FY 2010
Presentation on Management Plan
Tohoku Electric Power Co., Inc.April 2, 2010
Vision 2020 for the Tohoku Electric Power Group - together with local communities -
I. Medium-term business planTohoku EPCO Group Medium-term Business Plan (FY 2010 to 2014)Steadily boost nuclear power generation by stronger, unified operations of the whole GroupCreate electrification market by encouraging customers to be more energy efficient
II. Supply planProactively work toward a low-carbon societyDemand outlookCapital investment plan
III. Numeric targets
(Ref.)Auto industry cluster Transmission and transformation planElectric power salesTrends in large industrial demandAccumulated number and ratio of all-electric housing, and accumulated number of
semi-electric housingPower generated by energy sourcesPlant and equipment expendituresCapital raised for plant and equipment
・・・・・
・・・・・
・・・・・
・・・・・
・・・・・
・・・・・
・・・・・
・・・・・
・・・・・
・・・・・
・・・・・
・・・・・
・・・・・
・・・・・
・・・・・
・・・・・
1
234
567
8
9101112
13141516
Contents
Vision 2020 for the Tohoku Electric Power Group - together with local communities - 1
Management principles:“Prospering together with the community” and “Promotion of creative business management”
To grow together with the Tohoku region and local communities long into the futureTo proactively adapt to the changing business environment, simultaneously achieve energy security, environmental protection, and economic growth, and improve overall management of the businessTo become an indispensable part of the local community by creating unique values in partnership with it
To grow together with the Tohoku region and local communities long into the futureTo proactively adapt to the changing business environment, simultaneously achieve energy security, environmental protection, and economic growth, and improve overall management of the businessTo become an indispensable part of the local community by creating unique values in partnership with it
Changes in power demand caused by the modal shift of supply and use of energy
Higher costs incurred by addressing global warmingBusiness operation based on societal changes in the
Tohoku region; Need to work together with the community
Declining population Creating a low-carbon societyIncreasingly difficult to procure resources A new direction for the global economy
<Economic trends> <Impact on our business>
Prospects for the business environment
2Tohoku EPCO Group Medium-term Business Plan (FY 2010 to 2014)
1. Steadily boost nuclear power generation by stronger, unified operations of the whole Group1. Steadily boost nuclear power generation by 1. Steadily boost nuclear power generation by stronger, unified operations of the whole Groupstronger, unified operations of the whole Group
5. Increase profitability by streamlining and combining resources of the entire Group5. Increase profitability by streamlining and 5. Increase profitability by streamlining and combining resources of the entire Groupcombining resources of the entire Group
2. Operate facilities by simultaneously achieving energy security, environmental protection and economic growth
2. 2. Operate facilities by simultaneously achieving Operate facilities by simultaneously achieving energy security, environmental protection and energy security, environmental protection and economic growtheconomic growth
6. Establish a corporate climate of greater safety and quality of operations6. Establish a corporate climate of greater safety 6. Establish a corporate climate of greater safety and quality of operationsand quality of operations
Key measures
3. Create electrification market by encouraging customers to be more energy efficient 3. Create electrification market by encouraging 3. Create electrification market by encouraging customers to be more energy efficient customers to be more energy efficient
7. Secure and develop human resources as a growth engine and build a work environment that encourages creativity
7. Secure and develop human resources as a 7. Secure and develop human resources as a growth engine and build a work environment growth engine and build a work environment that encourages creativitythat encourages creativity
4. Proactively work toward a low-carbon society4. Proactively work toward a low4. Proactively work toward a low--carbon societycarbon society 8. Strengthen ties with the community through discussions and events8. Strengthen ties with the community through 8. Strengthen ties with the community through discussions and eventsdiscussions and events
Evolve business operationsWe must strengthen, or “evolve”, our core operations by adapting previous measures and operations to the
changing environment, strengthening those which are to be continued, and reviewing those which need improvement.
Open the futureWe must “open” the future through new actions to proactively adapt to the changing business environment,
including the trend toward a low-carbon society and possible demand fluctuations.
Evolve business operationsWe must strengthen, or “evolve”, our core operations by adapting previous measures and operations to the
changing environment, strengthening those which are to be continued, and reviewing those which need improvement.
Open the futureWe must “open” the future through new actions to proactively adapt to the changing business environment,
including the trend toward a low-carbon society and possible demand fluctuations.
Actions on key measures
I. Medium-term business plan
3Steadily boost nuclear power generation by stronger,
unified operations of the whole Group
The safety and reliability of nuclear power are ensured by putting top priority on safety and improving operational quality, through reviewing and strengthening the business system.To secure the future of nuclear power, nuclear power management is strengthened, human resources developed, engineering capabilities secured, and the trust of the local community is gained.
Earthquake safetyEarthquake safety
PluthermalPluthermal
Outline of the pluthermal project・MOX fuel is being used at Onagawa Unit 3.・The MOX fuel is identical in appearance and shape to
conventional uranium fuel.・Out of all 560 fuel assemblies, less than 228 MOX fuels are
to be used.
In conjunction with regular inspections, construction work to raise the seismic margin of supporting structures of piping and circuits, which are important for safety, was implemented at plants. The work was completed at all four units (by September 2009).Exhaust stacks continue to be built.The reliability of nuclear power plants will continue to be improved.
Onagawa 1 3,600
Onagawa 2 900
Onagawa 3 2,100
Higashidori 1 1,900
Total 8,500
Schedule・January 8, 2010 Approval by national government for
changes of nuclear reactor installations
・March 18, 2010 Acceptance by local authorities through prior discussions based on the safety agreement
・Pluthermal operations to start by FY 2015
Approx. number of construction points of piping and circuits
I. Medium-term business plan
14,890
32,463
58,669
95,892
129,882
0
20,000
40,000
60,000
80,000
100,000
120,000
140,000
FY2005 FY2006 FY2007 FY2008 Feb. 2010
Waterheatingsystems27.5%
Lights andelectrical
appliances32.9%
Airconditioners
0.2%Heaters39.4%
4
Accumulated number of ecocute
Over 120,000
The future key to energy
saving
Promotion of energy saving by spreading the use of
highly-efficient equipment such as heat pumps
Breakdown of energy used in households (Tohoku region)
Source: “Residential Eenergy Statistics Yearbook 2008”, the Jyukankyo Research Institute Inc.
Create electrification market by encouraging customersto be more energy efficient
Creating an electrification market to match the characteristics of the Tohoku regionResidential:
Promote heat-pump electrification with excellent environment and energy-saving performance⇒ Intensive campaign for “ecocute” for hot water supply and “heat-pump heating” for room-heating
Commercial:Offer solution services to resolve customers’ problems
⇒Offer services that meet customers’ needs such as discussions on energy-saving and ESCO businessesIntroduce industrial electrification systems based on heat-pump
⇒Propose highly-efficient multi-air conditioners for buildings in cold regions and heat-pump hot-water supply for commercial use (ecocute), and electric kitchen systems
I. Medium-term business plan
5
Facilities Location/name Output(MW) Start of operation
Moriyoshi 11 May 2011Tsugaru 8.5 May 2016
H1 0.23 Dec. 2013
Sendai Solar 2 Jan. 2012
Namie Odaka 825 FY 2021
Nuclear Higashidori Unit 2 1,385 FY 2021 or later
H2 4.5 Jul. 2015Sendai Unit 4 446 Jul. 2010
Niigata Unit 5 Series 109 Jul. 2011Aikawa Unit 3 7.5 Jul. 2011
Shin-SendaiUnit 3 Series 980 Jul. 2016 (half capacity)
Jul. 2017 (remaining half)
Joetsu Unit 1 Series 1,440 FY 2023Noshiro Unit 3 600 FY 2025 or later
Hachinohe Solar 1.5 Jan. 2012
Haramachi Solar Approx. 1 By around FY 2013
New
Energy(Solar)
Thermal
Hydro
3728
4
4
22
20
60
4
13
14
21
40
3
30
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
FY2009 FY2019
Nuclear
Hydro
Geothermal and
New Energy
Gas
Oil
Coal
target
Power generated by energy sources and plan for development of power sources
※Including purchased power Key: Red text indicate changes from the previous plan.
II. Supply plan
Proactively work toward a low-carbon society
Boosting nuclear powerBoosting nuclear power・To achieve the long-term goal of nuclear power accounting for 40% of generated electric power, the power source development plan (Namie Odaka
and Higashidori Unit 2) is being promoted.・Improve the capacity factors of existing nuclear power plants by improving seismic margin, promptly preparing for long-term cycle operations, and
overhauling the plant operation system. LowLow--carbon thermal power generationcarbon thermal power generation
・Increase the thermal efficiency of thermal power generation plants by upgrading the advanced combined cycle.・Increase the efficiency of coal-fired power generation with high economic performance and take measures to reduce CO2 emissions (R&D on
IGCC and CCS).Renewable energiesRenewable energies
・Tohoku EPCO owns the most hydropower generation facilities in Japan (210 sites), has the largest capacity output of geothermal power generation in Japan (about 250 MW for the entire Group) and the largest interconnected wind power in Japan (about 510 MW), and is also developing mega solar power generation and woody biomass fuel systems. *Figures in parentheses are actual data for FY 2008.
6Demand outlook
52.3 49.6 50.5 51.0 51.357.6 55.0 55.7
28.828.9 28.9 29.0 29.3
32.031.1 31.4
300
400
500
600
700
800
900
1000
平成20年度 平成21年度 平成22年度 平成23年度 平成24年度 平成30年度 平成30年度 平成31年度
(billion kWh)
40.0
50.0
60.0
70.0
80.0
90.0
FY2008 FY2009(Est.)
FY2010 FY2011 FY2012 FY2018(Previous plan)
FY2018(Current plan)
FY2019
81.178.5 79.4 80.0 80.6
89.6 86.1 87.1
Specified scale demand (Deregulated segment) Annual growth rate 0.6%
Non-specified scale demand (Excluding deregulated segment) Annual growth rate 0.8%
Annual growth rate 0.7%Annual growth rate 0.7%100.0
Compared with FY 2009 (Est.)・Specified scale demandCompared with FY 2009 (Est.)・Specified scale demand
+ 0.9 billion kWh+ 0.9 billion kWh
Decrease of 3.5 billion kWh from the previous plan
Decrease of 3.5 billion kWh from the previous plan
NonNon--specified scale demandspecified scale demand: Thanks to increase of all-electric housing, demand is expected to grow, although it will be negatively affected by population decrease and energy conservation.
Specified scale demandSpecified scale demand: Demand is expected to grow in the medium to long term due to the development of industrial clusters, but to be negatively affected by global recession in the short term.
II. Supply plan
0.0
55.977.4 87.8
154.2131.2 119.3
47.6 46.5 46.5
68.4(Power
Sources)
157.2(Supply
Facilities)
57.7(Other)
0.0
50.0
100.0
150.0
200.0
250.0
300.0
平成2 1年度 平成2 1年度 平成2 2年度 平成2 3年度
(billion yen)
7Capital investment plan
257.7 255.1 253.6
283.3
FY2009(Previous plan)
FY2009(Est.)
FY2010(Plan)
FY2011(Plan)
To simultaneously achieve energy security, environmental protection and economic growth, necessary facility measures are incorporated in the plan. Capital investment for FY 2009 to 2011 is around 250 billion yen.
II. Supply plan
: Causes of increase/decrease from the previous plan or fiscal year are described in the box.
・Niigata Unit 5 retention
・Software
・Decreased northern trunk line constructions
・Construction of new main building of Onagawa (plant)・Renovation of Toyomi (plant)
・Decreased northern trunk line constructions
・To secure 40% share by nuclear power generation in total generated power in the long term.
・To reduce five-year average end-use CO2 emissions from FY 2008 to 2012 by 20% from FY 1990 level.
・To develop about 10 MW of mega solar power generation facilities by FY 2020.
・To create demand of about 2.2 billion kWh (from FY 2010 to 2014).Shift to electric hot-water supply and heating from gas or oil-basedMajor actions:
Introduce all-electric housing: Expansion by about 140 thousand houses (from FY 2010 to 2014)Introduce semi-electric housing: Expansion by about 140 thousand houses (from FY 2010 to 2014)Introduce air-conditioning systems: Expansion by about 420 MW (from FY 2010 to 2014)Introduce commercial electric kitchens: Expansion by about 170 MW (from FY 2010 to 2014)
III. Numeric targets 8
This medium-term business plan does not include numeric targets as it is difficult to set quantitative goals amid the current business uncertainties with sudden large fluctuations in fuel prices, large-scale decline of power demand caused by global recession, and environmental policies.Emphasis is placed on achieving goals for reducing CO2 emissions and winning new accounts.
Ratio of nuclear power generationRatio of nuclear power generation
CO2 emission reduction goalCO2 emission reduction goal
Creation of electrification marketCreation of electrification market
Mega solar power generation facilitiesMega solar power generation facilities
*Data based on news releases
SendaiHarbor
AkitaHarbor
NiigataHarbor
SakataHarbor
Tohoku Expressway
※ Sea and Rail Vision
* Sea and Rail VisionThis concept envisions connecting Japan and
Russia by sea and rail with Akita port as its hub.
KamaishiHarbor
To Russia
To North America
-Toyota Motor Corporation has a vision for creating “three domestic manufacturing hubs.” As one of these manufacturing hubs, the Tohoku region has the potential for developing as: 1) a large production base for small cars and environment-friendly vehicles; and 2) an export hub to Russia and northeastern China. - Panasonic EV Energy commenced operations in January 2010, and Toyota’s vision of transferring the Tohoku region into its production base has already started. -Nissan Motor Company is expected to produce its first engine for hybrid cars in the Tohoku region.
(Ref.) Auto industry cluster
①
②
③④
⑤
⑥
⑦
Toyota Boshoku Corp. (Ohira Village)<Car Interiors>Jan. 2011 expected to commence operations
Kanto Auto Works, Ltd. (Kanegasaki Town)<Compact Vehicles>1993 commenced operations
Central Motor Co., Ltd. (Ohira Village)<Compact Vehicles> Jan. 2011 expected to commence operations
Aisin Takaoka Co., Ltd. (Ohira Village)<Iron casting for automotive products>New construction (in planning stage)
①Toyota Boshoku Corp. (Kitakami City)<Car Interiors> 1993 commenced operations
【Iwate Pref.】
②
【Miyagi Pref.】
③
Toyota Motor Tohoku, Inc. (Taiwa Town)<Engine Parts> 1998 commenced operationsFactory Expansion (in planning stage)
Panasonic EV Energy Co., Ltd. (Taiwa Town)<Nickel-hydrogen battery for hybrid cars>Jan. 2010 commenced operations
Denso Higashinihon Corp. (Tamura City)<Car Air Conditioners>May 2011 expected to commence operations
【Miyagi Pref.】
④
⑤
Keihin Corp. (Kakuda City)<Electronic Control Parts>1969 commenced operations
【Fukushima Pref.】
Nissan Motor Co., Ltd. (Iwaki City)<Engine Parts> 1994 commenced operations
⑥
⑦
:Toyota affiliate
:Honda affiliate
:Nissan affiliate
9
10(Ref.) Transmission and transformation plan
Work periodFacilities
Name of construction
Commencement Start of operation
Installation of Towada Trunk Line Aug. 2006 Sep. 2013 500 kV 114 km double circuit line
Installation of Kitakami Trunk Line Aug. 2006 Oct. 2013 500 kV 184 km double circuit line
Upgrade of Aoba Trunk Line Apr. 2009 Jun. 2010500 kV (←275 kV) 57 km
double circuit line
Transm
ission
Upgrade/capacity expansion of Iwate Substation Aug. 2007 Oct. 2013 500/275 kV 1,000,000 kVA 1 unit
Transform
ation
Upgrade of Miyagi Chuo Branch Line Apr. 2009 Jun. 2010
500 kV (←275 kV) 0.5 kmdouble circuit line
Upgrade/capacity expansion of Kamikita Substation Aug. 2005 Sep. 2013 500/275 kV 1,300,000 kVA 2 units
Installation of Miyagi Chuo Substation Feb. 2007 Jun. 2010 500/275 kV 1,500,000 kVA 1 unit
Upgrade/capacity expansion of Miyagi Substation Feb. 2007 Oct. 2013 500/275 kV 1,000,000 kVA 1 unit
Capacity expansion of ShinchiSubstation Aug. 2010 Jun. 2012 500/154 kV 300,000 kVA 1 unit
Outline of facilities
Key: Red text indicate changes from the previous plan.
Construction of the northern trunk lines
To develop nuclear power sources in northern Tohoku and secure a stable supply of electric power in the Company’s service area, new constructions and step-up works for transmission lines and new constructions and step-up/expansion of substations are being implemented as part of the development of 500kV trunk lines.
Kitakami trunk lines: Nylon ropes are stretched by helicopter
Installing 500kV equipment at Iwate Substation
・Various new technologies and construction methods are being introduced and design specifications are being streamlined.
* For step-up/expansion construction of Kamikita Substation, the addition of transformers and step-up of the Mutsu trunk line were completed and operation started in November 2009, and pullout construction in conjunction with the addition of the Towada trunk line is scheduled to be completed and operation will start in September 2013.
22,229 22,914 22,793 23,612 24,355 24,291 25,073 24,679 24,845 24,940
34,098 34,552 34,510
24,250
4,724 4,302 4,346 4,078 4,051 3,985
16,17316,789 17,244
29,467
50,585 52,35754,653
52,344 49,603 50,507
-2.7
2.4
0.4
3.73.0
1.6
3.9
-3.5 -3.2
1.2
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
90,000
100,000
FY2001 FY2002 FY2003 FY2004 FY2005 FY2006 FY2007 FY2008 FY2009(Est.)
FY2010(Plan)
-40.0
-35.0
-30.0
-25.0
-20.0
-15.0
-10.0
-5.0
0.0
5.0
(million kWh) (%)
(Ref.) Electric power sales 11
Growth Rate(Right Scale)
Commercialand
Industrial
Residential
72,500 74,255 74,54777,329
79,66480,950
84,07281,101
78,499 79,432
*Deregulated segment is constituted by customers who use a supply system with a contracted demand of 2,000kW or above from FY2001 to FY2003, 500kW or above in FY2004, and 50kW or above after FY2005.
Specified scaledemand (*)
(Ref.) Trends in large industrial demand 12
1,500
1,750
2,000
2,250
2,500
Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.
(million kWh)
FY1998 FY2004 FY2005 FY2006FY2007 FY2008 FY2009
(Ref.) Accumulated number and ratio of all-electric housing, and accumulated number of semi-electric housing 13
91,744
130,217
206,419
1,840 6,02914,558
28,377
49,088
66,481
155,713
108,205
182,916
25.4
36.3
17.1
19.9
41.5
48.7
0
50,000
100,000
150,000
200,000
250,000
2004 2005 2006 2007 2008 Feb. 2010 (FY)
(houses)
0
5
10
15
20
25
30
35
40
45
50(%)
Accumulated Number of all-electric housing (left acale)
Accumulated Number of semi-electric housing (left scale)
Ratio of installation compared with new housing (right scale)
(※)
*The introduction rate of all-electric housing of FY 2009 is the figure as of January 31, 2010.
29% 27%30% 31%
36%
29%35% 35% 37%
26% 28%
7% 9%
11% 8%
12%
7%
7% 6% 4%
4%4%
25% 25%
25%
19%
19%
25%
22% 23% 22%
21%20%
3%
3%
3%
3%3% 2% 3%
4% 4%
16% 15%
17%
16%
15%
16% 12% 13% 13%
14% 14%
14%
23%
15%20% 21% 21% 21%
31% 30%
2%2%
22%21%
0%
20%
40%
60%
80%
100%
平成13 平成14 平成15 平成16 平成17 平成18 平成19 平成20 平成21
(推実)
平成26
(計画)
平成31
(計画)
(Ref.) Power generated by energy sources 14
※Including purchased power
Geothermal and
New Energy
Nuclear
Oil
Gas
Coal
Hydro
FY2001 FY2002 FY2003 FY2004 FY2005 FY2006 FY2007 FY2008 FY2009(Est.)
FY2014(Plan)
FY2019(Plan)
(Ref.) Plant and equipment expenditures 15
FY2001 FY2002 FY2004 FY2006 FY2008 FY2009(Est.)
68.5 55.9
62.5
46.0
44.7
0.9
154.2
27.7
19.9
47.6
257.7
70.3
20.0
42.7
0.9
134.0
35.6
14.0
49.6
252.1
FY2010(Plan)
37.9 77.4
47.3
33.2
49.1
1.7
131.2
20.6
25.9
46.5
255.1
52.7
20.9
39.5
3.4
116.7
13.1
11.9
Other and nuclear fuel 30.8 41.4 28.6 28.7 33.4 25.0 40.2
179.6
104.9
29.2
25.5
35.8
0.6
91.2
13.2
15.4
224.8
77.9
33.8
22.5
38.8
5.1
100.2
16.6
24.6
219.5
121.3
35.5
23.9
42.7
1.6
103.8
14.0
16.6
255.9
FY2003 FY2005 FY2007
Power sources subtotal 67.9 56.1 43.4
Transmission 27.6 41.0 66.1
Transformation
Distribution
Dispatch
20.8 17.4 18.4
43.2 38.9 43.8
0.3 0.5 2.2
Supply facilities subtotal 92.0 97.7 130.5
Other 12.3 16.8 27.3
Nuclear fuel 16.2 16.5 12.9
Electric business total 188.5 187.2 214.1
(billion yen)
(Ref.) Capital raised for plant and equipment 16
FY2009(Est.)
FY2010(Plan)
Plant and equipment expenditures 257.7 255.1
Internal funds 322.5 225.7
Internal reserve 283.1 273.1
Depreciation 216.1 215.7
Other 67.0 57.3
Customer construction etc.
( Bonds [amount of issue] )
Net proceeds from bonds
Borrowings
39.3 -47.4
External -64.8 29.4
(120.0) (140.0)
29.6 21.6
-94.4 7.8
(billion yen)
(Note)
This presentation solely constitutes reference material for the purpose of providing the readers with relevant information to evaluate our company.
The information contains forward-looking statements based on assumptions and projections about the future with regard to our company. As such, the readers are kindly asked to refrain from making judgment by depending solely on this information.
The forward-looking statements inherently involve a degree of risks and uncertainties. Consequently, these risks and uncertainties could cause the actual results and performance to differ from the assumed or projected status of the company.
Tohoku Electric Power Co., Inc. hereby disclaim any responsibility or liability in relation to consequences resulting from decisions made by investors.