  • 8/10/2019 Pfc Apdrp II

    1/19

    Funding for a brighter tomorrow1

    POWER SECTOR CONCLAVE14thJuly - 2008

    Avkash Saxena

    General Manager (APDRP)

    Power Finance Corporation Ltd.

    Restructured APDRPXITHPlan

  • 8/10/2019 Pfc Apdrp II

    2/19

    Funding for a brighter tomorrow2

    APDRP-II Scheme (Proposed)

    Restructured APDRP-II is GoIs initiative to

    reform Distribution Sector during XITHplan. TotalProgramme size is about Rs 50,000 Crores

    Proposed to cover urban areastowns and citieswith population of more than 30,000 (10,000 incase of special category states). Projects underthe scheme shall be taken up in Two Parts.

    Part-A will cover IT applications in distributionsector

    Part-B will cover System improvement,strengthening and augmentation etc.

  • 8/10/2019 Pfc Apdrp II

    3/19

    Funding for a brighter tomorrow3

    APDRP-II Scheme (contd)

    Part-A will include among others

    Consumer Indexing,

    GIS Mapping, Asset Mapping

    Metering of Distribution Transformers / Feeders, Automatic Data Logging

    Feeder Segregation/ Ring Fencing

    IT applications for redressal of consumergrievances, meter reading, billing & collection,

    Energy Audit

    Establishment of the Base Line data System

  • 8/10/2019 Pfc Apdrp II

    4/19

    Funding for a brighter tomorrow4

    Part-B will include among others

    Renovation, modernization and strengthening of11 kV level Substations,

    Transformers/Transformer Centres, Re-conductoring of lines at 11kv level and below,

    Load Bifurcation, Load Balancing,

    HVDS,

    Strengthening at 33 kV or 66 kV levels

    installation of capacitor banks and mobile servicecentres etc.

    APDRP-II Scheme (contd)

  • 8/10/2019 Pfc Apdrp II

    5/19

    Funding for a brighter tomorrow5

    Funding of Schemes/ Projects

    GoI will provide 100% Loan for part A of the

    schemes including IT applications and projects

    for establishing Base Line data.

    GoI will provide 50% Loan for Part B of theschemes (90% for special category States).

    The counterpart funding will be done by

    PFC/REC (FIs)

  • 8/10/2019 Pfc Apdrp II

    6/19

    Funding for a brighter tomorrow6

    Conversion of GoI Loan to Grant

    The entire amount of GoI loan (100%) for part A

    of the project shall be converted into grant after

    establishment of the required Base-Line data

    system within a stipulated time frame and dulyverified by Monitoring agency

    Upto 50% (90% for special category States) loan

    provided by GoI for Part-B projects shall be

    converted into grant progressively onachievement of AT&C loss reduction targets.

  • 8/10/2019 Pfc Apdrp II

    7/19Funding for a brighter tomorrow

    7

    Approval Mechanism

    The final SRS document and the various panels

    of Advisor/ Consultants/ Agencies will be

    approved by the APDRP Steering Committee of

    MoP Schemes to be approved by APDRP Steering

    Committee of MoP based on the DPRs.

    MoP will approve conversion of loan to grant/

    Release of grants to Utilities based on the

    Scrutiny of claims

  • 8/10/2019 Pfc Apdrp II

    8/19Funding for a brighter tomorrow

    8

    MoP

    Nodal Agency(PFC/ SPV)

    UtilitiesTechnical

    Advisors

    Monitoring

    Agencies

    Empanelled

    IT Consultants

    (Part-A)

    Empanelled

    IT Implementation

    Agencies (Part-A)

    Process

    Consultant

    Responsibilities Flow Dig

  • 8/10/2019 Pfc Apdrp II

    9/19Funding for a brighter tomorrow

    9

    Nodal Agency

    PFC through its subsidiary (SPV) will act as asingle window service under APDRP-II

    PFC will coordinate with agencies involved such

    as MoP, APDRP Steering Committee, CEA andvarious Consultants for speedy and timelycompletion of projects and thus assist the utilitiesachieving loss reduction targets

    As Nodal Agency, PFC will have overallresponsibility of Implementation of Programme

    Recommendation of projects for sanction to MoP/APDRP Steering Committee

  • 8/10/2019 Pfc Apdrp II

    10/19Funding for a brighter tomorrow

    10

    Nodal Agency ( contd)

    Provide necessary support to APDRP SteeringCommittee

    Scrutiny of claims & recommendation to MoP forconversion of loan to grant/ Release of grants to

    Utilities Preparation of biddable SRS document, model

    DPRs for Part A & B

    Scrutiny & vetting of DPRs for Part A & B

    Monitoring of the implementation of each project

  • 8/10/2019 Pfc Apdrp II

    11/19Funding for a brighter tomorrow

    11

    Nodal Agency ( contd)

    Establishment of base line data and evaluation ofyearly AT&C loss by Independent Evaluators

    Creation and maintenance of web based MIS

    Empanelment of IT consultants and implementingagency to assist Utilities

    Capacity building of utilities through workshops

    etc.

    PFC may engage consultants for some or all of

    the activities, as required

  • 8/10/2019 Pfc Apdrp II

    12/19

    Funding for a brighter tomorrow12

    Process Consultant

    Process Consultantwill assist Nodal Agency for

    Finalization of SRS biddable document

    Empanelment of IT consultants for Part A

    Empanelment of IT Implementing Agencies for

    Part A

    Short listing and appointment of Monitoring

    Agencies Design & installation of Web based MIS

  • 8/10/2019 Pfc Apdrp II

    13/19

    Funding for a brighter tomorrow13

    Web Based MIS

    Creation of Web based comprehensive MIS andmonitoring system for APDRP II. It will include

    The objective and guideline of the program.

    The coverage of the program State wise DPRs submitted, sanctioned etc

    Project Progress Status ( Physical & financial)

    Scheme wise Bench mark parameters[ The input from the bench mark parameters shall

    be obtained primarily from the base line datacollection system .]

  • 8/10/2019 Pfc Apdrp II

    14/19

    Funding for a brighter tomorrow14

    IT-Consultant

    IT Consultantswill assist Utilities To customize project level Bid Documents for Part-

    A, meeting the requirement of specific utility and

    comprising of Utility IT mapping,

    geographical area/ feeders to be covered for IT

    implementation,

    segregation of feeders,

    measures to increase customer satisfaction, base line data collection system etc.

    Hand hold the utility for implementation fromconcept to commissioning of the project

  • 8/10/2019 Pfc Apdrp II

    15/19

    Funding for a brighter tomorrow15

    IT-Implementation Agencies

    IT Implementation Agencieswill assist Utilities

    To Implement the IT related schemes in the

    defined area/ feeders as per scope and terms and

    condition stipulated by the Utility/ IT Consultant .

    [ Utilities may appoint the IT implementing agency

    directly by using Panel of IT Agencies with

    PFC/SPV or by using services of IT Consultants

    following the bidding process and selecting them.]

  • 8/10/2019 Pfc Apdrp II

    16/19

    Funding for a brighter tomorrow16

    Technical Advisor (s)

    Technical Advisorswill assist Nodal Agency in

    following areas

    Technical scrutiny & vetting of DPRs (A&B),

    Random inspection of works (Part B)

    Monitoring of implementation of Part A & B

    Certification of work completion (A&B)

    Examining & recommendation for deviations Periodic reports to SPV/ MoP

  • 8/10/2019 Pfc Apdrp II

    17/19

    Funding for a brighter tomorrow17

    Monitoring Agency

    Monitoring Agencieswill act as independentthird party agency for

    Establishing base line data (initial loss level in the

    system) Annual project wise verification of yearly loss

    levels against the benchmark parameters

    Assessment of claims for conversion of loan into

    grant for Part-A and Part-B projects Submission of report to PFC

  • 8/10/2019 Pfc Apdrp II

    18/19

    Funding for a brighter tomorrow18

  • 8/10/2019 Pfc Apdrp II

    19/19

    Funding for a brighter tomorrow19

    Ministry of Power

    Nodal Agency (PFC/SPV)As Nodal Agency, overall responsibility of Implementation of Programme

    Preparation of biddable SRS document, model DPRs for Part A & B

    Scrutiny & vetting of DPRs for Part A &BRecommendation of projects for sanction to MoP

    Monitoring of the implementation of each project

    Establishment of base line data and evaluation of yearly AT&C loss by Independent Evaluators

    Scrutiny of claims & recommendation to MoP for conversion of loan to grant

    Release of grants to Utilities

    Creation and maintenance of web based portable for MIS

    Empanelment of IT consultants and implementing agency to assist Utilities

    Provide necessary support to APDRP Steering Committee

    Capacity building of utilities through workshops etc.

    PFC may engage consultants for some or all of the activities, as required.

    Process Consultant

    Finalization of SRS biddable

    document

    Assist PFC in empanelment of IT

    consultants & Implementing

    Agencies for Part A

    Assist PFC in appointment of

    Technical Advisors & Monitoring

    Agencies

    Design & installation of Webbased MIS

    Technical Advisor (s)

    Technical scrutiny & vetting of DPRs

    (A&B), examine & recommending of

    deviations during implementation

    Random inspection of works (Part B)

    Monitoring of implementation of Part

    A & B

    Certification of work completion

    (A&B)

    Submission of report to PFC/ MoP

    Monitoring

    AgencyEstablishment of

    Base Line Data

    Annual project

    wise verification

    of AT&C level

    Submission of

    report to PFC