DATOS:
f´c = 210 Kg/cm²
fy = 4200 Kg/cm²
sT = 2.2 Kg/m²
Ko = 5000 Tn/m³
NPT = 0.25 m
Df = 1.7 m
S/C = 400 kg/m²
PD = 40.0 Tn PD = 60.0 Tn PD = 45.0 Tn
PL = 25.0 Tn PL = 35.0 Tn PL = 30.0 Tn
MDx = 2.8 Tn - m MDx = 2.0 Tn - m MDx = 3.2 Tn - m
MLx = 1.4 Tn - m MLx = 1.2 Tn - m MLx = 1.8 Tn - m
MDy = 2.2 Tn - m MDy = 2.1 Tn - m MDy = 2.4 Tn - m
MLy = 1.5 Tn - m MLy = 1.3 Tn - m MLy = 1.7 Tn - m
0.40 C1 0.40 C2 0.40 C3
5.00 m 6.00 m
12.20 m
0.45 m
1.00
m 0.40 m
1.40 m
SOLUCIÓN:
Verificación de la Rigidez:
VIGA DE CIMENTACIÓN FLEXIBLE O FLOTANTE
Columna 1 Columna 2 Columna 3
Lm = 5.90 m
Kc = 2.2*K750*((b+300)/2*b))²
Kc = 4054.85 Ton/m
I = 0.0611 m⁴
1.75*(4*E*I/Kc*b)¼ = 5.44 m
Lm = 5.90 > 5.44 \ Cimentación Flexible
Cálculo de la Elástica:
L = (4*E*I/Kc*b)¼
L = 3.11 m
M1 M2 M3
P1 P2 P3
0.2 5.40 m 6.40 m 0.2
Para P1: fig.
lL = 0.06
lR = 3.86 GT-15 0.06 3.86
Para P2:
lL = 1.80
lR = 2.12 GT-25 1.80 2.12
Para P3:
lL = 3.86
lR = 0.06 GT-15 3.86 0.06
Para M1:
lL = 0.06
lR = 3.86 GT-26 0.06 3.86
Para M2:
lL = 1.80
lR = 2.12 GT-27 1.80 2.12
Para M3:
lL = 3.86
lR = 0.06 GT-26 3.86 0.06
Determinación de los Coeficientes de esfuerzos del Terreno:
P1 P2
0.2 5.40 m 6.40
1 2 3 4 5
Debido a:
s1 = s7 0.00 0.00
s2 l = 0.00 l = 1.74 l =
2.00 0.04
s = 29.85 s = 0.87 s =
s3 l = 0.87 l = 0.87 l =
0.40 0.31
s = 5.97 s = 6.76 s =
s4 l = 1.74 l = 0.00 l =
-0.15 0.53
s = -2.24 s = 11.56 s =
s5 l = 2.77 l = 1.03 l =
-0.15 0.30
s = -2.24 s = 6.55 s =
s6 l = 3.79 l = 2.06 l =
0.00 -0.10
s = 0.00 s = -2.18 s =
Determinación de los Coeficientes de Momentos de Flexión:
Debido a:
M1 = M7 0.00 0.00
M2 l = 0.00 l = 1.74 l =
0.00 -0.01
M = 0.00 M = -2.95 M =
M3 l = 0.87 l = 0.87 l =
-0.31 -0.005
M = -62.67 M = -1.48 M =
M4 l = 1.74 l = 0.00 l =
-0.15 0.25
M = -30.33 M = 73.87 M =
M5 l = 2.77 l = 1.03 l =
-0.05 0.01
M = -10.11 M = 2.95 M =
M6 l = 3.79 l = 2.06 l =
0.00 -0.004
P1
GT-15 GT-25 GT-15
P2 P3
P1 P2 P3
M = 0.00 M = -1.18 M =
Determinación de los Coeficientes de Esfuerzos Cortantes:
Debido a:
V1 = V7 0.00 0.00
V2 l = 0.00 l = 1.74 l =
-1.00 0.04
V = -65.00 V = 3.80 V =
V3 l = 0.87 l = 0.87 l =
0.13 -0.10
V = 8.45 V = -9.50 V =
V4 l = 1.74 l = 0.00 l =
0.20 0.50
V = 13.00 V = 47.50 V =
V5 l = 2.77 l = 1.03 l =
0.00 0.00
V = 0.00 V = 0.00 V =
V6 l = 3.79 l = 2.06 l =
0.00 0.00
V = 0.00 V = 0.00 V =
Determinación del Refuerzo Longitudinal:
Punto 2:
Mu = 8708.79 Kg-m
d = 90.75 cm
a = 18.15 cm
b = 45 cm
ab = 0.01
As = 2.82
Asmin = 0.7*(f´c/fy)*bw*d
Asmin = 9.86 cm²
USAR : 2 Φ Nº 6 +
\ As = 9.66 cm2
Punto 3:
P1 P2 P3
Mu = 51089.51 Kg-m
d = 90.75 cm
a = 18.15 cm
b = 140.00 cm
ab = 0.03
As = 16.55
USAR : 6 Φ Nº 6
\ As = 17.10 cm2
Punto 4:
Mu = 26801.31 Kg-m
d = 90.75 cm
a = 18.15 cm
b = 45.00 cm
ab = 0.05
As = 8.68
Asmin = 0.7*(f´c/fy)*bw*d
Asmin = 9.86 cm²
USAR : 2 Φ Nº 6 +
\ As = 9.66 cm2
Punto 5:
Mu = 70665.63 Kg-m
d = 90.75 cm
a = 18.15 cm
b = 140.00 cm
ab = 0.04
As = 22.89
USAR : 3 Φ Nº 8 +
\ As = 23.75 cm2
Punto 5:
Mu = 13193.82 Kg-m
d = 90.75 cm
a = 18.15 cm
b = 45.00 cm
ab = 0.02
As = 4.27
Asmin = 0.7*(f´c/fy)*bw*d
Asmin = 9.86 cm²
USAR : 2 Φ Nº 6 +
\ As = 9.66 cm2
Determinación de los Coeficientes de esfuerzos del Terreno:
P3
m 0.2
6 7
0.00 0.00 0.00 0.00
3.79 l = 0.00 l = 1.74 l = 3.79
0.00 -2.00 -1.50 0.00
0.00 s = -1.93 s = -1.10 s = 0.00
2.93 l = 0.87 l = 0.87 l = 2.93
-0.15 0.20 0.40 0.10
-2.58 s = 0.19 s = 0.29 s = 0.11
2.06 l = 1.74 l = 0.00 l = 2.06
-0.20 0.40 -0.20 0.35
-3.44 s = 0.39 s = -0.15 s = 0.40
1.03 l = 2.77 l = 1.03 l = 1.03
0.40 0.20 -0.75 0.25
6.89 s = 0.19 s = -0.55 s = 0.29
0.00 l = 3.79 l = 2.06 l = 0.00
2.00 0.05 -1.50 -2.00
34.45 s = 0.05 s = -1.10 s = -2.30
0.00 0.00 0.00 0.00
3.79 l = 0.00 l = 1.74 l = 3.79
0.00 1.00 0.00 -0.09
0.00 M = 13.06 M = 0.00 M = -1.40
2.93 l = 0.87 l = 0.87 l = 2.93
0.02 0.79 0.08 -0.10
3.50 M = 10.32 M = 0.80 M = -1.56
2.06 l = 1.74 l = 0.00 l = 2.06
-0.10 0.125 0.31 0.12
-23.33 M = 1.63 M = 3.09 M = 1.87
1.03 l = 2.77 l = 1.03 l = 1.03
-0.30 -0.10 0.00 0.50
-69.98 M = -1.31 M = 0.00 M = 7.78
0.00 l = 3.79 l = 2.06 l = 0.00
0.00 -0.09 0.00 1.00
M3
GT-15 GT-26 GT-27 GT-26
P3 M1 M2
M3P3 M1 M2
0.00 M = -1.18 M = 0.00 M = 15.55
0.00 0.00 0.00 0.00
3.79 l = 0.00 l = 1.74 l = 0.02
0.00 0.10 -0.75 -0.09
0.00 V = 0.42 V = -2.40 V = -0.45
2.93 l = 0.87 l = 0.87 l = 2.93
0.00 -0.62 -0.22 0.00
0.00 V = -2.60 V = -0.70 V = 0.00
2.06 l = 1.74 l = 0.00 l = 2.06
0.15 -0.35 -0.30 -0.29
11.25 V = -1.47 V = -0.96 V = -1.45
1.03 l = 2.77 l = 1.03 l = 1.03
0.14 -0.04 0.00 -0.63
10.50 V = -0.17 V = 0.00 V = -3.15
0.00 l = 3.79 l = 2.06 l = 0.00
-1.00 0.02 0.00 0.10
-95.00 V = 0.08 V = 0.00 V = 0.50
cm
cm2
2 Φ Nº 5
M3P3 M1 M2
cm
cm2
cm
cm2
2 Φ Nº 5
cm
cm2
3 Φ Nº 6
cm
cm2
2 Φ Nº 5
TOTAL
0
27.70
10.75
6.52
11.12
28.92
TOTAL
0
8.71
-51.09
26.80
-70.67
27.70
10.75
6.52
11.12
28.92
8.71
51.09
26.80
13.19
13.19
TOTAL
0
-63.63
-4.36
67.87
7.18
-94.42
63.63
94.42
4.36
67.87
7.18
6.00
3Ø3/4"3Ø1"3Ø3/4"
2Ø3/4"+2Ø5/8"
2
.45 .455.00 .45
2Ø3/4"+2Ø5/8"
3Ø3/4" 1
1 2
6.00
3Ø3/4"3Ø1"3Ø3/4"
2Ø3/4"+2Ø5/8"
2
.45 .455.00 .45
2Ø3/4"+2Ø5/8"
3Ø3/4" 1
1 2
27.70
10.75
6.52
11.12
28.92
8.71
51.09
26.80
13.19
63.63
94.42
4.36
67.87
7.18
6.00
3Ø3/4"3Ø1"3Ø3/4"
2Ø3/4"+2Ø5/8"
2
.45 .455.00 .45
2Ø3/4"+2Ø5/8"
3Ø3/4" 1
1 2
6.00
3Ø3/4"3Ø1"3Ø3/4"
2Ø3/4"+2Ø5/8"
2
.45 .455.00 .45
2Ø3/4"+2Ø5/8"
3Ø3/4" 1
1 2
6.00
3Ø3/4"3Ø1"3Ø3/4"
2Ø3/4"+2Ø5/8"
2
.45 .455.00 .45
2Ø3/4"+2Ø5/8"
3Ø3/4" 1
1 2
6.00
3Ø3/4"3Ø1"3Ø3/4"
2Ø3/4"+2Ø5/8"
2
.45 .455.00 .45
2Ø3/4"+2Ø5/8"
3Ø3/4" 1
1 2