Team Meeting Team Meeting April 25, 2014 April 25, 2014 NSTX-U NSTX-U Construction Progress Construction Progress NSTX-U NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U Kyushu Tokai U NIFS Niigata U U Tokyo JAEA Inst for Nucl Res, Kiev Ioffe Inst TRINITI Chonbuk Natl U NFRI KAIST POSTECH Seoul Natl U ASIPP CIEMAT FOM Inst DIFFER ENEA, Frascati CEA, Cadarache IPP, Jülich IPP, Garching ASCR, Czech Rep Coll of Wm & Mary Columbia U CompX General Atomics FIU INL Johns Hopkins U LANL LLNL Lodestar MIT Lehigh U Nova Photonics Old Dominion ORNL PPPL Princeton U Purdue U SNL Think Tank, Inc. UC Davis UC Irvine UCLA UCSD U Colorado U Illinois U Maryland U Rochester U Tennessee U Tulsa U Washington U Wisconsin X Science LLC

Upload: polly-blake

Post on 26-Dec-2015

216 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Team Meeting April 25, 2014 NSTX-U Construction Progress NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U

Team MeetingTeam MeetingApril 25, 2014April 25, 2014

NSTX-UNSTX-UConstruction ProgressConstruction Progress

NSTX-UNSTX-U Supported by

Culham Sci CtrYork U

Chubu UFukui U

Hiroshima UHyogo UKyoto U

Kyushu UKyushu Tokai U

NIFSNiigata UU Tokyo

JAEAInst for Nucl Res, Kiev

Ioffe InstTRINITI

Chonbuk Natl UNFRI

KAISTPOSTECH

Seoul Natl UASIPP

CIEMATFOM Inst DIFFER

ENEA, FrascatiCEA, Cadarache

IPP, JülichIPP, Garching

ASCR, Czech Rep

Coll of Wm & MaryColumbia UCompXGeneral AtomicsFIUINLJohns Hopkins ULANLLLNLLodestarMITLehigh UNova PhotonicsOld DominionORNLPPPLPrinceton UPurdue USNLThink Tank, Inc.UC DavisUC IrvineUCLAUCSDU ColoradoU IllinoisU MarylandU RochesterU TennesseeU TulsaU WashingtonU WisconsinX Science LLC

Page 2: Team Meeting April 25, 2014 NSTX-U Construction Progress NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U

NSTX-UNSTX-U NSTXU Construction Progress – April 25th, 2014 2

NSTXU Construction – PUMPDOWN November 1998

NSTX turned over to operations February 1999NSTX turned over to operations February 1999

Page 3: Team Meeting April 25, 2014 NSTX-U Construction Progress NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U

NSTX-UNSTX-U NSTXU Construction Progress – April 25th, 2014 3

Good progress continues on NB and Machine Installations

Pumpdown December 2014

Page 4: Team Meeting April 25, 2014 NSTX-U Construction Progress NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U

NSTX-UNSTX-U NSTXU Construction Progress – April 25th, 2014 4

Recent Accomplishments & work underway Neutral Beam DI piping contract completed and tested. HVE water line installation has been

completed in NTC. Flexible hoses for the HVE lines can now be measured and fabricated. Pipe connections to the DI water pumps continued in the Pump Room.

Neutral Beam cabling contract completed.

NB duct installation completed

Neutral Beam Armor installed

VV feet installation complete. PF 4/5 support installation complete. Torquing of the upper outer TF support weldments to their final torque levels has been completed

The installation of the MPTS vacuum interfaces has been completed and they have passed leak check

Center stack casing stud installation complete and ready for PF 1B installation (PFC’s to follow)

CS pedestal prefit completed

RF antennas removed. Center compliant conductor posts delivery in April . Installation in MAY .

Diagnostics incl racks and cabling re-installation underway

Bus bar fabrication continues ... trial fit-ups under the vessel continue

2 PCHERS passive plates being fabricated by Major Tool with delivery expected May .

PFC installation started in the vacuum vessel.

DCPS stage I testing continued using the Autotester (AT) and waveform input files

Startup planning underway with PPPL Activity Certification Committee (ACC) and Operational Readiness Assessment

Page 5: Team Meeting April 25, 2014 NSTX-U Construction Progress NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U

NSTX-UNSTX-U NSTXU Construction Progress – April 25th, 2014 5

Neutral beam component installation nearing completion

Neutral Beam & TIV valve

Neutral Beam & TIV valve

• Neutral Beam connecting duct assembly (bellows(2) ,VPS duct) being lowered into position

• Entire assembly leak tested prior to installation

• Neutral Beam connecting duct assembly (bellows(2) ,VPS duct) being lowered into position

• Entire assembly leak tested prior to installation

Vacuum Vessel Bay J/K port

Vacuum Vessel Bay J/K port

Source installation planned for June

Source installation planned for June

Page 6: Team Meeting April 25, 2014 NSTX-U Construction Progress NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U

NSTX-UNSTX-U NSTXU Construction Progress – April 25th, 2014 6

NB component installation (cont)

Overhead view of duct assembly

Overhead view of duct assembly

Neutral Beam Armor InstalledNeutral Beam

Armor Installed

Page 7: Team Meeting April 25, 2014 NSTX-U Construction Progress NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U

NSTX-UNSTX-U NSTXU Construction Progress – April 25th, 2014 7

OH Coil Winding

Going Well

Started winding 4th and final layer

Started winding 4th and final layer

Good progress on the centerstack

Page 8: Team Meeting April 25, 2014 NSTX-U Construction Progress NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U

NSTX-UNSTX-U NSTXU Construction Progress – April 25th, 2014 8

Major milestones to completion

• Completion of OH winding should occur by May 5th• VPI completed by May 31• Complete OH/TF activities: May thru July

– Removing Aquapour

– Final OH testing– Silver plate electrical contact surfaces, Fit-up and installation of laminate crowns– Finalization of TF fittings and bulkheads, Installation of Belleville washer

assembly– Assembly and install of PF1A& C coils, Apply ground plane and diagnostics to

OH surface– Install “Micro therm” insulation

• Install CHERS PP June• Install HHFW compliant center post May-June• Last Access to Vacuum Vessel June 14th• Transport CS to NSTX Test Cell August 12th• Install centerstack August 25th• NB Ion source installation Late June• NB VPS system test July • Start NB He system and begin NB #1 & #2 pumpdown Mid July• Readiness review September• Pump down December• CD-4 December

Rollover schedule at;http://www-local.pppl.gov/dss/CurrentRollover.pdf

Page 9: Team Meeting April 25, 2014 NSTX-U Construction Progress NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U

NSTX-UNSTX-U NSTXU Construction Progress – April 25th, 2014 9

Summary

The project continues to make good technical progress and is on track for a December 2014 completion.

The project continues to make good technical progress and is on track for a December 2014 completion.