western region transmission (maharashtra) private limited ddr... · western region transmission...

42
WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

Upload: trandiep

Post on 01-May-2018

229 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

WESTERN REGION

TRANSMISSION

(MAHARASHTRA) PRIVATE

LIMITED

Social Safeguard Due Diligence Report

December 2010

Page 2: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 1

CONTENTS

PAGE NO.

LIST OF ANNEXURES……………………………………………………………. 2

ABBREVIATIONS………………………………………………………………… 3

Social Safeguard Due Diligence

1.0 Introduction…………………………………………………………………. 4

1.1 Background…………………………………………………………………. 4

1.2 Objective of Social Safeguard Due Diligence……………………………… 6

1.3 Project description………………………………………………………….. 6

2. Alternative analysis of the alignment……………………………................. 9

3. Methodology………………………………………………………………... 9

4 Social Impact Study of the project………………………………….............. 11

4.1 Impact on structure………………………………………………................. 11

4.2 Impact on Land……………………………………………………………... 11

4.3 Impact on Indigenous People………………………………………............. 11

4.4 Local employment………………………………………………………….. 11

4.5 Impact on livelihood and Crop Compensation ……………………………. 12

4.6 Accident Safety (Compensation for loss of life or Injury)………................ 13

5. Implementation Arrangement and Process………………………................ 13

6. Community Development Activities ………………………………………… 13

7. Conclusion and Recommendation………………………………………….. 13

8. Proposed monitoring by IIFCL……………………………………………... 14

TABLES

1.1 Project Highlights ………………………………………………………………. 4

1.2 Sub-project transmission lines………………………………………………… 6

1.3 Project Scope of Work………………………………………………………….. 7

1.4 Substation Details………………………………………………………………. 8

1.5 Sub-Project Construction Status……………………………………………….. 8

3.1 Availability of Social safeguard documents………………………………… 10

FIGURE

1.1 Western Region System Strengthening Scheme (WRSSS)-II……………..

5

Page 3: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 2

ANNEXURE

Annexure 1 List of Villages ………………………………………………………….. 15

Annexure 2 Justification of alignments …………………………………………….. 24

Annexure 3 License under Section 164 of The Electricity Act 2003…………… 26

Annexure 4 Crop Compensation Calculation ……………………………………... 30

Annexure 5 Crop production ………………………………………………………... 31

Annexure 6 Status of Crop compensation payment ……………………………… 32

Annexure 7 Formal Public consultation details …………………………………… 33

Annexure 8 Copy of 7/12 records ………………………………………………….. 36

Annexure 9 Copy of Notices issued to the affected landowners ……………….. 37

Annexure 10 Copy of Cheque issued to the affected landowners ……………….. 38

Annexure 11 Status of Community Development Activities ………………………. 39

Annexure 12 Summary of findings …………………………………………………. 40

Page 4: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 3

ABBREVIATIONS

CEA Central Electricity Authority

CRR Compliance Review Report

CSR Corporate Social Responsibility

ESPP Environment and Social Policy and Procedures

IIFCL India Infrastructure Finance Company Limited

IPTC Independent Private Transmission Company

LIE Lender’s Independent Engineer

PGCIL Power Grid Corporation of India Limited

PIM Project Information Memorandum

RAP Resettlement Action Plan

ROW Right of Way

SDD Social Due Diligence

SIA Social Impact Assessment

WB World Bank

WRSSS Western Region System Strengthening Scheme

WRTGPL Western Region Transmission (Gujarat) Private Limited

WRTMPL Western Region Transmission (Maharashtra) Private Limited

Page 5: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 4

SOCIAL SAFEGUARD DUE DILIGENCE

1.0 INTRODUCTION

1.1 Background:

1. To meet the growing power demand in the Western Region of India, a number of power

transmission projects are coming up in this region. The State of Maharashtra is part of the

Western Regional Electricity Grid comprising the States of Gujarat, Maharashtra, Madhya

Pradesh and Goa. As part of strengthening of the Western Grid, new transmission

strengthening proposed to be implemented under Western Region System Strengthening

Scheme (WRSSS)-II, which comprises of 4 projects namely A, B, C and D as shown in Fig

1.1. Project B and C that are coming up in the states of Maharashtra and Gujarat shall be

developed by Independent Private Transmission Company (IPTC) through 100.00% private

participation route. Power Grid Corporation of India Ltd. (PGCIL) carried out necessary

bidding process in selecting the IPTC and entrusted the implementation of project B and C

to Reliance Power Transmission Ltd (RPTL). RPTL then formed a wholly owned project

specific “Special Purpose Vehicle” (‘SPV”) for implementing the Project B and C. Accordingly

Western Region Transmission (Maharashtra) Private Limited (“WRTMPL”) and Western

Region Transmission (Gujarat) Private Limited (“WRTGPL”) were formed to undertake the

Project B and C respectively. The transmission project in Maharashtra involving

development of 1031.3 km 400kV line. The project highlights are given in table 1.1:

Table 1.1: Project Highlights

Project Name

- Western Region System Strengthening Scheme - II, Project B

Total length

- 1031.2 km

Location - Beed, Ahmednagar, Pune, Aurangabad, Sholapur,

Osmanabad, Latur, Sangli and Kolhapur districts in

Maharashtra and Bijapur district in Karnataka

Beneficiaries - MP Power Trading Company Ltd, Gujarat Urja Vikas Nigam Ltd, Maharashtra State Electricity Distribution Company Ltd., Chhattisgarh State Power Distribution Co. Limited, Electricity Department Govt. of Goa, Electricity Department Administration of Daman & Diu, Electricity Department Administration of Dadra & Nagar Haveli and MP Audyogik Kendra Vikas Nigam Ltd.

Project Cost

- Rs 912 crores

Page 6: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 5

2. The objective of the project is to:

• Provide adequate transmission system for reliable transfer of power to constituents

of Western region;

• Maintain system stability, security of the western grid under all operating conditions;

and,

• Increase the power transmission capacity of National Grid

.

3. WRTMPL has signed the Common Loan Agreement on 24th April 2009 with the lenders1 including India Infrastructure Finance Company Ltd. (IIFCL). IIFCL as part of its infrastructure scheme has approved Rs 124 crores to WRTMPL out of the total project cost of Rs 912. crores. Out of the approved Rs 124 crores, IIFCL has already disbursed Rs 15.65 crores to WRTMPL.

4. World Bank has sanctioned US$ 1,195 million line of credit to IIFCL to encourage flow of private investments into infrastructure. The sub-project has been considered for retroactive financing out of the above line of credit from World Bank. In order to be eligible for funding from the WB loan facility, Compliance Review Report (CRR) need to be prepared for the sub-projects which includes (i) Finance; (ii) Procurement; (iii) Environment and (iv) Social aspects. The Present report on Social Safeguard Due Diligence is part of the CRR.

1 The lenders of the project include State Bank of India (SBI), IIFCL, Vijaya Bank, Bank of Mysore and

State Bank of Bikaner and Jaipur (SBBJ.).

Fig 1.1: Western Region System Strengthening Scheme (WRSSS)-II

Page 7: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 6

1.2 Objective of Social safeguard Due Diligence

5. Social Safeguards due diligence study is carried out to assess the adequacy of the project with the applicable National and World Bank Social Safeguard policies. The main objective of this Social Due Diligence (SDD) is,

• To assess the likely social impacts of the project with respect to land acquisition and involuntary resettlement, ascertain adverse impacts, if any, on the people, in terms of displacement, loss of incomes, and community links.

• To ascertain, in case of any adverse impact, if appropriate mitigation measures have been taken during the project planning, designing and frameworks established for carrying out safeguard measures during the implementation stage to minimize and mitigate such any adverse impacts.

• To confirm if other critical social issues have been addressed in compliance with the National and World Bank Social Safeguard Policies.

1.3 Project Description:

6. As part of strengthening of the Western Grid, new power transmission lines are proposed

under WRSSS-II. Under this scheme 1031.2 km 400kV line is proposed to be developed in

the state of Maharashtra. The sub-project transmission lines passes through Beed,

Ahmednagar, Pune, Aurangabad, Sholapur, Osmanabad, Latur, Sangli and Kolhapur

districts in Maharashtra and Bijapur district in Karnataka. The sub-project details are given

in table 1.2.

Table 1.2: Sub-project transmission lines

Sl. No. Name of Transmission Lines

Name of Tehsil/ District

Approx. Line Length

(Km)

No. of towers to be footed

1 Parli – Pune 400kV D/C line

Parli/Beed to Pune/Pune

323.00 886

2 Pune-Aurangabad 400kV D/C line

Pune/Pune to Aurangabad

236.00 623

3 Parli-Solapur 400kV D/C line

Parli/Beed to Solapur/Solapur

136.00 355

4 Solapur (Limdi chincholi)- Kolhapur, 400KV D/C Line

Solapur to Kolhapur

219.00 575

5 LILO of Lonikhand-Kalwa 400Kv D/C Line at Pune

Lonikhand Kalwa/Thane

1.20 8

6 LILO of Solapur-Karad 400kV S/C line at Solapur

Solapur/Solapur 116.00 298

Total 1031.20 2745 Source: Lenders Independent Engineer (LIE) report, 4

th Quarterly Report

7. The scope of work of WRTMPL as part of the project include only gantry to gantry

connection and the major construction activities include (i) construction of tower foundation;

(ii) tower erection and (iii) stringing of wires. The interconnection facilities like sub-stations

and associated equipments are supported by PGCIL. WRTMPL has entered into an EPC

Page 8: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 7

contract with Reliance Infra. The scope of work of WRTMPL, PGCIL and Reliance Infra is

summarized in table 1.3 as given below:

Table 1.3: Project Scope of Work

Sl. No.

Scope of Work Primary Responsibility

Secondary Responsibility

1 Detailed survey with respect to route

alignment, optimization of tower

locations, soil resistivity, etc.

Reliance Infra WRTMPL

2 Design and testing of various

families of tower for different wind

zones through which the

transmission lines are passing.

Reliance Infra WRTMPL

3 Fabrication and supply of all types

of towers, tower accessories and

line materials.

Reliance Infra WRTMPL

4 Selecting different types of

foundations for different towers and

casting for foundation for tower

footings including river crossing

towers.

Reliance Infra WRTMPL

5 Erection of towers, painting of

towers and supply and erection of

span markers, obstruction lights,

fixing of insulator string, stringing of

conductors and earth wire along

with all necessary line accessories.

Reliance Infra WRTMPL

6 Testing and commissioning of respective transmission lines.

Reliance Infra WRTMPL

7 Maintenance of Right of Way. WRTMPL

8 Crop compensation. WRTMPL

9 Statutory clearances from Govt.

authorities.

WRTMPL

10 Interconnection facilities (like

substation, gantries etc)

PGCIL WRTMPL (to obtain necessary permission for charging)

Source: Project Information Memorandum for Project B and Implementation Agreement

8. According to the Implementation agreement (IA) between PGCIL and WRTMPL, PGCIL

shall provide all the necessary interconnection facilities to WRTMPL. The interconnection

facilities include substations/switch stations. The substation facility for the present sub-

project shall be provided by PGCIL from the existing sub-stations as detailed in table 1.4.

Page 9: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 8

Table 1.4: Substation Details

S.No. Transmission Line Name of Substation

1 Parli-Pune 400kV D/C line 400kV substation at Parli

400KV Substation at Pune

2 Pune-Aurangabad 400kv D/C line 400 KV substation at Pune

400 KV substation at Aurangabad

3 Parli- Solapur 400kv D/C Line 400 kV substation at Parli

400kV substation at Solapur

4 Solapur-Kolhapur, 400kV D/C Line

400kV substation at Solapur

400kV substation at Kolhapur

5 LILO of Lonikhand-Kalwa 400kV D/C line Pune

400kV substation at Pune

6 LILO of Solapur-Karad 400kV S/C line at Solapur

400kV substation at Solapur

9. Lenders Independent Engineer (LIE) has been appointed by State Bank of India to monitor

the progress in construction activities. The status of construction activities as per the LIE

report is given in table 1.5.

Table 1.5: Sub-Project Construction Status

Sl. No.

Name of transmission Line

Length (km)

Activities Progress up to 30.11.10

Total Unit 1 Parli-Pune 400kV

D/C line 323 Detailed

Survey 323 Km Completed

Foundations 886 Nos. 471 Erection 886 Nos. 108 Stringing 323 Km 0

2 Pune-Aurangabad 400kv D/C line

236 Detailed Survey

236 Km 212

Foundations 623 Nos. 323 Erection 623 Nos. 44 Stringing 236 Km. 0

3 Parli- Solapur 400kv D/C Line

136 Detailed Survey

136 Km Completed

Foundations 355 Nos. 118 Erection 355 Nos. 44 Stringing 136 Km 0

4 Solapur-Kolhapur, 400kV D/C Line

219 Detailed Survey

219 Km Completed

Foundations 575 Nos. 227 Erection 575 Nos. 59

Page 10: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 9

Sl. No.

Name of transmission Line

Length (km)

Activities Progress up to 30.11.10

Stringing 219 Km 0 5 LILO of Lonikhand –

Kalwa 400kV D/C line at Pune

1.2 Detailed Survey

1.2 Km Completed

Foundations 8 Nos. 4 Erection 8 Nos. 0 Stringing 1.2 Km 0

6 LILO of Solapur-Karad 400kV S/C line at Solapur

116 Detailed Survey

116 Km Completed

Foundations 298 Nos. 298 Erection 298 Nos. 298 Stringing 116 Km 115

Total for Project Detailed Survey

1031.2 Km 1007

Foundation 2745 Nos. 1441 Erection 2745 Nos. 553 Stringing 1031.2 Km 115

Source: Information as received from WRTMPL

2.0 ALTERNATIVE ANALYSIS OF ALIGNMENTS

10. The project transmission line passes through two states namely Maharashtra and Karnataka, covering 10 districts and 345 revenue villages (Annexure 1). A comprehensive route justification criterion has been followed towards route selection (Annexure-2). A detailed alternative study of various options has been done before finalization of the alignment.

11. The visiting team held discussions with the site engineers of the Developer, who explained the long and diligent process through which the transmission line alignment is fixed after all necessary measures to minimize impact on habilitations, trees and to reduce inconvenience to the farmers. First the alignment is drawn using topo sheet and then detail alignment is fixed based on field survey, which helps in avoiding impact on villages, forests, any other sensitive zones/ points. The preparatory process starts with OD survey which involves making straight lines on topo sheet (1:50,000); three alternative routes are marked and the best route is chosen based on minimum line length and obstructions. The sensitive spots avoided include National and State Highways, rivers, drainage systems, forests, human settlement, major development works; route lengths are also considered. No human settlement area is being affected due to the project.

3.0 METHODOLOGY

12. Social due diligence for the project was initiated by IIFCL after review of Project Information Memorandum (PIM) to understand the salient features of the project and various social and resettlement concerns. For better understanding, following key social safeguard documents were requested/ received from the Developer, and reviewed by the IIFCL Social Safeguard team, the status of which is given below:

Page 11: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 10

Table 3.1: Availability of documents

Sl. No. Key Social Safeguard documents requested

Availability Status

Remark

1 Social Impact Assessment (SIA) or sections of feasibility report containing SA

Not Available

An initial social study of the project suggested that no involuntary resettlement and rehabilitations issues are involved in the project. The project alignment has been so selected that it does not pass through any settlement area. No land acquisition issue is involved as part of the project.

2 Resettlement Action Plan Not Applicable

Since no resettlement impact, Resettlement Action Plan (RAP) is not required to be prepared for the project.

3 Tribal Development Plan

(if Required) Not

Applicable The route does not pass through any settlement area. The Developer has also confirmed that no tribal population is found on the corridor till date. Thus no Tribal Development Plan required.

4 Lenders Engineer Terms of Reference

Available The scope of work of LIE include – Observe and determine whether the social measures are in place.

13. In absence of any social study report, following relevant documents were collected for

assessing likely social risks and impacts of the project in order to prepare the social safeguard DDR:

• Lender’s Independent Engineer’s report, August 2010; and, • Information pertaining to justification of alignment selection; • Information regarding the methodology adopted for crop compensation; • Information regarding formal public consultation and information disclosure that are

being adopted. • Consultation with developer

14. Relevant information has also been collected during the Lender’s site visit (including LE meet), from 13th April – 15th April 2010, by IIFCL representative. A site visit was jointly conducted by World Bank, IIFCL and project Developer during June 9-10, 2010.

Page 12: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 11

4.0 SOCIAL IMPACT STUDY OF THE PROJECT

4.1 Impact on structure

15. The finalization of the design has been done by consideration the route selection criteria (Annexure 2) to minimize resettlement impact if any. With the analysis of various alternatives, the final route has such been selected that the transmission lines are not passing through any settlement areas and thus there is no adverse impact on residential; or commercial or any other structures along the proposed alignment.

4.2 Impact on land

16. As per section 164 of The Electricity Act 2003 and Indian Telegraph Act 1885, part III, section 10 to 19, the appropriate Government has the authority to place and maintain transmission lines under, over, along or across and posts in or upon any immovable property. Indian Telegraph Act 1885, Part III, Section 10 (b) prohibits acquisition of any right other than that of use only. Land for towers and right of way is not acquired and agricultural activities are allowed to continue. The developers have received clearance from Ministry of Power under section 68 and section 164 of Electricity Act 2003 which is a mandatory requirement for execution of new transmission lines (Annexure 3).

17. Project does not require any land acquisition for erection of tower under the Telegraph Act. The standard tower base area is of a dimension of 12 m. x 12 m. The flooring of each Stub or leg of the tower has a dimension of 400 mm x 400 mm (approx.). Apart from the land used for tower, a larger periphery of land will be required to be cleared temporarily to carry out the construction activities to erect the tower. The area to be temporarily affected varies for different locations, but on an average 40m x 40m. of land is affected temporarily to carry out the tower erection work. The land is temporarily excavated for the pit area which is then filled back and rehabilitated to allow continuation of normal agricultural activities. Moreover, land would also be affected for creating access roads for bringing in the material and the mobile machinery.

18. The impact on land is therefore temporary and the ownership status of the land remains with the landholder. Since the project does not involve setting up of any new sub-stations, thus no land acquisition is required for the project.

19. The substations for these transmission lines are not a part of this project and as per Implementation Agreement shall be facilitated by Power Grid Corporation of India Limited (PGCIL). PGCIL is an entity which has a corporate level Environment and Social Policy and Procedures (ESPP) endorsed by the World Bank according to which Social Due Diligence for these sub-stations has been conducted by PGCIL (http://www.powergridindia.com/PGCIL_NEW).

4.3 Impact on Indigenous people

20. As per the Census of India 2001 data, the percentage of Schedule Tribe population in the affected districts is very low. Moreover, the criteria followed towards route selection indicate that the proposed route does not pass through any settlement area. And thus it does not disturb any tribal settlement and does not have any adverse impact or create any threat to the survival of any tribal community along the alignment.

4.4 Local employment

21. The project provides limited employment opportunities to the local people during the construction stage, especially with respect to unskilled labor. As informed during the site visit, the nature of work requires specialized skill for the highly technical work such as

Page 13: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 12

erecting or stringing. Local people normally do not have such experience. Thus, the contractors working for tower erection have their own gang of skilled labour who are trained in similar activities. As confirmed by the developer, no local labour has been employed for the Maharashtra section.

4.5 Impact on Livelihoods and Crop compensation

22. In total 2748 numbers of towers is being erected under the project. For each tower an average area of 40 m x 40 m land is being temporarily cleared for carrying out the construction activities. Approximately 439.68 Ha of land will be temporarily affected due to the construction activities. Moreover, additional land would also be affected for creating access roads for bringing in the material and the mobile machinery. As per the electrical clearance, if there are losses to the trees on the tower location and as well as on the line corridor, then the trees are to be removed completely below the conductor and / or lopped for the balance corridor area. Any damage for the loss of crops or any other temporary impacts due to the activities involved in tower erection and access roads during the construction stage is mitigated by providing adequate compensation.

23. The crop compensation procedure for the loss of crops is done in three steps. First step: Identification/ measurement of the exact area, extent of crop damaged and the type of the standing crop during execution.

Second Step: Finding out the yield of the crop with the help of Agricultural University. In the process of crop damage assessment and calculation of compensation, the Agricultural University also refers to daily market price of the crops as published in the local newspaper.

Third step: Calculation of the crops compensation amount is done by using the area, yield and the rate. It can be shown as below,

Crop compensation= Area x Yield x Rate of crop

An example of crop compensation calculation and yield chart is attached as Annexure 4 and Annexure 5 respectively.

24. The compensation for the temporary losses is paid three times during the whole

construction stage. At first it is paid during the laying of Foundation of the tower, second time during the tower Erection and lastly during the Stringing stage. As per the 4th Quarterly LIE report of August 2010, the expenditure towards crop compensation till 30.11.2010 is Rs. 3.65 Crores. Refer Annexure 6 for details of the affected landholders and the progress of crop compensation till November 2010.

25. During the site visit, the team interacted with some affected farmers and their families in

one village along the transmission alignment and found that compensation was transparently determined and distributed; those doing multiple cropping (the number is very small as these are dry land areas) perceived that the compensation is almost close or equal to their crop loss. However they all verified that all the affected farmers were duly identified and compensated. It was found that farmers those who raise limited or no crop also received minimum compensation, which is generally more than what they lose in terms of crop damage. The visiting team did not notice any opposition to the project and people were found to have been cooperative, and that any grievances regarding entitlement were duly addressed.

Page 14: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 13

4.6 Accident Safety (Compensation for Loss of Life or Injury due to the Project)

26. As per Project Information Memorandum, WRTMPL has issued and REL Infra has accepted Letter of Award along with term sheet for the engineering, procurement and construction of the transmission lines under this project. The key terms of the proposed EPC contract entered into between WRTMPL and REL Infra includes that the Contractor shall provide insurance for Worker’s Compensation for any untoward incidents. Moreover, Reliance has Health & Safety policy which gives specific instructions to the contractors regarding the various health and safety issues that has to be taken into consideration during the project implementation stage.

5.0 IMPLEMENTATION ARRANGEMENTS AND PROCESS

27. As per the implementation arrangement, people are informed by a notification published in newspaper about the project and the tentatively affected villages (Annexure 7). As per the procedure, any individual/ organization can file their observation/ reservation to the authorized executive within 60 days of the notification. After which, a detailed land survey is done after the alignment has been finalized on the revenue map. Based on land records (called 7/12) available with the Tehsildar, plot numbers and their owners are identified. A list of Titleholder is prepared based on the 7/12 records (refer Annexure 8) and notices (Annexure 9) are served personally to each of the land owner after measurement of the area of crop loss. A copy of the receipted notice is kept as records by the Developer for all future purposes. The rightful owner then submits a copy of its ownership paper which is then confirmed with the Revenue department. Local farmers and representatives from the local government authorities (Sarpanch) are involved in the distribution process by way of identifying the entitled farmer and testifying in case of change in names.

28. The crop compensation amount is estimated by the developer as per the above mentioned crop compensation calculation methodology. Compensation amount is paid by Demand draft/Cheque to the affected landholders by the Developer (refer Annexure 10). The compensation data are maintained and the process of compensation payment is monitored at the site office level by the site engineers. They have no social scientist, but the process is well understood and managed by the site engineers. The grievances, if any, are addressed by senior executives of Developer or Project Incharge.

6.0 COMMUNITY DEVELOPMENT ACTIVITY 29. It was reported that Community welfare activities such as eye camps, blood donation

camps etc, is organized by the contractor on ad hoc basis. The details of the same as conducted till the last quarter has been attached as Appendix-11.

7.0 CONCLUSIONS AND RECOMMENDATIONS

30. The sub-project has been prepared by WRTMPL with adequate social safeguard consideration. Various alternative alignments have been considered as part of the project to minimize the impact on settlements, forests and tribal groups. The selected alignment has been approved by Central Electricity Authority (CEA) and the Developer has already been granted license under sections 14 and 15 of the Electricity Act 2003. The justifications towards route selection indicate that the proposed route of transmission line does not create any threat to the survival of any tribal community.

Page 15: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 14

31. No land acquisition is involved in the project. The damage to the crops during the construction stage has been adequately compensated to the landholders. The details of such payments have been provided by the Developer. The checklist briefing the findings of SDD is attached as Annexure 12.

32. It can be summarized that apart from the loss of crops, the project does not involve any major social safeguard issues.

8.0 PROPOSED MONITORING BY IIFCL

33. IIFCL has taken up the monitoring of various social issues such as crop compensation status and CSR activities undertaken by the Developer and the villages benefitted under such activity. The details of the same are attached as Annexure 6 and 11.

34. IIFCL shall further undertake site visits to carry out checks and review compliance in terms of distribution of compensation and community development activity undertaken by the developer and shall include such details in the IIFCL’s report to the Bank.

Page 16: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 15

ANNEXURE 1

Western Region Transmission (Maharashtra) Pvt. Ltd.

List of villages and affected districts

Sl. No. State District Taluk/ Tehsil Village Name

1 Maharashtra Beed, Ahmadnagar, Pune, Aurungabad, Sholapur, Osmanabad, Latur, Sangil, Kolhapur

Ambejogai, Kaiij, Beed, Patoda, Ashti, Ahmadnagar, Parner, Shirur, Ragurunagar (Khed), Vadgaon (Mawal), Shirur, Parner, Rahuri, Nevasa, Gangapur, South Sholapur, Barshi, Paranda, Renapur, Latur, Osmanabad and Tuljapur, Mangalwedha, Jath, Kavathemahanke, Mirajghat, Shirol, Hathakanangale

Pimla

2 Morewadi

3 Chanai

4 Sanegaon

5 Umrai

6 Lade Vadgaon

7 Lkala Amba

8 Mulegaon

9 Chandan Sawargaon

10 Kanadi Mali

11 Umeri

12 Kothi

13 Massa Jog

14 Sarola

15 Jhola

16 Dhawanjewadi

17 Pandherwadi

18 Chakurwadi

19 Vaitagwadi

20 Vangaon

21 Masewadi

22 Limba Ganesh

23 Saudana

24 Soni

25 Bhayal

26 Sawargaon

27 Balewadi

28 Bensur

29 Tale Pimpalgaon

30 Jakalka

31 Yewlewadi

32 Bhurewadi

33 Sautada

34 Matkuli

35 Pokhri

Page 17: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 16

36 Wadgaon

37 Kare Pandhri

38 Hajipur

39 Aashti

40 Bamhagaon

41 Shindewadi

42 Radhapur

43 Jalgaon

44 Chola Nimgaon

45 Kanudi Khura

46 Pimpalgaon

47 Dani

48 Parodi

49 Borodi

50 Mathepimprl

51 Ganwadi

52 Deulgaon

53 Sidhi

54 Ghonsapura

55 Babherwadi

56 Sarasgaon

57 Apdhupa

58 Narayan Ghavhan

59 Jategaon

60 Kandelwadi

61 Annapur

62 Nimgaon Dude

63 Nimgaon Boghi

64 Sone Sanghvi

65 Vaghale

66 Varude

67 Chinchoti

68 Khairwadi

69 Hiware

70 Thidewadi

71 Nimgaon

72 Rethewadi

73 Kharpudi Khuurd

74 Vaki Badrukh

75 Chandus

76 Koregon

Page 18: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 17

77 Shelu

78 Warle

79 Shinde

80 Thakuewadi

81 Vasuli

82 Umbre

83 Navlakh

84 Umbre Navlakh

85 Shinde

86 Vasuli

87 Varate

88 Shelu

89 Koregaon

90 chandus

91 Shiroli

92 Waki Badrukh

93 Thakurwadi

94 Kendur

95 Thintewadi

96 Khairnagar

97 Kanhur

98 Lakhewadi

99 Mitgulwadi

100 Maithan

101 Ranadewadi

102 Dongaran

103 Mhase Budrule

104 Gunhore

105 Jarale

106 Nighoj

107 Pimpri Jaisen

108 Wadjhire

109 Jadhavwadi

110 Hatal Khindi

111 Karandi

112 Diksal

113 Jamgaon

114 Shangaon

115 Kallup

116 Wadgaon Anali

117 Milkup

Page 19: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 18

118 Bhalwani

119 Bhalwani

120 Nimgaon Ghana

121 Khatgaon takali

122 Hingagaon

123 Bothegaon

124 Nagapur

125 Wadagaon Gupta

126 Pimpalgaon malwa

127 Vilad

128 Dehare

129 Shigave

130 Dhanori

131 Lkhadwa

132 Kukkudmedha

133 Umbrae

134 Pimpil

135 Awachad

136 Brahmini

137 Shilegaon

138 Kendal

139 Khurd

140 Pimpri Walane

141 karajgaon

142 Amalner

143 Banjulwadi

144 Nimbari

145 Tilapur

146 Goigaon

147 Panchegaon

148 Jaygudge Arawadha

149 Belpandhari

150 bel Pimpalgaon

151 Suregaon

152 Mevergaon

153 Bagadi

154 Agarkanadgaon

155 Nababpur

156 Gangapur

157 Sidhapur

158 Ambawnadi

Page 20: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 19

159 babargaon

160 Bhangaon

161 Bolegaon

162 Kalegaon

163 Jinlethan

164 Kasoda

165 Jogeshwari

166 Shirpunj

167 Ranjangaon

168 Limbdi Chincholi

169 Rampur

170 Wudgain

171 Kardehalli

172 Dhotri

173 Darshanhalli

174 Sangdari

175 Bormani

176 Tandulwadi

177 Kasari

178 Mizanpur

179 Raulgaon

180 Bhalgaon

181 Ambergaon

182 Hatji

183 Malegaon

184 ratanjan

185 Ladole

186 Bhanegaon

187 Sakat

188 Pimpri

189 Panegaon

190 Kalambwadi

191 Dadshinge

192 Kavhe

193 Kasarwadi

194 Khandawi

195 Uplai

196 Khadaki

197 Dhotri

198 Katgaon

199 Pimpla Badrukh

Page 21: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 20

200 Devkurali

201 Pimpla Khurd

202 Godhalwadi

203 Malumba

204 Masala

205 Pangdharwadi

206 Pimplawadi

207 Saranwadi

208 Brahmagaon

209 Wasgaon

210 Rui

211 Asu

212 Bavachi Pimpla

213 Magarwadi

214 Dastagirwadi

215 Pokhri

216 Selu

217 Saigan

218 Daitna

219 Mulegaon

220 Akola

221 Morwad

222 Chategaon

223 Motgaon

224 Wagandari

225 Panjakheda

226 Gandwad

227 Pimpri Amba

228 Shirala

229 Bhorgaon

230 Nivali

231 Kond

232 Kondwadi

233 Nitil

234 Ghugi

235 Lasona

236 Kanegaon

237 Samudrawani

238 Borgaon

239 Bombli

240 Vittalwadi

Page 22: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 21

241 Umergaon

242 Baramgaon

243 Bamani

244 Bamniwadi

245 Khandala

246 Karala

247 Halora

248 Barul

249 Tirth (Budruk)

250 Devsingha

251 Bijanwadi

252 Arati (Hurd)

253 Arali (Budruk)

254 Yevata

255 Kalegaon

256 Dindegaon

257 Khanapur

258 Tandulwadi

259 Musti

260 Sangdari

261 Dhotri

262 Wadgaon

263 Rampur

264 Dindur

265 Limbi

266 Chincholi

267 Limbi Chincholi

268 Hanamgaon

269 Shinadgaon

270 Achegaon

271 Auj

272 Nilehal

273 Alergaon

274 Ratnapur

275 Aherwadi

276 Bankalgi

277 Badalagi

278 Sanjwad

279 Chincholi

280 Auradh

281 Nandani

Page 23: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 22

282 Malkavathe

283 Kurghot

284 Takali Chinchpur

285 Karkal

286 Lavangi

287 Soddi

288 Shivangi

289 Sagar Budrukh

290 Lavangi

291 Maroli Nigadi Khurd

292 Bobald

293 Lakdewadi

294 Tonewadi

295 Sanwadi

296 Nurale

297 Wayphal

298 Nigadi Khurd

299 Gholeshwar

300 Achkanhalli

301 Revnal

302 Tipehalli

303 Birnal

304 Bagewadi

305 Kanthi

306 Baj

307 Belunki

308 Basappachiwadi

309 Ranjani

310 Shinganapur

311 Dhulagaon

312 Lonarwadi

313 Sarathi

314 Kuktoli

315 Kongnail

316 Kadamwadi

317 Belanki

318 Payappachiwadi

319 Shipur

320 Eerandali

321 Bolwad

322 Bedag

Page 24: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 23

323 Mirajghat

324 Dharati

325 Arjunwad

326 Ghalwad

327 Malwadi

328 Bhanguti

329 Nandani

330 Janbali

331 Haroli

332 Yadrav

333 Takwade

334 Shiradwad

335 Rangoli

336 Hupari

337 Talandage Umbre

338 Navlakh

339 Karnataka Bijapur Indi Takli

340 Umrani

341 Hattali

342 Nivaragi

343 Havinal

344 Hathalli

345 Chadchan

Page 25: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 24

ANNEXURE 2

Page 26: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 25

Page 27: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 26

ANNEXURE 3

Page 28: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 27

Page 29: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 28

Page 30: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 29

Page 31: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 30

ANNEXURE 4

Page 32: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 31

ANNEXURE 5

Page 33: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 32

ANNEXURE 6

WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED

Crop compensation details till November 2010

S.No.

T/Line Description

Amount in Rs. No. of Cases

1 Solapur - Karad (LILO) 16,693,872 1628

2 Parli - Pune 7,843,121 732

3 Pune - Aurangabad 7,820,511 444

4 Solapur - Parli 1,402,744 130

5 Solapur - Kolhapur 2,764,511 254

Sub Total 36,524,759 3188

Page 34: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 33

ANNEXURE 7

Page 35: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 34

Page 36: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 35

Page 37: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 36

ANNEXURE 8

Page 38: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 37

ANNEXURE 9

Page 39: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 38

ANNEXURE 10

Page 40: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 39

ANNEXURE 11

WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED

Community Development Activity details for the period of April 10 to June 2010

Project section

Type of Community

Development Activity

Number of villages benefited

Date of the programme/

activity

Budget allocated (in

Rs.)

WRTM Ambajogai Office

Purchase of two oxen for a physically challenged farmer

1 8th April 2010 Rs. 10,000/-

WRTM Pune Office at ‘Kiwale’ Village

Free for all ‘Medical Camp’

5 23rd April 2010 Rs. 1,50,000/-

WRTM Blood Donation - Throughout the

year -

Page 41: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 40

ANNEXURE 12

Findings of Social Due Diligence

The below table briefs the findings of the Due Diligence and the remarks by IIFCL.

Sl.

No.

Social Safe

Guard Issues

Findings Remark

1. Impact

Minimization

Measures

Various alternative alignments have

been considered as part of the

project. The selected alignment has

been approved by Central Electricity

Authority (CEA).

Justification towards route

selection indicates that utmost

care is taken to avoid congested

inhabitant areas, villages and

towns wherever possible at the

time of route alignment.

2. Census and

Socio-

Economic

Survey

No such survey has been carried out Since no resettlement issues are

involved therefore such surveys

are not envisaged as part of the

project.

3. Land

Acquisition

Plan

No land acquisition for the project.

Land is used only during the

construction stage and the

ownership of the land remains with

the landholders.

Adequate compensation is

being provided for the loss of

crops and any other temporary

losses.

4. Entitlement

Matrix

The Calculation of the crop

compensation amount is done by

using the area, yield and the rate.

The yield of the crop is decided with

the help of Agricultural University.

In the process of crop damage

assessment and calculation of

compensation, the Agricultural

University also refers to daily

market price of the crops as

published in the local newspaper.

The methodology of crop

compensation is well in place

and a sample document

showing a few cases of crop

compensation calculation is

attached as Annexure 4 and 5.

5. Public

consultation

and disclosure

As part of obtaining authorization

for the selected alignment from

Ministry of Power under section 164

of the Electricity Act 2003 and

obtaining license under sections 14

and 15 of Electricity Act, 2003,

these processes have already been

carried out.

People have been adequately

notified through paper

advertisement. No public

observation/reservation on

project scheme was received

within a notice period of two

months. The relevant document

towards the public notification

and information disclosure is

Page 42: WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED DDR... · WESTERN REGION TRANSMISSION (MAHARASHTRA) PRIVATE LIMITED Social Safeguard Due Diligence Report December 2010

India Infrastructure Finance Company Limited Page 41

enclosed in Annexure-7.

6. Impact on

tribal people

The proposed alignment passes

mainly through villages and semi-

urban to urban limits. The

justification towards route selection

(refer Annexure-2) indicate that the

proposed route of transmission line

does not create any threat to the

survival of any tribal community.

As informed by the Developer,

no tribal population is found on

the corridor till date. IIFCL has

advised the Developer to adopt

appropriate mechanism to

minimize the inconvenience to

the Schedule Tribe people if

any.

7. Alternative

resettlement

sites

No resettlement is involved as part

of the project.

No structure will be affected as

part of the project and hence

alternative resettlement is not

required.

8. Socio-

economic

rehabilitation

measures

Adequate compensation is being

provided for any damage to crops

and any other temporary losses.

9. Implementation

Arrangement

There is project implementation

arrangement. WRTMPL is

responsible for :

- Crop Compensation

- Reporting and mitigating the

complaints received for the crop

loss and any other temporary

losses.

- Right of Way

The grievances, if any, are

addressed by senior executives

of Developer or Project

Incharge.

10. Corporate

Social

responsibility

(CSR)

activities

Apart from compensating the

affected people with adequate

compensation, Developer is also

engaged in various CSR activities

which are solely done for the

community development. In this

respect, the Developer has been

organizing free Eye check-up camps

for the local people.