"tajikistan’s hydro energy – basis of a potential power corridor between central asia &...

12
1 "Tajikistan’s Hydro Energy – basis of a Potential Power Corridor between Central Asia & South Asia " Ambassador Sherali Jononov Embassy of the Republic of Tajikistan to the Islamic Republic of Pakistan

Upload: magdalen-harris

Post on 18-Jan-2016

215 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: "Tajikistan’s Hydro Energy – basis of a Potential Power Corridor between Central Asia & South Asia " Ambassador Sherali Jononov Embassy of the Republic

"Tajikistan’s Hydro Energy – basis of a Potential Power Corridor be-

tween Central Asia & South Asia

"

Ambassador Sherali Jononov

Embassy of the Republic of Tajikistan to the Islamic Republic of Pakistan

Page 2: "Tajikistan’s Hydro Energy – basis of a Potential Power Corridor between Central Asia & South Asia " Ambassador Sherali Jononov Embassy of the Republic

1.Energy Profile2.Power Projects3.Prospective -

Hydro4.Prospective-

Thermal5.Regional Initia-

tives - OHL

Page 3: "Tajikistan’s Hydro Energy – basis of a Potential Power Corridor between Central Asia & South Asia " Ambassador Sherali Jononov Embassy of the Republic

3

Tajikistan Energy ProfilePotential for gen-erate 527 billion.

KW. hours per yearThe installed ca-pacity of power

plants of 5400 MWOf these, 95% hy-dro and 5% ther-

mal power stations The annual gener-ation more than 17

billion. KW. hourExcess of hy-

dropower in the summer months

(from 3 to 5 billion.

KW. hour)

Winter energy shortages more

than 2,5 billion. KW.

hour

Page 4: "Tajikistan’s Hydro Energy – basis of a Potential Power Corridor between Central Asia & South Asia " Ambassador Sherali Jononov Embassy of the Republic

4

Power Projects Implementation

Completed Projects

1.7 billion. USD

Ongoing Projects

268 million. USD

Projectson design and

preparation stage938,3 million. USD

Page 5: "Tajikistan’s Hydro Energy – basis of a Potential Power Corridor between Central Asia & South Asia " Ambassador Sherali Jononov Embassy of the Republic

5

Power Projects Implementation

• EMERGENCY BAYPAZA HPP LANDSLIDE STABILIZATION • RECONSTRUCTION OF DUSHANBE CITY ELECTRICAL NET-

WORKS• CONSTRUCTION OF MHPP IN RURAL AREAS OF THE REPUBLIC

OF TAJIKISTAN• CONSTRUCTION OHL-500kV SOUTH-NORTH• CONSTRUCTION OHL-220kV • ADDITIONAL WORKS OF CONSTRUCTION OHL-500/220kV

SOUTH-NORTH & LOLAZOR-KHATLON• REHABILITATION OF ENERGY SECTOR OF THE REPUBLIC OF

TAJIKISTAN• REGIONAL POWER INTERCONNETION TRASMISSION PROJECT• RECONSTRUCTION OF 220kV SWITCHYARD AT NUREK HPP• CONSTRUCTION OF 220KV OHL HUJAND-AYNI• ESTABLISHMENT OF UNIFIED POWER SYSTEM OF THE NORTH

OF TAJIKISTAN• REGIONAL POWER TRANSMISSION PROJECT• ENERGY LOSS REDUCTION PROJECT IN DUSHANBE CITY• CONSTRUCTION OF SANGTUDA HPP-1 • CONSTRUCTION OF SANGTUDA HPP-2

Completed Projects

1.7 billion. USD

Page 6: "Tajikistan’s Hydro Energy – basis of a Potential Power Corridor between Central Asia & South Asia " Ambassador Sherali Jononov Embassy of the Republic

6

Power Projects Implementation

• Reconstruction of 500kV Switchyard at Nurek HPP

• Regional power transmission project • Rehabilitation of 500kV Regar substation • Energy loss reduction project• Energy loss reduction project in Sughd

Region

Ongoing Projects

268 mil-lion. USD

Page 7: "Tajikistan’s Hydro Energy – basis of a Potential Power Corridor between Central Asia & South Asia " Ambassador Sherali Jononov Embassy of the Republic

7

Power Projects Implementation

• Golovnaya 240 MW HPP rehabilitation project

• Rehabilitation of 220kV Ravshan substa-tion

• Construction of 2x50 MW second phase of Dushanbe TPP 2

• Rehabilitation of Kayrakum HPPP• Wholesale Metering and Transmission Re-

inforcement Project• CASA-1000

Projects on design and prepara-

tion stage938,3

million. USD

Page 8: "Tajikistan’s Hydro Energy – basis of a Potential Power Corridor between Central Asia & South Asia " Ambassador Sherali Jononov Embassy of the Republic

8

Our Development Partners

ADB63,27 mln. USD – loan366, 77 mln. USD –grant

WB63 mln. USD – loan17,2 mln. USD - grant

IDB52,73 mln. USD – loans

KfW18,0 mln. Euro–loan7,0 mln. Euro-grant

KFAED 3, 600 mln. KD–loan

SECO15,2 mln. USD– grant

China Eximbank801,43 mln. USD –loan

BT co-financ-ing63,63 mln. USD

EBRD70 mln. USD – loan11,7 mln. USD - grantSangtuda HPP-1174,6 mln. USD – Taj. Gov.524 mln. USD – Rus. Gov

Sangtuda HPP-240 mln. USD – Taj. Gov.318,8 mln.USD – Iran Gov.

OPEC8,5 mln. USD – loan

Page 9: "Tajikistan’s Hydro Energy – basis of a Potential Power Corridor between Central Asia & South Asia " Ambassador Sherali Jononov Embassy of the Republic

9

Prospective Projects HydroROGUN HPP (3600 MW)

SHUROB HPP (850 MW)

NUROBOD HPP– 1 (460 MW)

NUROBOD HPP– 2 (400 MW)

FONDARYO HPP (300 MW)

AYNI HPP (160 MW)

SANOBOD HPP (125 MW)

ZARAFSHON HPP (150 MW)

Page 10: "Tajikistan’s Hydro Energy – basis of a Potential Power Corridor between Central Asia & South Asia " Ambassador Sherali Jononov Embassy of the Republic

10

Prospective Projects -ThermalDUSHANBE-2

TPP 2х150 MW – SECOND PHASE

(300 MW)

SHUROB TPP(300 MW)

FON YAGNOB TPP (600 MW)

Page 11: "Tajikistan’s Hydro Energy – basis of a Potential Power Corridor between Central Asia & South Asia " Ambassador Sherali Jononov Embassy of the Republic

11

Regional Initiatives - OHL

CASA-1000 PROJECT

500kV OHL TAJIKISTAN-

AFGHANISTAN-TURKMENISTAN

500kV OHLTAJIKISTAN-

AFGHANISTAN-IRAN

500kV OHL TAJIKISTAN - PAKISTAN

(through Vakhan corri-dor)

TUTAP PROJECT

Page 12: "Tajikistan’s Hydro Energy – basis of a Potential Power Corridor between Central Asia & South Asia " Ambassador Sherali Jononov Embassy of the Republic

12

12

Project CASA-1000500kV line that will con-

nectKyrgyzstan-Tajikistan-Afghanistan-Pakistan

(1200 km)

Construction of 500kV OHLTajikistan-Afghanistan-

Turkmenistan(length -650 km)

Construction of 500kV OHL

Tajikistan-Afghanistan-Iran(length-715 km)

Construction of 500kV OHLTajikistan-Pakistan

through Vakhan corridor(length – 750 km)