  • 8/15/2019 VCC Navigator E

    1/12

    VCC – Völkel Compaction Control®

    Modern compaction control with the VCC Navigator

  • 8/15/2019 VCC Navigator E

    2/12 2 | VCC Navigator

    Comprehensive Compaction Control (CCC)

    Independent of the roller manufacturer and roller type:

      Automatic measurement values recording

      Wireless data transfer

    Complete administration at the PC

    Web server

    PC software

    CompactDoc

    Mobile phone station

    Machine in operation

    GNSS receiver VDS modem

    Display

    Compaction measurement

    USB

  • 8/15/2019 VCC Navigator E

    3/12 VCC Navigator | 3

    CCC - simple using the Navigator

    The VCC Navigator enables separation of the tasks. The administrative tasks are dealt with at the PC by the

    respective specialists. Therefore, the driver can concentrate absolutely on the compaction of the material to beinstalled.

    Easy to assembe

    Plug and play - the Navigator package is supplied ready to connect for all vibratory rollers:

    - The sensors are assembled on the compactor and chassis.

    - The quick-release adapter supports the attachment of the display in the cabin.

    - The modem and GNSS receiver are affixed to the driver’s cabin with magnetic bases.

    - The connection node NAB connects all the parts of the Navigator.

    Easy to set up

    The compaction project is prepared in the site office with the CompactDoc PC software.

    The construction drawing is effortlessly imported with the axis data. It simplifies the

    orientation on the construction site for the roller driver.

     All specifications for compaction measurement can be communicated by the site office

    to the roller via a modem or USB stick using wireless transmission. Input on the display

    in the machine is also possible.

    Easy to operate

    Measurement starts automatically after switching the vibration on.

    The display in the driver’s cabin shows all the important information such as

    compression status and increase, number of passes, position of the roller or the

    temperature.

    The coloured presentation of the measurement values according to the traffic lights

    principle visualises on the card when the compaction target is reached. This enables

    the roller driver to react fast if required.

    Easy to save

    The VCC Navigator saves all measurement data automatically. The VDS modem

    transfers them encoded via mobile communications directly to a server. There the data

    is ready for call-up with the CompactDoc PC software.

    It is also possible to exchange the data between the Navigator and a PC using a USB stick.

     

    Easy to evaluate

    To analyse and document the compaction the PC software CompactDoc is used.

     Via a safe Internet connection the program accesses the current measurement values for the roller.

    In addition, CompactDoc enables comprehensive evaluation of the construction project at all times,e. g. as a measurement protocol in accordance with CCC Guidelines. Export functions support further

    processing using other programs.

  • 8/15/2019 VCC Navigator E

    4/12 4 | VCC Navigator

    Proof of load-bearing capacity

    More and more often, the building contractors require

    proof of load-bearing capacity of the substructure.

    Traditional measurement methods such as statistical

    test plans or sample compaction work and proof are

    very time-intense. Several samples and detailed

    documentation are necessary. These techniques

    require trained experts and only provide selective

    results.

    The VCC Navigator earthwork uses the results from

    selective samples and applies these comprehensively

    to the entire construction site. A partial area sufficesfor calibration, enabling the measurement of the entire

    construction field according to the CCC rules if the

    material characteristics are the same.

    The work-integrated measurement method can be

    applied faster and also records data away from

    selective random sampling.

    The VCC Navigator earthwork 

  • 8/15/2019 VCC Navigator E

    5/12 VCC Navigator | 5

    Increasing efficiency 

    The VCC Navigator supports the building contractor

    and the installation team in their actual task:

    completion of the construction site. For this purpose,

    the measurement system is optimised to enable the

    easiest of usability.

      The administrative tasks are dealt with at the

    PC and transferred wireless to the roller.

      The VCC Navigator carries out the transferred

    tasks independently without interaction with the

    roller driver. The recording of measurementvalues starts automatically after switching the

    vibrator on.

      Additionally, the touch screen enables the

    intuitive implementation of all tasks incurred

    on the construction site for CCC, for example

    calibration of the measurement.

    The roller driver’s assistant

    The roller driver is informed of the subsoil status at

    all times. The display shows the compaction values,

    compaction increase or the number of dynamic passes.

    Thus, weaknesses can be recognised immediately.

     

    The reasons for inadequate compaction can include

    too high or too low water content in the ground, a poor

    grain structure or several other reasons.

    The driver can initiate correction in good time withground improvement measures.

    Equally, the Navigator warns against over-compaction.

    The roller driver can use this, for example, to avoid

    the loosening of the ground via grain destruction and

    act accordingly.

    The VCC Navigator earthwork 

  • 8/15/2019 VCC Navigator E

    6/12 6 | VCC Navigator

    The assistant in the construction office

    With its software, the VCC Navigator supports the

    planning and documentation of the compaction project:

    Setting up the construction site

      Import of the geo-referenced construction drawing

      Calibration of the measurement data

      Evaluation of the compaction data

    etc.

    The Navigator assistance enables faster and more

    reliable preparation of all compaction data because the

     VCC Navigator is based on the latest methods of theCCC information sheet from the Forschungsgesellschaft

    für Straßen- und Verkehrswesen (FGSV) [Road and

    Transportation Research Association].

    The printout for documentation of the construction

    measure to the client contains all relevant information

    for CCC. The print assistant enables filtering it for the

    client. The template editor serves to adapt the printout

    to the building contractor’s corporate design.

    Sample printout of a documentation

    The VCC Navigator earthwork

      Relieves the roller driver of the

    measurement tasks

      Increases availability of the compaction values

      Enables direct or time-shifted analysis

    of the vibro-compaction 

    The VCC Navigator earthwork 

    Easy calibration with the VCC Navigator

  • 8/15/2019 VCC Navigator E

    7/12 VCC Navigator | 7

    Task

     As opposed to earthwork, no official installation

    compaction control regulations exist for asphalt

    installation. Accordingly, the client does not prescribe

    the use of measurement technology but this is

    necessary to proof the compaction quality.

     Asphalt paving is a time-critical process. In order to

    achieve the specified compaction, a calculated number

    of crossings within a certain temperature range of the

    mix is required.

    To assess the load-bearing capacity of the building,in asphalt compaction, the number of dynamic passes

    is considered first, and not the rigidity value, which also

    increases when the asphalt cools down.

    For this reason, it is crucial to comply with the agreed

    rolling scheme throughout. This is already a tough

    challenge for smaller construction sites because, after

    a few passes, the roller driver can no longer recognise

    how frequently he has dynamically compacted certain

    points.

     

    The VCC Navigator asphalt

    The VCC Navigator asphalt works as in earthwork

    without the help of the roller driver.

    The gapless takeover of a rolling scheme from a

    team colleague who has to leave his workplace tofill the water supply is virtually impossible without an

    assistance system.

    The VCC Navigator asphalt helps the installation team

    to fulfil the networked roller scheme over the course

    of the long installation day with all of its incidents. The

    benefit for the building contractor is the minimisation

    of expensive reworking of construction projects.

  • 8/15/2019 VCC Navigator E

    8/12

    Comparison: asphalt installation with and without

    the VCC Navigator

    The tests were made with a team known to be

    “experienced”. First, the asphalt was installed

    conventionally. The display was covered. Then, the

    Navigator was applied as an assistance system.

     Already the first cycle with the Navigator demonstrated

    considerably better evenness during paving.

    The PC evaluation shows the results from a meter for

    dynamic passes:

    The roller driver worked via the display without help

    in the travel direction south to north. The image shows

    a clearly right-biased roller scheme and gaps on theleft-hand side in travel direction.

    The driver rolled with an open display in the north to

    south travel direction. The covering of dynamic passes

    is considerably more even.

    8 | VCC Navigator

    The VCC Navigator asphalt

  • 8/15/2019 VCC Navigator E

    9/12 VCC Navigator | 9

    Solution: asphalt installation using leading edge

    measurement technology 

    In particular for larger construction sites, VCC

    measurement technology provides an overview of

    all construction phases as several rollers are equipped

    with the Navigator system and networked via mobile

    communications. This enables all team members to

    record the overall paving progress at a glance.

     

    The roller drivers distinguish the different rollers

    on the display via their colour allocation: their own

    roller is displayed black, other rollers are shown in

    grey. All drivers are therefore able to assume the taskof another roller with their own roller and to continue

    compaction precisely where their predecessor

    stopped.

    Increasing know-how

    The paving process can be followed precisely

    at the PC. This enables the use of the data gained

    for training purposes: the PC software CompactDoc

    can be used to show the entire team’s installation

    process in selected partial areas in fast motion.

    Quality proof of the installation

    Comprehensive compaction control in asphalt

    installation doesn’t yet enjoy tradition. There are no

    sets of rules as for earthwork. Nonetheless, the

    comprehensive documentation for asphalt compaction

    is increasingly becoming valid as quality proof.

    Printout of the compaction data is derived from the

    CCC information sheet for earthwork.

    It fully documents the quality of the asphalt

    compaction.

    The VCC Navigator asphalt

  • 8/15/2019 VCC Navigator E

    10/12 10 | VCC Navigator

    Display properties

    The display with a 10-inch screendiagonal is encased in robust

    aluminium housing and planned

    for the rough environmental

    conditions of a construction site.

    The vertical alignment of the display

    supports the situation on the

    construction site: mostly, the card

    shows the working area in front of

    and behind the roller driver.

    The touch screen is protectedwith scratchproof mineral glass,

    supporting intuitive operation.

    Large buttons enable ergonomic

    working.

     Also when visibility is poor because

    of too much or too little light, the

    display remains easy to read off

    due to its non-reflecting glass and

    backlighting.

    Display assembly For easy installation in the driver’s

    roller cabin, a quick-release adapter

    for the display, which also makes the

    contact, is available.

     VCC Navigator display technical data

    Dimensions 252mmx199.2mmx26.5mmWeight 1350g

    Operation Capacitive touch screen

    Memory 8 GB

    Display 10.4 inch, LED backlighting

    Housing  Anodised cast aluminium

    Protection category IP65

    Temperature range - 30 ... +70 °C

    Supply + 8 … 32V, reverse pole protection

     Assembly  Vesa standard 100mmx 100mm

      or quick-release adapter

    The VCC Navigator display

  • 8/15/2019 VCC Navigator E

    11/12 VCC Navigator | 11

    Option A

     ASC sensor

    Front binding

     VCC display with Vesa mount

    Components and connection of the VCC Navigator

    Basic equipment: the VCC Navigator as a pass counter

    Extensions

    Extension levels [complete packages] Option A Option B Option C

     VCC Navigator pass counter P2516

     VCC Navigator asphalt light P2517

     VCC Navigator asphalt pro P2510

     VCC Navigator asphalt P2518

     VCC Navigator earthwork P2519

     Assembly plate with

    modem and GNSS

    Modem /GNSS cable

    Machine cable

    Connection cable

    NAB

     Vehicle roof

    Driver's cabin

    Machine room

    Option B

     ASC sensor

    Back binding

    Option C

    TSC sensor

    Beneath the driver’s cabin

    Sensor connection

    [not required for VCC Navigator earthwork]

    Sensor connection

    [only for the VCC Navigator asphalt pro]

  • 8/15/2019 VCC Navigator E

    12/12

    Further information regarding our other products and our company is available under www.voelkel.de

     Völkel Mikroelektronik GmbH

    Otto-Hahn-Straße 30

    D-48161 Münster

    Germany

    Talk with us about your project Tel. +49 [0]2534.9731-0

    Fax +49 [0]2534.9731-10

    [email protected]

    www.voelkel.de

       ©    V

       ö   l   k  e   l   M   i   k  r  o  e   l  e   k   t  r  o  n   i   k   G  m   b   H   |   2   0   1   6   0   2   0   1