weekly report 008
DESCRIPTION
wrTRANSCRIPT
CLIENT
KINGDOM OF SAUDI ARABIA الـممـلـكــة العــربـيــة الســعـوديـــة
المـؤســســــة العــامــة لتحــلـية الـمــيــاه الـمــالــحــة
SALINE WATER CONVERSION CORPORATION محطة تحلية المياه المالحة وتوليد الطاقة الكهربائية
المرحلـة االولـى–رأس الخيــر RAS AL KHAIR POWER AND DESALINATION PLANT-PHASE 1
CONSULTANT
PÖYRY ENERGY AG
MAIN CONTRACTOR
SEPCOIII ELECTRIC POWER CONSTRUCTION CORPORATION
SUB CONTRACTOR
FIRE FIGHTING & FIRE DETECTION SYSTEMLOCATION: East CoastPACKAGE: “P” Power Plant
TITLE:
Weekly HSE Report For the Period 18st Jan 2013 – 23th Jan 2014
DOCUMENT No.: SHEET
R A K - Z N R - H S E - W R - 0 0 8 1 OF 4
SEPCOIII ELECTRIC POWER CONSTRUCTION CORPORATION
PACKAGE “P” POWER PLANTRAS AL KHAIR POWER AND DESALINATION PLANT – PHASE 1
Subject: Weekly HSE ReportFor the Period (18th Jan 2013 TO 23th Jan 2014)
Page 2 of 4
Doc No.: R A K - Z N R - H S E - W R - 0 0 8
CONTENTS
1.0 WEEKLY HSE STATISTICS 3
2.0 NARRATION OF INCIDENT/ACCIDENT AND NEAR-MISS REPORTED 4
3.0 HSE TRAINING 4
4.0 INSPECTION/ASSESSMENT/AUDIT/MEETINGS 4
5.0 WEEKLY MEETINGS ON HSE 4
6.0 IMPROVEMENT/PROHIBITION NOTICES 4
7.0 NON-CONFORMANCE (NO. OF NON-CONFORMANCE AND CLOSED ITEMS) 4
SEPCOIII ELECTRIC POWER CONSTRUCTION CORPORATION
PACKAGE “P” POWER PLANTRAS AL KHAIR POWER AND DESALINATION PLANT – PHASE 1
Subject: Weekly HSE ReportFor the Period (18th Jan 2013 TO 23th Jan 2014)
Page 3 of 4
Doc No.: R A K - Z N R - H S E - W R - 0 0 8
1.0 WEEKLY HSE STATISTICS
No. Subject This Week Figures Cumulative
01 Employees on Site working Hours 6,510 4,39,687
02 Employees in office Man-Hours 240 25,320
03 Total Safe working Hours 6750 4,65,007
04 Direct manpower 520 41,100
05 Indirect manpower 360 10,800
06 Saudi National Manpower - 253
07 Total Manpower 880 52,153
08 Lost Workday Case (LWC) 0 0
09 Restricted Workday Case (RWC) 0 0
10 Medical Treatment Case (MTC) 0 0
11 First Aid Case (FAC) 0 0
12 Property Damaged (PD) 0 0
13 Near Miss (NM) 0 0
14 Motor Vehicle Accident (MVA) 0 0
15 Fire Incident 0 0
16 Environmental Incident 0 0
17 Total Number of Recordable Injuries 0 0
18 Safe Man Days (No LTI) 6 288
Table 1
SEPCOIII ELECTRIC POWER CONSTRUCTION CORPORATION
PACKAGE “P” POWER PLANTRAS AL KHAIR POWER AND DESALINATION PLANT – PHASE 1
Subject: Weekly HSE ReportFor the Period (18th Jan 2013 TO 23th Jan 2014)
Page 4 of 4
Doc No.: R A K - Z N R - H S E - W R - 0 0 8
2.0 NARRATION OF INCIDENT/ACCIDENT and NEAR-MISS REPORTED(THE ACCIDENT/INCIDENT REPORT WILL BE ATTACHED WITH THE RE-PORT)
Events (NM/MT/FA/PD ETC...)
NO INCIDENT
Table 2
3.0 HSE TRAININGNo. Training Topic Time Location Trainer
1 Hot work procedures 7.00am FIRE FREEZE YARD Mr.Farooq (HSE )
2
Table 3
4.0 INSPECTION/ASSESSMENT/AUDIT/MEETINGSNo. Subject Time Conductor
Table 4
5.0 WEEKLY MEETINGS ON HSENo. Subject Time Conductor
Table 5
6.0 IMPROVEMENT/PROHIBITION NOTICESNo. Notice No. Issue Date Subcontractor Status
1.
Table 6
7.0 NON-CONFORMANCE (NO. OF NON-CONFORMANCE AND CLOSED ITEMS)No. Notice No. Issue Date Subcontractor Status
1.
Table 7