RIVER WATER PIPELINE CONSORTIUM PO Number - Revision 0A AIR BLADDER TANK – STRUCTURAL - CALCULATIONS SONAREF PROJECT REFINERY RIVER WATER PIPELINE PIP-CIV-CAL-0301 Rev. Statu s Date Revision memo Issued by Checked by Approved by 00 IFA 2016.02. 02 First Issue Júlio César Adriano Ribeiro André Queiróz 0A IFA 2016.06. 25 Issued For Approval Júlio César Adriano Ribeiro André Queiróz PIP-CIV-CAL-0301 RIVER WATER PIPELINE Page. 1 / 19

Upload: jc6128

Post on 07-Jul-2016

214 views

Category:

Documents


0 download

DESCRIPTION

MEMORIA DE CÁLCULO DE BLOCOS DE ANCORAGENS

TRANSCRIPT

Page 1: SC-0009-RWPC-PIP-CIV-CAL-0301_0A

RIVER WATER PIPELINE CONSORTIUM

PO Number

-

Revision

0A

AIR BLADDER TANK – STRUCTURAL - CALCULATIONS

SONAREF PROJECT REFINERY

RIVER WATER PIPELINE

PIP-CIV-CAL-0301

Rev. Status Date Revision memo Issued by Checked by Approved by

00 IFA 2016.02.02 First Issue Júlio César Adriano Ribeiro

André Queiróz

0A IFA 2016.06.25 Issued For Approval Júlio César Adriano Ribeiro

André Queiróz

PIP-CIV-CAL-0301 RIVER WATER PIPELINE Page. 1 / 17

Page 2: SC-0009-RWPC-PIP-CIV-CAL-0301_0A

INDEX

1 GENERAL................................................................................................................................................... 3

1.1 PURPOSE AND OBJECTIVE...........................................................................................................................................3

2 REFERENCES............................................................................................................................................ 3

3 STANDARDS.............................................................................................................................................. 3

4 BIBLIOGRAPHY......................................................................................................................................... 3

5 MATERIALS................................................................................................................................................ 3

6 BASIC DATA FOR DESIGN........................................................................................................................ 4

7 GENERAL CONSIDERATIONS.................................................................................................................. 4

7.1 STRUCTURAL MODEL...........................................................................................................................................4

8 LOADS........................................................................................................................................................ 4

8.1 COMBINATION LOADING....................................................................................................................................7

9 DIMENSIONING........................................................................................................................................ 10

PIP-CIV-CAL-0301 RIVER WATER PIPELINE Page. 2 / 17

Page 3: SC-0009-RWPC-PIP-CIV-CAL-0301_0A

1 GENERAL

1.1 Purpose and ObjectiveThis calculation memory aims to present the basic assumptions and calculations for the dimensioning

of the foundation for hydramer VN25 reservoirs, which is part of the implementation of Sonaref

REFINERY PROJECT - RIVER WATER PIPELINE.

2 REFERENCES Hydramer 25m³ PN30_Vertical_R01-RESERVATÓRIOS HYDRAMER – GERAL–

IMPLANTAÇÃO GERAL

SC-0009-RWPC-BWS-LAY-DWG-0001 - ATP-RACs-Biopio-HYDROSTEC-1de2

SC-0009-RWPC-BWS-LAY-DWG-0001 - ATP-RACs-Biopio-HYDROSTEC-2de2

ISO 14001 Environmental management system – Requirement with guidance for use

OHSAS 18001 Occupational health and safety management systems — Specification

KBR Purchasing Standard: SDR-1IM-C736

3 STANDARDS

ACI 318-11 - Building Code Requirements for Structural Concrete

ACI 332-04: Requirements for Residential Concrete Construction and Commentary;

ACI 351.2R-10 Report on Foundations for Static Equipment;

ASTM D1143 / D1143M - Standard Test Methods for Deep Foundations Under Static Axial Compressive Load

ASCE-07 – 10 - Guide to the Wind Load Provisions

4 BIBLIOGRAPHY

MOLITERNO, Antônio. Caderno de muros de arrimo. São Paulo: Edgard Blucher, 1980;

MASSARO Jr, Mário. Reinforced Concrete Manual. 2nd edition, São Paulo: Private Edition 1979;

VELLOSO, Dirceu e Lopes, Francisco – Foundations;

PFEIL, Walter – Bridges in reinforced concrete;

BOWLES, Joseph E. – Foundation Analysis and Design;

5 MATERIALS

Structural Concrete:

- Characteristic resistance to compression = fck = 30 MPa

PIP-CIV-CAL-0301 RIVER WATER PIPELINE Page. 3 / 17

Page 4: SC-0009-RWPC-PIP-CIV-CAL-0301_0A

- Characteristic resistance to traction = fctk = 0,21 . (fck)2/3 = 2,03 MPa

- Average tensile strength = fctm = 0,30 . (fck)2/3 = 2,90 MPa

- Longitudinal secant modulus of elasticity = Ecs = 4760 . √ fck = 26071 MPa

Steel for structural concrete: CA-50

6 BASIC DATA FOR DESIGN

- Apparent specific weight of the soil t = 18 kN/m³

- Allowable stress soil adm = 200 kN/m²

7 GENERAL CONSIDERATIONS

7.1 STRUCTURAL MODEL

The structure of the foundation for hydramer VN25 reservoirs was analyzed with the assistance of

software STAAD Pro and Microsoft Excel spreadsheet developed by the responsible engineer.

8 LOADS

- Self Weight (PP)

The self weight of the structure was found automatically by Staad Pro software.

- Empty (Va)

Was considered the empty weight (180 kN) indicated in the document Hydramer 25m ³

PN30_Vertical_R01 applied on four supports.

PIP-CIV-CAL-0301 RIVER WATER PIPELINE Page. 4 / 17

Page 5: SC-0009-RWPC-PIP-CIV-CAL-0301_0A

- Fluid (Pf)

Was considered the weight of the water (250kN), as indicated capacity of the reservoir in the

document Hydramer 25m ³ PN30_Vertical_R01 applied on four supports.

PIP-CIV-CAL-0301 RIVER WATER PIPELINE Page. 5 / 17

Page 6: SC-0009-RWPC-PIP-CIV-CAL-0301_0A

- Wind

Was applied loads related to wind calculated according to the recommendations of the ASCE-07-10.

PIP-CIV-CAL-0301 RIVER WATER PIPELINE Page. 6 / 17

Page 7: SC-0009-RWPC-PIP-CIV-CAL-0301_0A

8.1 COMBINATION LOADING

The following load combinations in the design of foundations for shells were considered:

PIP-CIV-CAL-0301 RIVER WATER PIPELINE Page. 7 / 17

Page 8: SC-0009-RWPC-PIP-CIV-CAL-0301_0A

PIP-CIV-CAL-0301 RIVER WATER PIPELINE Page. 8 / 17

Page 9: SC-0009-RWPC-PIP-CIV-CAL-0301_0A

PIP-CIV-CAL-0301 RIVER WATER PIPELINE Page. 9 / 17

Page 10: SC-0009-RWPC-PIP-CIV-CAL-0301_0A

9 DIMENSIONINGFollowing are the results of the design of foundations for hydramer VN25 reservoirs.

PIP-CIV-CAL-0301 RIVER WATER PIPELINE Page. 10 / 17

Page 11: SC-0009-RWPC-PIP-CIV-CAL-0301_0A

PIP-CIV-CAL-0301 RIVER WATER PIPELINE Page. 11 / 17

Page 12: SC-0009-RWPC-PIP-CIV-CAL-0301_0A

PIP-CIV-CAL-0301 RIVER WATER PIPELINE Page. 12 / 17

Page 13: SC-0009-RWPC-PIP-CIV-CAL-0301_0A

PIP-CIV-CAL-0301 RIVER WATER PIPELINE Page. 13 / 17

Page 14: SC-0009-RWPC-PIP-CIV-CAL-0301_0A

PIP-CIV-CAL-0301 RIVER WATER PIPELINE Page. 14 / 17

Page 15: SC-0009-RWPC-PIP-CIV-CAL-0301_0A

PIP-CIV-CAL-0301 RIVER WATER PIPELINE Page. 15 / 17

Page 16: SC-0009-RWPC-PIP-CIV-CAL-0301_0A

PIP-CIV-CAL-0301 RIVER WATER PIPELINE Page. 16 / 17

Page 17: SC-0009-RWPC-PIP-CIV-CAL-0301_0A

PIP-CIV-CAL-0301 RIVER WATER PIPELINE Page. 17 / 17