Preventing work-related cancer, conference on carcinogens Amsterdam, May 23 - 25, 2016 Heinz KROPIUNIK A-1150 Vienna www.aetas.at RISK PREVENTION DURING ASBESTOS REMOVAL PROJECT AT THE VIENNA INTERNATIONAL CENTRE Preventing work-related cancer Conference on Carcinogens Amsterdam, May 23-25, 2016 SELECTION OF SLIDES RISK PREVENTION DURING ASBESTOS REMOVAL PROJECT AT THE VIENNA INTERNATIONAL CENTRE Dipl.-Ing. Heinz KROPIUNIK aetas Ziviltechniker GmbH, Vienna www.aetas.at www.asbestos.at www.azbest.at

Upload: magazineonthespot

Post on 11-Apr-2017

69 views

Category:

Health & Medicine


0 download

TRANSCRIPT

Page 1: Presentation Heinz Kropiunik

Preventing work-related cancer, conference on carcinogensAmsterdam, May 23 - 25, 2016

Heinz KROPIUNIKA-1150 Vienna www.aetas.at /www.asbestos.at

RISK PREVENTION DURING ASBESTOS REMOVAL PROJECT

AT THE VIENNA INTERNATIONAL CENTRE

Preventing work-related cancerConference on Carcinogens

Amsterdam, May 23-25, 2016

SELECTION OF SLIDES

RISK PREVENTION DURING ASBESTOS REMOVAL PROJECT

AT THE VIENNA INTERNATIONAL CENTRE

Dipl.-Ing. Heinz KROPIUNIKaetas Ziviltechniker GmbH, Vienna

www.aetas.at www.asbestos.at www.azbest.at

Page 2: Presentation Heinz Kropiunik

Preventing work-related cancer, conference on carcinogensAmsterdam, May 23 - 25, 2016

Heinz KROPIUNIKA-1150 Vienna www.aetas.at /www.asbestos.at

RISK PREVENTION DURING ASBESTOS REMOVAL PROJECT

AT THE VIENNA INTERNATIONAL CENTRE

1998 Realization of Status Report 1999 – 2003 Pilot project / small sized removal projects 2001 – 2004 Planning of overall removal project 2004 – 2007 Asbestos removal in 4 office towers 2007 – 2009 Asbestos removal in 2 service buildings 2008 – 2013 Asbestos removal in conference building

Total time span appr. 14 years (for asbestos related tasks) Regular air monitoring and routine checks to avoid health hazards 150 – 200 workers, supervisors and consultants On site supervisory team of appr. 12 persons On site SEM-laboratory

OVERVIEW OF THE VIC - ASBESTOS MANAGEMENT PLAN

Page 3: Presentation Heinz Kropiunik

Preventing work-related cancer, conference on carcinogensAmsterdam, May 23 - 25, 2016

Heinz KROPIUNIKA-1150 Vienna www.aetas.at /www.asbestos.at

RISK PREVENTION DURING ASBESTOS REMOVAL PROJECT

AT THE VIENNA INTERNATIONAL CENTRE

Site map of the buildings

of the VICSource: aetas Ziviltechniker GmbH

Page 4: Presentation Heinz Kropiunik

Preventing work-related cancer, conference on carcinogensAmsterdam, May 23 - 25, 2016

Heinz KROPIUNIKA-1150 Vienna www.aetas.at /www.asbestos.at

RISK PREVENTION DURING ASBESTOS REMOVAL PROJECT

AT THE VIENNA INTERNATIONAL CENTRE

Page 5: Presentation Heinz Kropiunik

Preventing work-related cancer, conference on carcinogensAmsterdam, May 23 - 25, 2016

Heinz KROPIUNIKA-1150 Vienna www.aetas.at /www.asbestos.at

RISK PREVENTION DURING ASBESTOS REMOVAL PROJECT

AT THE VIENNA INTERNATIONAL CENTRE

Page 6: Presentation Heinz Kropiunik

Preventing work-related cancer, conference on carcinogensAmsterdam, May 23 - 25, 2016

Heinz KROPIUNIKA-1150 Vienna www.aetas.at /www.asbestos.at

RISK PREVENTION DURING ASBESTOS REMOVAL PROJECT

AT THE VIENNA INTERNATIONAL CENTRE

Asbestos removal area in

principleSource: aetas Ziviltechniker GmbH

Page 7: Presentation Heinz Kropiunik

Preventing work-related cancer, conference on carcinogensAmsterdam, May 23 - 25, 2016

Heinz KROPIUNIKA-1150 Vienna www.aetas.at /www.asbestos.at

RISK PREVENTION DURING ASBESTOS REMOVAL PROJECT

AT THE VIENNA INTERNATIONAL CENTRE

Vienna Int. Centre

Enclosure of the whole

conference building during

asbestos removal

Source: Strabag AG

Page 8: Presentation Heinz Kropiunik

Preventing work-related cancer, conference on carcinogensAmsterdam, May 23 - 25, 2016

Heinz KROPIUNIKA-1150 Vienna www.aetas.at /www.asbestos.at

RISK PREVENTION DURING ASBESTOS REMOVAL PROJECT

AT THE VIENNA INTERNATIONAL CENTRE

Asbestos removal work

under PPE (personal protective

equipment)Source: aetas Ziviltechniker GmbH

Page 9: Presentation Heinz Kropiunik

Preventing work-related cancer, conference on carcinogensAmsterdam, May 23 - 25, 2016

Heinz KROPIUNIKA-1150 Vienna www.aetas.at /www.asbestos.at

RISK PREVENTION DURING ASBESTOS REMOVAL PROJECT

AT THE VIENNA INTERNATIONAL CENTRE

Worker with PPE (personal protective

equipment)Source: aetas Ziviltechniker GmbH

Page 10: Presentation Heinz Kropiunik

Preventing work-related cancer, conference on carcinogensAmsterdam, May 23 - 25, 2016

Heinz KROPIUNIKA-1150 Vienna www.aetas.at /www.asbestos.at

RISK PREVENTION DURING ASBESTOS REMOVAL PROJECT

AT THE VIENNA INTERNATIONAL CENTRE

Annex:

3 exclamation marks to occupational health and

safety risks due toasbestos cement products

on roofs and facades

Page 11: Presentation Heinz Kropiunik

Preventing work-related cancer, conference on carcinogensAmsterdam, May 23 - 25, 2016

Heinz KROPIUNIKA-1150 Vienna www.aetas.at /www.asbestos.at

RISK PREVENTION DURING ASBESTOS REMOVAL PROJECT

AT THE VIENNA INTERNATIONAL CENTRE

Gutter with sediments, consisting high

concentrated asbestos particles

Source: aetas Ziviltechniker GmbH

Page 12: Presentation Heinz Kropiunik

Preventing work-related cancer, conference on carcinogensAmsterdam, May 23 - 25, 2016

Heinz KROPIUNIKA-1150 Vienna www.aetas.at /www.asbestos.at

RISK PREVENTION DURING ASBESTOS REMOVAL PROJECT

AT THE VIENNA INTERNATIONAL CENTRE

MMMF-insulation with asbestos debris

Source: aetas Ziviltechniker GmbH

Page 13: Presentation Heinz Kropiunik

Preventing work-related cancer, conference on carcinogensAmsterdam, May 23 - 25, 2016

Heinz KROPIUNIKA-1150 Vienna www.aetas.at /www.asbestos.at

RISK PREVENTION DURING ASBESTOS REMOVAL PROJECT

AT THE VIENNA INTERNATIONAL CENTRE

Nearly pure chrysotile-asbestos

Source: aetas Ziviltechniker GmbH

Merry Christmas and Happy New Year 2007
Page 14: Presentation Heinz Kropiunik

Preventing work-related cancer, conference on carcinogensAmsterdam, May 23 - 25, 2016

Heinz KROPIUNIKA-1150 Vienna www.aetas.at /www.asbestos.at

RISK PREVENTION DURING ASBESTOS REMOVAL PROJECT

AT THE VIENNA INTERNATIONAL CENTRE

Asbestos cement: Dos and

Don‘tsSource: aetas Ziviltechniker GmbH

Merry Christmas and Happy New Year 2007
Page 15: Presentation Heinz Kropiunik

Preventing work-related cancer, conference on carcinogensAmsterdam, May 23 - 25, 2016

Heinz KROPIUNIKA-1150 Vienna www.aetas.at /www.asbestos.at

RISK PREVENTION DURING ASBESTOS REMOVAL PROJECT

AT THE VIENNA INTERNATIONAL CENTRE

Chrysotile asbestos,

associated with man made mineral

fibres (SEM-print,

magnification 1,00 kX)

Source: aetas Ziviltechniker GmbH