Sector Roads & Highway Project Type Expressway Construction Project Title Hanoi City Ring Road No. 3 Construction Project Mai Dich – North Linh Dam Section Location Mai Dich – North Linh Dam Lake, Hanoi, Vietnam Client Ministry of Transport (Project Management Unit Thang Long) / JICA Project Period May 2010 – October 2012 View of Viaduct Off Ramp at Trung Hoa Interchange Thanh Xuan Intersection Problems addressed by the Project The implementation of the ‘Doi Moi’ (Renovation) policy has yielded drastic socio-economic and cultural development in Hanoi, Capital of Vietnam. Subsequently, rapid urbanization and population growth has increased demand for transportation in the city resulting in serious traffic congestion. In order to meet this traffic demand, implementation plan for the Hanoi City Ring Road No. 3 (H3RR) was planned since 1998. H3RR is a ring road functioning as an urban expressway linking the centre of Hanoi with radial road and arterial roads. The South – West section of H3RR (the Red River Bridge Construction Project) has been constructed already funded by JICA and supervised by OC Global. Since the completion of Red River Bridge Construction Project, traffic volume of section Mai Dich – North Linh Dam rapidly increased. This necessitated implementation of this Project. Section Mai Dich – North Linh Dam is one of most rapidly urbanized areas in Hanoi. Frontage Road was constructed before commencement of this Project. Therefore, the construction work was executed under very limited construction space and there was much public traffic adjacent to the construction site. Therefore, maintaining safety during construction was one of the most important issues in this Project. Service Provided OC Global conducted two of the earlier studies for this Project: review of Feasibility Study of this Project by Special Assistance for Project Formation (SAPROF) funded by JICA in 2007. OC Global was subsequently engaged to provide detailed design, pre-qualification and tender assistance. OC Global also provided the construction supervision and defect liability services from May 2010 to 2014. Actual Project Works Expressway : 4 Lane, Design Speed = 100 km/h Length of Viaduct : 8,521.1 m Ramp : 8 set of On/Off Ramp Structure Type (Superstructure) : Super-T Girder Structure Type (Sub-Structure) : T-shape RC Pier with PC pier head Structure Type (Foundation) : Bored Pile Structure (D=1.5m)

Upload: lamthuan

Post on 12-Apr-2018

218 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Problems addressed by the Project - 株式会社オリエン … Roads & Highway Project Type Expressway Construction Project Title Hanoi City Ring Road No. 3 Construction Project

Sector Roads & Highway

Project Type Expressway Construction

Project Title Hanoi City Ring Road No. 3 Construction Project Mai Dich – North Linh Dam Section

Location Mai Dich – North Linh Dam Lake, Hanoi, Vietnam

Client Ministry of Transport (Project Management Unit Thang Long) / JICA

Project Period May 2010 – October 2012

View of Viaduct

Off Ramp at Trung Hoa Interchange

Thanh Xuan Intersection

Problems addressed by the Project

The implementation of the ‘Doi Moi’ (Renovation) policy has yielded drastic socio-economic and cultural development in Hanoi, Capital of Vietnam. Subsequently, rapid urbanization and population growth has increased demand for transportation in the city resulting in serious traffic congestion. In order to meet this traffic demand, implementation plan for the Hanoi City Ring Road No. 3 (H3RR) was planned since 1998.

H3RR is a ring road functioning as an urban expressway linking the centre of Hanoi with radial road and arterial roads. The South – West section of H3RR (the Red River Bridge Construction Project) has been constructed already funded by JICA and supervised by OC Global. Since the completion of Red River Bridge Construction Project, traffic volume of section Mai Dich – North Linh Dam rapidly increased. This necessitated implementation of this Project.

Section Mai Dich – North Linh Dam is one of most rapidly urbanized areas in Hanoi. Frontage Road was constructed before commencement of this Project. Therefore, the construction work was executed under very limited construction space and there was much public traffic adjacent to the construction site. Therefore, maintaining safety during construction was one of the most important issues in this Project.

Service Provided

OC Global conducted two of the earlier studies for this Project: review of Feasibility Study of this Project by Special Assistance for Project Formation (SAPROF) funded by JICA in 2007. OC Global was subsequently engaged to provide detailed design, pre-qualification and tender assistance. OC Global also provided the construction supervision and defect liability services from May 2010 to 2014.

Actual Project Works

Expressway : 4 Lane, Design Speed = 100 km/h Length of Viaduct : 8,521.1 m Ramp : 8 set of On/Off Ramp Structure Type (Superstructure) : Super-T Girder Structure Type (Sub-Structure) : T-shape RC Pier with PC pier head Structure Type (Foundation) : Bored Pile Structure (D=1.5m)