Session 4: Potential & Lucrative Investment Opportunities
فرص متاحة وواعدة: اإلستثمار: الجلسة الرابعة
Eng. Mahmoud Khaled Karam
Head Engineer
Sanitary Engineering, Ministry of Public Works
June
2015
STATE OF KUWAIT
MINISTRY OF PUBLIC WORKS
MAHMOUD KARAM
CHIEF ENGINEER OF THE SANITARY SECTOR
MPW
SUMMARY ABOUT
STATE OF KUWAIT
In Kuwait
SANITARY
ENGINEERING
SECTOR
In Kuwait
The Sanitary Engineering Sector in the Ministry of Public Works is in charge of:
• Achieving our vision to maintain a healthy and good environment for citizens and residents of Kuwait by promoting Sustainability in Environmental conservation
• Constraction, maintaining and enhancing the sewage networks and water treatment facility capacity to meet the increase in population growth
• Wastewater Management
• Preparation of technical assistance studies to construct new facilities and upgrading existing ones
SANITARY ENGINEERING SECTOR
The Sewage System In Kuwait
EXISTING
SEWAGE SYSTEM
IN KUWAIT
The Sewage System In
Kuwait
Total Gravity lines 8000 Km
Total pressurized line 200 Km
Diameter:
from 0.150 m to 2.250 m
DEEP SEWERS AND PUMPING STATIONS
Four main sub-catchments will be served by the new system
1.Mishref PS – Serves areas to the south and east of Kuwait
Metropolitan Area (KMA) and transfers sewage to Ardiya PS and
on to Sulaibiya Sewage Treatment Plant (STP)
2.Riggae PS – Serves areas in the north and east of KMA and
transfers to the Ardiya PS
3.Egaila PS – Serves the south of KMA and transfers sewage to the
Riqqa STP.
4.Jahra PS – Serves the north and Jahra catchment area and
transfer sewage to Kabd STP
Jahra WWTP
Um Al-hayman WWTP
Kabbed WWTP
Egalia P.S
Mishref P.S
Sulaybia WWTP
Riqqea P.S
Ardiya P.S
middle Area
North Area
South Area
DEEP SEWERS AND PUMPING STATIONS
EXISTING
TREATMENT
PLANTS
Sulaibiya is the largest STP in
the world that uses Reverse
Osmosis (RO) technology as an
advanced treatment for
wastewater . It was established
in 2004
Treated wastewater produced
is potable water quality
standard and it treats 425,000
m3/day. The plant could be
further expanded to treat a
maximum of 600,000 m3/day
0.00
2.00
4.00
6.00
8.00
10.00
12.00
14.00
16.00
Ja
n
Fe
b
Ma
r
Ap
r
Ma
y
Ju
n
Ju
l
Au
g
Se
p
Oc
t
No
v
De
c
Millio
ns Inflow m^3 TSE m^3
Total inflow and treated
wastewater for Sulaibiya STP
2013
Month Inflow m^3 TSE m^3
Jan 14,192,738 10,789,078
Feb 12,779,254 9,692,332
Mar 13,887,844 10,843,902
Apr 13,632,462 10,501,119
May 14,175,125 10,860,848
Jun 13,797,345 10,432,020
Jul 14,434,667 10,885,778
Aug 14,391,274 10,897,749
Sep 13,953,634 10,613,199
Oct 14,246,765 10,875,803
Nov 13,880,596 10,458,123
Dec 14,231,798 10,893,199
SULAIBIYA STP, REVERSE OSMOSIS
The plant was started on 2011
with designed capacity of
180,000 m3/day Tertiary treated
product
KABED W.W.T.P
2,050.00
2,100.00
2,150.00
2,200.00
2,250.00
2,300.00
2,350.00
2,400.00
2,450.00
2,500.00
2,550.00
Ja
n
Fe
b
Ma
r
Ap
r
M…
Ju
n
Ju
l
A…
Se
p
Oc
t
No
v D…
Tho
usa
nd
s Total inflow and treated wastewater for Kabd STP 2014
Month Inflow m^3 TSE m^3
Jan 2,523,488 2,477,655
Feb 2,296,600 2,258,677
Mar 2,278,710 2,237,397
Apr 2,361,701 2,314,213
May 2,436,773 2,391,664
Jun 2,350,421 2,298,574
Jul 2,421,441 2,362,902
Aug 2,432,457 2,384,660
Sep 2,370,288 2,321,651
Oct 2,494,911 2,463,175
Nov 2,434,827 2,407,582
Dec 2,483,760 2,451,423
The plant was started on 1982
with capacity of 85,000 m3/day
then it has expanded on 1999
with designed capacity of
180,000 m3/day. It receive
currently 220,000 m3/day(2015)
Tertiary treated product
REQQA W.W.T.P
0
1
2
3
4
5
6
7
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Millio
ns
Inflow m^3 TSE m^3
Total inflow and treated wastewater for Al
Reqqa STP 2014
Month Inflow m^3 TSE m^3
Jan 6,580,500 5,880,500
Feb 6,067,200 5,567,000
Mar 6,602,722 5,752,989
Apr 6,491,135 5,677,382
May 6,682,638 5,829,355
Jun 6,445,141 5,602,875
Jul 6,550,749 5,700,503
Aug 6,342,483 5,729,531
Sep 6,409,897 5,855,618
Oct 6,578,782 6,008,798
Nov 6,723,015 6,168,005
Dec 6,923,015 6,368,015
The plant was started on 2001
with designed capacity of 27,000
m3/day , it receive now 22,000
m3/day.It produce Tertiary Water
Um-Alhyman W.W.T.P
Total inflow and treated wastewater forr Um Al hiyman STP 2014
Month Inflow m^3 TSE m^3
Jan 636,210 635,954
Feb 577,016 575,473
Mar 679,246 677,637
Apr 659,561 658,359
May 680,306 678,917
Jun 565,762 564,259
Jul 575,970 566,227
Aug 541,998 540,433
Sep 582,112 580,682
Oct 615,134 613,575
Nov 664,614 663,296
Dec 742,298 741,466
0
100
200
300
400
500
600
700
800
Tho
usa
nd
s
Inflow m^3
TSE m^3
Quantity of Treated Wastewater 2015
STP Site Wastewater Received
TSE produced RO Product Water
produced
Wastewater converted to re- usable product
m3/d (avg.) m3/d (avg.) m3/d (avg.) %
Sulaibiya 565,000 - 452,000 80
Umm Al Hayman
26,000 26,000 - 100
Riqqa 230,000 230,000 - 100
Jahra 156,000 156,000 - 100
Al Khiran 400 400 - 100
TOTAL 977,400 412,400 452,000 88,4
In Kuwait
Per capita consumption of water in the State
of Kuwait, compared with some of the world
Wa
ter
use
in
ga
llo
ns p
er
ca
pit
a p
er
da
y
Continued growing demand for fresh water
will double production in 2030 to 4 times
the current production
0
500
1000
1500
2000
2500
million c
ubic
metr
es p
er
year
In Kuwait
TOTAL INFLOW OF WASTEWATER
2013 2015 2020 2030
907,000 السعةالتصميمية 907,000 1,360,000 1,960,000
914,000 الكمية 988,982 1,117,480 1,374,476
0
500,000
1,000,000
1,500,000
2,000,000
2,500,000M
^3/D
AY
In Kuwait
REUSE OF
TREATED
WASTEWATER
In Kuwait
Treated wastewater (TSE) provides both moisture and nutrients for the growth of plants and other vegetation
Reuse of treated wastewater for irrigation and landscaping has proved to be an important and alternate source for irrigation and other uses in Kuwait
The volume of wastewater is estimated to be 70 to 80 % of the potable water consumption by the population.
Treated wastewater is available to different standards in Kuwait; Tertiary & RO Product Water
REUSE OF TREATED WASTEWATER
Parameter UNIT INFLOW Tertiary R.O
الرباعي
Irrigation مواصفات
مياه الري
MEW Drinking
water
PH 7.5 – 6.8 8 – 6.5 8-6 7.5 -6.5 8 -6.5 ـــــ
Conductivity µs/cm 1200- 3000 1100- 2200 42 1500 515
T.S.S. mg/L 100- 500 < 10 < 1 15 _
V.S.S. mg/L 70- 350 < 7.0 < 1 _ _
C.O.D. mg/L 250- 750 < 40 0 100 _
B.O.D 5 mg/L 100- 400 < 10 < 1 20 _
Grease & Oil mg/L 10- 50 NIL < 0.05 5 _
T.D.S. mg/L 700- 1800 800- 1500 < 100 _ 400
Chloride mg/L 200- 400 200- 400 12 _ 103
Ammonia mg/L 15- 50 1- 5 < 1 15 _
Nitrite mg/L 0.04- 0.7 0.1- 1.5 < 1 _ _
Total Count colony/100mL 2.40E+09 2.2E+04 NIL _ NIL
T.Coli colony/100mL 3.20E+08 400 NIL 400 NIL
F.Coli colony/100mL 4.10E+07 0 - 10 NIL 20 NIL
Salmonella colony/100mL 4.50E+06 NIL NIL _ NIL
Streptococci colony/100mL 1.40E+07 NIL NIL _ NIL
Fungi colony/100mL 2.10E+05 2- 100 NIL _ NIL
Laboratory quality control
Evolution of Wastewater Reuse
Kuwait
Border
Bubiyan
Island
Failaka Island
N
Project C: 16 MIGD
40 MIGD
40 MIGD
Project D: 25 MIGD
20 MIGD: Z Farms
0.5 MIGD scientific club
1.1 MIGD Hunting & Chivalry Club
1 MIGD Civil Aviation Kuwait
Airport
1.5 MIGD Alshohada Farm
2 MIGD West Fintas
3.6 MIGD Umm Al Hayman
0.1 MIGD Omari & Rabiya Farm Future Projects :
Different Projects : Ongoing Projects :
Project A:8 MIGD
Project B: 26 MIGD (B1&B2) DM•
C
Abdally
Farms
Wafra
Farms
Um-al Ramam Lake
شبكات الري بالمياه المعالجة في مناطق الكويت المختلفة
29
Golf course
Golf course/Race track
Alfalfa Farms
Agriculture Project
بحيرة أم الرمم
34
FUTUER SEWAGE NETWORK
In Kuwait
FUTUER SEWAGE NETWORK
MAIN GRAVITY LINES 100 Km
MAIN PRESSURE LINES 120 Km
NORTH
A7
Mishref
Egaila
Ardiya
JAHRA
PUMP
Sulaibiya
WWTP- 600,000
M3/D
Kabed WWTP- 250,000 M3/D
&
North Kabed WWTP- 600,000
M3/D
Um Hyman
WWTP- 700,000 M3/D
MAIN PUMPING STATIOS (5)
Al-Mutlaa
WWTP- 400,000
M3/D
Scheme Dates Total Sewer
Renovation / Upgrade (km)
2015 – 2020 213.2
2021 – 2030 220.4
2031 – 2045 595.2
TOTAL 1,028.8
PLANNED NETWORK SCHEMES
Sludge treatment
Aerobic digestion
Anaerobic digestion