PRACTICA DIRIGIDA N ° 03-VIGAS Y LOSAS - 23.1O.13CURSO: METRADOSDOCENTE: L. ANTONIO APARICIO V. Ingeniero CivilTEMA: METRADOS EN ESTRUCTURAS VIGAS Y LOSAS
DESCRIPCION N° de Veces Largo (m) Ancho (m) Altura (m) SUB - TOTAL TOTAL
CONCRETO ARMADO
DESCRIPCION N° de Veces Largo (m) Ancho (m) Altura (m) SUB - TOTAL TOTAL
VIGAS, Concreto f´c = 210 Kg/cm2 (m3) m3
VP-01(EJE 1-1 ENTRE DYI") 1 13.00 0.25 0.40 1.30
VP-01(EJE 3-3 ENTRE DYI) 1 14.00 0.25 0.40 1.40
VP-01(EJE 4-4 ENTRE DYI) 1 14.00 0.25 0.40 1.40
VP-01(EJE 1"-1" ENTRE FYG) 1 1.83 0.25 0.40 0.18
VS-01(EJE D-D ENTRE 1Y4) 1 6.25 0.25 0.20 0.31
VS-01(EJE E-E ENTRE 3Y4) 1 3.00 0.25 0.20 0.15
VS-01(EJE F-F ENTRE 1Y3) 1 3.25 0.25 0.20 0.16
VS-01(EJE G-G ENTRE 1Y4) 1 6.50 0.25 0.20 0.33
VS-01(EJE G"-G" ENTRE 3Y4) 1 3.00 0.25 0.20 0.15
VS-01(EJE H-H ENTRE 1Y3) 1 3.25 0.25 0.20 0.16
VS-01(EJE H"-H" ENTRE 3Y4) 1 3.00 0.25 0.20 0.15
VS-01(EJE I"-I" ENTRE 1Y3) 1 3.25 0.25 0.20 0.16
VS-01(EJE I"-I" ENTRE 3Y4) 1 3.00 0.25 0.20 0.15
VS-02(EJE 3"-3" ENTRE GYH") 1 3.55 0.15 0.20 0.11
VS-02(EJE 1"-1" ENTRE HYI") 1 3.55 0.15 0.20 0.11
VS-02(EJE H"-H"ENTRE 1Y2) 1 2.00 0.15 0.20 0.06
VS-02(EJE I-I ENTRE 1Y4) 1 3.25 0.15 0.20 0.10
6.38
PRACTICA DIRIGIDA N ° 03-VIGAS Y LOSAS - 23.1O.13CURSO: METRADOSDOCENTE: L. ANTONIO APARICIO V. Ingeniero CivilTEMA: METRADOS EN ESTRUCTURAS VIGAS Y LOSAS
VIGAS, Encofrado y Desencofrado (m2) (M2)
VP-01(EJE 1-1 ENTRE DYI") 1 13.00 0.40 5.20
1 11.71 0.25 2.93
1 11.71 0.20 2.34
VP-01(EJE 3-3 ENTRE DYI) 2 13.25 0.20 5.30
1 11.30 0.25 2.83
VP-01(EJE 4-4 ENTRE DYI) 1 14.00 0.40 5.60
1 11.30 0.25 2.83
1 13.25 0.20 2.65
VP-01(EJE 1"-1" ENTRE FYG) 2 2.33 0.20 0.93
1 1.83 0.25 0.46
VS-01(EJE D-D ENTRE 1Y4) 1 6.25 0.25 1.56
VS-01(EJE E-E ENTRE 3Y4) 1 3.00 0.25 0.75
VS-01(EJE F-F ENTRE 1Y3) 1 3.00 0.25 0.75
VS-01(EJE G-G ENTRE 1Y4) 1 6.00 0.25 1.50
VS-01(EJE G"-G" ENTRE 3Y4) 1 2.85 0.25 0.71
VS-01(EJE H-H ENTRE 1Y3) 1 3.25 0.25 0.81
VS-01(EJE H"-H" ENTRE 3Y4) 1 0.85 0.25 0.21
VS-01(EJE I"-I" ENTRE 1Y3) 1 3.00 0.25 0.75
VS-01(EJE I"-I" ENTRE 3Y4) 1 3.00 0.25 0.75
VS-02(EJE 3"-3" ENTRE GYH") 1 3.05 0.15 0.46
VS-02(EJE 1"-1" ENTRE HYI") 1 3.55 0.15 0.53
VS-02(EJE H"-H"ENTRE 1Y2) 1 2.00 0.15 0.30
VS-02(EJE I-I ENTRE 1Y4) 1 3.25 0.15 0.49
40.64
LOSAS (ENCOFRADO Y DESENCOFRADO) M2
67.79
Concreto f´c = 210 Kg/cm2 (m3) m3
67.79 0.09 6.10
LADRILLO DE TECHO LD
67.79 8.33 564.69
∑ DE AREAS
SOLUCION PRACTICA DIRIGIDA N ° 01_VERSION 02CURSO: METRADOS
DOCENTE: L. ANTONIO APARICIO V. Ingeniero CivilTEMA: METRADOS EN ESTRUCTURAS ACERO
DESCRIPCION DIAMETRO N° deCANTIDAD
LONGITUD 1/4" 3/8" 1/2" 5/8" 3/4" TOTAL(Pulg.) VECES X PIEZA 0.256 0.560 0.994 1.552 2.235 (Kg.)
VIGAS, Acero Grado 60° - f`y = 4,200 Kg/cm2.
VP-01(EJE 1-1 ENTRE DYI") 5/8" 1 5 13.40 67.00ESTRIBOS 3/8" 1 96 1.30 124.80
VP-01(EJE 3-3 ENTRE DYI) 5/8" 1 5 14.40 72.00ESTRIBOS 3/8" 1 103 1.30 133.90
VP-01(EJE 4-4 ENTRE DYI) 5/8" 1 5 14.40 72.00ESTRIBOS 3/8" 1 116 1.30 150.80
VP-01(EJE 1"-1" ENTRE FYG) 5/8" 1 5 1.23 6.13ESTRIBOS 3/8" 1 20 1.30 26.00
VS-01(EJE D-D ENTRE 1Y4) 1/2" 1 6 7.20 43.20ESTRIBOS 3/8" 1 55 0.90 49.50
VS-01(EJE E-E ENTRE 3Y4) 1/2" 1 6 3.20 19.20ESTRIBOS 3/8" 1 27 0.90 24.30
VS-01(EJE F-F ENTRE 1Y3) 1/2" 1 6 3.45 20.70ESTRIBOS 3/8" 1 26 0.90 23.40
VS-01(EJE G-G ENTRE 1Y4) 1/2" 1 6 7.20 43.20ESTRIBOS 3/8" 1 56 0.90 50.40
VS-01(EJE G"-G" ENTRE 3Y4) 1/2" 1 6 3.40 20.40ESTRIBOS 3/8" 1 29 0.90 26.10
VS-01(EJE H-H ENTRE 1Y3) 1/2" 1 6 3.45 20.70ESTRIBOS 3/8" 1 28 0.90 25.20
VS-01(EJE H"-H" ENTRE 3Y4) 1/2" 1 6 3.40 20.40ESTRIBOS 3/8" 1 29 0.90 26.10
VS-01(EJE I"-I" ENTRE 1Y3) 1/2" 1 6 3.45 20.70ESTRIBOS 3/8" 1 26 0.90 23.40
VS-01(EJE I"-I" ENTRE 3Y4) 1/2" 1 6 3.40 20.40ESTRIBOS 3/8" 1 27 0.90 24.30
VS-02(EJE 3"-3" ENTRE GYH") 1/2" 1 4 3.85 15.40ESTRIBOS 3/8" 1 21 0.70 14.70
VS-02(EJE 1"-1" ENTRE HYI") 1/2" 1 4 3.75 15.00ESTRIBOS 3/8" 1 21 0.70 14.70
VS-02(EJE H"-H"ENTRE 1Y2) 1/2" 1 4 2.40 9.60ESTRIBOS 3/8" 1 12 0.70 8.40
VS-02(EJE I-I ENTRE 1Y4) 1/2" 1 4 3.45 13.80ESTRIBOS 3/8" 1 18 0.70 12.60
TOTAL DE ACERO EN METROS = 758.60 1408.09 217.13PESO ESPECIFICO DE CADA VARILLA (KG/ML) = 424.82 1399.65 336.98TOTAL ACERO EN KILOS = 2161.44
SOLUCION PRACTICA DIRIGIDA N ° 01_VERSION 02CURSO: METRADOS
DOCENTE: L. ANTONIO APARICIO V. Ingeniero CivilTEMA: METRADOS EN ESTRUCTURAS ACERO
DESCRIPCION DIAMETRO N° deCANTIDAD
LONGITUD 1/4" 3/8" 1/2" 5/8" 3/4" TOTAL(Pulg.) VECES X PIEZA 0.256 0.560 0.994 1.552 2.235 (Kg.)
LOSAS, Acero Grado 60° - f`y = 4,200 Kg/cm2.
1/2" 10 2 1.35 27.00PAÑO 1 1/2" 10 1 6.95 69.50
1/2" 10 1 2.55 25.501/2" 5 1 2.45 12.25
PAÑO 2 1/2" 8 1 1.35 10.801/2" 5 1 4.53 22.651/2" 7 1 1.30 9.10
PAÑO 3 1/2" 5 1 2.31 11.551/2" 5 1 4.70 23.501/2" 4 2 1.30 10.40
PAÑO 4 1/2" 4 1 2.25 9.001/2" 4 1 6.87 27.481/2" 6 1 2.35 14.10
PAÑO 5 1/2" 7 1 1.30 9.101/2" 7 1 4.68 32.761/2" 3 2 1.30 7.80
PAÑO 6 1/2" 3 1 2.25 6.751/2" 3 1 6.93 20.79
TOTAL DE ACERO EN METROS = 350.03PESO ESPECIFICO DE CADA VARILLA (KG/ML) = 347.93TOTAL ACERO EN KILOS = 347.93
UNIVERSIDAD “ALAS PERUANAS”
INGENIERIA CIVIL – "Costos y Presupuestos” EXAMEN
Alumno……..……………………………………………………………………………………..……………..…(Apellidos y Nombres)
VALOR REFERENCIAL
OBRA : CONSTRUCCION DE "DOS AULAS" - PIURA.PROPIETARIO : MINISTERIO DE EDUCACIONFECHA : OCTUBRE DEL 2,010.
PRECIO
ITEM PARTIDA UNIDAD CANTIDAD UNITARIO
( S/. )
3.00.00 MOVIMIENTO DE TIERRAS
3.01.00 Excavación manual de zanjas, h= 1.00 m. m3.
3.02.00 Relleno compactado con material Propio m3.
3.03.00 Eliminación de mat. excedente, a 5 Km. m3.
4.00.00 OBRAS DE CONCRETO SIMPLE
4.01.00 Cimientos corridos, concreto 1:10+30% P.G. m3.
4.02.00 Falso piso, concreto 1:10, espesor = 10 cm. m2.
4.02.00 Solado para zapatas, concreto 1:12, espesor = 10 cm. m2.
5.00.00 OBRAS DE CONCRETO ARMADO
5.01.01 Concreto en Zapatas, f`c= 210 Kg/cm2. m3.
5.01.02 Acero para Zapatas, fy= 4,200 Kg/cm2. kg.
5.02.01 Concreto en Vigas de Cimentación, f`c= 210 Kg/cm2. m3.
5.02.02 Encofrado y desencofrado de Vigas de Cimentación m2.
5.02.03 Acero para Vigas de Cimentación, fy= 4,200 Kg/cm2. kg.
5.03.01 Concreto en Sobrecimientos, f`c= 175 Kg/cm2. m3.
5.03.02 Encofrado y desencofrado de Sobrecimientos m2.
5.03.03 Acero para Sobrecimientos, fy= 4,200 Kg/cm2. kg.