presentation cranes (manish)

Upload: yash-pani-shukla

Post on 06-Apr-2018

225 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Presentation CRANES (Manish)

    1/17

  • 8/3/2019 Presentation CRANES (Manish)

    2/17

    INTRODUCTION

    A crane is a lifting machine,

    generally equipped with a

    winder (also called a wire

    rope drum), wire ropes or

    chains and sheaves that can

    be used both to lift and

    lower materials and to

    move them horizontally.

  • 8/3/2019 Presentation CRANES (Manish)

    3/17

    HISTORY

    Ancient Greece

    The crane for lifting

    heavy loads was

    invented by the Ancient

    Greeks in the late 6th

    century BC.

  • 8/3/2019 Presentation CRANES (Manish)

    4/17

    Ancient Rome

    In the High Middle Ages,

    harbour cranes were introduced

    to load and unload ships and

    assist with their construction

    some were built into stone towers

    for extra strength and stability.

    The earliest cranes wereconstructed from wood, but cast

    iron and steel took over with the

    coming of the Industrial

    Revolution.

  • 8/3/2019 Presentation CRANES (Manish)

    5/17

    MECHANICAL PRINCIPLE

    There are three major considerations in the design of

    cranes-

    1- The crane must be able to lift the weight of the load.

    2- The crane must not topple.3- The crane must not rupture.

    Lifting capacity

    Stability

  • 8/3/2019 Presentation CRANES (Manish)

    6/17

    Major Cranes Used In Construction

    Mobile

    Cranes

    Fixed

    Cranes

  • 8/3/2019 Presentation CRANES (Manish)

    7/17

    MOBILE CRANES

    Mobile cranes are mounted oneither wheels or crawlers and

    usually do not require a specialpermanent foundation from which

    to lift.

    Mobile cranes can be furtherclassified by boom type and carrier

    type. Booms are either conventionallattice truss boom or telescopic

    boom. Virtually all telescopic boomcranes in use today use hydrauliccylinders to extend and retract the

    boom.

  • 8/3/2019 Presentation CRANES (Manish)

    8/17

    Crawler Crane

    A 500-ton crawler-mounted

    mobile crane (not the biggest)

    may take several days to erect

    on site and to travel to the lift

    location. However, a 45-ton truck-

    mounted telescopic boom crane

    is ready when it arrives on site

    and can execute many lifts that

    same day.

  • 8/3/2019 Presentation CRANES (Manish)

    9/17

    Main Parts of Crawler Crane

    Upper works of a

    Crane

  • 8/3/2019 Presentation CRANES (Manish)

    10/17

    Carrier

    Crawler Base

  • 8/3/2019 Presentation CRANES (Manish)

    11/17

    Crawler Crane Reaction

  • 8/3/2019 Presentation CRANES (Manish)

    12/17

    FIXED(Tower) CRANE

  • 8/3/2019 Presentation CRANES (Manish)

    13/17

    Tower Crane Cabin

    The average fee to rent a 150-

    foot (46 m) crane is $60,000 for

    assembly and disassembly and

    an additional $15,000 per month.

  • 8/3/2019 Presentation CRANES (Manish)

    14/17

    CRANE SAFETY AND SELECTION

    Plan Drawing is required.

    Never consider operation in TippingPortion.

    calculated weight of load is approximate, a5 percent margin of error should be

    considered.

    U.S. Department of Labour booklet MobileCrane Inspection Guidelines for OSHACompliance Officer.

  • 8/3/2019 Presentation CRANES (Manish)

    15/17

    The following devices provide aid to

    crane operators:

    Boom angle indicator.

    Drum turning indicator.

    Empty or overfill drum indicator.

    Over hoisting indicator.

    Over hoisting limiter.

    Over booming limiter.

    Load indicator device.

    Load moment indicator.

    Rated capacity limiter.

  • 8/3/2019 Presentation CRANES (Manish)

    16/17

  • 8/3/2019 Presentation CRANES (Manish)

    17/17

    Questions