study on dew condensation risk for commercial building … · study on dew condensation risk for...
TRANSCRIPT
Study on dew condensation risk
for commercial building with the
Liquid cooling air conditioning
system
Speaker Dr. Shizuo Iwamoto, Kanagawa University, Japan
Wanghee Cho, IIS., the University of Tokyo, Japan
Hitoshi Kono, ASAHI KOGYOSHA CO.,LTD.,Japan
Shinsuke Kato, IIS., the University of Tokyo, Japan
Kanagawa UniversityKUCLIMA2016, WS14
24 May 2016
Aalborg, Denmark
・reduction of dew condensation (D.C.
hereafter) in rooms and air handling
units
・indoor air quality and thermal comfort
Introduction
Background
Kanagawa UniversityKU
Patation
Radiant cooling
panel
Lighting
Chilledbeams
Dry air from the
desiccant AHU
liquid cooling pipes
Liquid cooling pipes
liquid cooling unit
The summary of the Liquid Cooling
Air-conditioning System
Desiccant air-conditioning system
D.C. in FCUs, AHUs,
liquid cooling panels and /or pipes ?
D.C.risks with the Liquid
cooling system and
conventional air-conditioning
system should be evaluated.
ConclusionCalculation condition Calculation results
事務室 階段室廊下
事務室
事務室
1F
2F
5F
6F
RF
地下ピット
Introduction
Background
Health and
Comfort…
Kanagawa UniversityKU
D.C. causes the growth of molds, so we
must consider a method for reduction of
D.C.
Water vapor tends to spread throughout
the whole building, thus reduction of
D.C. must be considered in the whole
building and air-conditioning units.
ConclusionCalculation condition Calculation results
office
office
Underground pit
Introduction
The purpose of this study
• D.C. risks by TRNSYS and TRNFLOW simulation
• Comparison between conventional and the Liquid cooling air-
conditioning system
• Modeling of desiccant air-conditioning unit for dedicated outdoor air
system
Kanagawa UniversityKU
ConclusionCalculation condition Calculation results
Calculation condition
Kanagawa UniversityKU
The building for simulation and the setting condition
事務室 廊下 トイレ
事務室 廊下 トイレ
2,400
事務室 廊下 トイレ
事務室 廊下 トイレ
事務室 廊下 トイレ
G.L
4,000
4,000
4,000
4,000
4,000
4,000
1F▽
2F▽
3F▽
4F▽
5F▽
6F▽
1,500
800
2,600
1,500
800
2,600
1,500
800
2,600
1,500
800
2,600
1,500
800
2,600
1,500
800
2,600
2,400
2,400
2,400
2,400
2,400
事務室 廊下 トイレ
G.L
District :Tokyo, Japan
Purpose of use : office
Total floor area:3,525 m2
Occupant rate:0.1 person/m2
Number of stories:6
Internal heat generation :
Human :121 W/person
Lighting :14 W/m2
Office application:15 W/m2
Ventilation rate :
Office:30 m3/h/person
WC :5 ACH
The summary of the building and setting condition
The section of the building The floor plan of the standard floor
Time 0~9 9~12 12~13 13~17 17~19 19~21 21~24
[%] 0 100 50 100 70 50 0
The internal heat generation rate of occupants, lighting and OAs
Introduction ConclusionCalculation results
office
office
office
office
office
office
office WC
WC
WC
WC
WC
WC
N
UPDN
UPDNEV
EV
事務室
トイレ×2、倉庫・湯沸室
(1室とする)
廊下+
エレベータ
ホールDS
+
機械室
3,600 3,600 3,600 3,600 3,600 4,800 2,400 3,600
28,800
3,6
00
3,6
00
3,6
00
3,6
00
2,0
00
4,0
00
20,4
00
corridor
EV hallWC and storageDS
M.R.
office
Calculation condition
Kanagawa UniversityKU
Setting condition for air flow network in the building
N
UPDN
UPDNEV
EV
事務室
トイレ×2、倉庫・湯沸室
(1室とする)
廊下+
エレベータ
ホールDS
+
機械室
3,600 3,600 3,600 3,600 3,600 4,800 2,400 3,600
28,800
3,6
00
3,6
00
3,6
00
3,6
00
2,0
00
4,0
00
20,4
00
The floor plan and air flow network setting
Crack
Large Opening
supply
return
Under cut
10 mm
Grille in a door
600 mm×300 mm
Room and
openings
Crack length
[m]
Crack coefficient
[kg/(s・m@1Pa)]
Window in the
office1.0×2+1.5×2 0.000033
Window in the
corridor2.4×2+0.8×2 0.000067
Doors against
outside air2.4×2+2.0×2 0.0001
Doors in stairs 1.8×2+2.0×2 0.0013
Doors of EVs 0.9×2+2.4×2 0.0013
Air leakage for windows and doors
Inlets and outlets in the ceiling of offices
Outlets in WC and storage
Consideration on over all ar flow
calculation in the building with one
hour time-step
Introduction ConclusionCalculation results
office
exhaust
corridor
EV hallWC and storageDS
M.R.
The method on evaluation of dew condensation risk in buildings
①D.C. rate=𝑡ℎ𝑒 𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑠𝑢𝑟𝑓𝑎𝑐𝑒𝑠 𝑤ℎ𝑒𝑟𝑒 𝐷. 𝐶. 𝑜𝑐𝑐𝑢𝑟𝑠 𝑎𝑡 𝑒𝑎𝑐ℎ 𝑜′𝑐𝑙𝑜𝑐𝑘
𝑡ℎ𝑒 𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑡𝑜𝑡𝑎𝑙 𝑠𝑢𝑟𝑓𝑎𝑐𝑒𝑠 𝑖𝑛 𝑡ℎ𝑒 𝑏𝑢𝑖𝑙𝑑𝑖𝑛𝑔×100 [%]
②D.C. frequency=𝑡ℎ𝑒 𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 ℎ𝑜𝑢𝑟𝑠 𝑤ℎ𝑒𝑛 𝐷. 𝐶. 𝑜𝑐𝑐𝑢𝑒𝑟𝑠 𝑎𝑡 𝑒𝑎𝑐ℎ 𝑠𝑢𝑟𝑔𝑎𝑐𝑒
8,760×100 [%]
③Annual D.C. risk=∑D.C.rate 𝑖𝑛 𝑡ℎ𝑒 𝑏𝑢𝑖𝑙𝑑𝑖𝑛𝑔
𝑡ℎ𝑒 𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑡𝑜𝑡𝑎𝑙 𝑠𝑢𝑟𝑎𝑓𝑎𝑐𝑒𝑠 𝑖𝑛 𝑡ℎ𝑒 𝑏𝑢𝑖𝑙𝑑𝑖𝑛𝑔×100 [%]
Index of D.C. risk
Kanagawa UniversityKU
Calculation conditionIntroduction ConclusionCalculation results
The setting condition for conventional air-conditioning system
Period Air temperature [deg. C] Relative humidity [%] Humidity ratio [kg/kg’]
Cooling period
(May~Octber)26 50 0.0105
Intermediate period
(April and November)24 50 0.0093
Heating period
(December ~ March)22 40 0.0066
Indoor set point within air-conditioning in the conventional condition
Kanagawa UniversityKU
Annual air-conditioning heat load is calculated at set point shown in above table.
The inlet condition such as inlet air temperature, humidity and air volume is
controlled form calculation result of heat load every hour.
In the conventional condition, VAV duct system is adapted in the building.
Calculation conditionIntroduction ConclusionCalculation results
まとめ
The setting condition for the Liquid cooling system
The condition for the Liquid cooling system
Cooling period (May~October) Heating period(November~April)
Desiccant
AHU
①when outside air temp. > 25.5 deg.C
inlet air temp. 25.5 deg.C
inlet air humidity 11.3 g/kg’
②when outside air temp. <25.5 deg.C
if relative humidity of outside air
within 40 – 70 %
→ inlet air is outside air without heat
exchanger
if not above
→ inlet air is outside air with heat
exchanger
①when xOA≦{xMAX・(1‐η)
‐⊿x}/(1‐η)
inlet air is outside air with heat
exchanger
②when xOA>{xMAX・(1‐η)‐⊿x}/(1‐η)
all outside air
③when xOA>xMAX‐⊿x
inlet volume is maximum
V’=⊿x・V/(xMAX‐xOA)
The
Liquid
cooling
system
When PMV>0.5, the Liquid cooling system works and supplies cooling water at 21
deg. C to radiant cooling panels, chilled beams and liquid cooling units.
Kanagawa UniversityKU
●In PMV calculation, metabolic rate, air velocity and clothing are set to 1.2 Met,0.1 m/s and 0.58
(summer)/0.7(winter) clo respectively.
● xMAX is the humidity ratio where PMV is equal to 0.5 in relative humidity is 70%.
Calculation conditionIntroduction Calculation results
For -0.5 < PMV < +0.5
Liquid cooling system : calculation results of indoor air
Kanagawa UniversityKU
温度 [℃] 温度 [℃]
30
40
50
60
70
80
20 22 24 26 28 30
1F
2~6F
30
40
50
60
70
80
20 22 24 26 28 30
1F
2~6F
In heating and cooling period , relative humidity varies from 40 to70 %.
At 1st floor (black plot), the Liquid cooling system sometime doesn’t work because of PMV < 0.5.
At 2-6 floor, in heating period, Liquid cooling system sometimes works against PMV>0.5.
Indoor air temperatures and
humidity in heating period
Introduction Conclusion
Indoor air temperatures and
humidity in cooling period
Indoor air temperatures [degree C] Indoor air temperatures [degree C]
Ind
oo
r a
ir r
ela
tive
hu
mid
ity [%
]
Ind
oo
r a
ir r
ela
tive
hu
mid
ity [%
]
Calculation resultsCalculation condition
Calculation results
Calculation results on D.C. risk in the building
Kanagawa UniversityKU
Annual D.C. risk 0.012%
The maximum D.C. rate at 30th March 20:00
・There is no D.C. in office rooms and radiant cooling panels.
・There is D.C. sometimes in core section such as corridor and stairs.
・Dew condensation occurs most frequently at the windows at 6th floor in stairs and D.C. frequency is 1.23%.
・In the Liquid cooling system, relative humidity is not controlled well in winter.
D.C. rate at the Liquid cooling system
Introduction ConclusionCalculation condition
0
1
2
3
4
5
6
結露比率[%]
1 2 3 4 5 6 7 8 9 10 11 12
時間 [月]
The maximum D.C.rate is 5.3%
D.C
.rat
e[%
]
Month
There is no D.C. in the building at conventional condition.
34
5
20
8
5 6
0
5
10
15
20
25
30
35
40
除湿による結露 加湿による結露 合計
一般空調機内 デシカント空調機内
空調機内結露頻度
[%]
Calculation results of D.C. risk in the AHU
Kanagawa UniversityKU
1/4
1/3
D.C. Frequency in the AHU
Overall annual D.C. risk (building and AHU) Conventional : 0.043%
Liquid cooling : 0.027%
Calculation resultsIntroduction ConclusionCalculation condition
Conventional
D.C. by dehumidification
Desiccant
D.C. by humidification total
D.C
. F
req
uen
cy i
n A
HU
[%
]
Conclusion
Conclusion
Kanagawa UniversityKU
1. In this presentation, the D.C. risk is estimated in commercial
building with the Liquid cooling air-conditioning system or
conventional air- conditioning system by TRNSYS and TRNFLOW
simulation.
2. There is no D.C. in office rooms. There is no D.C. on radiant
cooling panels in the Liquid cooling system.
3. As result, it is confirmed that the D.C. risk in the building and
air-conditioning system is less than 1 %.
4. In addition, it is confirmed that desiccant air-conditioning
system is effective for D.C. risk reduction by compared with the
result of conventional air-conditioning system.
Introduction Calculation condition Calculation results