saipem limited - gassco · pdf filesaipem limited saipem scope was to remove the 2/4-s jacket...
TRANSCRIPT
saipem limited
Statoil 2/4S Removal Project
GASSCO HSE Summit ‘Removal of the Statoil 2/4 S Platform’
23rd October 2014
saipem limited
Introduction of the Scope of Saipem Work
Project specific details
Summary of project including history, change development and methods employed.
HSE approach
Animation update for ‘as removed’ condition
Lessons Learnt
Conclusion
Presentation of the Removal of the Statoil 2/4 S Platforms
2
saipem limited
Saipem scope was to remove the 2/4-S Jacket and Tripod structures and deliver to the Deconstruction facility at Kvaerner Stord, Norway
All Engineering and Structure Preparations, Removal and Transportation (EPR)by Saipem
Contract awarded in mid 2011
Topsides had been previously removed by others, so minimal access available and the structures have been unattended for a long time.
The preparation and removal work was performed in Q2/Q3 2014
10 different vessels and 2# cargo barges used in the execution of the Project.
Introduction
3
saipem limited
Project Details - Key Operational Dates
• Campaign 1 – Survey 22nd June 2012
S7000 Flyby – Survey 30th August 2012
Grout Survey Campaign 28th November 2012
Campaign 2 – OCV 21st April 2014
Campaign 3 – OCV – Incorporated in to S7000 Removal Campaign
Pre-tow survey 4th July 2014
Removal Phase 1 – S7000 1st July 2014
Removal Phase 2 – S7000 8th August 2014
All structures delivered to KV Stord 18th August 2014
4
saipem limited
Project Details - Interfaces and Subcontracts
Interfaces:
2/4-S deconstruction Kværner Stord
Warranty Surveyor London Offshore Consultants
Supplier and Subcontractors used:
Dredging and Excavation X-Subsea
External cutting (Piles and Riser) Cut UK
OCV EMAS
Lift Frame (Design and Build) WESL
Offshore access and NDE Kaefer Opus
Corner Platform Fabrication Hollandia
Survey (offshore and Pre/post tow) Fugro
Survey (onshore) Parker Maritime
Rigging supply Hendrik Veder/Franklin
Lifting Clamps (2000t and 1100t)capacity IHC
Weather Forecasting Met Office
Radiation Services Tracerco
5
saipem limited
- EKOFISK 2/4S Removal
COPSAS {Field Operator}
Gassco AS {Operator}
Statoil {Client}
- EKOFISK Field
218 NM to Stord
3.5 day tow @ 2.5 Knots
c80m water depth
Project Details - Field location and ‘wet tow’ route
6
saipem limited
- EKOFISK Field information
Live Field
c80m between structures
2/4T tank adjacent
80m water depth
Project Details - Platform locations within Ekofisk
7
saipem limited
2-4S Jacket 2-4S Tripod and Deck
Project Details - Structures removed
8
saipem limited
S7000 Scope – Tripod & Jacket removal
Tripod Deck ~ 142 tonnes in air
Tripod ~ 2500 tonnes in air - Pile Diameter = 72” x 2½” thick
2/4S Jacket~ 8000 tonnes in air 72” x 2½” thick
Project Details - Lifted and removed weights
9
saipem limited
OCV Scope
- Campaign 2 – Intervention Campaign
April / May 2014
Excavation
Pile Cutting
Debris relocation
Anode removal
Leg cleaning
Project Details – OCV Scope
10
saipem limited
- Subsea Surveys
- Campaign 1 Inspection (Grampian Surveyor)
Structure appraisal (GVI, CVI, FMD, Wall thickness, etc..)
Marine growth measurements
Densitometers (Radiation)
- Statoil Subsea Survey (Edda Flora)
Grout Inlet Recovery
Pile Weld inspection
Project Details – Survey Scopes
11
saipem limited
Summary of project – Original Removal Method
Original Offshore plan was to:
Prepare the Structures by OCV
Use OCV in SIMOPS with the S7000 campaign
Remove the Tripod (lift on the S7000 deck)
Lift the Jacket
Wet tow the Jacket to the deconstruction site
Place the Jacket on the seabed
Place tripod on quay
Cut jacket and place one section onto the quay, the other section in front of the quay
12
saipem limited
Summary of project changes/development
Unexpected challenge discovered – weld at top part of jacket (at water line) not as expected
Revise lift method – lift from piles
High risk with work on tripod very close to waterline
Development of access method by utilising bespoke access systems and Lift tools rather than welding lifting points.
Schedule challenge with other Statoil installation projects
Adjust S7000 schedule to allow a split campaign
OCV Availability challenge
Combine work on one vessel and avoid SIMOPS
13
saipem limited
Summary of project changes - Solutions
Success By
Develop a robust removal solution for the Jacket – ALARP application
Evaluating how methods can improved and developed access and reduce risk to personnel
Vessel planning and flexibility
Work with Client to realise each others drivers to agree the best way forward
14
saipem limited
HSE Approach – Some background
Saipem History
Serious Accident
A complete review of the process was carried out and follow-up plan and implemented further areas of focus were identified for improvement.
– ‘Bullseye’– identified areas where risk ‘step’ changed.
– Identified the “5 ring strategy” for success.
– Ensure that there are no ‘holes’ in our barriers.
– Use of Jobcard rather than long cumbersome manuals.
– Better communication (animations/snap t.v. screens/dirty briefing room onboard)
Saipem now have a robust risk management / project execution strategy
15
saipem limited
Saipem risk management – Project / Vessel interfacing
Risk reduced ALARP through
Complete project life cycle
3. VESSEL / SITE ACTIVITIES NOT CONNECTED TO
PROJECT SPECIFIC ACTIVITIES (ROUTINE)
2. VESSEL / SITE ACTIVITIES INTERACTING DIRECTLY
WITH PROJECT SPECIFIC ACTIVITIES (SOME ROUTINE)
1. PROJECT SPECIFIC ACTIVITIES (MOSTLY NON
ROUTINE)
Vessel / Site action
− Task Risk Assessment
− JSA if activity is complex
Project Action
− HAZID / Risk Assessment / HAZOP
− Project familiarisation
Vessel / Site action
− Participate in and implement the above
− JSA at time of execution
Project Action
− HAZID / Risk Assessment / HAZOP
− Project familiarisation
Vessel / Site action
− Participate in and implement the above
− JSA at time of execution
Interface Point (Step Change in Risk profile)
saipem limited
Training
Procedures Culture
Organisation & Communication
Current & Alternative Technology Programs
TASK / EVENT
5 Ring Strategy
• There are 5 key areas that hold together and overlap
• If there is failure in any of these areas, there is the increased risk of an event
• Maintain the function and input of these areas and the likelihood of an accident is reduced
17
saipem limited
Current & Alternative Technology Programs
Accident – causation components and actions
Key improvement action areas:
Management of man / machine interface
Assessment of existing / new technology
Equipment replacement / enhancement
Key improvement action areas:
LiHS
JSA / TBT training
Key improvement action areas:
Extensive procedure revision
New procedures introduced
S7000 participation in project solutions
Enhanced risk management process
Key improvement action areas:
Defined workflow communications process
Re-affirmation of responsibility / authority
Control of general deck access
Enhancements to project familiarisation
Informational screens
Key improvement action areas:
Training and competency system
Culture
Procedures
Organisation and Communication
Training
18
saipem limited
Training
Procedures Culture
Organisation & Communication
Current & Alternative Technology Programs
TASK / EVENT
• Comprehensive planning and preparation of the operation must be deeper to ensure each activity is thoroughly investigated and challenged.
5 Ring Strategy applied to 2/4-S
Think ahead! Think ahead!!
19
saipem limited
Training
Procedures Culture
Organisation & Communication
Current & Alternative Technology Programs
TASK / EVENT
- Method Statement for “each” activity step developed.
- Can we remove a human
interface?? - Challenge.
• Use of job card approach where activities are
grouped allowing:
5 Ring Strategy
20
saipem limited
Training
Procedures Culture
Organisation & Communication
Current & Alternative Technology Programs
TASK / EVENT
- Task Plan for group activity
- J.S.A conducted for each activity
- Permit to Work part of job card
- Progress measurement and feedback to facilitate onward planning.
• Use of job card approach where activities are
grouped allowing:
5 Ring Strategy
21
saipem limited
Training
Procedures Culture
Organisation & Communication
Current & Alternative Technology Programs
TASK / EVENT
- Equipment lists for each activity given
- Simplification of activities and specific information to allow T.B.T to be conducted
• Use of job card approach where activities are
grouped allowing:
5 Ring Strategy
- Pre plan any specialist training or get expertise
22
saipem limited
Training
Procedures Culture
Organisation & Communication
Current & Alternative Technology Programs
TASK / EVENT
• Use of job card approach where activities are
grouped allowing:
- Task Plan for group activity
- Method Statement for each activity set-out
- Equipment lists for each activity given
- J.S.A conducted for each activity
- Simplification of activities and specific information to allow T.B.T to be conducted
- P.T.W. part of job card
- Progress measurement and feedback to be allowed
5 Ring Strategy
23
saipem limited
Contents of a Job Card for Decommissioning
• Task overview • Safety particulars • Personnel requirements for task • Description of details of the work • Work permits • JSA forms • Discrete Risk Assessment of the
task • Plan of times for task • Completion checklists
24
saipem limited
The Challenge – Gain and make safe access and remove
Remote structures, no access available Plan and develop solutions
25
saipem limited
The Challenge – Gain and make safe access and remove
26
saipem limited
Safe access and work platform established
27
saipem limited
The Challenge – Establish safe access for cutting
28
saipem limited
The Challenge – Establish safe access for cutting
29
saipem limited
Guidance systems that are remotely installed and released
New and existing technology – Remove the human interface
Remove the human interface
30
saipem limited
New and existing technology – Remove the human interface
Bespoke access, lifting and lift point systems
Remove the human interface
31
saipem limited
Animations and physical models
To improve understanding, communication, and task briefings, physical models and animations are utilised
Better solutions, communication and briefings
32
saipem limited
Task Avoidance
Personnel Protective Equipment (PPE)
Undesired Event
Principle of barriers – Swiss cheese model
Protect
Eliminate
33
saipem limited
Risk Process Familiarisation Process
• HAZID
• Risk Assessments
• HAZOPS
• Table Top Exercises
• Review of Procedure together
• Familiarisation of Crew via Animations/Presentations • Campaign safety
awareness especially in “routine” activities.
Examples
• Working at Height
• Personnel Transfer
• Emergency Preparedness
This Must Capture :
• Residual Risks (ALARP) from Project Risk
Assessments • Energy Sources Inside The Work Process • Emergency Recovery
action plans • Risk Mitigation Toward Tasks Covered Under S7000 Procedures
• JSA / TBT
Familiarise Project
Personnel with S7000 Procedures
Interface Between
Project/Vessel
Procedures
Saipem Limited
Project
Procedures
S7000
Procedures /
Standing Orders
Risk process / Bridging the gap between project and vessel
34
saipem limited
HSE Statistics – Total Project
GENERAL SUMMARY TOTAL (Hrs) SAIPEM &
Subcontractors
Total Hours Worked 308,368
No. of Fatalities 0
No. of Lost Time Injuries (LTI) 0
No. of Medical Treatment Cases (MTC) 0
No. of Restricted work Cases (WRC) 1
No. of First Aid Cases 0
No. of Lost Work Days 0
No. of Safety Observations (S7000) 221
35
saipem limited
HSE Statistics – Removal Campaigns
GENERAL SUMMARY TOTAL (Hrs) SAIPEM &
Subcontractors
Total Hours Worked 171,319*
No. of Fatalities 0
No. of Lost Time Injuries (LTI) 0
No. of Medical Treatment Cases (MTC) 0
No. of Restricted work Cases (WRC) 0
No. of First Aid Cases 0
No. of Lost Work Days 0
No. of Safety Observations (S7000) 108 (removal)
• - Includes all onshore and offshore activities in June
36
saipem limited
Good project understanding and robust removal method development is key
Use Jobcards, physical models and animations for decommissioning
Perform as much subsea work from the same vessel to avoid simops
Invest in understanding the soils behaviour before construction activities and ensure that suitable contingency is available
Use pre-fabricated access wherever possible and get scaffold plans introduced earlier in project
Early engagement of contractors is recommended. All contractors to correctly plan their deliverables (avoid last minute work)
Ensure a good Client / Contractor relationship and accept correct managed change is likely
Never view decommissioning as “reverse installation” both operationally and contractually
Lessons Learnt
37
saipem limited
Conclusions
Project was a great success from both HSE performance and schedule
Both Contractor and Client were focused on the issues and understood the differences due to a decommissioning project
Proactive HSE approach from client (not just a ‘policing’ approach)
Change is probable in a decommissioning project however it must be correctly managed.
38
saipem limited
Animation
39