documents.worldbank.orgdocuments.worldbank.org/.../99723-ad-p120913-financi…  · web...

21
DRAFT THE AUDIT REPORT ON FINANCIAL SITUATION OF THE STRENGTHENING THE EFFECTIVNESS OF THE SOCIAL SAFETY NET PROJECT FOR 2014 99723 2015 COURT OF ACCOUNTS OF THE REPUBLIC OF MOLDOVA

Upload: trinhquynh

Post on 06-Feb-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: documents.worldbank.orgdocuments.worldbank.org/.../99723-AD-P120913-Financi…  · Web viewConsidering the fact that, in 2014, from IDA credit account for the Component I implementation

DRAFT

THE AUDIT REPORT ON FINANCIAL SITUATION OF THE STRENGTHENING

THE EFFECTIVNESS OF THE SOCIAL SAFETY NET PROJECT FOR 2014

997232015COURT OF ACCOUNTS OF THE REPUBLIC OF MOLDOVA

Page 2: documents.worldbank.orgdocuments.worldbank.org/.../99723-AD-P120913-Financi…  · Web viewConsidering the fact that, in 2014, from IDA credit account for the Component I implementation

CONTENTLIST OF ABBREVIATIONS ...…………………………………………………………………………………3

I. INTRODUCTION..............................................................................................................................................41.1. Legal mandate and audit period ...................................................................................................................4

1.2. Responsibility of the counterparts involved in Project implementation ......................................................4

1.3. Responsibility of the audit team ...................................................................................................................4

1.4. Audit methodology and approach ................................................................................................................4

II. GENERAL OVERVIEW..................................................................................................................................52.1. The project general data ...............................................................................................................................5

2.2. The information about Project financial sources disbursed and executed ...................................................6

III. FINDINGS, CONCLUSIONS AND RECOMMENDATIONS ....................................................................63.1. Procurement procedures related to the implementation of the Component II of the Project took place without deviations ...............................................................................................................................................6

3.2.Proper registration of the economic opearations has assured the accurate reporting of the IFR to the WB .....7

3.3. Budget Reporting took place in accordace with the national general framework on financial reporting ....7

3.4. MLSPF did not ensure full implementation of the previous recommendation ............................................7

IV. THE AUDIT TEAM STATEMENTS ...........................................................................................................8ANNEXES: INTERMIDIAT FINANCIAL REPORTS OF THE PROJECT, THE WORLD BANK TEMPLATES ................................................................................................................................................9

Annex no.1. Project Sources and funds use in Component II for 31.12.2014...............................................9

Annex no.2. Funds use in Component II of the Project per activities for 31.12.2014................................10

Annex no.3. Special account statement of the Project for 31.12.2014.........................................................11

Annex no.4. Report on Ajutor Social benefit for 31.12.2014......................................................................12

Annex no.5. Report on Heating Allowance benefit for 31.12.2014............................................................13

Annex no.6. Summary report on cash benefits execution for 31.12.2014..................................................14

2 | P a g i n ă

Page 3: documents.worldbank.orgdocuments.worldbank.org/.../99723-AD-P120913-Financi…  · Web viewConsidering the fact that, in 2014, from IDA credit account for the Component I implementation

LIST OF ABBREVIATION

MLSPF Ministry of Labor, Social Protection and Family

PROJECT Strengthening the Effectiveness of the Social Safety Net Project

POM Project Operational Manual

ISSAI International Standards of Supreme Audit Institutions

TOR Terms of Reference of the Project

WB World BankPAD Project Appraisal DocumentIFR Intermediate Financial ReportsIBRD International Bank for Reconstruction and DevelopmentIDA International Development Agency$M Million dollars USDM MDL Million Moldovan Lei

3 | P a g i n ă

Page 4: documents.worldbank.orgdocuments.worldbank.org/.../99723-AD-P120913-Financi…  · Web viewConsidering the fact that, in 2014, from IDA credit account for the Component I implementation

This Audit Report is for the Parliament, Government of the Republic of Moldova, WB, MLSPF, and to the other interested parties to be informed.

I. INTRODUCTION1.1. Legal Mandate and audit period.

Under the legal framework provided for the art. 28 and 31 para. (1) a) of the Court of Accounts Law no. 261-XVI of 05.12. 20081,and Audit Activity Program for 20152, the Court of Accounts carried out the audit of the financial statement of the Strengthening the Effectiveness of the Social Safety Net Project for 2014. 1.2. Responsibility of the counterparts involved in Project implementation.

MLSPF has a role of Executive Coordinator of the Project and is responsible for implementing and submitting of the Intermediate Financial Reports to the World Bank and Budgetary Financial Reports to the Ministry of Finance related to the Project.

According to the POM and Financing Agreement provisions, in order to carry out daily administration activities, the MLSPF has established a team responsible for the project coordination, financial management, developing and submitting interim financial Reports, cash-basis accounting, including executed sources from the funds per items and corresponding components.1.3. Responsibilities of the audit team.

The audit mission aimed at assess the operations and financial transactions, applying the related procedures in order to get sufficient and appropriate audit evidences, to support audit finding and opinions on financial statements reporting of the Project for 2014. The team of auditors is not responsible to prevent fraud and errors. 1.4. Audit methodology and approach.

The audit mission has been planned and carried out based on the Audit Standards approved by the Court of Accounts3, ISSAI 100 and ISSAI 2004, and by applying the good practices from the financing audit field. Thus, the audit approach is based on:

assessing the functionality of the internal controls related to the Project; applying the basic procedures on categories related to the financial operations to

record the accuracy of the economic transactions accounting, also reliability and completeness in reporting of financial statements.

1 The Court of Accounts Law no. 261-XVI of 05.12.2008 (with future amendments and addendums) 2 The Court of Accounts Decision no. 57 of 08.12.2014 “On approval the audit Program of activity of the Court of Accounts for 2015” (with farther addendums) 3 The Court of Accounts Decision no.7 of 10.03.2014 „On approval the audit guidelines (ISSAI 1000-5999) as the own audit standards”.4 The court of accounts Decision no.60 of 11.12.2013 ,,on applying the international standards of the Audit supreme institutions of the 3rd level – ISSAI 100, ISSAI 200, ISSAI 300, ISSAI 400, within the audit missions of the Court of Accounts”.

4 | P a g i n ă

Page 5: documents.worldbank.orgdocuments.worldbank.org/.../99723-AD-P120913-Financi…  · Web viewConsidering the fact that, in 2014, from IDA credit account for the Component I implementation

The overall objective of the audit mission was to express the opinions in relation whether the interim financial Reports and budgetary financial Report in all material aspects presents the factual and accurate view on budgetary year ending on 31.12.2014.

To carry out the proposed objective, and given the significance threshold and therefore the risks areas identification have been audited:

assessing the functionality of the internal controls which ensures the regularity in carrying out of procurement procedures related to the Project;

establishing accuracy, reliability and completeness of the interim financial Reports submitted to the WB;

examining of the financial statements reporting, and other aspects related to the budgetary accounting.

The audit Report’s findings and conclusions have been provided based on synthesizing, analyzing and interpreting of physical, verbal, documental and analytical evidences submitted by the MLSPF officials.

Considering the fact that, in 2014, from IDA credit account for the Component I implementation have not been disbursed the funds that have to be reimbursed to the State Treasury for financing the Ajutor Social and Heating Allowances Programs (due to the fact that the expected outcomes have not been achieved), the audit mission has been primarily focused on assessing the compliance of the financing commitments for the implementation of the Component II of the Project.

II. GENERAL OVERVIEW2.1. Project general data.

In order to launch the reforms in the social benefits area the Moldovan’s Government, has signed the Financing Agreement with IDA in amount equivalent to 22, 9 million XDR, or $ US 37, 0 million, approved by the Law no.174 of 29.07.20115.

Based on the financial support, that took a form of a credit, the Government is supporting the efficiency and equity of the social protection system by Strengthening the Effectiveness of the Social Safety Net Project, implemented by the MLSPF in 2011-2016.

The development objective of the project is to improve the efficiency and equity of Moldova's social safety net through a fiscally sustainable expansion and strengthening of the Ajutor Social Program. The project development objective will be achieved by two interrelated components of the Project, which are presented schematically in Figure no.1.

Figure no. 1Components

Source: The scheme was developed by the audit team based on POM provisions

5 Law no. 174 of 28.07.2011 “on approving the Financing Agreement between Republic of Moldova and International Development Association to carry out Strengthening the Effectiveness of the Social Safety Net Project.

5 | P a g i n ă

Page 6: documents.worldbank.orgdocuments.worldbank.org/.../99723-AD-P120913-Financi…  · Web viewConsidering the fact that, in 2014, from IDA credit account for the Component I implementation

Component 1. Sustainable Expansion of Ajutor Social Benefits and targeted Heating Allowances US$31 million equivalent, designated to co-finance the Ajutor Social Program, as well as the targeted seasonal Heating Allowances, which would be partly reimbursed to the State Treasury supported under these, and the disbursements would be triggered by achievement of results, which are grouped into three Results Areas.

Component 2. Institutional Strengthening for Benefits Administration US$6 million, would support strengthening of institutions and administration of social benefits, around five sub-components aimed to develop institutional capacities needed to measure and monitor Ajutor Social and Heating Allowances programs performance.

The project activity is regulated by the provisions of the Financing Agreement, PAD and POM, including its annexes. However, some processes (disbursements, procurement of goods/works and non-consulting services, consulting services) are regulated by the relevant Guidelines developed by the WB applicable to its projects. 2.2. The information about Project financial sources disbursed and executed. In 2014, to implement the Component II of the Project from the IDA credit Account have been disbursed the funds in amount of $US 0, 79 million. Testing reveals that financial statements and transactions have made and have recorded the expenditures in total amount of $US 0, 87, the difference being covered from the account of the balance recorded at 01.01.2014, in amount of $US 0, 10 million.

The overall analysis on the disbursed funds and expenses recorded in 2014, and also, cumulatively, from the very beginning, are presented in the Table no.1

Table no.1Analysis on the disbursements and funds used related to the Project

Name

2014 Total for the period01.07.2011 – 31.12.2014

Disbursements, including, direct

payments to the state budget

UsedDisbursements, including,

direct payments to the state budget

Expenses

$US million $US million $US million $US millionComponent I 0,00 0,00 20,02 20,02Component II 0,79 0,87 2,64 2,20

Total 0,79 0,87 22,66 22,22Source: The data summarized by the audit team based on the information provided by the financial management

consultant of the Project

III. FINDINGS, CONCLUSIONS AND RECOMMENDATIONS

3.1. Procurement procedures related to the implementation of the Component II of the Project took place without deviations

In the Project, the procurement has to be carried out according to the World Bank’s Guidelines67. According to the guidelines specifications, the WB has carried out review

6 Guidelines on Procurement of goods, works and non-consulting services under BIRD Loans and IDA credits. .7 Guidelines Selection and Employment of the consultants under IRBD Loans and IDA credits and Grants by World Bank Borrowers.

6 | P a g i n ă

Page 7: documents.worldbank.orgdocuments.worldbank.org/.../99723-AD-P120913-Financi…  · Web viewConsidering the fact that, in 2014, from IDA credit account for the Component I implementation

and approval of the procurement plans and of the documents related to the procurement process, such as: terms of references/ technical specifications; evaluation reports; bidding documents and contract drafts.

The audit mission found that in 2014, following the procurement procedures, 9 contracts for consulting services and 4 contracts for goods and non-consulting services have been made.

In the result of the audit specific proceedings application, the integral testing of two procurement procedures8 and key controls testing of 5 procurement procedures9 , hence, the audit have not find any deviations, and “no objection” have been received from the World Bank part for all the stages of the procurement process.

3.2 Proper registration of the economic operations has assured the accurate reporting of the IFR to the WB .

Following the verification of the functionality of existing controls within project management, examination of primary documents and ex-post checks reconciliations made between accounting records and interim financial reports, the audit has found that all economic transactions were properly recorded, and the Project management being functional and ensures reporting of financial statements reflected in the RFI.

3.3. Budget reporting took place in accordance with the national general framework on financial reporting.

In 2014, to carry out the Project were approved and specified funds in total amount of 15, 7 million MDL, actual expenditures were executed at 75,8%, totaling 11,9 million. Several factors have influenced that the planned funds were not executed entirely, such as: procurement process repeating on renovation and equipping of the training center; terms extension to carry out two consulting contracts.

Inspections and testing made by the audit mission have revealed the accuracy in the financial and banking operations recording related to: discounts for the goods and services delivered by the providers; the movement of assets and liabilities funded from external sources.

Similarly, the results of data reconciling reflected in accounting statements, account book and balance of budget execution, revealed the accuracy of the information regarding assets and liabilities, balance at the beginning and end of the budget year, and economic operations recorded.

3.4. MLSPF did not ensure full implementation of the previous recommendation.In terms of implementation of recommendation of the financial audit Report,

approved by the Court of Accounts Decision no. 32 of 27.06.201410, the audit reveals a low level of their implementation.

Accounting software (1C) is applied partly, in parallel, being used Word and Excel for some fields. Also, it is to mention that this problem was revealed under first 8 2 procurement procedures, including: 1 for the goods and 1 for the consulting services. 9 5 procurement procedures, including: 2 procedures for goods and 3 procedures for consulting services procurement. 10

7 | P a g i n ă

Page 8: documents.worldbank.orgdocuments.worldbank.org/.../99723-AD-P120913-Financi…  · Web viewConsidering the fact that, in 2014, from IDA credit account for the Component I implementation

evaluation carried out by the Court of Accounts in 201311. The process of risks identification and management specific to the Project for

2015 was not implemented, although the MLSPF has trained some employees in the field.

To this extent, the audit renews in the current Report previous recommendations to ensure their full implementation.

Recommendation to the MLSPF management:1. to accelerate the automation of accounting, which would allow applying of

analytical procedures for recording of the aggregated financial data and automated developing of the financial reports.

2. to assess and monitor the Project implementation, through continuous appraisal and identification of the risks specific to the components and stages of implementation.

IV. THE AUDIT TEAM STATEMENTS

Unqualified opinion on interim financial Reports The audit team opinion is based on sample and adequate proofs, the interim

financial Report for the year ended on December 31, 2014, in all material aspects, reveals true and accurate financial statement of the Project.

Unqualified opinion on budgetary reporting

According to the audit team, and based on audit activities, financial budgetary reports, in all material aspects, reveals true and accurate vision on financial statement for 31.12. 2014, in accordance with the financial reporting framework applied to the budget field.

Responsible for audit monitoring and execution, and Audit Report aggregation, Head of Performance audit Department Marianna Spoialo

Team of audit:Head of audit team,Superior state controller

The audit member,Superior state controller

Veronica Dolineanschi

Ada Railean

11 Courts of Accounts Decision no. 23 of 19.04.2013 on approval of the audit report on regularity of the Strengthening the Effectiveness of the Social Safety Net Project for 31.12.2012”.

8 | P a g i n ă

Page 9: documents.worldbank.orgdocuments.worldbank.org/.../99723-AD-P120913-Financi…  · Web viewConsidering the fact that, in 2014, from IDA credit account for the Component I implementation

ANNEXES

Annex no.1Project's sources and funds' use for Component II on 31.12.2014

$USDReal Planned Deviations

Project sumCurrent

quarter

annual, until the

date

cumulative, until the date

Current quarter

annual, until the date

cumulative, until the date

Current quarter

annual, until the

date

cumulative, until the date

Start balanceSeparate account 282.916,20 100.000,00 0,00Other accounts 0,88 399,06 0,00

Total start balance 282.917,08 100.399,06 0,00

Plus: financing sourcesSeparate account 0,00 750.000,00 2.177.790,55

Direct payments 36.103,67 36.103,67 36.103,67

Other sources 0,00 0,00 0,00Total sources 36.103,67 786.103,67 2.213.894,22Minus: using the funds

(eligible expenditures in accordance with the Financing Agreement)

306.784,46 874.266,44 2.201.657,93 246.033,60 1.199.778,60 2.527.170,10 60.750,86 -325.512,16 -325.512,16 6.000.000,00

Total used 306.784,46 874.266,44 2.201.657,93 246.033,60 1.199.778,60 2.527.170,10 60.750,86 -325.512,16 -325.512,16 6.000.000,00

Final balanceSeparate accounts 12.235,5 12.235,5 12.235,5Other accounts 0,79 0,79 0,79Total final balance 12.236,29 12.236,29 12.236,29 246.033,60 1.199.778,60 2.527.170,10 60.750,86 -325.512,16 -325.512,16 6.000.000,00

9 | P a g i n ă

Page 10: documents.worldbank.orgdocuments.worldbank.org/.../99723-AD-P120913-Financi…  · Web viewConsidering the fact that, in 2014, from IDA credit account for the Component I implementation

Annex nr.2Using the funds for the Component II of the Project per activities on 31.12.2014

$ USD

Project Components/Activities

Actual Planned DifferenceProject

DurationCurrent quarter

From the beginning of

the year

From the beginning of the project

Current quarter

From the beginning of

the year

From the beginning of the project

Current quarter

From the beginning of

the year

From the beginning of the project

Institutional Strengthening for Benefits Administration 253.380,81 764.172,43 1.911.051,59 191.000,00 1.073.967,00 2.220.846,17 62.380,81 -309.794,57 -309.794,57

6.00

0.00

0

(i) Strengthening institutions and improving information management 72.219,22 150.359,05 433.403,37 65.000,00 158.080,00 441.124,32 7.219,22 -7.720,95 -7.720,95

(ii) Developing and establishing mechanisms to strengthen oversight and

controls.4.229,05 43.142,72 420.503,58 5.000,00 64.327,10 441.687,96 -770,95 -21.184,38 -21.184,38

(iii)Developing a system based on performance for LA financing of AS

Program29.947,27 32.755,58 296.632,66 23.000,00 113.664,00 377.541,09 6.947,27 -80.908,42 -80.908,42

(iv) Improving communications, promotion and outreach. 146.985,27 417.916,83 520.142,13 98.000,00 476.348,90 578.574,20 48.985,27 -58.432,07 -58.432,07

(v) Developing activation measures and establishing institutional capacities for

social assistance’s beneficiaries integration into labor market

0,00 119.998,25 240.369,85 0,00 261.547,00 381.918,60 0,00 -141.548,75 -141.548,75

Project Management 53.403,65 110.094,01 290.606,34 55.033,6 125.811,6 306.323,93 -1.629,95 -15.717,59 -15.717,59Total general 306.784,46 874.266,44 2.201.657,93 246.033,60 1.199.778,6 2.527.170,10 60.750,86 -325.512,16 -325.512,16 6.000.000

10 | P a g i n ă

Page 11: documents.worldbank.orgdocuments.worldbank.org/.../99723-AD-P120913-Financi…  · Web viewConsidering the fact that, in 2014, from IDA credit account for the Component I implementation

Annex no.3Statement of separate account of the Project at 31.12.2014

$USDStart balance of separate account at 30.09.2014 282.917,08Total credit (plus): IDA credit on separate account for the period 36.103,67

IDA Additional financing at separate account for the period 0,00

0 319.020,75

Total debit (minus): Reimbursement to IDA from separate l account for the period 0

Eligible expenditures from IDA sources paid from the separate account for the period 306.784,46

IDA funds transferred to the separate account of the project, in MDL 0,79

0 0Final balance of the separate account at 31.12.2014 12.236,09

11 | P a g i n ă

Page 12: documents.worldbank.orgdocuments.worldbank.org/.../99723-AD-P120913-Financi…  · Web viewConsidering the fact that, in 2014, from IDA credit account for the Component I implementation

Annex. no 4

Report on Ajutor Social benefits on 31.12.2014

Balance at the beginning of the

period

Transferred from the Ministry of

Finance

CalculatedTransferred to the

financial institution

Reimbursed to the National Social Insurance HouseTotal paid

Balance at the end of the period

Credit From unpaid From paid Unpaid over 6 months Credit

Number of beneficiaries, thousand

Sum, mil.

MDL

Sum, mil. MDL

Number of beneficiaries, thousand

Sum, mil.

MDL

Number of beneficiaries, thousand

Sum, mil.

MDL

Number of beneficiaries, thousand

Sum, mil.

MDL

Number of beneficiaries

Sum, mil.

MDL

Number of beneficiaries, thousand

Sum, mil.

MDL

Number of beneficiaries, thousand

Sum, mil.

MDL

Number of beneficiaries, thousand

Sum, mil. MDL

January 3,4 2,4 15,4 23,1 15,6 23,1 15,6 39 12,2 21 25,9 0 0 21,8 15,7 3,0 2,3February 3 2,3 22,9 31,0 22,9 31,0 22,9 1 0,5 44 50,3 413 368,5 27,7 22,3 4,4 2,6March 4,4 2,6 22,3 30,4 22,7 30,4 22,7 1 1,4 21 62,2 169 217,3 29,3 23,0 3,1 2,1

Subtotal 60,6 61,2 61,2 14,1 138,4 585,8 61,0April 3,1 2,1 24,4 32,3 24,6 32,3 24,6 0 0,0 49 44,2 246 361,0 30,6 24,5 2,8 1,9May 2,8 1,9 22,9 31,7 23,3 31,7 23,3 3 5,4 50 47,6 141 152,2 29,5 22,9 3,3 2,1June 3,3 2,1 28,8 27,0 19,0 27,0 19,0 1 0,4 48 58,5 435 206,3 25,2 18,9 3,1 2,0

Subtotal 66,1 66,9 66,9 5,8 150,3 719,4 66,3July 3,1 2 16,7 24,8 17,0 24,8 17,0 0 0,0 55 84,3 79 109,4 23,3 17,0 2,9 1,9

August 2,9 1,9 15,1 22,5 15,5 22,5 15,5 6 7,6 25 46,9 111 137,2 21,2 15,4 2,8 1,9September 2,8 1,9 14,8 20,9 14,9 20,9 14,9 30 32,8 106 156,4 116 101,7 19,6 14,8 2,8 1,9Subtotal 46,5 47,5 47,5 40,5 287,6 348,3 47,2October 2,8 1,9 13,2 19,9 13,5 19,9 13,5 32 26,6 17 24,6 0 0,0 18,8 13,5 2,5 1,8

November 2,5 1,8 17,2 26,3 17,2 26,3 17,2 0 0,0 14 21,5 351 280,0 24,0 16,9 3,4 1,8December 3,4 1,8 20,7 31,7 20,9 31,7 20,9 7 6,8 23 44,7 254 177,0 30,0 20,9 2,9 1,6Subtotal 51,1 51,6 51,6 33,4 90,9 457,0 51,4

Total 224,2 227,2 227,2 93,7 667,1 2110,5 225,9

12 | P a g i n ă

Page 13: documents.worldbank.orgdocuments.worldbank.org/.../99723-AD-P120913-Financi…  · Web viewConsidering the fact that, in 2014, from IDA credit account for the Component I implementation

Annex no.5

Report on Heating Allowance Benefits on 31.12.2014

Balance at the beginning of the

priod

Transferred to the

Ministry of Finance

CalculatedTransferred to the financial institution

Reimbursed to the National Social Insurance HouseTotal paid

Balance at the end of the period

Credit From unpaid From paid Unpaid over 6 months Credit

Number of beneficiaries, thousand

Sum, mil.

MDL

Sum, mil. MDL

Number of beneficiaries, thousand

Sum, mil.

MDL

Number of beneficiaries, thousand

Sum, mil.

MDL

Number of beneficiaries, thousand

Sum, mil.

MDL

Number of beneficiaries, thousand

Sum, mil.

MDL

Number of beneficiaries, thousand

Sum, mil.

MDL

Number of beneficiaries, thousand

Sum, mil.

MDL

Number of beneficiaries, thousand

Sum, mil.

MDL

January 7,9 2,0 16,3 59,1 16,4 59,1 16,4 17 5,8 1 0,3 0 0 54,2 16,1 6,8 2,3February 6,8 2,3 22,7 69,6 22,7 69,6 22,7 28 9,6 3 1,0 0 0 63,2 21,5 9,3 3,5March 9,3 3,5 23,5 79,8 23,5 79,8 23,5 6 1,7 2 1,0 0 0 74,4 23,8 8,0 3,2

Subtotal 62,6 62,7 62,7 17,0 2,3 0 61,5April 8,0 3,2 23,8 84,2 23,8 84,2 23,8 24 9,0 0 0 0 0 77,7 23,5 9,0 3,5May 9,0 3,5 1,7 3,2 1,8 3,2 1,8 17 5,7 2 0,8 0 0 7,3 3,1 4,9 2,1June 4,9 2,1 0,3 0,5 0,3 0,5 0,3 24 9,3 0 0 1174 658,6 1,7 0,8 2,6 1,0

Subtotal 25,9 25,9 25,9 23,9 0,8 658,6 27,5July 2,6 1,0 0 0,2 0,1 0,2 0,1 33 16,6 0 0 383 205,3 0,7 0,3 1,8 0,6

August 1,8 0,6 0 0,03 0,02 0,03 0,02 9 2,9 0 0 368 174,0 0,2 0,09 1,2 0,4September 1,2 0,4 0 0,05 0,04 0,05 0,04 23 11,4 46 12,0 386 154,0 0,2 0,07 0,6 0,2Subtotal 0,0 0,2 0,2 30,8 12,0 533,3 0,5October 0,6 0,2 0 0,03 0,03 0,03 0,03 6 4,7 9 2,3 0 0 0,08 0,04 0,6 0,2

November 0,6 0,2 0 0,02 0,01 0,02 0,01 4 1,0 586 146,5 0,01 0,01 0,01 0,01December 0,01 0,01 18,4 78,9 19,7 78,9 19,7 7 3,5 8 2,0 3 0,8 73,3 18,3 5,6 1,4Subtotal 18,4 19,8 19,8 9,2 4,3 147,3 18,4

Total 106,9 108,6 108,6 80,9 19,3 1339,1 107,8

13 | P a g i n ă

Page 14: documents.worldbank.orgdocuments.worldbank.org/.../99723-AD-P120913-Financi…  · Web viewConsidering the fact that, in 2014, from IDA credit account for the Component I implementation

Annex no.6

Summary Report on social benefits execution on 31.12.2014(millions)

Benefits

Budgeted Financed by the Ministry of

Finance

Executed Debts to beneficiaries

approved Précised Précised for the reported period transferred paid actual receivable debts

MDL USD XDR MDL USD XDR MDL USD XDR MDL USD XDR MDL USD XDR MDL USD XDR MDL USD XDR MDL USD XDR MDL USD XDR

Ajutor social 374,4 28,6 18,5 256,7 19,6 12,7 256,7 19,6 12,7 224,2 17,1 11,1 227,2 17,3 11,2 225,

9 17,2 11,2 227,4 17,4 11,2 0 0 0 0 0 0

Heating Allowance* 192,7 14,7 9,5 137,

8 10,5 6,8 137,8 10,5 6,8 106,9 8,2 5,3 108,6 8,3 5,4 107,8 8,2 5,3 107,2 8,2 5,3 0 0 0 0 0 0

Total 567,1 43,3 28,9 394,5 30,1 20,1 394,5 30,1 20,1 331,1 25,3 16,8 335,8 27,7 18,5 333,

7 27,6 18,4 334,6 25,5 17,0 0 0 0 0 0 0

*Exchange rate USD-MDL, according to the State Budget Law for 2014 (13,1 MDL / 1 USD)**Approved budget for allowances and compensations for the cold period ***Exchange rate USD-XDR, according to www.clientconection.org la 13.05.2014 1,545160(USD/XDR)

14 | P a g i n ă