pt 150 kv
TRANSCRIPT
-
8/7/2019 PT 150 KV
1/1
PT PLN ( Persero )
PENYALURAN DAN PUSAT PENGATUR BEBAN SUMATERA
UNIT PELAYANAN TRANSMISI PEMATANG SIANTAR
E. POTENTIAL TRANSFORMER (PT)
BURDEN BILL
PRIMER SEKUNDER (VA) (Kv) BUAT OPERASI
1 P.Sidempuan- Sibolga 1 R 150 KV Energoinvest KNT170 0,5 150KV/V3/100V/V3 100 72418/91 1991 1992 Operasi
S 150 KV Energoinvest KNT170 0,5 150KV/V3/100V/V3 100 72419/91
T 150 KV Energoinvest KNT170 0,5 150KV/V3/100V/V3 100 72420/91
2 P.Sidempuan- Sibolga 2 R 150 KV Trench Limited VP161A 0,5 150KV/V3/100V/V3 100 28579801 2002 2003 Operasi
S 150 KV Trench Limited VP161A 0,5 150KV/V3/100V/V3 100 28579802
T 150 KV Trench Limited VP161A 0,5 150KV/V3/100V/V3 100 28579803
3 P.Sidempuan- R.Prapat 1 R 150 KV Trench Electric VP161A 0,5-3P 150KV/V3/100V/V3 100 947123703 1994 1994 Operasi
S 150 KV Trench Electric VP161A 0,5-3P 150KV/V3/100V/V3 100 947123702
T 150 KV Trench Electric VP161A 0,5-3P 150KV/V3/100V/V3 100 947123701
4 P.Sidempuan- R.Prapat 2 R 150 KV Trench Electric VP161A 0,5-3P 150KV/V3/100V/V3 100 48988305 2004 2007 Operasi 20 Nop 2007
S 150 KV Trench Electric VP161A 0,5-3P 150KV/V3/100V/V3 100 48988304
T 150 KV Trench Electric VP161A 0,5-3P 150KV/V3/100V/V3 100 48988306
5 Bus Coupler ( Bus 1 ) 150 KV Trench VP161A 0,5-3P 150KV/V3/100V/V3 120 38794104 2003 2006 OFF PT diambil untuk GI RTP
Tgl. 18 Mar 2010
6 Bus Coupler ( Bus 2 ) 150 KV Trench VP161A 0,5-3P 150KV/V3/100V/V3 120 38794103 2003 2006 Operasi PT diambil untuk GI RTP
Tgl. 16 Juni 2010
Padang Sidimpuan, 1 Januari 2011
Supv. GI Padang Sidimpuan,
EKO SUBANDI
RATIOPHASA STATUS KETERANGAN
TAHUNNO
DATA PERALATAN TERPASANG
GARDU INDUK PADANG SIDEMPUAN
BAY TEG MERK TYPE CLASS NO SERI