probing ppps in thailand

Upload: pppnews

Post on 30-May-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/9/2019 Probing PPPs in Thailand

    1/5

    All content Copyright 2010 Emap Limited, all rights reserved.

    Probing PPPs in Thailand

    Stephen Jaggs and Tony Lui Allen & Overy

    27/05/2010

    In Thailand, private sector involvement in the delivery of public infrastructure has

    usually taken the form of concession based projects implemented using traditional

    project finance structures. More recently there has been increased recognition and

    support from within the Thai government for more sophisticated forms of private

    sector involvement in the form of public private partnerships.

    These initiatives include the drafting of a new PPP law, the release of draft PPP Guidelines and

    proposals to establish a PPP taskforce. This coupled with the Thai government's Baht1.4

    trillion Stimulus Package No.2. (SP2) to be spent over the next few years may present good

    opportunities for PPPs in Thailand.

    BackgroundIn Thailand, PPP is a term which has historically been used in a broad sense to cover

    concession based private investment in public infrastructure made on the basis of traditional

    project finance structures. These traditional forms of project financing have played a major

    role in many sectors of the Thai economy for more than a decade, most notably in the

    energy, telecommunications and transport sectors.

    A common feature of almost all project financings in Thailand is a long term concession

    agreement (usually between 20-30 years) between the relevant government authority and

    the investor. The type of structure used depends on the type of project being implemented

    and the relevant governmental authority. The most common structures that are used in

    Thailand include: BOO (Build, Own, Operate), BTO (Build, Transfer, Operate), BOT (Build,

    Operate, Transfer), DBOM (Design, Build, Operate, Maintain) and BOOT (Build, Own,

    Operate, Transfer).

    A list of the major project financings undertaken in the last decade is set out in the table

    below.

  • 8/9/2019 Probing PPPs in Thailand

    2/5

    All content Copyright 2010 Emap Limited, all rights reserved.

    The Private Participation in State Undertaking Act B.E 2535

    (1992)

    Despite having implemented a large number of projects by way of project finance, Thailand

    does not have specific legislation to govern project finance or PPPs. Instead, such activities

    are governed under the normal background Thai legal framework and under the Private

    Participation in State Undertaking Act B.E 2535 (1992) (the PPSU Act).

    The PPSU Act was enacted primarily to prevent corruption in the granting of rights to private

    investors or use of state property and was not enacted with the intention of providing a legal

    framework for PPPs. As a consequence, it does not contain a number of the concepts

    commonly found in the PPP framework found in other international models.

    Concepts like providing for (i) a method to evaluate projects, (ii) procurement methods, and

    (iii) a methodology for sharing risks with the private sector are not dealt with in the PPSU

    Act. The current institutional set-up is also somewhat fragmented, with regulatory power and

    authority resting with several different agencies.

    In recognising the limited scope the PPSU Act has for PPPs, the Thai government has been

    working on a number of initiatives that are aimed at aligning the PPP framework in Thailand

    closer to the PPP framework of other international models. These include the drafting of a

    http://www.ijonline.com/cmsv2/Images/Uploaded/147-12-3-3-287_crp_LG.jpeg
  • 8/9/2019 Probing PPPs in Thailand

    3/5

    All content Copyright 2010 Emap Limited, all rights reserved.

    new PPP law, the release of the draft PPP guidelines and proposals to establish a PPP

    taskforce unit to oversee and facilitate the implementation and operation of PPP's in Thailand.

    Draft PPP law

    The Ministry of Finance is currently in the process of drafting a new PPP law. It is understood

    that the new law will provide a clearer legal framework for the implementation and operation

    of PPPs in Thailand and will incorporate concepts and best practices found in PPP enabling

    legislation of other countries. The Ministry of Finance anticipates that it will take at least 2

    years before a new PPP law comes into effect.

    PPP Guidelines

    Given the lead time before a new PPP law can come into effect, the Public Debt Management

    Office of Thailand (being a department of the Ministry of Finance) issued draft PPP Guidelines

    in November 2009. The PPP Guidelines have been developed as a means of providing

    government departments with a better understanding of PPP projects and to serve as a guide

    on how to implement PPP projects within Thailand's existing legal framework. The draft PPP

    Guidelines were subject to a public consultation period of 45 days and are expected to be

    revised and finalised before being submitted for review and approval by the Thai government.

    The guidelines include basic principles on:

    comparing investment costs between projects implemented by way of PPP versus

    projects implemented via traditional procurement methods;

    undertaking a project risk analysis and the allocation of those risks between the

    government and the private sector;

    procurement and selection processes and procedures; and

    the standard terms of the contract to be entered into between the government and the

    private sector.

    The PPP Guidelines represent a step towards modernizing the PPP framework in Thailand and

    displays the Thai government's commitment to developing this sector further. Some of

    initiatives under the Thai governments SP2 programme are expected to follow the PPP

    Guidelines with the first project being the purple line extension to the MRTA project which will

    link metropolitan Bangkok to the western suburbs of Bangkok.

    PPP taskforce

    The Thai government proposes to establish a PPP taskforce to oversee the implementation

    and operation of PPPs in Thailand to assist in addressing institutional obstacles. The

    taskforce unit will be comprised of representatives from various departments including the

    Ministry of Finance, the PDMO, the Comptroller General's Department and the National

    Economic and Social Development Board (the agency responsible for infrastructure planning).The key responsibilities of the taskforce will be to:

  • 8/9/2019 Probing PPPs in Thailand

    4/5

    All content Copyright 2010 Emap Limited, all rights reserved.

    set PPP policies and guidelines;

    act as the interface between the public and private sector by co-ordinating among the

    various Thai authorities that are involved in a PPP project;

    disseminate information about PPP project pipeline and guidelines to the public and

    private sectors;

    conduct market soundings for PPP projects; and

    prioritise the implementation of PPP projects under the Thai government's SP2

    programme.

    The procedures under the PPSU Act have sometimes been criticised as being overly

    bureaucratic and it is encouraging to see the establishment of a taskforce to streamline

    administrative procedures. The taskforce is expected to set the foundations from which PPPs

    will grow by developing predictable and transparent PPP policies.

    Stimulus Package No.2 (SP2)

    On 6 May and 15 June 2009, the Thai Cabinet approved a second economic stimulus package

    of Baht 1.45 trillion to be spent on public infrastructure projects over the next few years. The

    package is aimed at effecting substantial improvements to public infrastructure over a range

    of sectors including, energy, telecommunications, transport, public health and education.

    Under the SP2 programme, the Thai government has categorised projects according to their

    suitability for PPP as follows:

    The First Tier (commercially viable): These projects are commercially viable projects

    that have a strong financial internal rate of return and are ready for private sector

    participation. Projects falling within this category can earn sufficient revenues from end

    users and do no require government support. These include projects in the energy,

    telecom and air transport sectors.

    The Second Tier (economic infrastructure): These projects are economic

    infrastructure projects, including mass transit, rail, roads etc. which typically have a low

    financial internal rate of return. As such, whilst users can be made to pay, government

    support may be required for these projects to attract private investment. The

    government recognises that projects falling within this category could be implemented

    by way of PPP, so long as the government provides support that makes these projects

    financially viable.

    The Third Tier (social infrastructure): These projects are social infrastructure

    projects (e.g those in the health, education and water resources sector) which have a

    zero financial internal rate of return and the nature of the services provided by the

    project are such that users cannot be made to pay. As such, full support from the

    government will be required if these are to be implemented by way of PPP.

    Out of the Baht 1.4 trillion to be spent on infrastructure, the Thai government hopes to fund

    Baht 145 billion from PPPs. Of this, Baht 57 billion worth of projects have been identified as

  • 8/9/2019 Probing PPPs in Thailand

    5/5

    All content Copyright 2010 Emap Limited, all rights reserved.

    commercially viable, with projects with a value of Baht 45 billion in economic infrastructure

    and projects with a value of Baht 42 billion in social infrastructure.

    Stephen Jaggs is a partner at Allen & Overy's Bangkok office with extensive experience of

    project financings in Thailand and Indochina. He has worked in Asia for 15 years.

    Tony Lui is an associate at Allen & Overy's Bangkok office who has also advised on a number

    of project financings in the region. He has wide experience in banking transactions including

    project finance, property finance and syndicated finance, debt.

    This article was first published by the Infrastructure Journalon May 27, 2010. An online copy

    of the feature may be seenhere.

    http://www.ijonline.com/genv2/Secured/DisplayArticle.aspx?ArticleID=62648http://www.ijonline.com/genv2/Secured/DisplayArticle.aspx?ArticleID=62648http://www.ijonline.com/genv2/Secured/DisplayArticle.aspx?ArticleID=62648http://www.ijonline.com/genv2/Secured/DisplayArticle.aspx?ArticleID=62648