2

• Based on the given input data file we will add LID (Low Impact De-velopment) options for subcatchments

Page 3: Training SWMM LID control

3

• EPA’s SWMM 5.1 has been extended to model the hydrologic per-formance of specific types of low impact development (LID) controls.• LID controls that you can choose include 7 green infrastructure practices 1. Permeable pavement 2. Rain gardens 3. Green roofs 4. Street planters 5. Rain barrels 6. Infiltration trenches 7. Vegetative swales (not optional in WMAM)• You will edit 6 types of LID structures by using the LID control option of EPA SWMM5.1 • Follow the instructions (step 1 to step 7) to enter all values • The following tables are information of the LID control you will edit

Page 4: Training SWMM LID control

4

Control name LID type Layer Parameter Value

GR_your initial Green Roof

Surface

Berm Height 3Vegetation Volume Frac-

tion 0.2Surface Roughness 0.1

Surface Slope 1.0

Soil

Thickness 6Porosity 0.5

Field Capacity 0.2Wilting Point 0.1Conductivity 0.5

Conductivity Slope 10Suction Head 3.5

Drainage MatThickness 1

Void Fraction 0.5Roughness 0

<Table 1> Information of green roof

Page 5: Training SWMM LID control

5

<Table 2> Information of permeable pavement

Control name LID type Layer Parameter Value

PP_your initial Permeable Pavement

Surface

Berm Height 1Vegetation Volume Fraction 0.1

Surface Roughness 0.02Surface Slope 2

Pavement

Thickness 8Void Ratio 0.15

Impervious Surface Fraction 0Permeability 100

Clogging Factor 0

Storage

Thickness 12Void Ratio 0.75

Seepage Rate 0.2Clogging Factor 0

Under-drain

Flow Coefficient 0Flow Exponent 0.5Offset Height 0

Page 6: Training SWMM LID control

6

<Table 3> Information of bio-retention cellControl name LID type Layer Parameter Value

BC_your initial Bio-Retention Cell

Surface

Berm Height 6Vegetation Volume Fraction 0.0

Surface Roughness 0.2Surface Slope 0

Soil

Thickness 12Porosity 0.5

Field Capacity 0.2Wilting Point 0.1Conductivity 0.5

Conductivity Slope 10Suction Head 3.5

Storage

Thickness 12Void Ratio 0.5

Seepage Rate 0.5Clogging Factor 0.2

UnderdrainFlow Coefficient 0Flow Exponent 1Offset Height 0.5

Page 7: Training SWMM LID control

7

<Table 4> Information of infiltration trench

Control name LID type Layer Parameter Value

IT_your initial Infiltration Trench

Surface

Berm Height 0.0Vegetation Volume Fraction 0.0

Surface Roughness 0.24Surface Slope 0.4

Storage

Thickness 36Void Ratio 0.4

Seepage Rate 0.2Clogging Factor 0

Under-drain

Flow Coefficient 0Flow Exponent 0.5Offset Height 0

Page 8: Training SWMM LID control

8

<Table 5> Information of rain barrel

Control name LID type Layer Parameter Value

RB_your initial Rain Barrels

Storage Berm Height 48

Underdrain

Flow Coefficient 1

Flow Exponent 0.5

Offset Height 0

Drain Delay 6

Page 9: Training SWMM LID control

9

<Table 6> Information of rain garden

Control name LID type Layer Parameter Value

RG_your initial Rain Garden

Surface

Berm Height 6

Vegetation Volume Fraction 0.0

Surface Roughness 0.0Surface Slope 0.0

Soil

Thickness 12Porosity 0.5

Field Capacity 0.2Wilting Point 0.1Conductivity 0.5

Conductivity Slope 10Suction Head 2.5

Page 10: Training SWMM LID control

10

• Select LID Controls from the project browser (under Hydrology)

Step 1

Page 11: Training SWMM LID control

11

• Left click the add button or select Project -> Add a new LID Control from the main menu

Step 2

Page 12: Training SWMM LID control

12

• Enter the Control Name for the LID structure

Step 3

Page 13: Training SWMM LID control

13

• Choose the type of the LID structure

Step 4

Page 14: Training SWMM LID control

14

• Enter the parameter values of the surface layer

Step 5

Page 15: Training SWMM LID control

15

• To enter the parameter values of the Soil, Storage, and Under-drain layer click the tab of the layer

Step 6

Page 16: Training SWMM LID control

16

• Follow step 1~6 and use the information in table 1~6 to edit the LID control• After you have entered all the values, you can find your designed LID controls

• Now you will plan the subcatchment area with the designed LID struc-tures• Step 7 to step 11 shows how to edit the LID Usage Editor• Follow the instructions from (step 7 ~ 11) and use the following infor-mation to complete the editing process

Page 17: Training SWMM LID control

17

Subcatchment LID Process

S1 Infiltration trench

S1 Rain barrel

S4 Bio-retention cell

S5 Permeable pavement

S5 Green roof

S6 Rain garden

<Table 7> LID controls for subcatchments

Page 18: Training SWMM LID control

18

Subcatchment LID ProcessArea of Each Unit

Numb of Unit

Surface Width

per Unit

% Ini-tially Satu-rated

% of Imperv Area

Treated

Return all

out-flow to perv

S1 Infiltration trench 2320000 4 133 0 40 -

S1 Rain barrel 100 32 0 0 17 Check

S4 Bio-retention cell 47500 500 0 10 50 -

S5 Permeable pave-ment 3828720 1 683 0 0 -

S5 Green roof 1840000 12 136 0 0 -

S6 Rain garden 1650000 1 0 15 5 -

<Table 8> LID planning parameters for each structure

Page 19: Training SWMM LID control

19

• Open the editing window (properties) of one of the subcatchments

Step 7

Page 20: Training SWMM LID control

20

• Left click on the box in LID controls

Step 8

Page 21: Training SWMM LID control

21

• Left click Add to open the LID usage editor

Step 9

Page 22: Training SWMM LID control

22

• Select the LID control name• Enter the planning parameter values for the selected LID structure

Step 10

Page 23: Training SWMM LID control

23

• If you check the LID Occupies Full Subcatchment, the LID struc-ture will automatically calculate the Area of each unit as it is de-signed

Step 11

Page 24: Training SWMM LID control