phone: 586.576.7600 fax: 586.576.0850...

18
Phone: 586.576.7600 Fax: 586.576.0850 www.Conquest-Firespray.com [email protected] 28408 Lorna Ave. Warren, MI 48092

Upload: phungkhanh

Post on 02-Jul-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

Phone: 586.576.7600Fax: 586.576.0850

[email protected]

28408 Lorna Ave. Warren, MI 48092

2

……………………………. .3

…………………………….3

………………...….4

………….5

……………………………...7

…………...…………….….9

……………………………...12

…….......14

………..……….15

© COPYRIGHT 2009-2010 Firespray International Ltd. All Rights Reserved; Revision 2.0

3

The Firespray Flamebar BW11 System is an innovative solution for Commercial Kitchen Grease

Duct Ventilation in full compliance with the recent changes to the model codes for 2009. Duct

segments are constructed from 20-gauge galvanized sheet metal in flanged sections up to 49” x

49” cross section. The duct is then degreased and factory fire sprayed with Flamebar BW11

which is a specially formulated, water based compound which contains selected mineral filters in

a lower permeability elastomeric binder to a thickness of approximately 0.04” (1mm) to give a

VOC-free finished product. The ductwork is fabricated in flanged sections up to 59” in length

and is assembled on site utilizing Flamebar gaskets and sealants. For Grease Duct applications

requiring a shaft enclosure or a zero clearance installation, the ductwork can then be wrapped

with Unifrax FyreWrap Elite 1.5 or Max 2.0 duct insulation, consisting of two layers applied

directly to the duct surface in accordance with Unifrax’s installation instructions.

Firespray International utilizes a Complete System approach to perform the task of complying

with the rigorous testing and application requirements associated with the exhaust ventilation of

grease-laden vapors from a commercial cooking facility:

Duct segments incorporate a strict fabrication specification including gauge, seams, flanges,

reinforcement, access door construction, wall and floor penetration seals, etc.

Further, recognizing that the supports are an integral part of the system, and that the tensile

strength of steel is significantly reduced under a fire load, the comprehensive specification

directly addresses both vertical and horizontal arrangements and the enhanced hardware

requirements (anchors, threaded bar, unistrut, etc.).

Spray facilities are operated by trained and licensed operators, performing the degreasing and

coating application to strict guidelines, in addition to being subject to periodic inspection by

Intertek ETL inspectors.

Installation of ductwork is performed on site by contractors that receive both training and

support by Firespray and its Licensees, in accordance with the Flamebar specification.

All installations are inspected by Firespray and/or its Licensees subject to a comprehensive

checklist, and issued an Approval Certificate affixed with a Seal of Compliance.

The Firespray Flamebar BW11 System is a purpose built system that is uniquely constructed as a

fire resistive enclosure for commercial kitchen Grease Ducts. It is a tested and proven performer

on a worldwide basis and fully complies with standards UL 1978 and ASTM E-2336, as

referenced by the IMC, UMC, and the NFPA. It is an acceptable alternative to a 2-hour fire

resistant rated shaft enclosure when used in conjunction with the Unifrax FyreWrap Elite 1.5 or

Max 2.0 insulation, thus providing zero clearance to combustibles.

4

There are numerous advantages to the Flamebar system that apply to all parties involved,

including the Building Owner, the Architect, the Consulting Engineer, General Contractor,

Mechanical Contractor, and Installing Contractor:

Safety with Single Source Responsibility

o The design of all Flamebar BW11 Fire Duct Systems is to a certified standard.

o Flamebar BW11 Grease Duct is manufactured and sprayed to standards set by Firespray.

o Flamebar BW11 Grease Duct is erected to Firespray installation standards.

o All Flamebar BW11 installations meeting specification requirements are issued a

Certificate of Conformity.

Code Compliance and Testing

o Flamebar BW11 Grease Duct complies with ASTM E-2336 and is listed by Intertek ETL

Testing Services to provide a 2-hour rating for fire resistive Grease Ducts (as referenced

by the IMC, UMC, and NFPA96).

o Flamebar BW11 Grease Duct also fully complies with the performance requirements of

UL 1978 and is tested by Intertek ETL Testing Services.

o Refer to the “Testing” section below in this document for additional related tests.

A Competitive and Proven Solution

The Flamebar BW11 Fire Duct system has been used extensively throughout Europe, the

Middle East, and the Far East for more than 20 years in a variety of applications and in the

United States since 2002. The Flamebar BW11Grease Duct is particularly competitive

against alternative systems and can yield significant cost savings on an installed basis

depending on the project parameters.

Rapid Installation

The Flamebar BW11 Grease Duct System’s relatively light weight and use of conventional

flanged sections enables contractors to perform the installation on site at a substantially

greater rate than the conventional approach utilizing welded joints on 16-gauge carbon steel.

Large Size Capability

The Flamebar BW11 Grease Duct is Listed by Intertek ETL for rectangular ductwork in sizes

up to 49” x 49”, the largest ever tested.

Relatively Light Weight

The Flamebar BW11 Fire Duct is the lightest fire duct system available.

Leakage Testing

The construction and sealing of the Flamebar BW11 Fire Duct System allows the ductwork

to be tested up to a maximum of 6” wg pressure per SMACNA, if required by the client.

Moisture Absorption

The Flamebar BW11 Fire Duct system is non-hygroscopic and has been tested in an artificial

weatherometer to an equivalent of 60 years of external exposure. Systems installed outdoors,

however, require additional protection (refer to Installation Section on page 10).

Mold Resistance

The Flamebar BW11 Duct System contains antimicrobial biocide and has been evaluated for

resistance to fungal attack. It does not support the growth of mold, fungi or bacteria.

Easily Cleaned

The robust and smooth internal finish of Flamebar BW11 Systems enable easy cleaning of

the ductwork and is therefore ideal for Commercial Kitchen Grease Duct installations.

5

ASTM E-2336: Fire Resistive Grease Duct Enclosure

Systems

Complies, Listed by Intertek ETL

Zero clearance to combustibles at all locations on duct

wrap’s surface

ASTM E-84 / UL723: Surface Burning Characteristics

- Flame Spread Rating

- Smoke Developed Rating

Unfaced Blanket Encapsulated

Zero <25

Zero <50

ASTM E-814: Firestop Test

Classified by UL: F-Rating = 2 Hrs; T-Rating = 2 Hrs.

Refer to section on Through Penetration Fire Seals in the

Installation section of this document for more detail

ASTM E-136: Non Combustibility Test

Complies

ASTM C-518: Durability Test

Complies

UL 1978: Test Standard for Grease Ducts

Complies, Evaluation Report by Intertek ETL confirms

that all performance requirements of UL 1978 have been

met, including Section 16, (Grease/Lard) Leakage Test

ASTM E2336: Fire Resistive Grease Duct Enclosure Systems

Flamebar BW11 Grease Duct is a Listed System to ASTM E-2336. The Standard evaluates

enclosure materials and grease duct enclosure systems using five test methods as outlined below:

1. Non-Combustibility: As defined by ASTM E-136, it demonstrates the enclosure material’s

ability to resist combustion at a standardized temperature and duration.

2. Fire Resistance: as defined by E-119, it illustrates the ability of the enclosure material to

resist the effects of fire when applied in a vertical application; includes a hose stream test.

3. Durability: As defined by ASTM C-518, it simulates the effects of long term exposure of

typical in-service conditions on the thermal conductivity of the enclosure materials.

4. Internal Fire: Uses two standardized fire exposures occurring inside the grease duct where

first the temperature is raised to 500F and maintained for 4 hours, and then elevated to

2,000°F and maintained for 30 min. In addition to verifying that there are no openings on the

surface of the enclosure material and also the absence of flaming, the temperature of the

outer surface is measured against set limits for both tests. Passing this test provides the zero

clearance to combustibles rating.

5. Fire Engulfment with through penetration fire stop: As defined by ASTM E-119, it

simulates a fire on the outside of the grease duct and incorporates a subsequent hose stream

test. The integrity and stability of the duct is evaluated for a 1-hour or 2-hour rating period,

and the through penetrations must comply with ASTM E-814

6

Additional Flamebar BW11 Properties and Classifications

When Installed Without Insulation

Flamebar BW11 Fire Duct is classified by Underwriters Laboratories in accordance with ISO

6944 (1985) for up to 4 hours as a smoke and

fire duct.

ASTM E-119 Full Scale Engulfment Test: Two

Hour Fire Rating. Includes the Hose Stream

Test with water Pressure of 30psi for 2.5 min

ASTM E-84 / UL723 Surface Burning

Characteristics: Flame Index: 9.4; Smoke

Index: 0.2

Artificial Weather of Flamebar BW11: The samples have undergone over 22,000 hours of

alternate UV and condensation cycling which is considered excessive in duration terms,

normally 1,000 hours is sufficient to predict whether a material is suitable for exterior semi-

exposed conditions. 22,000 hours is equivalent to 60 years external exposure.

Expansion of Flamebar BW11: As all steel expands with temperature, there will naturally be an

expansion of fire duct under fire conditions as follows:

At 2012°F an expansion of 0.016 in per in

At 1112°F an expansion of 0.008 in per in

At 806°F an expansion of 0.006 in per in

Commercial kitchen extract ductwork presents a particular hazard in that combustible deposits

can accumulate on its internal surfaces. Therefore, the ductwork should resist fire from inside

the duct (Type B) and from outside the duct (Type A). Fire dampers must not be used:

7

The Firespray Flamebar BW11 System grease duct is constructed from 20-gauge galvanized

sheet metal in flanged sections of up to 59” in length with a maximum cross section of 49” x 49”.

The duct is then degreased and factory fire sprayed with Flamebar BW11 to a thickness of

approximately 0.04” (1 mm) to give a finished product. The ductwork is assembled on site

utilizing Flamebar gaskets and sealants. For Grease Duct applications requiring a shaft enclosure

or a zero clearance installation, the ductwork can then be wrapped with Unifrax FyreWrap Elite

1.5 or Max 2.0 duct insulation, consisting of two layers applied directly to the duct surface.

All of the above components are necessary to comply with the ASTM E-2336 and UL 1978 test

requirements. Detailed below are all aspects of the fabrication, installation and insulation of the

Flamebar BW11 Grease Duct System:

Fabrication:

Table 1 itemizes fabrication details for Flamebar BW11 Grease Duct rectangular ductwork based

on SMACNA HVAC Duct Construction Standard, 2nd

Edition, for static pressures up to 6” wg,

positive or negative, constructed of G60 coated galvanized steel of lockforming grade to ASTM

A924, coated with 0.03” - 0.04” of Flamebar BW11.

Table 1: Flamebar BW11 Grease Duct Fabrication Details, 120 min Fire Endurance

Reinforcement:

The Mechanical Code for grease ducts stipulates that there

shall be no protrusions into the duct, so conventional tie rod

reinforcement would not be acceptable. Flamebar Grease

Duct utilizes rolled steel angle (RSA) spot welded at 6”

centers around the external perimeter of the duct at

midsection per the schedule in Table 1 above, and is

illustrated in Figure 1 to the right.

Flanges:

The Grease Duct system utilizes Ductmate flanges for sides

up to 42” (Figure 3), or alternatively RSA Flanges for sides

up to 49” (Figure 2). Grease Ducts flanged with Ductmate

Figure 1: Duct Reinforcement

8

Figure 2: Steel Angle (RSA) Flanged Joint

Figure 3: Ductmate Flange with G-Clamp

Figure 5: Duct Seam Figure 6: Ductmate Flange

with Gasket

would have 3/8” bolts at the corners and intermediate G-Clamps at 12” maximum spacing.

Angle Flanges would have 3/8” bolts at the corners and at 6” maximum centers. Ductmate

flanges would have Flamebar Fire Sealant applied to the inner seam between the flange and the

duct as shown in Figure 3, in addition to the corners. Flamebar self-adhesive gasket is applied in

between all joints during installation, with two layers of gasket (positioned side by side,

essentially double width) required for ducts with sides greater than 24”. Care must be taken to

apply the gasket along the inner edge of the flange in order to avoid the formation of a potential

grease trap. Gasket can be installed in one or more strips which must all fully overlap each other

at intersecting corners (or ends) as shown in Figure 6. Gasket ends must never be simply butted

up against each other. The intumescent impregnated closed cell gasket supplied with the system

ensures that joint leakage is a non-issue when properly applied (UL 1978 Grease Leakage Test).

All Flamebar BW11 duct segments shall be fabricated with Pittsburgh Lock Seams or Grooved

Corner Seams incorporating fire sealant as illustrated in Figures 4 and 5.

Access Doors for Insulated Flamebar to ASTM E-2336 & UL 1978:

Field fabricated and prefabricated grease duct access doors are permitted for use with Flamebar

BW11 Grease Duct Systems. Installation details are provided in Figure 7, either as field

fabricated or prefabricated Ductmate Ultimate & F2-HT

Figure 4: Duct Seam

9

Table 2: Grease Duct Support Details

Figure 8: Duct Segment Repair

Figure 7: Insulated Access Door Assembly

Table 2 itemizes all relevant support

information for the installation components

of Flamebar BW11 Grease Duct related to

the trapeze style supports which are spaced

out at 59” horizontal centers maximum, for

all sizes up to 49” on a side. When

designing and testing fire resistant

ductwork, it is critical that the reduction on

tensile strength of steel under fire load is

given proper consideration. For example,

it must be recognized that the “pull-out”

load of an anchor under fire conditions is

significantly less than at ambient

temperature. By specifying the Flamebar

BW11 System, it can be assured that these

issues have been adequately addressed.

Field Repair:

In the event that a duct segment sustains limited

damage on site, contractors can perform the repair as

illustrated in Figure 8. The replacement panel is to

be 20-gauge minimum, oversized by 1.5” on all

sides, coated by the licensed spray facility, and fire

sealed and fastened as shown.

If a duct segment is simply scratched with slight

damage to the coated surface, contractors may

reapply coating with a touch up kit provided by the

spray facility.

10

Figure 9: Supports for Risers

Field Modification:

If necessary, the length of a Flamebar BW11 duct segment can be reduced in the field. The duct

can be cut to the desired length utilizing standard sheet metal cutting tools, and replacement

Ductmate flanges can be installed (per Table 1 specification). The replacement flanges do not

require coating. The new Ductmate flanges should then be inserted over the raw end of the duct,

riveted or spot welded in place (at 6” centers), and require Flamebar Caulk to be smoothed along

the inner seam of the flange and duct. Caulk should also be applied to the corners.

Recognizing that field measurements for a duct project seldom align on site without a final

measurement and modification, it can be good practice to order the coated duct segments with at

least one select segment that has a flange on one end only, with the other end left raw. The duct

segment can then be easily cut to size with flanges fastened in place as described in the

preceding paragraph.

Outdoor Installation:

While the coating on Flamebar BW11 ductwork is non-hygroscopic and particularly durable, all

duct segments installed outdoors should have a protective water based paint applied to the coated

surface of the duct, and ideally incorporate a watershed structure over the duct system in order to

avoid any pooling of water on the top surface. Firespray International should be contacted for

additional information on the recommended paint or alternative methods of protection.

Supports for Risers:

Vertical ducts are supported by spanning floor

slabs with appropriately-sized bearer support

steel. The maximum height between floor

supports is 4 yards. Alternatively, cantilever

type supports may be utilized. Both methods are

illustrated in Figure 9 and incorporate 3” x 3” x

¼” steel angle welded to the side of the duct

during the fabrication process and fastened to

the bearer support.

Note that the angle steel fastened to the duct

which forms part of a Through Penetration

Firestop System, as described in the next

section, is also considered a duct support.

11

Figure 10: Penetration Seals

Through Penetration Seals:

Where a ventilation duct penetrates a fire rated wall, floor or ceiling assembly, the resulting

opening around the duct shall be properly fire stopped. Figure 10 below illustrates a typical

condition for both horizontal and vertical orientations.

The following Through Penetration Firestop Systems are UL Classified for use with the

Flamebar BW11 Coated Steel fire rated duct systems: C-AJ-7029, C-AJ-7030, F-A-7017,

F-B-7005, W-L-7133, W-L-7160 (www.ul.com, UL Category: XHEZ)

12

In order to fully comply with the listing to ASTM E-2336

and testing to UL 1978, and secure a one or two hour rated

enclosure with zero clearance to combustibles, only

Unifrax FyreWrap Elite 1.5 or Max 2.0 may be used to

insulate Flamebar BW11 Grease Duct. The wrapping of

the duct must adhere to the specific instructions provided

below, which are provided in greater detail in Unifrax’s

installation instructions. Additional information on the

Unifrax products can be found on their website,

www.unifrax.com.

Insulation shall be applied in a minimum of two layers. The first layer of insulation can be

installed with transverse (perimeter) joints butted and minimum 3” joint size longitudinal

overlaps on the top side of the horizontal ducts. All overlaps for the second layer are required to

be a minimum of 3”. For the second layer, transverse (perimeter) overlaps of adjacent blankets

may be installed using one of the following three methods as shown in Figure 11 below.

Insulation is attached to the duct with steel bands for ducts with sides of 24” or less, and with

both steel bands and weld pins on one surface of the duct (bottom for horizontal, and back for

vertical) for ducts up to 49”. Weld pins shall be attached to 1” x 1” 20-gauge steel plates that are

riveted to the Flamebar duct with ⅛” diameter steel blind pop rivets. All pins and bands locations

and type are per Unifrax’s standard installation instructions for Fyrewrap Elite 1.5 or Max 2.0.

Figure 11: Insulation of Flamebar BW11 Grease

Duct

13

Field Installation Inspection Checklist: Site installations are inspected by Firespray and/or its Licensees to ensure full conformance with

specification (refer to drawing STD-380, next page, Figure 13) with particular attention to the

items listed in the standard form below, Figure 12:

Figure 12: Sample Inspection Checklist

14

Fig

ure

13:

Fir

espra

y S

TD

38

0

15

Drafted below is a typical specification in CSI format for Flamebar BW11 fire rated ductwork,

including Grease Duct. While fairly comprehensive, the document may not address all related

subjects to the level of detail desired, but it can be used as the basis for an actual product

specification and modified as desired.

FIRE RATED AND GREASE DUCTWORK SYSTEMS

PART 1 GENERAL

1.1 Summary

A. Provide an Underwriter’s Laboratory classified 2-hour fire resistive assembly as indicated

on the drawings. The assembly shall provide the fire rating incorporating a specially

enhanced duct construction with a factory applied coating of Flamebar BW11, for shaft,

risers and horizontal duct systems. Ducted systems shall include, but not be limited to,

utility dryer and toilet exhausts, stair and elevator pressurizing systems, smoke

evacuation and make-up air systems and primary air-conditioning systems.

B. Grease duct systems shall be an ASTM E2336 and UL 1978 tested product in compliance

with IMC, UMC, and NFPA96 code.

C. Specifically enhanced duct systems shall be manufactured in accordance with the

relevant construction standards as published by Firespray International and as considered

by UL and Intertek ETL Semko in their classification and listings of the Flamebar BW11

system. Any qualified licensed sheet metal contractor may manufacture the ductwork to

the Firespray construction standard. A Licensee appointed by Firespray International

shall apply the Flamebar BW11 coating. Any qualified, licensed installer may install the

coated ductwork, in accordance with the Firespray construction standard. Upon

completion, the Flamebar BW11 Licensee shall inspect the installation to ensure

compliance with the relevant published Firespray construction standard, the requirements

of the UL classification requirements, and the Intertek ETL listings. On confirmation of

the required compliance, the Licensee shall issue a certificate of conformity.

1.2 References

A. SMACNA (Sheet Metal and Air Conditioning Contractors National Association)

Standards: Comply with the detailing required for this ductwork assembly as shown in

the Firespray International relevant published construction standards.

B. NFPA (National Fire Protection Association): Comply with ANSI/NFPA 90A “Standard

for the Installation of Air Conditioning and Ventilation Systems” and ANSI/NFPA 90B

“Standard for the Installation of Warm Air Heating and Air-Conditioning Systems”.

Comply with ASTM E 2336 requirements for Grease duct systems

16

C. UL File #18284: “Report on Ventilation Duct and Through-Penetration Firestop System.”

D. ASTME E-119: Compliance as Intertek ETL Semko test and evaluation number

3114842. This includes compliance with the hose stream test requirements.

E. ISO 6944 (1985): “Fire Resistance Tests Ventilation Ducts.”

F. ISO 834 (1975): “Fire Resistance Tests-Elements of Building Construction.”

G. ASTM E-2336: “Fire Resistive Grease Duct Enclosures Systems”

1.3 Submittals

A. Shop Drawings. Submit properly scaled and dimensioned layouts for each fire rated

system showing individual identifying marks for each component of the system in

accordance with the UL and Intertek ETL Semko classifications and listing

requirements.

B. Record Drawings. At project closeout submit record drawings of installed ductwork

systems including accessories, outlets and inlets.

C. Certificate of Conformity. Provided by the manufacturer’s local Licensee. The qualified

Licensee’s representative shall inspect the completed installations and submit a

certificate in the name of the Owner certifying compliance with the relevant Firespray

International Construction and Installation standards.

1.4 Quality Assurance

A. All ductwork used as part of this system shall be manufactured by a licensed and

qualified and insured sheet metal contractor with a minimum of five (5) years experience

with the manufacture of ductwork systems.

B. All ductwork to be used on fire rated systems shall be inspected at the factory of the local

Flamebar BW11 Licensee, to confirm compliance with the relevant enhanced

construction standards and with the shop drawings. After inspection the ductwork shall

be degreased and coated with BW11. After coating and curing, each individual section

shall be inspected and labeled in accordance with the UL classification and Intertek

Listing requirements. Records of all pieces shall be kept for inspection by the Authority

Having Jurisdiction (AHJ).

1.5 Delivery, Storage, and Handling

A. Protect factory fabricated and coated ductwork, accessories and purchased products from

damage during shipping, storage and handling. Prevent end damage, and prevent dirt and

moisture from entering ducts and fittings.

B. Store ductwork indoors and dry, and protect from damage from other trades. Where

necessary to store outside for a short time period, store above grade on skids and enclose

with secured waterproof wrapping.

17

PART 2 PRODUCTS

2.01 Manufacturer of Flamebar BW11 Coating and Ancillaries

A. Approved Manufacturer: Firespray International, 101 Tiffany Dr, Waynesboro,

VA 22980. Tel: (972) 365-5302. www.FiresprayUSA.com

1. Coating Flamebar BW11

2. Ancillaries including Gasket, Caulk, G-Clamps, etc. as supplied by the

Manufacturer.

3. Moisture absorption: The system is considered non-hydroscopic with resulting

equivalent to sixty years external exposure by artificial weatherometer.

4. Chemical resistance: The coating is chemically resistant to many acids and

solvents.

5. Smoke and toxic emissions: Meets NFPA 90 Smoke emissions and toxic fume

emission. Tested in accordance with UL 723 (ASTM E84).

6. Cleaning: Smooth monolithic finish cleans easily with soap and water or the

manufacturers recommended cleaning solutions.

7. Color and finish: Natural buff finish of the factory applied monolithic coating

can be painted with any water-based paint.

B. Appointed Licensee: Please contact Firespray International at (972) 365-5302 or

[email protected] for a current listing of Flamebar Licensees in North

America.

2.02 Ductwork Construction

A. Exposed ductwork materials: Where ductwork is indicated to be exposed to view in

occupied spaces, provide materials which are free from visual imperfections including

pitting of the finished coating, marks, surface imperfections, including that which would

impair painting. Oil based paint shall not be used on Flamebar BW11 coating.

a. Outer coating: Provide a factory applied coating as per the manufacturer’s

recommendation. The coating should be applied and cured in a controlled

environment as required by the UL classification and Intertek listing

requirements.

b. Ductwork Metal and Gages: Fabricate ductwork from galvanized steel sheet.

Thickness shall be as per the relevant Firespray construction standards.

B. Comply with ASTM A527, Lock forming quality.

C. Comply ASTM A 525 G90 Zinc coating, mill phosphate.

D. Comply with Firespray International standards (STDs) for rectangular, circular and flat

oval ductwork (STDs 353, 355 and 357 respectively). Copies of these are available on

request.

E. Duct Sealant: As supplied by Firespray International.

18

F. Gasketing: As supplied by Firespray International.

G. G-Clamps: As supplied by Firespray International.

H. Duct Access Doors: Removable access doors where required to be as shown on the

relevant construction standard as provided by Firespray International.

2.03 Fabrication

Ductwork shall be fabricated in accordance to the relevant construction standard as issued

by Firespray International

2.04 Insulation

Insulation applied to Flamebar BW11 Grease Duct shall be Unifrax Fyrewrap Elite 1.5 or

Max 2.0, and installed per Unifrax’s product installation instructions

PART 3 EXECUTION

3.01 Inspection

Examine areas and conditions under which ductwork is to be installed. Do not proceed

with the work until unsatisfactory conditions have been corrected in a manner acceptable

to the manufacturer.

3.02 Installation of Ductwork

Install in accordance with the relevant Firespray construction standard and any applicable

local codes.

© COPYRIGHT 2009-2010 Firespray International Ltd. All Rights Reserved

Revision 2.0