school building ready for slab casting.. view of the children's home

18
School Building ready for Slab casting .

Upload: edmund-sullivan

Post on 28-Dec-2015

215 views

Category:

Documents


0 download

TRANSCRIPT

School Building ready for Slab casting .

View of the Children's Home

View of the Adults Home

Staff Qtrs completed up to plinth Level, Filling in progress.

View of the Admin , Hospital Blocks

Slab Reinforcement work in progress at School Building

View of the Internal Stair Case – School; Building.

Plinth Beam Completed - Staff Qtrs

Compound Wall Footings Completed – Main Road Side

Compound Wall work in progress

Plinth Filling at Staff Qtrs.

Work progress at Hospital Block

Status of the Guest House building – 12.06.2010

Status of the Admin Block – 12.06.2010

Electrical Pole Crossing Staff Qtrs to be shifted,

View of the Adults Home – Columns Completed

Dining Hall work in progress

Children's Home pcc completed, ready for slab casting.