process dsign line balancing
TRANSCRIPT
Process Design and Facility Layout
6/28/2015 DMA Kulasooriya, NIBM (UCD -BSc-2011)
DMA Kulasooriya
ISL- Certified Six Sigma Black Belt
Cellular Layouts
Cellular Manufacturing
Group Technology
Flexible Manufacturing Systems
6/28/2015 DMA Kulasooriya, NIBM (UCD -BSc-2011)
A Flow Line for Production or Service
Flow Shop or Assembly Line Work Flow
Raw
materials
or customer
Finished
item Station
2
Station
3
Station
4
Material
and/or
labor
Statio
n
1
Material
and/or
labor
Material
and/or
labor
Material
and/or
labor
6/28/2015 DMA Kulasooriya, NIBM (UCD -BSc-2011)
A U-Shaped Production Line
1 2 3 4
5
6
7 8 9 10
In
Out
Workers
6/28/2015 DMA Kulasooriya, NIBM (UCD -BSc-2011)
Cellular Manufacturing Layout
-1111 -1111
222222222 - 2222
As
se
mb
ly
3333333333 - 3333
44444444444444 - 4444
Lathe
Lathe
Mill
Mill
Mill
Mill
Drill
Drill
Drill
Heat
treat
Heat
treat
Heat
treat
Gear
cut
Gear
cut
Grind
Grind
6/28/2015 DMA Kulasooriya, NIBM (UCD -BSc-2011)
Design Product Layouts: Line Balancing
Line Balancing is the process of
assigning tasks to workstations in such
a way that the workstations have
approximately equal time requirements.
6/28/2015 DMA Kulasooriya, NIBM (UCD -BSc-2011)
Cycle Time
Cycle time is the maximum time
allowed at each workstation to
complete its set of tasks on a unit.
6/28/2015 DMA Kulasooriya, NIBM (UCD -BSc-2011)
Line Balancing
Assembly line balancing operates under two constraints,
precedence requirements and cycle time restrictions’
Precedence requirements are expressed in the form of a
precedence diagram- network
Cycle time is calculated by dividing the time available for
production by the number of units to be produced – time
taken to completed item rolling off the assembly line.
6/28/2015 DMA Kulasooriya, NIBM (UCD -BSc-2011)
Determine Maximum Output
Output capacity = OT
CT
OT operating time per day
D = Desired output rate
CT = cycle tim e = OT
D
6/28/2015 DMA Kulasooriya, NIBM (UCD -BSc-2011)
Determine the Minimum Number of Workstations Required: Efficiency
s task timeof sum = t
CT Desired
t)( = N
6/28/2015 DMA Kulasooriya, NIBM (UCD -BSc-2011)
Real fruit Snack are made from a mixture of dried fruits and packaged. To meet demand real fruit needs to produce 6000 fruit strips every 40-hour week. Design an assembly line with fewest number of workstations that will achieve the production quota without violating precedence constraints
6/28/2015 DMA Kulasooriya, NIBM (UCD -BSc-2011)
Work Element Precedence Time (Min)
A Press out sheet of fruits
----- 0.1
B Cut into strips A 0.2
C Outline Fun Shapes A 0.4
D Roll up and package B,C 0.3
Total 1.0
6/28/2015 DMA Kulasooriya, NIBM (UCD -BSc-2011)
Precedence Diagram
Precedence diagram: Tool used in line
balancing to display elemental tasks and
sequence requirements A Simple Precedence
Diagram
A B
C
D
0.1 min. 0.2 min.
0.4 min.
0.3 min.
6/28/2015 DMA Kulasooriya, NIBM (UCD -BSc-2011)
Calculate the desired CT (Takt Time) TT = 40 h * 60 m/ h = 2400 6000 units 6000 = 0.4 minute
6/28/2015 DMA Kulasooriya, NIBM (UCD -BSc-2011)
Calculate the theoretical minimum number of workstations
N = 0.1 + 0.2 + 0.3 + 0.4 = 1.0 = 2.5
0.4 0.4
N= 2.5 = 3 workstations
6/28/2015 DMA Kulasooriya, NIBM (UCD -BSc-2011)
Assembly Line Balancing
Arrange tasks shown in the previous slide into workstations.
◦ Use a cycle time of 0.4 minute
◦ Assign tasks in order of the most number of followers
6/28/2015 DMA Kulasooriya, NIBM (UCD -BSc-2011)
Work Station
Work Element
Remaining time
Remaining Elements
1 A 0.3 B C
B 0.1 C D
2 C 00 D
3 D 0.1 None
6/28/2015 DMA Kulasooriya, NIBM (UCD -BSc-2011)
A B
C
D
0.1 min. 0.2 min.
0.4 min.
0.3 min.
Assembly line with three workstations
6/28/2015 DMA Kulasooriya, NIBM (UCD -BSc-2011)
A B C D
Workstation -01 Workstation -02 Workstation -03
0.3 m 0.4 m 0.3 m
Assembly Line
6/28/2015 DMA Kulasooriya, NIBM (UCD -BSc-2011)
Calculate Percent Idle Time
Percent idle time = Idle time per cycle
(N)(CT)
PIT = 0.2/ 3 (0.4) = 16.6 %
6/28/2015 DMA Kulasooriya, NIBM (UCD -BSc-2011)
Determine the Efficiency
s task timeof sum = t
actual) (CTn
t)( = E
E = 0.1 +0.2+0.3+0.4 = 1.0/ 1.2 = 83.3%
3 (0.4)
6/28/2015 DMA Kulasooriya, NIBM (UCD -BSc-2011)
Requirements:
◦ List of departments
◦ Projection of work flows
◦ Distance between locations
◦ Amount of money to be invested
◦ List of special considerations
Designing Process Layouts
6/28/2015 DMA Kulasooriya, NIBM (UCD -BSc-2011)
6/28/2015 DMA Kulasooriya, NIBM (UCD -BSc-2011)