in the private land.

      Approval for capacity allocation is sought from the SNA after the wind resource

    assessment is done.

    Karnataka and Madhya Pradesh

      In Karnataka and Madhya Pradesh, site for the mast installation is indicated and applied

    for permission to SNA. The SNA gives permission directly on capacity allotment basis.

    Maharashtra:

       No permission is required from MEDA for mast installation. Permission from forest

    department is needed if the proposed mast location is in the forest land (fees of Rs 1

    lakh/mast).

      The data collected is then registered with CWET. CWET examines and approves the

    data.

      MEDA, based on approval from CWET, certifies that the area within 10 Km radius from

    the mast is windy.

      An application, along with the MEDA certificate has to be submitted in forest

    department for land diversion.

  • 8/17/2019 Parth Belani

    45/83

    33

      MEDA allots the land on Capacity Allocation basis.

    Gujarat:

     

    Mast installation is to be done directly after the purchase of the land and no permission isrequired from GEDA. CWET and GEDA are only need to be informed about installation

    of mast.

     Approval from forest department is required if the proposed location for mast installation

    is in the forest land for which the fees are Rs 1 Lakh/mast.

    3.6.2 Installation of Wind Mast 

    Wind Mast installation is started after the permission has been received from the SNA/forest

    department.

    Experienced teams, skilled at installing wind monitoring met masts and equipment to the

    highest standards are required for the Wind Mast Installation. Generally, consultants who

    have core competency in the mast installation are hired. The consultants also provide wind

    monitoring product for the specific application and install instrumentation.

    3.6.3 Data collection

    MNRE published guidelines for wind data measurement on 20.06.2008. The

    following basic parameters are needed to be collected with the installed masts, for

    minimum 12 months.

      Wind speed (measure by anemometer)

      Wind direction (measure by wind vane)

     

    Wind shear - Increase in wind speed at greater height above ground

      Wind speed distribution

      Temperature (measure by temperature sensor)

      Vertical wind speed (optional)

      Change in temperature with height (optional)

      Barometric pressure (optional)

      Roughness of terrain (obstacles presence like nearby trees, buildings etc.)

  • 8/17/2019 Parth Belani

    46/83

    34

    Wind power can be measure by:

    WPD (W/m2) = ½*air density*rotor swept area*(wind speed) 3 

    3.6.4 Validation of Data through CWET

    The data collected though the mast has to be verified through CWET. The CWET Verifies

    the method and procedure of wind monitoring including installation details, sensors

    calibrations and data collection by the company at the station and prepares report

    accordingly. The cost is to be paid by the developer. The Developer also has to arrange site

    visits for the CWET scientists for verification of ground realities if the CWET asks for the

    same.

    3.7 Site Survey

    After the data has been approved by the CWET, team of the developer makes a visit to the

    site to conduct a site survey. Primary feasibility of the site for a wind farm development is

    checked at this stage.

    3.7.1 Soil / Ground Conditions

    Wind turbine generators require very solid foundations to secure that large structure in high

    wind conditions.