saskpower’s challenge

23
1 Distributed Generation Programs, Incentives and Interconnections Ian Loughran, P.Eng. DSM Program Leader Renewable Energy Programs [email protected] 306-566-6108

Upload: francesca-haney

Post on 30-Dec-2015

26 views

Category:

Documents


0 download

DESCRIPTION

Distributed Generation Programs, Incentives and Interconnections Ian Loughran, P.Eng. DSM Program Leader Renewable Energy Programs [email protected] 306-566-6108. SaskPower’s Challenge. Unprecedented demand for power Strong provincial economy - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: SaskPower’s Challenge

1

Distributed Generation Programs, Incentives

and Interconnections

Ian Loughran, P.Eng.DSM Program Leader

Renewable Energy Programs

[email protected]

Page 2: SaskPower’s Challenge

2

SaskPower’s Challenge• Unprecedented demand for power

• Strong provincial economy

• Industry is approximately 50 per cent of total load

• Last 10 years, demand has been 1.8 per cent per year

• Next 10 years forecast at 2.4 per cent growth per year.

• $5B asset value company; 80 years old• Spending $15B in the next 10 years- aging

infrastructure

• Provincial environmental legislation has yet to be released;

• Alignment with Federal government coal phase out plans

Page 3: SaskPower’s Challenge

3

SaskPower Distributed Generation Programs

Net Metering Program (up to 100 kW)• Typically rural and urban residential customers

Small Power Producers Program (up to 100 kW)• Small commercial Independent Power Producers (IPP)

Green Options Partners Program (>100 kW to 10 MW)• Small commercial to large commercial IPP

Benefits of DG• Capital offset• Less line losses• Environmental benefits• Job creation• Empowering customers

Page 4: SaskPower’s Challenge

4

Preferred Environmental Technologies

• Technologies permitted for all programs:

• Micro-hydro• Small wind turbines• Solar photo voltaic (PV)• Biomass fuels (gas, liquids and solids)• Flare gas• Waste heat/Heat recovery technologies

• SaskPower owns environmental credits associated with power generation

Page 5: SaskPower’s Challenge

5

Net Metering Program

Up to 100 kW

– Started in 2007; 230 customers; 85 per cent small wind; 15 per cent solar PV

– Primary purpose is to offset your consumption

– Bank credits for your excess power delivered

• Credit at customer retail rate

• Credit will be taken off next month’s bill

• After 12 months the credits are forfeited

– Two-year contract

– Making some improvements to this program in 2011

Page 6: SaskPower’s Challenge

6

Small Power Producers ProgramUp to 100 kW:

– Started in 1994, currently five participants

• (one Combined Heat and Power, four Wind)

– Two options:

• Sell all power

• Sell excess power

– 2011 price SaskPower will pay is $0.09609/kWh escalating two per cent /year for a 20-year contract

Page 7: SaskPower’s Challenge

7

Green Options Partners Program

7

>100 kW and 10 MW

• Program cap of 50 MW in 2011

– No more than 25 MW can be made of wind

– A lottery to select applications for the 2011 program closes June 1

• The 2011 program’s payment rate is $96.09/MWh for projects that reach commercial operation in 2011

• Rate escalates at 2 per cent per annum for the duration of the 20-year contract. 40 year contract for hydro projects.

• GO Partners Program reviewed annually

Page 8: SaskPower’s Challenge

8

Net Metering Wind and Solar Applications

114k

W

15kW

16kW

9kW

310k

W

450k

W

320k

W

63kW

424k

W46

5kW

336k

W

72kW

0

10

20

30

40

50

60

70

80

2007 2008 2009 2010

Year

Inc

rea

se

in A

pp

lica

tio

ns

Solar Wind Total

Page 9: SaskPower’s Challenge

9

CanSIA PV Solar Grid Parity

0.00

0.05

0.10

0.15

0.20

0.25

0.30

0.35

0.40

0.45

2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Year

Co

st

($/k

Wh

)

Solar Low Scenario Solar High Scenario Conventional

Page 10: SaskPower’s Challenge

10

Net Metering Rebate Program

• 35 per cent rebate to total installed cost (max of $35,000 rebate):• 35 per cent total = 10 per cent SaskPower and 25 per cent Go Green

Fund

• Program led by Ministry of Environment’s Go Green Fund• Rebate program ended March 31, 2011

• Go Green Fund is finalizing outstanding rebates to customers that committed to projects by end date

• Public and industry pressure on Ministry to offer a bridge financing program until a new program is in place

• Decisions will be made in the upcoming weeks (months?)

Page 11: SaskPower’s Challenge

11

Renewable Energy Incentive Program Development

New REI Program• Saskatchewan Ministry of Environment issued an RFP (December

2010)• Consultant to help develop and design a new REI program

• Awarded to Dunsky Energy Consulting (Montreal)-end of February 2011, and work began in March 2011

• Program design work should be completed by September 2011

• This is a new program, not policy change

• Implementation plans TBD

Page 12: SaskPower’s Challenge

12

REI Program FundingValue Propositions• Funding agencies being solicited

• Ministry of Environment- Go Green Fund- $/tGHG avoided• Net Metering Rebate $200/tCO2; Clean Coal $80/tCO2

• Enterprise Saskatchewan- Job creation; $/Jobs

• Saskatchewan Innovation- Technology development

• SaskPower- Supply value- $/MWh and/or $/MW

• Ministry of Energy and Resources- Supply value-$/MWh and/or $/MW

Page 13: SaskPower’s Challenge

13

Renewable Energy Incentive Program Development

New REI Program Considerations:• Quality- Industry standard (CanSIA, CanWEA,SWCC) and CSA

certification for product, product performance and installation

• Financing- Mechanisms for accessing capital

• Incentives- Production (by kWh); capital costs; combination of both; possibly up to 500kW; possible variations by technology type

• Implementation- Interconnection processes and contracts

Page 14: SaskPower’s Challenge

14

Supply Planning

Northpoint

DSM

T&D

District Metering

Services

Billing

Services

Electrical

Inspections

T&D

Engineering

Customer

Services

Customer

DG Program

Interconnection Process- 10 Entities; 30 Steps

Page 15: SaskPower’s Challenge

15

Interconnection Application ProcessSmall Power and Net Metering

• All application forms, templates and processes are on SaskPower web site

• Apply for Preliminary Interconnection Study $315 (includes GST)

• Items needed• Electrical single line diagram• Site diagram• Generator and inverter detailed specifications (CSA approved)

• Interconnection costs involved • Bi-directional meter (approx $500 incl GST)• Electrical inspections permit ($200-300)• Transformer upgrade costs split 50-50 with customer (up to $35/kW of generator) • Customer pays for service upgrade costs

• Contracts• Power Purchase Agreement and Interconnection Agreement

• Total cost is approximately $1,000; total time is approximately five months

• + Generator, installation, maintenance, etc.

Page 16: SaskPower’s Challenge

16

Average Net Metering Application Process Time

50% Reduction

0

2

4

6

8

10

12

2007 2008 2009 2010

Year

Mo

nth

s

Page 17: SaskPower’s Challenge

17

Interconnection Application ProcessGO Partners Program

• 500 kW Solar PV

• Apply for program- $1,725 (see SaskPower web site)– Lottery selection– Fee used for General Interconnection Feasibility Study (GIFS)– Approximately four months

• Contracts – Power Purchase Agreement; General Interconnection Agreement

• Interconnection costs involved • Bi-directional meter (approximately $8,000 including GST)• Electrical inspections permit ($1,000)• Transformer upgrade costs split 50-50 with customer (up to $35/kW of generator) • Customer pays for service upgrade costs

• Total cost is approximately $11,000; total time is approximately one year

Page 18: SaskPower’s Challenge

18

Thank You.

Ian Loughran, P.Eng.Renewable Energy Program Leader

[email protected]

Page 19: SaskPower’s Challenge

19

Net Metering Customers April 2011

WB6%

NB8%

Yorkton8%

PA8%

Regina17%

Swift Current18%

Saskatoon35%

Page 20: SaskPower’s Challenge

20

10

1

20

5

11

2

24

1

12

1

8

3

15

30

5

10

15

20

25M

onth

s

NB PA Regina S'toon Swift Wey York

Region

Net Metering Application Time

Max Min

Page 21: SaskPower’s Challenge

21

Distributed Generation Programs – Why?

• Capital investment offset: Customers purchase, install, and operate renewable power generation equipment

• Energy produced closer to where it is consumed: Less line losses equals less energy produced at power plant

• Offsets some central power generation: Time of day; types of generation at various times in the day

– Winter peaking utility; 7:00 pm November-February

• Clean, green and local: Develops green industry, creates local jobs – Distribution, sales, installation (electrical contractors)

• Empowering our customers to choose the source of their electricity

Page 22: SaskPower’s Challenge

22

Solar Resource

Yearly PV potential map for latitude tilt and the 13 "PV hotspots” in each

province and territory in Canada (NRCan, 2006)

Page 23: SaskPower’s Challenge

23

Solar System Costs

$-

$20,000

$40,000

$60,000

$80,000

$100,000

$120,000

0 2 4 6 8 10

Capacity (kW)

Cost

2008 2009 2010