sizing a pv system.ppt

Upload: nicholas-valdez

Post on 03-Apr-2018

258 views

Category:

Documents


3 download

TRANSCRIPT

  • 7/28/2019 Sizing a PV system.ppt

    1/58

    Sizing a PV system

  • 7/28/2019 Sizing a PV system.ppt

    2/58

    Content

  • 7/28/2019 Sizing a PV system.ppt

    3/58

    Systems

  • 7/28/2019 Sizing a PV system.ppt

    4/58

    Importance

  • 7/28/2019 Sizing a PV system.ppt

    5/58

    Steps

  • 7/28/2019 Sizing a PV system.ppt

    6/58

    Load evaluation

  • 7/28/2019 Sizing a PV system.ppt

    7/58

    Energy use profile of individual

    appliances

    Refrigerator Energy Consumption Profile

  • 7/28/2019 Sizing a PV system.ppt

    8/58

    They are very good candidates to enhance them with smartness.

    The intermittent peak electricity use can be shifted in time, in order to reduce the

    overall peak energy demand on the grid.

    From the household perspective, time-of-use pricing will enable significant

    energy bill savings.

    However, the DR algorithms have to be implemented without incurringunacceptable consequences for the consumers.

    The main benefits of utilities that arise from using DR include:

    > automatic energy reduction without any inconvenience to consumers;

    > precise control of appliance power usage on a network level a powerful

    facility for sharing the load among participating consumers;> a clear, real-time view of the aggregated demand-side energy-saving

    potential on the network that enables:

    > the prediction of required supply;

    > the setting of time-of-use and dynamic energy pricing;

    > the ability to minimize the need for purchasing spinning reserve, thereby

    lowering costs and significantly reducing carbon emissions

    demand response (DR).

  • 7/28/2019 Sizing a PV system.ppt

    9/58

    problems related to loads

    For all systems (AC and DC supply

    systems): A1 - Wrong selection: some loads are non-adapted for

    stand-alone PV systems.

    A2 - wiring: substandard or inadequate wiring andprotection devices will also cause poor system response.

    A3 Low efficiency: low electrical efficiency loads leadto over energy consumption.

    A4 - Stand-by loads: stand-by mode of some loads

    waste energy. A5 - Start-up: current spikes during the start-up of some

    loads can create temporal overload of the system.

  • 7/28/2019 Sizing a PV system.ppt

    10/58

    problems related to loads:

    Only for AC

    AC1 - Reactive power: when appliances withcapacitive or inductive loads are used, realcirculating current differs from the consumed.

    AC2 - Harmonic distortion: some electronicappliances with non-linear loads can createwaveform deformation of the inverter outputsignal.

    AC3 - Mismatch between load and invertersize: Low overall efficiency can result fromoversized inverters operating at low-power forlong periods.

  • 7/28/2019 Sizing a PV system.ppt

    11/58

    A1 Wrong Selection.

    For good energisation it is better not to use electricity for all types ofload.

    For example, generally it is not appropriate to use PV electricity toproduce heat.

    Example

    The energy needed to take a shower is about 1 kWh, this daily habitaccounting 30 kWh/month, or 500 Wp of installed PV power*

    Using thermal collectors to directly heat water is much more cost-effective for this usage (about 10 times cheaper than PV) *

    Assuming a water temperature of 10 C, and raise it to 38 C; forheating 30 l of water to take a shower we need: 30 lwater * 4,18kJ/(kg*C) * 1 kg/1lwater * (38-10)C water * 3600s = 1kWh.

    Calculation of installed Wp: assuming a daily average irradiation of4000 Wh/m2, and a performance of the system of 50%, the Wpneeded are: 1 kWh/day/50% * 1kWp/4hp = 500Wp

  • 7/28/2019 Sizing a PV system.ppt

    12/58

    A2 - wiring

    Wiring is an important issue to guarantee correctperformance when using appliances. Havingundersized or damaged distribution cables, canlead to the following problems:

    Problems:

    If section of wires is undersized or selection offuses is incorrect, high current through these can

    cause a fire ( by resistive heating). Undervoltage may detrimentally affect the

    performance of some appliances.

  • 7/28/2019 Sizing a PV system.ppt

    13/58

    A3 Low efficiency

    Generally speaking, inefficient appliances are cheaper tobuy.

    Problems:

    If the system was sized for efficient loads and, inefficient

    devices are used, insufficient energy is available,resulting in:

    Frequent cut-offs.

    Frequent low SOC of batteries resulting in low life.

    System undersized.

    User unsatisfied and may even by-pass the controller. If diesel genset runs periodically, operating costs can

    increase dramatically due to increase in demand/ orincreased demand.

    i ith hi h

  • 7/28/2019 Sizing a PV system.ppt

    14/58

    saving energy with high-

    efficiency appliances:

  • 7/28/2019 Sizing a PV system.ppt

    15/58

    A4 Stand-by loads

    Problems:

    When these appliances are left on stand-by forhours or even days, their cumulative effect can

    become a significant part of systemconsumption. This may be reflected as lowcharge of the batteries and earlier cutoff of thesystem.

    A recent study carried out in Japan estimatedthat about 10% of domestic electricityconsumption is used to power appliances onstand-by.

  • 7/28/2019 Sizing a PV system.ppt

    16/58

    A5 Start-up

    Some appliances consume high electric power (several times its rated

    power) at start-up. In case of AC current, the inverters should resist peaks of power severaltimes higher than its rated power value, during the short start-up periods.

    The loads affected should have a starter, which could soften the start-up.

    The problem would be solved using loads according to the availability ofpower, always considering energy-availability (e.g. water pump with less kWbut operating during longer time).

    In case of simultaneous start-up of the appliances, the peak power wouldbe the sum of each one. Progressive start-up of the loads connected shouldbe done, controlled by the inverter or another device.

    The last solution would be to use an alternative power source forproblematic loads (e.g. a diesel generator,...).

    Specify the inverter continuous watts and surge watts by estimating the

    surge requirements correctly. Use a linear current booster or use permanent magnets in pumpingsystems to assist start-up.

    A starter used for a water pump could be a device, which produces afrequency variation of the output inverter AC signal, to improve the start-upof the water pump.

  • 7/28/2019 Sizing a PV system.ppt

    17/58

    start-up o f a refr igerato r

  • 7/28/2019 Sizing a PV system.ppt

    18/58

    start -up o f a water pump

  • 7/28/2019 Sizing a PV system.ppt

    19/58

    AC1 Reactive power

    Problems:

    The current to be delivered by the inverter is muchhigher than the real consumption,

    resulting in a possible overcharging of the system.

    Current through the cables is higher than necessary,resulting in the need to increase the wire section toreduce voltage drops. This will add to the cost of cabling.

    The consumption of an electric motor can have a phasebetween current and voltage of 50 (cos(50)=0.64). Theinverter has to supply, in this case, 1 / 0.64 of the currentused by the load (1.56 x the motor current).

  • 7/28/2019 Sizing a PV system.ppt

    20/58

    AC1 Reactive power

    Solut ions:

    Reduce the need for inductive loads likeconventional ballasts, etc.

    Use of synchronous motors instead ofinduction motors in the relevantappliances.

    Install capacitors at the inductive load orthe distribution panel to provide therequired amount of capacitive reactance.

  • 7/28/2019 Sizing a PV system.ppt

    21/58

    AC2 Harmonic distortion

    Problems:

    This causes voltage deformation in the output signal ofthe inverter, which may occasion problems with the otherloads.

    Harmonics can shorten the life of the appliances byvoltage stress and increased heating of electricalinsulation.

    Some devices need to sense zero-crossings to controlinternal switching and could malfunction as the zero-crossings may appear to shift because of harmonics.

    Solut ions:

    Use of output filtering or use of inverters with highswitching frequency in situations where harmonics areexpected.

    AC3 Mismatch between load and

  • 7/28/2019 Sizing a PV system.ppt

    22/58

    AC3 Mismatch between load and

    inverter size

    Problems:

    The energy consumed is higher than the expectedone, resulting in:

    Cutout of the system or permanent low SOC ofbatteries

    High non-useful energy consumption.

    Solut ions:

    Use of a specific dedicated inverter for theapplication, or a modular inverter with workingpoints of good performance ranging from low toits maximum power.

  • 7/28/2019 Sizing a PV system.ppt

    23/58

    Smart Consumers

    A key feature of the Hybrid grid is demand response (DR).

    As defined by the Association of Home Appliancesmanufacturers (AHAM) in December 2009 in a smart gridwhite paper, DR refers to a set of scenarios whereby theconsumer, utility can reduce energy consumption during peakusage or other critical energy use periods.

    It is critical to reduce peak demand to avoid the use ofhigh-cost and high-emission power-generating resourcesor when the utility encounters some other issue on the

    electrical grid that requires the reduction of electricitydemand, it can send a signal to the home so that thesystem will reduce its electrical load during this criticaltime periods.

  • 7/28/2019 Sizing a PV system.ppt

    24/58

    Smart appliances

    In the smart appliances concept, the appliances are nolonger passive devices, but active participants in theelectricity infrastructure contributing to energy reduction andoptimization of the electrical grid for greater compatibility withits greenest energy-generation sources.

    On this line, by providing a variable load, smart appliancesconnected to the smart grid are ideal complements torenewable energy such as wind and solar power, which areinherently variable in supply.

    First, the focus is on residential consumers, where thedevelopment of DR is more straightforward.

    Developing the smart grid and linking it to smart appliancesand others products having DR capabilities will reliably andpredictably reduce appliance electricity consumption in realtime

  • 7/28/2019 Sizing a PV system.ppt

    25/58

    Smart appliances

    The way consumers interact with the grid is essential.

    Consumers must be able to choose when and how they want theirsmart appliances to participate in the smart grid.

    The offer of financial incentive through time-of-use pricing or otherincentive plans will be the single biggest driver for consumers to

    change their energy consumption habits. Therefore, the smart appliances concept provides benefits to

    both the consumers that obtain direct economic benefits, andthe utility and society at large.

    The best candidates for smart home appliances are: clothes washer,refrigerator, clothes dryer, dishwasher, water heaters and heating,air conditioning, battery charger (for electric cares).

    In the next years the smart appliance market is expecting to recordan important grow.

    S li b i i

  • 7/28/2019 Sizing a PV system.ppt

    26/58

    Smart appliances, by integrating

    them in the Whirlpool Smart

    Device Network (WSDN):

  • 7/28/2019 Sizing a PV system.ppt

    27/58

    Resource Evaluation

  • 7/28/2019 Sizing a PV system.ppt

    28/58

    Resource Evaluation

  • 7/28/2019 Sizing a PV system.ppt

    29/58

    Resource Evaluation

  • 7/28/2019 Sizing a PV system.ppt

    30/58

    Resource Evaluation

  • 7/28/2019 Sizing a PV system.ppt

    31/58

    Resource Evaluation

  • 7/28/2019 Sizing a PV system.ppt

    32/58

    Resource Evaluation

  • 7/28/2019 Sizing a PV system.ppt

    33/58

    Resource Evaluation

  • 7/28/2019 Sizing a PV system.ppt

    34/58

    Resource Evaluation

  • 7/28/2019 Sizing a PV system.ppt

    35/58

    Resource Evaluation

  • 7/28/2019 Sizing a PV system.ppt

    36/58

    Resource Evaluation

  • 7/28/2019 Sizing a PV system.ppt

    37/58

    PV Module selection [JRC]

  • 7/28/2019 Sizing a PV system.ppt

    38/58

    Connection

  • 7/28/2019 Sizing a PV system.ppt

    39/58

    Inverters [JRC]

  • 7/28/2019 Sizing a PV system.ppt

    40/58

    Inverters

  • 7/28/2019 Sizing a PV system.ppt

    41/58

    Inverters

  • 7/28/2019 Sizing a PV system.ppt

    42/58

    Inverters

  • 7/28/2019 Sizing a PV system.ppt

    43/58

    Losses in PV system

  • 7/28/2019 Sizing a PV system.ppt

    44/58

    Losses in PV system

  • 7/28/2019 Sizing a PV system.ppt

    45/58

    PV Yield

  • 7/28/2019 Sizing a PV system.ppt

    46/58

    Final Yield including losses

  • 7/28/2019 Sizing a PV system.ppt

    47/58

    Final Yield including losses

  • 7/28/2019 Sizing a PV system.ppt

    48/58

    Costs

  • 7/28/2019 Sizing a PV system.ppt

    49/58

    Project Example

  • 7/28/2019 Sizing a PV system.ppt

    50/58

    Project Example

  • 7/28/2019 Sizing a PV system.ppt

    51/58

    Project Example

  • 7/28/2019 Sizing a PV system.ppt

    52/58

    Project Example JRC

  • 7/28/2019 Sizing a PV system.ppt

    53/58

    Resource JRC

  • 7/28/2019 Sizing a PV system.ppt

    54/58

    Resource JRC

  • 7/28/2019 Sizing a PV system.ppt

    55/58

    PV Photon Database

  • 7/28/2019 Sizing a PV system.ppt

    56/58

    PV Photon Database

  • 7/28/2019 Sizing a PV system.ppt

    57/58

    Inverters Photon Database

  • 7/28/2019 Sizing a PV system.ppt

    58/58

    Module placement