    CONTINENTAL BRIDGE & WEST DALLAS GATEWAY trinity river corridor project committee 01.09.12dallas citydesign studio 1

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    3/44

    purpose

    Provide an overview of all of the projects affiliated with the Continental Bridge conversion

    Review anticipated schedule and budget

    Outline additional next steps

    dallas citydesign studio 2

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    4/44

    2006 Bond Program included $1.9 million for Continental Bridge and $1.8 million for the WestDallas Gateway

    $8 million in additional funds donated for the Continental Bridge Project

    Planning efforts with the community by the dallas citydesign studio defined the program for theWest Dallas Gateway project to connect West Dallas to the Continental Bridge

    backgrounddallas citydesign studio 3

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    5/44

    ContinentalBridge

    dallas citydesign studio 4

    WRT

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    6/44dallas citydesign studio 5

    WRT

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    7/44dallas citydesign studio 6

    WRT

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    8/44

    FLOWER

    GATEWAYTrefoil shadestructures with vines& seatingVending areas

    150.

    dallas citydesign studio 7

    WRT

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    9/44dallas citydesign studio 8

    WRT

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    10/44dallas citydesign studio 9

    WRT

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    11/44

    PLAY AREA

    Shade TreesSeatingBocce CourtChess PanelClimbing BlocksSidewalk Games

    150 300

    dallas citydesign studio 10

    WRT

    (POTENTIALINTERIM,USE)

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    12/44dallas citydesign studio 11

    WRT

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    13/44dallas citydesign studio 12

    WRT

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    14/44

    dallas citydesign studio 13

    WRT

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    15/44

    FOUNTAIN/ MISTPLAZAProgrammable Mistand Water JetsSeating AreaCooling Fog Poles

    150150 300

    dallas citydesign studio 14

    WRT

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    16/44

    ISLAND GARDENS

    Shade treesPlantersHanging vinesSeating

    150 300 180150

    dallas citydesign studio 15

    WRT

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    17/44

    dallas citydesign studio 16

    WRT

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    18/44

    dallas citydesign studio 17

    WRT

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    19/44

    MEDITATION PLAZA

    Labyrinth

    150 300 180 230150

    dallas citydesign studio 18

    WRT

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    20/44

    dallas citydesign studio 19

    WRT

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    21/44

    EVENT PLAZAShade treesPlantersSeatingElectrical supply

    150 300 180 230 640150

    dallas citydesign studio 20

    WRT

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    22/44

    dallas citydesign studio 21

    WRT

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    23/44

    dallas citydesign studio 22

    WRT

    example style of light fixture

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    24/44

    dallas citydesign studio 23

    WRT

    limits of constructionlandscaping to include 9 staircase

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    25/44

    PEDESTRIANPEDESTRIAN

    ZONEZONE

    SPECIALSPECIAL

    EVENTEVENTCONTROLCONTROL

    POINTPOINT

    NORMALNORMALCONTROLCONTROLPOINTPOINT

    removable bollards

    dallas citydesign studio 24

    WRT

    limits of construction

    on eastern end of projectlandscaping to include 9

    trees and shrubs

    no change proposed

    to street configuration

    area for parallel parking

    RIVE

    RFRONTBLVD

    RIVE

    RFRONTBLVD

    CONTINENTALST

    CONTINENTALST

    staircase

    landscaping to include 9 staircase

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    26/44

    dallas citydesign studio 25

    WRT

    landscaping to include 9

    trees and shrubs

    area available for special

    event parkingremovable bollards

    Section through the eastern end of Continental looking toward Riverfront Blvd

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    27/44

    WesternGateway

    dallas citydesign studio 26

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    28/44

    TxDOT reconfigured intersection

    levee top canada drivecontinental

    pedestrian bridge singleton avenue margaret hunt hill bridge

    dallas citydesign studio 27

    id t bi l & id f i l

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    29/44

    early community planning to define the projects program

    provide neighborhood

    access to the park and

    Continental Bridge

    provide much-needed

    vehicular parkingcreate a

    plaza/gathering

    space

    provide a strong bicycle &

    pedestrian connection from the

    bridge/plaza to adjacent

    development opportunities

    provide for occasional

    vehicular access to the

    Continental Bridge for

    emergency and service vehicles

    utility station/additional median

    enhancements as a future design

    opportunity for the gateway

    utility station/additional median

    enhancements as a future design

    opportunity for the gateway

    dallas citydesign studio 28

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    30/44

    GuldenSt. S

    ingle

    ton

    Blv

    d.

    N.Beckle

    dallas citydesign studio 29

    WRT

    FUTURE

    IMPROVEMENTS

    current proposed design

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    31/44

    dallas citydesign studio 30

    WRT

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    32/44

    dallas citydesign studio 31

    WRT

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    33/44

    GuldenSt. S

    ingle

    ton

    Blv

    d.

    N.Beckle

    dallas citydesign studio 32

    pedestrian connectivity

    WRT

    SEAT WALL(SPECIALFEATURE)

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    34/44

    dallas citydesign studio 33

    WRT

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    35/44

    GuldenSt. S

    ingle

    ton

    Blv

    d.

    N.Beckle

    dallas citydesign studio 34

    bike connectivity

    WRT

    Potential futureDART bus stop

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    36/44

    Sin

    gleton

    Blv

    d.

    N.Beckle

    dallas citydesign studio 35

    WRT

    vehicular connectivity

    GuldenSt.

    EMERGENCYACCESS

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    37/44

    FUTURECONCESSIONS& RESTROOM

    GuldenSt. S

    ingle

    ton

    Blv

    d.

    N.Beckle

    dallas citydesign studio 36

    WRT

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    38/44

    PICNIC AREA

    GuldenSt. S

    ingle

    ton

    Blv

    d.

    N.Beckle

    dallas citydesign studio 37

    WRT

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    39/44

    POTENTAILAREA FORFUTURE STREET

    FAIR/ MARKETTENTS

    GuldenSt. S

    ingle

    ton

    Blv

    d.

    N.Beckle

    dallas citydesign studio 38

    WRT

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    40/44

    GuldenSt. S

    ingle

    ton

    Blv

    d.

    N.Beckle

    POTENTIALAREA FORFUTURESTAGE /

    FESTIVALTENT

    dallas citydesign studio 39

    WRT

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    41/44

    Project Budget:Continental Bridge: $9.9 million Inclusive of design/ engineering and construction

    West Dallas Gateway: $1.8 million Inclusive of design/ engineering andconstructionTotal Budget: $11.7 millionAvailable Funding: $11.7 million

    Project Schedule:Bid Documents Design underway

    Bid Advertisement March 2012Thoroughfare Plan Amendments March 2012Bid Award April 2012Construction Duration 16 monthsProject Opening August 2013

    Project Awards for Continental Bridge:

    2011 Dream Award from the Greater Dallas Planning Council

    dallas citydesign studio 40

    anticipated schedule and budget

    Delete Continental

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    42/44

    Sin

    gleton

    Blv

    d.

    N.Beckle

    dallas citydesign studio 41

    WRT

    thoroughfare plan amendments

    Delete Continental

    Avenue from Singleton

    to Riverfront from the

    Thoroughfare Plan

    GuldenSt.

    Delete Canada Drive

    from Singleton to

    Gulden from the

    Thoroughfare Plan, ifnecessary

    Change Beckley-

    Canada Connection to

    North Beckley Avenue

  • 7/31/2019 TRC_ContinentalBridgeWestDallasGateway_010912

    43/44

    next steps: thoroughfare plan amendment process

    1| CPCTransportationCommittee February2,20122| CityPlanCommission February16,20123| CityCouncil March28,2012

    dallas citydesign studio 42