power transmission - renewable

47
ENERCON TRANSMISSION ENERCON INDIA LTD Energy for the world…. Transmission Department - By Niranjan Shukla 14 th July 2011

Upload: vivek-kumar

Post on 18-Dec-2015

222 views

Category:

Documents


3 download

DESCRIPTION

A PPT Describing the scope of power transmission in Indian Context

TRANSCRIPT

  • ENERCONTRANSMISSION

    ENERCON INDIA LTD

    Energy for the world.

    Transmission Department

    - By Niranjan Shukla14th July 2011

  • ENERCONTRANSMISSION

    Objective

    In this module, we shall discuss

    Overview of Transmission Sector a national perspectivePast, Present & Future trends Need of Large grid & Inter-regional transmission Understanding the grid dynamics Present challenges

    Power evacuation philosophy in EILSchemesConstruction aspects Issues & MitigationO&M Needs

  • ENERCONTRANSMISSION

    1. Importance & Information on Indian Transmission Sector, National Plan & Policies

    2. How we, Energities evacuate power to the grid3. Points to build an robust & effective transmission

    system

    A QUICK OVERVIEWA QUICK OVERVIEWAt the conclusion of this module, you will be able to understand:

  • ENERCONTRANSMISSION

  • ENERCONTRANSMISSION

  • ENERCONTRANSMISSION

    Ice breaking ?1) What was the total generation capacity of India at

    the time of Independence? 2) What is the present generation capacity of India ?3) Name the largest power generation utility in India?4) What is the highest Grid System Voltage in India ?5) Who is deemed transmission licensee in

    Maharashtra?6) What do you understand by -

    Transmission System Regional Grid Operation Open Access ABT IPTC AT & C Losses

  • ENERCONTRANSMISSION

    Answers:1) What was the total generation capacity of India at the time of

    Independence? 1350 MW2) What is the present generation capacity of India ? 132330 MW3) Name the largest power generation utility in India? NTPC4) What is the highest AC Grid System Voltage in India ? 765KV5) Who is deemed transmission licensee in Maharashtra? MSETCL,REL, TPC6) What do you understand by -

    Transmission System Regional Grid Operation Open Access ABT (Availability based Tariff) IPTC (Independent Power Transmission Company) AT & C losses (Aggregate Technical & Commercial Losses)

  • ENERCONTRANSMISSION

    8

    Flow:Present status, considerations and future outlookWhat is present power scenario ?What is present Transmission network ?What are our transmission requirements Inter statetransmission,

    Electricity Act2003: Impacts & evolutionGrid Operation: Open access &Grid discipline-ABTTransmission as business To break the natural monopoly of state- IPTCEIL - Philosophy

  • ENERCONTRANSMISSION

    9

    Supply

    Demand

    Real Time

  • ENERCONTRANSMISSION

    Capacity Addition as % of Target

    54.0

    75.0

    47.0

    0

    20

    40

    60

    80

    VIII IX X

    Plan

    %

    10

  • ENERCONTRANSMISSION

    11

    Capacity addition XI FYP Planned v/s Actual under construction

  • ENERCONTRANSMISSION 12

    Capacity Addition - Perspective Programme

    Present installed capacity - 1,32,330 MW.

    Targeting economic growth rate of 8-10% pa

    Projected installed capacity by 2012 - 2,07,000 MW

    Thereafter, doubling of capacity every 10 years.

    Projected installed capacity by 2030 - 8,00,000 MW.

  • ENERCONTRANSMISSION

    13

  • ENERCONTRANSMISSION

    14

    NEW Grid

    SouthGrid

    South

    West

    North

    East

    Northeast

    Five Regional GridsFive Frequencies

    October 1991East and Northeast synchronized

    March 2003West synchronized With East & Northeast

    August 2006North synchronized With Central Grid

    Central Grid

    Five Regional GridsTwo Frequencies

    Installed Capacity 156 GW

  • ENERCONTRANSMISSION

    15

    5 Regional Grids

    Northern Region

    Eastern Region

    Southern Region

    Western Region

    NE Region

  • ENERCONTRANSMISSION

    14100

    37700

    05000

    10000150002000025000300003500040000

    Existing by 2012MW16

    Name of SystemAt the end of 10 th Plan i.e. end of 2006-07

    Additions during 11th plan 2007-12

    At the end of 11th Plan i.e. end of 2011-12

    ER - SR : 3120 500 3620ER - NR : 4220 9400 13620ER - WR : 1760 4900 6660ER - NER : 1240 1600 2840NR - WR : 2080 2100 4180WR - SR : 1680 2100 3780NER/ER-NR/WR 0 3000 3000TOTAL ALL INDIA 14100 23600 37700

    Power Transfer Capacity (MW)Inter- regional transmission Existing & Planned (220KV & above)

    Emerging opportunities

  • ENERCONTRANSMISSION

    17

  • ENERCONTRANSMISSION

    18

    Growth in Indian Transmission Sector

    Source: CEA :http://www.cea.nic.in/power_sec_reports/Executive_Summary/2007_09/13.pdf

  • ENERCONTRANSMISSION

    Emerging Opportunities National Grid Integrated National Grid by 2012

    Inter-regional power transfer capacity of

    30,000 MW to be established (currently

    8,050 MW)

    Total Investments estimated at approx

    Rs. 64,000 crores (2003-2012)

    Investment in projects under

    implementation/ approval taken by

    PGCIL approx. Rs 16000 crores

    Investment opportunity of Rs.

    48,000 crores

    From 2005-07 : Rs 7,000 Crore

    From 2008-12 : Rs 41,000 Crore

    LAKSHADWEEP

    AND

    AMAN

    &

    NIC

    OBAR

    TRANSFER CAPACITY- 30000 MWINTER-REGIONAL

    BHUTANTALA

    BONGAIG'N

    MAITHON

    SILIGURI

    KAHALGAON

    P'RNEA

    ROURKELA

    BINA

    RAICHUR

    GOOTY

    HYDERABAD

    SR

    RAMAGUNDAM

    CHANDRAPUR

    MYSORE

    DAVANGERE

    TRIVANDRUM

    UDUMALPET

    KOZIKODE

    NORTH TRICHUR

    NARENDRA

    KAIGASIRSI

    KOLHAPUR

    PONDA

    WR

    BANGALORE

    MADURAI

    TRICHY

    HOSUR

    SALEMNEYVELI

    KORBA

    VIJAYAWADA

    MADRAS

    NELLORECUDDAPAH

    N'SAGAR

    KHAMMAM

    RAIPURSEONI

    SIPAT

    GAZUWAKA

    TALCHERJEYPORE

    RANCHIER

    NATIONAL GRID - 2009-10

    KISHENPUR

    MALANPUR

    AGRANRSHIROHI

    ZERDA

    BHIWADIHISSAR

    JAIPUR

    (DELHI RING)BALLABGARH

    MOGA

    URI

    BALIA

    LUCKNOW

    UNNAO

    S'NGRL

    SATNA

    SATLUJ

    ABDULLAPUR

    MEERUT

    NALAGARH

    DULHASTI

    PARBATI

    TEHRI

    M'PUR

    SRAMNKSTP

    G'PUR

    BARH

    TEESTA

    CHICKEN NECK

    WAGOORA

    DESHBANGLA

    BALIPARA

    MISA

    NERMARIANI

    RANGANADI GURIKATHAL-

    19

  • ENERCONTRANSMISSION

    20

    India

    Northern Region

    Eastern Region

    Southern Region

    Western Region

    NE Region

  • ENERCONTRANSMISSION

    21

  • ENERCONTRANSMISSION 22

    Drivers for Network Expansion:Capacity additions by

    State generation Central allocation CPPs IPPs

    Load flow study System strengthening Standing committee recommendations Directives from Regulator

    Summarize ?

  • ENERCONTRANSMISSION

    Electricity Act, 1887 & 1903 * Minimum regulation * Private Capital

    Indian Electricity Act, 1910* Basic Legal frame work* Private Capital

    Indian Constitution, 1950 * Electricity under concurrent

    jurisdiction of State and Centre

    Industrial Policy Resolution, 1956* Generation &

    Distribution reserved in the domain of the State

    State Reforms Act * State level reforms * Unbundling of SEBs

    Act, 1998 * Independent

    Regulators

    * Unbundling continues

    * Private Capital

    Electricity Act , 2003* Autonomous Regulation

    * Private Capital* Open Access

    Electricity Act Amendments * Central Utilities

    created * Private capital in "G" & "T"* FDI encouraged

    Electricity (Supply) Act, 1948* Creation of SEBs * CEA to

    formulated

    power policy

    23

  • ENERCONTRANSMISSION

    Transmission Planning- Role as of today - emanating from Electricity Act2003

    24

    Electricity Act

    National ElectPolicy

    + National Plan

    CEA

    STU Intra-State lines

    CTU Inter state

    Licensee Inter state and Intra stateCERC

  • ENERCONTRANSMISSION

    Unified Grid Operation

    25

    NationalLevel

    RTU RTU RTU

    SUB LDC SUB LDC SUB LDC

    SLDC SLDC SLDC

    ERLDC WRLDC* NRLDC SRLDC NERLDC

    NLDC*

    32 Nos.

    54Nos.

    1160Nos.

    5 Nos. RegionalLevel

    State HQLevel

    Group / Distt Level

    Plant / Sub-Station Level

  • ENERCONTRANSMISSION

    26

  • ENERCONTRANSMISSION

    27

  • ENERCONTRANSMISSION

    WORLD ELECTRICITY PRODUCTION BY SOURCE

    %, Coal, 36

    %, Natural Gas, 18

    %, Hydro Electricity, 18

    %, Nuclear, 17

    %, Oil, 9.5

    %, Renewable Energy, 1.5

    28

    Source: IEA; Organisation for Economic cooperation & Development

  • ENERCONTRANSMISSION

    29

    Fuel MW %

    Total Thermal 93725.34 63.34

    Coal 77648.88 53.3Gas 14876.71 10.5

    Oil 1199.75 0.9Hydro 36877.76 24.7

    Nuclear 4120 2.9Renewable 13242.41 8.9

    Total 147965.51

    Fuel wise installed capacity (as on 31.3.09)

    Source : MoP site

    Renewable,

    13242, 9%

    Nuclear, 4120, 3%

    Hydro, 36878,

    25% Thermal, 93725, 63%

  • ENERCONTRANSMISSION

    30

    All India Generating Installed Capacity (MW) as on 30.09.07

    Source: CEA http://www.cea.nic.in/power_sec_reports/Executive_Summary/2007_09/9.pdf

  • ENERCONTRANSMISSION

    31

  • ENERCONTRANSMISSION

    Electrical power grid is an unique one in which generation anddemands are balanced instantaneously and continuously.

    Fluctuations in power consumed by the consumers and variationsin uncontrolled generators are compensated by the controlledgenerators.

    When generation equal to load, frequency operates at 50 Hz.Variation in frequency indicates rise of load or generation viceversa is term as a balancing.

    In the grid system, it is not necessary for compensating each andevery variation from individual consumers / generators.

    Only aggregate variation in the control area is balanced. Aggregation is the powerful tools with the power system

    operators. When wind power plants are introduced into the power system, an

    additional source of variation is added to the already variablenature of system.

    32

    Electrical grid

  • ENERCONTRANSMISSION

    There are number of unresolved technical, institutional and regulatoryquestions concerning distributed generation in general and windgeneration in particular.

    On the technical level, major barriers are..

    Novelty and unfamiliarity of distributed technologies. Lack of substantial field experience with these technologies. Costs and complexity associated with thorough engineering evaluations. Weak evacuations network as well as onward transmission networks. Less availability of evacuations corridors. Less consumptions in local area due to wide variation in load due to

    variable load in agriculture, less and variable industrial demand and lowdemand on staggering day.

    Variable local load pattern leads to overloading of transformers and maintransmission lines which requires high capacity of strengthening oftransmission network.

    Average PLF observed 15-20% which leads to inefficient occupation oftransformer capacity and non utilization of infrastructures.

    33

    Integration with grid

  • ENERCONTRANSMISSION

    Load-Generation balance

    In large interconnected system, load generation is reflected withchange in tie line flows.

    In a small system, load generation balance is reflected with variation infrequency.

    Variation in frequency is limiting factor for capacity addition of the windfarms.

    In predominantly hydro and gas generation system with good ramprate will be positive factor, helping for compensating variation of windgeneration.

    34

  • ENERCONTRANSMISSION

    Balancing Balancing in power system occurs over wide time frames: Years in advance : Enough generation has to be planned and built so

    that there is sufficient capacity available to meet load requirements Day Ahead : Select which available generator can reliably meet

    expected requirements at lowest cost. Real Time : Real time balancing can be obtained by two different

    methodology: Load Following (Backing down) Load Regulation (Load Shedding)

    35

  • ENERCONTRANSMISSION

    Grid operation with Wind GenerationScenario 1:

    An increase in load along with increase in wind generation OR dropin load along with drop of wind generation Additional generationrequired for frequency maintenance is less.

    System Operator:

    It is a safe operation for grid operators. Most favorable condition for grid operators. During evening peak, maximum wind energy available and it

    helps to meet peak demand.

    36

  • ENERCONTRANSMISSION

    Grid operation with Wind GenerationScenario 2(A) :

    A drop in load along with increase in wind generation.

    System Operator:

    Backing down of other generators. High Voltage problem and switching off lines. System operation

    with critical loading. If local load is very low, overloading of associated transmission

    lines.

    37

  • ENERCONTRANSMISSION

    Grid operation with Wind GenerationScenario 2(B) :

    An increase in load along with drop in wind generation .

    System Operator :

    Increasing load along with decrease in wind generation is avery critical nature of situation for system operator.

    Additional generation is to be brought into system very quickly. If no generation available, heavy load shading to be resorted. If frequency permits, overdrawl at that prevailing rate. Requisition of costly generation i.e. on SPOT gas , Naphtha if

    available

    Remedies :

    Additional generation capacity is required for maintenance ofload generation balancing especially gas based and hydrobased.

    38

  • ENERCONTRANSMISSION

    Power Quality with Wind Generation

    Generally it is believed that with increase in wind generation, the powerquality suffers.

    Main power quality problems are:o Voltage Regulation,o Harmonics. Old WTG machines with induction generators have not been required

    to participate in system voltage regulation. Their reactive powerdemand are compensated by switched shunt capacitors.

    New WTG machines with variable frequency drives have inherentcontrol of reactive power output and can participate in voltageregulation.

    If wind farm is far from generation source, high voltage witnessednear to wind farms with increase in wind generation.

    The variable frequency generators in WTGs use AC-DC converter forconnection with Grid, which increases the Harmonics level in thesystem.

    39

  • ENERCONTRANSMISSION

    Conclusion If the share of wind generation instantaneous penetration at any point of

    time is excessively high compared to the total system demand, then,following new operating methodology need to be adopted for ensuingreliability and stability of system:

    Methodology for accurate long term & short term forecasting. Real time data from wind farm to system operator to be made

    available for effective grid operation. Reserve capacity with high ramp up generators such as a hydro

    and gas shall be kept. All wind energy generation be brought under regulations of ABT

    which means elimination of generation in case of high frequencyor system constraints.

    Reinforcement of main transmission network and power corridors. Augmentation and reinforcement of voltage regulating equipments

    such as reactors, switched capacitors including FACTS devices.

    40

  • ENERCONTRANSMISSION

    41

    Non-conventional energy plans beyond - 2012

  • ENERCONTRANSMISSION

    42

  • ENERCONTRANSMISSION

    Enercon Philosophy:

    StabilityAvailabilityOptimizationScalabilityFuture provisionInnovations

  • ENERCONTRANSMISSION

    Current Projects:

    SynopsisSalient features

  • ENERCONTRANSMISSION

    Typical process flow:

    PRSSEID / BDOSIQAEISD

    Transmission

  • ENERCONTRANSMISSION

  • ENERCONTRANSMISSION

    Lets make a green move together Thank you !!