the us chapter of buildingsmart international -...

29
The US chapter of buildingSMART International FOUNDING ORGANIZATION SPONSOR SPONSOR SPONSOR

Upload: vominh

Post on 20-May-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

The US chapter of buildingSMART International

FOUNDING ORGANIZATION SPONSOR

SPONSORSPONSOR

INTEND DEFINES PROCESS“the right process for the project”

John AllenGEO-SLAM

Joseph Romano, PLSLANGAN

Will Ikerd, PEIKERD CONSULTING

Tomer PorianMATTERPPORT

Peter L. StevensonSTEVENSON SYSTEMS

Origin and Goal of session`

q Along the lines of part 2 of the “Material Board Session”q Understanding the tools & systems we work withq Desire to challenge the vendors and technologyq Take a deeper dive into the options available to service providersq Open conversation on the topicq Circle back around for the need for a common language, “standards”

Some comments relating to intent`

q In this session “intent” related to our clients needs and meeting their expectationsq Are all tools we have available to us created equal and provide the same results?q Technology and data overuse or misuseq Under educated client, providers and fast changing technologyq Legal and financial responsibilityq Possible licensure issues

Intent: Design, resolve or determination.Refers to the objective with which an act iscompleted or omitted.

Measurement is the assignment of a numberto a characteristic of an object or event, whichcan be compared with other objects or events

Sample “RFP’s”`

Project : Public building this is 500 ft x 200 ft.

Sample “RFP’s”`

Scope – A 3D Scan of an existingspace and respective 3D Structuraland MEP Revit model. LOD-300,generic models are acceptable, butthe models must reflect as-builtgeometry.

Project : Multi story office building.

Session execution

q Use difference technologies to “document “ the room we are in.q Each service provider was ask to provide a floor planq Each was asked to document the tools they used, the time required to

complete their efforts and their findingsq NO OTHER INTENT WAS PROVIDED

Panel download

John AllenGEO-SLAM

Will Ikerd, PEIKERD CONSULTING

Tomer PorianMATTERPPORT

Peter L. StevensonSTEVENSON SYSTEMS

CONTROL

Total station details:Topcon Robotic Total Station, model PS 103ADate of last calibration: March 2015Time associated with

Field task: 20min (including setup)Reduction task: 10minPlan/image preparation: 10min

CONTROL

20

Automaticcreatedorthophotosin PointCab

Creationin: 5minutes

21

Measuredroomarea

Creationin: 5minutes

22

Complete creation timetable

Creation step Used time [minutes]

Import point cloud in PointCab 5

Orthophotos 2

Vectorization 8

Area measurement 5

Model 10

Panoramas 2

ReCap point cloud 10

WebExport 5

Sum 47

Faro 120Date of last calibration: January 2017Time associated with

field task: 1hr (including setup)Processing: 30 min to process and registerplan/image preparation.: 1 hr to make a floorplan

64.46 Handheld64.56 Terrestrial64.88 Mobile64.03 Photo

36.0

7Ha

ndhe

ld36

.08

Terr

estr

ial

36.3

4M

obile

35.6

4Ph

oto

AREA (calc)2,277.89 sf Handheld2276.25 sf Terrestrial2303.58 sf Mobile2232.26 sf Photo

RESULTS

What we foundq Equipment choice matters.q Would we reach the “intent” of the 2 sample RFPs’?q Match equipment to accomplish the desired “intent”q Educate your client relating to yourq Documentation may require more than one piece of equipmentq Challenge the vendors on the WOW FACTORq Education your staff in the fundamental of the tools you use

RESULTS

Joseph Romano, [email protected]

Conversationand

Thank You!

John AllenGeo-SlamJohn.allen#groslam.com

Tomer [email protected]

Peter L. StevensonStevenson [email protected]

Will Ikerd, PEIkerd [email protected]